EVSE SOW for AAAP Ad.docx
DOCX document 20 KB Posted
- Attached to
- Lease of Office Space within Region 3. Request for Lease Proposals (RLP) #23-REG00_3MD0377 - Office Space
- Solicitation number
- 3MD0377
About this file
This Statement of Work outlines requirements for the installation of electric vehicle supply equipment and supporting infrastructure at the USDA-FPAC Service Center in Annapolis, Maryland. The lessor will obtain all required permits and install conduit, electrical infrastructure, and dedicated circuits to support two dual-port Level 2 EV charging stations with SAE J1772 connectors. Signage will also be installed identifying the stations are reserved for USDA-FPAC electric government vehicle use only. Costs for furnishing and installing the charging stations, infrastructure, and signage will be covered by the government's tenant improvement allowance. The related solicitation is for the lease of office space within Region 3 of the General Services Administration and does not provide any product or service requirements.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Delieneated Area for AAAP Ad.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USDA Statement of Work (SOW) Installation of EVSE Charging Station(s) Supporting Infrastructure Annapolis, Maryland
Installation of Electric Vehicle Supply Equipment (EVSE) Infrastructure and Reserved Parking for Electric Vehicles shall comply with all local electrical codes, and if none, National Electric Code.
1) Obtain all required permits for the installation and construction of supporting infrastructure of the EVSE Charging Station(s) as follows:
a. Install conduit and all other required base-building electrical infrastructure necessary to support metered 120/208 V, 3-phase, 4-wire with bond, 60 hertz electric service to USDA’s EVSE Charging Station(s) at the location identified at LCO discretion.
b. Dedicated single and/or three-phase electrical circuit(s)(32A at 208/240V).
c. New dual pole 40 A circuit breaker(s) at the electrical panel required for each charging station.
d. Conductor wiring sized in accordance with the National Electric Code requirement for 125% capacity for continuous load for all branch circuits from panel to stations via raceway or conduit.
2) Install the supporting infrastructure for two (2) dual-port Level 2 Electric Vehicle Supply Equipment (EVSE) Charging Stations with SAE J1772 connectors at the Annapolis, MD, USDA-FPAC Service Center in support of USDA’s EVSE Plug-in Hybrid Electric Vehicles (PHEV) or Battery Electric Vehicles (BEVs).
3) Lessor will furnish, install, and maintain two (2) dual-port Level 2 Electric Vehicle Supply Equipment (EVSE) Charging Stations with SAE J1772 connectors and software systems for remote management to monitor, maintain, and allow access.
4) Install signage identifying the EVSE is for USDA-FPAC reserved for eGOV use only.
5) Costs to furnish and install the charging stations, infrastructure and signage above shall be paid via the Government’s Tenant Improvement allowance.
File details come from the government source that posted it. Updated .