This notice provides information for industry in preparation for the release of a request for proposals for the Eglin Wide Agile Acquisition Contract. The government intends to release the RFP on July 6, 2021, with technical evaluations beginning on early submissions received starting July 19th. Proposals will be due August 4th, with incremental awards starting August 11th and final contract awards by September 6th. The post-award conference will include both general and individual sessions held in-person or virtually. The government seeks capabilities in digital engineering, continuous integration/continuous delivery, and artificial intelligence/machine learning, or plans to achieve proficiency. Proposals should focus on recent and relevant experience in areas such as program management, systems engineering, and test and evaluation.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| UPDATED - EWAAC Industry Enagement in prep for RFP.pptx | PPTX presentation |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
I n t e g r i t y - S e r v i c e - E x c e l l e n c e 1
EWAAC
Proposals and Post-Award Conference
Notional – Refined to streamline award process and still subject to change.
Government is preparing a proposal template to aid in proposal preparation, submission and evaluations – more info will be posted
Early submission of proposals is recommended Incremental Award process
The Government intends to conduct evaluations on an incremental, first-in-first-out basis as proposals are received. Contractors are encouraged to submit proposals early. The Government will evaluate as received. The Government will not make award to any contractor prior to the solicitation closing date and time in order to allow contractors to update the proposal and/or to fix any discrepancies discovered after early submission. All awardees will have the same effective date of award in block 3 of their DD FM 1155, regardless of the date of proposal submission. Notice of award will be no later than five (5) business days prior to the effective date via email to Contractor’s obligation POC.
Post-Award Conference will be in-person and/or virtual Concurrent general session to ALL awarded contractors – 1 hour duration Virtual or in-person sidebar conferences with each awardee – 15 min duration Attendance in-person is voluntary and not seen differently as virtual attendance Intent is to establish potential future relationship and educate on Digital Trinity and future of AFPEO Weapon’s goals
Changes in Blue
I n t e g r i t y - S e r v i c e - E x c e l l e n c e 2
POCs and Schedule
PCO: Stephen Gilligan Program Manager: Chris Moore Email stephen.gilligan.3@us.af.mil or cameron.white.8@us.af.mil with questions or comments
Milestone Date Release RFP July 6th 2021 Technical evaluations start on early submissions July 19th 2021 Proposals due August 4th 2021 Incremental awards start August 11th 2021 Final contract award(s) September 6th 2021
Notional Schedule Subject to change
Changes in Blue
I n t e g r i t y - S e r v i c e - E x c e l l e n c e 3
Miscellaneous
Digital Capabilities will Revolutionize Weapon Procurement https://acquisitiontalk.com/2020/10/there-is-no-spoon-a-look-into-will-ropers-new-digital-acquisition-reality/
Digital Trinity (DT) – The Government is seeking demonstrated proficiency in all three DT areas, however to maximize participation in the IDIQ will accept at this time an offeror’s roadmap (plan) for how to achieve proficiency within a specific timeline set by the contractor. The contractor’s roadmap must meet page limit restrictions in Sec. L requirements for Subfactor A.
Scope – The Government is interested in demonstrated technical adequacy for the initial award. Proposals should focus on recent and relevant experience in accordance with Sec. M, paragraphs 3.0-3.2.
Cage Codes – Offerors with multiple cage codes would need to propose separately for the IDIQ to be considered for DO/TO awards independently.
Security Requirement at IDIQ Level – SECRET clearance level is preferred for the initial post-award conference DO, however following higher security conditions may be determined by the programs based on specific requirements.
Proposed Proposal Guide – See Proposal template posted separately
File details come from the government source that posted it. Updated .