About this file
Summary of Evansville Riverfront Painting Upgrades IFB
This is an Invitation for Bids (IFB-949-01-2026) issued by the City of Evansville through the Evansville-Vanderburgh Levee Authority District for a comprehensive painting and coatings project on the Evansville Riverfront. The project involves surface preparation, concrete finishing, handrail painting, galvanized steel component coating, chain link fencing treatment, and light and speaker rack finishing on a riverfront wall extending approximately 1,760 feet with sections reaching 25 to 30 feet in height. Bidders are required to conduct mandatory field verification to confirm actual square footage before submission. The pre-bid conference is scheduled for November 2, 2026, at 10:00 AM at 1200 Stanley Avenue, Evansville, Indiana, with attendance mandatory; failure to attend results in the vendor being deemed non-responsive. Bids are due November 17, 2026, at 9:00 AM CDT. Contract award is anticipated December 1, 2026, with the successful bidder required to begin work within ten days of notice to proceed and complete all work within 60 days of that notice. The contractor must provide all labor, materials, tools, equipment, and services necessary for project completion.
Bidders must submit a sealed bid with one original, one paper copy, and one electronic PDF copy on flash drive, along with required documentation including a bid bond or certified check equal to five percent of the total bid amount. All bids of $150,000 or more must comply with the City's Responsible Bidding Ordinance and include subcontractor disclosures. Contractors must maintain a compliant written drug-testing program for bids exceeding $10,000 and provide proof of appropriate licensing under Evansville Municipal Code 3.95.030. The selected contractor must furnish a one hundred percent performance bond prior to work commencement and maintain specified insurance coverage including general liability with minimum combined single limits of $1,000,000 per occurrence, workers' compensation as required by Indiana law, and umbrella/excess liability of at least $3,000,000. The contractor guarantees all improvements for two years from final acceptance, with the City retaining 90 days after the warranty period to identify and notify the contractor of qualifying defects. Liquidated damages of $100 per day apply if the contractor fails to meet the required project timeline unless circumstances are determined to be unforeseen and beyond contractor control. The City reserves the right to reject any or all bids and holds the authority to reject all bids if total project costs exceed available funding.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Invitation For Bids:
IFB-949-01-2026
Project: Evansville Riverfront Painting Upgrades
Issue Date: October 26, 2026
Issued By: City of Evansville – Vanderburgh County Levee Authority District
Transmitted Via: City of Evansville – Purchasing Department Webpage https://www.evansvillegov.org/city/department/division.php?structureid=133
Bids Due: November 17, 2026, at 9:00 am CDT
1200 Stanley Ave.
Evansville, IN 47711 https://www.evansvillegov.org/city/department/division.php?structureid=133
SECTION 1 - INTRODUCTION & VENDOR INSTRUCTIONS
1. Purpose The Evansville-Vanderburgh Levee Authority District (“Board”), by and through the City of Evansville-Vanderburgh County Levee Authority (Department), is seeking competitive sealed bids from qualified contractors to complete upgrades to the Evansville Riverfront through a comprehensive painting and coatings project. This IFB defines the minimum project requirements and outlines the responsibilities and expectations for all potential Vendors (“Respondents” or “Contractors”).
Vendors are encouraged to review the full project scope and site conditions carefully before preparing a response.
2. Contractor Responsibilities
Contractors responding to this IFB are expected to provide all necessary labor, materials, tools, equipment, and services to successfully complete the project. At a minimum, the selected Contractor will be responsible for:
• Procuring all materials and supplies required for performance of the work.
• Providing all labor, tools, and equipment needed to complete the project safely and efficiently.
• Implementing all necessary pedestrian and/or vehicle traffic control measures.
• Meeting all local licensing requirements under Evansville Municipal Code 3.95.030 at the time of bid opening.
• Ensuring that any prime Contractor submitting a bid over $150,000 meets Responsible Respondent criteria pursuant to Evansville Municipal Code 3.95.040.
• Maintaining a compliant written drug-testing program for bids exceeding $10,000, in accordance with
Municipal Code 3.95.020.
• Maintaining all required liability, workers’ compensation, and specialty insurance coverage throughout the duration of the contract, as specified in the General Conditions.
3. Project Schedule
Bid documents available to bidders October 26, 2026.
Pre-bid meeting November 2, 2026
Last day for contractor questions November 6, 2026
Final addendum (if applicable) November 11, 2026
Bids due November 17, 2026
Anticipated contract award December 1, 2026
*The Successful Bidder will begin within ten (10) days of notice to proceed.
