Ex-1 Plant City RC Lighting SOW .pdf
PDF 97 KB Posted
- Attached to
- 217047 Plant City Lighting
- Solicitation number
- ITB-10076
- Issued by
- Hillsborough County, Florida
About this file
This document is a Scope of Work (SOW) for a lighting upgrade project for the Plant City Exterior Lighting Upgrade located at 4004 Airport Rd., Plant City, FL 33563. The project requires the removal of existing equipment, including 18 wall packs, 3 pole mount luminaires, and 2 luminaires from a pole, and the installation of new equipment, including 18 LED wall packs, 2 pre-cast round rusticated concrete pole bases, 2 25' tapered round steel light poles, 7 tenon mount luminaires, and 8 pole-mounted photocells. The contractor must have a current State of Florida Contractors License and is responsible for securing necessary permits, environmentally appropriate disposal of any waste, and maintaining a clean job site. The contractor cannot subcontract more than 50% of the total work for the project.
The document does not provide information about pricing terms, set asides, incumbents, funding requirements and sources, or any other salient details beyond the scope of work. The project must meet Florida Building Code, State Fire Marshall, local Authorities Having Jurisdiction and Area Water Management requirements, and any other permits and fees required by other county, local or state authorities.
View the file
Other files
Show all 33
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROJECT NUMBER: 12217047
PROJECT NAME & LOCATION: Plant City Exterior Lighting Upgrade – 4004 Airport Rd., Plant City, FL 33563
Exhibit 1
Project must meet Florida Building Code, State Fire Marshall, local Authorities Having Jurisdiction and Area Water Management requirements, and any other permits and fees required by other county, local or state authorities.
Regulatory permitting to include the preparation, submittal, payment and review coordination of the Water Management District, Environmental Resource Permit (including permit fees), Florida Department of Environmental Protection (FDEP) Notice of Intent (including filing fees), City and/or County Review Permit Fee, and any other permits and fees required by other county, local or state authorities.
Detailed Scope of Work:
1. Removal of existing equipment
1.1. Main Armory Building
1.1.1. Contractor will remove Qty 18 Wall Packs
1.2. Public Parking Area (POV)
1.2.1. Contractor will remove Qty.1 Pole mount Luminaire and concrete pole (Demo Plan ID- Z)
1.3. Motor Pool (MOV)
1.3.1. Contractor will remove Qty. 2 Pole mount Luminaires and concrete poles (Demo Plan ID - Z)
1.3.2. Contractor will remove Qty. 1 Pole mount Luminaire and steel pole (Demo Plan ID - P)
1.3.3. Contractor will remove luminaires (2) from pole. Pole to remain. (Demo Plan ID Z1)
2. Installation of new equipment
2.1. Main Armory Building – Furnish and install:
2.1.1. Qty - 18 LED Wall Packs WA and W2 (Specifications - Exhibit 8)
2.2. Public Parking Area (POV) – Furnish and install:
2.2.1. Qty 2 – Pre-Cast round rusticated concrete pole base (Specifications – Exhibit 6)
2.2.2. Qty 2 – 25’ tapered round steel light pole (Specifications – Exhibit 7)
2.2.3. Qty 2 – Tenon mount luminaire SL4s (Specifications – Exhibit 8)
2.3. Motor Pool (MOV) – Furnish and install:
2.3.1. Qty 5 – Pre-Cast round rusticated concrete pole base (Specifications – Exhibit 6)
2.3.2. Qty 5 – 25’ tapered round steel light pole (Specifications – Exhibit 7)
2.3.3. Qty 5 – Tenon mount luminaire SL4s (Specifications – Exhibit 8)
2.3.4. Qty 2 – Tenon mount luminaire FA (Specifications – Exhibit 8)
2.4. Underground Conduit Caution
2.4.1. Contractor is responsible for conduction locates for any/all potential hidden underground assets prior to any excavation/drilling/boring.
2.5. Manufacturer/Model Designation
2.5.1. All luminaires listed in this section (Exhibit 1) are Basis of Design
2.5.1.1. See Luminaire Specifications and performance requirements (Specifications – Exhibit 8)
3. Lighting Controls
3.1 Photocell
3.1.1. Furnish and install (Qty 8) pole mounted photocell on each light pole
3.1.1.1. Manufacturer – WattsStopper - EM-24A2 or
equal 3.1.1.2. Photocells to be mounted 10’ AFG.
3.1.2. There are no additional new lighting controls in this specification.
This space intentionally left blank
PROJECT NUMBER: 12217047
Exhibit 1 – Cont’d.
4. Electrical Connections
4.1 Existing AsBuilt plans indicate 277VAC
4.1.1. It is the responsibility of the contractor to confirm the voltage on site, and to confirm and/or revise the voltage code in the basis of design manufacturer’s model designation listed in Luminaire Specifications (Pages 3, 4, and 5)
4.2 Contractor will utilize all existing wiring and connections where available.
4.3 Contractor will inspect all existing wiring and connections related to this scope of work and repair and/or upgrade to meet current NEC requirements where applicable.
4.4 Contractor will furnish and install new underground electrical feeders and conduit to added/relocated light poles and luminaires
4.4.1. Conduit
4.4.1.1. Sch 40 1 ¼” dia
4.4.2. Wire
4.4.2.1. 2 #10 THHN/THWN & #10 THHN/THWN Gnd
5. Environmental
5.1. The contractor is responsible for environmentally appropriate disposal of any and all waste associated with the removal of existing lighting fixtures and installation of new fixtures.
6. General
6.1. Contractor must have a current State of Florida Contractors License (General and/or Electrical)
6.2. Contractor will not be a business performing services under another contract to a services dispatch entity
6.3. Contractor will sub-contract no more than 50% of total work for this project
6.4. All work performed must be performed in accordance with current NEC Guidelines and local building codes.
6.5. Contractor is responsible for securing any necessary permits.
6.6. Contractor will leave job site free of debris, tools, and/or equipment at the end of each work day.
6.7. Any storage of contractor’s tools and/or equipment on site, during this project, must be approved, in advance, by the POC on site.
6.8. Contractor will clean job site upon completion of work.
6.9. Contractor is responsible for environmentally appropriate disposal, off site, of any project related materials/equipment.
6.10. Contractor will perform start-up per manufacturer’s recommendations and check system for proper operation.
End of Section