Exhibit 1 (Technical Specifications)~5.doc
DOC document 52 KB Posted
- Attached to
- ESB ODOT Baker Hwy 7 Crack Seal
- Solicitation number
- S-73000-00012331
- Issued by
- Baker County, Oregon
About this file
This is a technical specifications exhibit from the Oregon Department of Transportation (ODOT) for District 13 crack sealing work on State Highway Route 071 (OR 7). The project involves crack sealing approximately 102,400 linear feet of roadway between mile posts 24.9-50.5 on both east and west bound lanes, including travel lanes and shoulders. The work must commence after April 1, 2025, with final completion by June 15, 2025. The contractor must follow the 2024 Oregon Standard Specifications for Construction and be capable of preparing and sealing approximately 10,000 linear feet per 10-hour shift. The work requires pre-construction meeting with the Project Manager, and work must begin within five working days of this meeting after Notice to Proceed is issued.
The contractor is responsible for providing all labor, equipment, machinery, materials, and traffic control. Technical requirements include heating sealant materials between 280-400 degrees Fahrenheit, sealing cracks 1/8" or wider, and maintaining two separate work zones to meet Freight Mobility standards with 22' horizontal clearance for oversized loads. Traffic control must allow for loads to be waved through with delays not exceeding 20 minutes. The project manager is Allen Jensen, and payment will be made per linear foot of sealed cracks, including all materials, equipment, labor, and traffic control costs.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| ESB.RFCQ.Attachments.docx | DOCX document | |
| 00012331 Preliminary Results.xlsx | XLSX spreadsheet | |
| 00012331 Intent To Award.xlsx | XLSX spreadsheet | |
| Findings - Franklin Boulevard.pdf | ||
| ESB.RFCQ.Services.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
EXHIBIT 1 (Technical Specifications)
PROJECT SPECIFICATIONS
District 13 Crack Seal Locations and Project Manager
| Item No. |
| State Highway |
| Route Number |
| Estimated Mile Post Location |
| Estimated Linear Feet |
| Project Manager |
| Phone No. |
OR 7
24.9-50.5
East & West Bound
102,400
Allen Jensen
541-523-4566
* Crack Seal full width of roadway (travel lanes and shoulders) Start Date: After April 1, 2025 Final Completion Date: June 15, 2025 Scope - This project scope consists of supplying all labor, equipment, machinery, material, and traffic control for repairing and resealing cracks in flexible pavements at the described location in the designated state highway section in District 13 according to the Oregon Standard Specifications for Construction 2024 and modifications listed in these contract documents.
General - The Contractor shall always have a responsible party on the job while work is in progress, capable and with authority to make job-site decision as an official Contractor's representative. The Contractor shall provide the Project Manager with a summarization of activities and work performed daily if requested. The Contractor shall mark the quantity of cracks completed in spray paint on the shoulder in half mile sections for verification purposes.
Contractor shall have pre-con meeting with Project Manager.
Contractor shall start at M.P. 50.5 and work west towards M.P. 24.9 Contractor shall carry on the work and adhere to the contract schedule during all disputes or disagreements with the State. No work shall be delayed or postponed pending resolution of any disputes or disagreements, except as specifically permitted by the specifications or as Contractor and State may otherwise agree in writing.
The Contractor must follow the manufacture recommendation for applying the product. The pavement temperature must be 40° and raising for the minimal and the district recommends no crack sealing when the pavement temperature exceeds 130°.
Contractor shall meet with the State Project Manager for a pre-work conference at a time mutually agreed upon. Work shall commence within five working days of this meeting, providing the Notice to Proceed has been issued. A pre-bid conference will not be required. Bidders are solely responsible for inspecting the sites prior to bidding. In no event shall failure to inspect the site constitute grounds for charges to the State more than the bid price. The Project Manager will be as listed above for the section they will be in.
2024 OREGON STANDARD SPECIFICATIONS FOR CONSTRUCTION: The 2024 Oregon Standard Specifications for Construction (“Standard Specifications”) include detailed technical specifications that apply to this Request for Competitive Quotes and resulting Contract.
Some sections of the technical specifications are identified and modified below. Sections of the technical specifications not identified below remain applicable to the Contract according to their original terms. Part 00100 of the Standard Specifications (General Conditions) is not applicable to the Contract; however, if a technical specification (Parts 200 and beyond) references a section from Part 00100, that section from Part 00100 applies to the Contract for purposes of supporting and giving full effect to the technical specification. The Standard Specifications are available online:
http://www.oregon.gov/ODOT/HWY/SPECS/Pages/standard_specifications.aspx Section 00746 - Crack Sealing Flexible Pavements
Comply with Section 00746 of the Standard Specifications modified as follows:
Description
00746.00 Scope – Replace paragraph with:
Work of this contract consists of supplying all labor, material, equipment, machinery, and traffic control for repairing and resealing cracks in flexible pavements at locations designated by the Project Manager. Crew size will be the contractor’s option, but the crew must be able to prepare and seal approximately 10,000 linear feet per 10-hour shift.
Materials
00746.10 Sealants – Furnish all sealant materials for crack repair of flexible pavements that is approved by the engineer before being incorporated into the work. Before beginning work, furnish a complete written statement of origin, composition and manufacturer of materials that are to be used.
Furnish hot applied joint sealants of the type intended for use in sealing cracks in asphalt concrete pavement that meet the requirements of 02440.30.
Equipment
00746.20 Equipment - Replace paragraph with:
Use proper sealing equipment for the specific material listed according to the manufacturer's recommendations. The equipment for sealing compounds shall be a melting kettle of the double boiler, indirect heating type, using oil as a heat-transfer medium. The kettle shall be an effective, mechanically operated agitator equipped with a positive, thermostatic temperature control. All equipment and installation procedures are subject to prior approval of the ODOT Section Manager/ Project Manager.
Construction
00746.40 General - Revise: 00220 and 00221. For this contract, refer only to the bulleted item: ODOT “Oregon Temporary Traffic Control Handbook for Operations of three days or less. 2011 -September 2016
ADD THE FOLLOWING PARAGRAPHS:
Traffic control for this contract shall be set-up in 2-separate work zones to meet Freight Mobility standards. Traffic cones for the lane joint work zone shall be placed to the right of centerline far enough to allow for 22’ of horizontal clearance to accommodate oversized load movement in the travel lane.
The contractor shall be able to accommodate all loads, including oversize loads. Work equipment and traffic control devices must be able to be moved quickly to enable a load that approaches the work zone unannounced to be waved through. Waved through means that for width, length or weight the work equipment and traffic control devices can be moved (and there is an understanding that it would be) if a permitted vehicle comes to the work zone the contractor shall provide the required clear distance. This may result in a slight delay to the oversize load or the traffic behind the load. It is okay to have a slight delay up to 20 minutes if the load can get through the work zone.
Contractor shall notify property owners 24 hours prior to any work that will interfere with or restrict the use of their property or improvements, such as but not limited to driveways, mailboxes, and utilities.
00746.41 Mixing and Heating - Follow the manufacturer's recommendations for application. Mix and heat the sealant materials to a minimum temperature of 280-degree F. Do not heat the material above 400-degree F.
00746.42 Installation Procedure – Add the following paragraphs: In the event of adverse weather conditions the Contractor shall receive authorization from the State Project Manager before continuing work.
Contractor shall seal cracks 1/8” or wider. “Alligator” areas shall not be sealed.
00746.43 Cleaning and Sanding – Add the following paragraph: The Contractor shall be responsible for cleanup and removal/disposal of all materials used on the project, including all containers of crack sealant materials. Left over materials and containers, (including but not limited to items classified as “hazardous materials”), that are designated as excess or refuse by the State Project Manager shall become the property of the Contractor and disposed of in accordance with all local, State, and federal guidelines.
Measurement
00746.80 Measurement – The quantities of sealed cracks will be measured by length.
Payment
00746.90 Payment – The accepted quantities of sealed cracks will be paid for at the Contract unit price, per foot as appropriate, for item “Crack Sealing”.
Payment will payment in full for furnishing and placing all materials, and for furnishing all equipment, labor, traffic control and incidentals necessary to complete the work as specified.
No separate or additional payment will be made for required cleaning and routing.