*The Successful Bidder will have work completed within 60 days of notice to proceed.
4. Pre-Bid Conference A mandatory pre-bid conference will be held on November 2, 2026, at 10:00 AM (local time) at 1200 Stanley Ave. Evansville, IN 47711. Failure to attend will result in the Vendor being deemed non-responsive.
5. Right of Rejection
The Board reserve the right to reject any one or all bids, or any part of any bid, to waive any irregularities in any bid, and to award the purchase in the best interest of the City. Furthermore, the City reserves the right to hold the bid of the three (3) lowest contractors for a period of sixty (60) calendar days from and after the time of the bid opening.
6. Communication Protocol
To ensure a fair and consistent evaluation process, there shall be no verbal communication regarding this solicitation between prospective bidders and any City of Evansville and/or Vanderburgh County employee, representative, or Board member. All questions must be submitted in writing to DaChenae Streeter via email at dstreeter@evansville.in.gov with the subject line: Evansville Riverfront Painting Upgrades.
Inquiries must be received no later than November 6, 2026. Questions received after this deadline may not be answered.
Only written addenda issued by the City will modify this solicitation; verbal statements will not be binding. No specification changes may be made within five business daysof the bid opening.
7. Access to Solicitation Documents Vendors are responsible for reviewing all drawings, specifications, site conditions, and supporting materials before submitting a bid. Failure to familiarize yourself with these documents will not relieve the Vendor of required performance obligations
8. Bid Preparation & Submission Costs Each vendor shall be responsible for all costs incurred in order to prepare and submit their response to this IFB.
9. Bid Bond A bid bond or certified check equal to 5% of the total bid amount, payable to the Evansville-Vanderburgh Levee Authority District.
No bid may be withdrawn for 30 days following the bid opening without written approval from the Evansville- Vanderburgh Levee Authority District. Bonds and checks will be returned to unsuccessful contractors once performance bond has been received from the awarded contractor.
10. Performance Bond The successful Contractor shall furnish and pay for an approved one hundred percent (100%) Performance Bond (Indiana Form 86A) pursuant to the provisions of I.C. 36-1-12-14 covering the faithful performance of the Contract and the payment of all obligations arising thereunder, with such sureties as the Owner may approve, prior to work beginning. The Performance Bond serves as a guarantee that all provisions of the solicitation, the specifications and resulting Contract shall be met. The surety of the performance bond may not be released until one (1) year after the date of the board’s final settlement with the Contractor.
11. Public Bid Opening Procedures At the public opening, only the following information will be given:
• Vendor name and amount of bid No award will be made or implied at this time, unless otherwise indicated. Bids nor related documents will be reviewed at the public opening. No discussion of any nature concerning brand names, deliveries, samples, etc. can be entered into between any municipal employee and any contractor during or after the public opening until the evaluation process has concluded and a recommendation for award has been made.
12. Public Records Disclosure A. All submissions may be considered public documents under applicable laws and may be subject to disclosure.
Some solicitation records are public as soon as received by the City, others become public at public opening, and others at contract award. Contractor recognizes and agrees that City will not be responsible or liable in any way for any losses that the Contractor may suffer from the lawful disclosure of information or materials to third mailto:dstreeter@evansville.in.gov parties.
B. Any materials requested to be treated as confidential documents, proprietary information, or trade secrets must be clearly identified and readily separable from the balance of the bid submission. Such designations will not necessarily be conclusive, and Contractor may be required to justify why such material should not, upon written request, be disclosed by the City under the applicable public records act.
C. City will make reasonable effort to provide at least two (2) business days’ notice to the Contractor of a public records request for material submitted pursuant to this IFB (Invitation for Bid). The City will then release the document in accordance with the City’s policy for responding to such requests unless both of the following are true:
i. the Contractor responds to the notice with any objection to the production of the document within two (2) business days of receipt of the notice; and
ii. the Contractor agrees in writing to indemnify City, in a form acceptable to City, in the event a challenge is brought for withholding a public record based on Contractor having designated it a trade secret.
13. Bid Format & Submission Requirements Each bid must:
• Be submitted in a sealed envelope clearly marked with the IFB number and project title.
• Include one (1) original, one (1) paper copy, and one (1) electronic copy (PDF on flash drive).
• Include unit pricing in both words and numerals, with written amounts governing in the event of discrepancies.
• Be typewritten, complete, and signed by an individual authorized to bind the firm.
• Follow the sequence and format of the IFB; incomplete bids may be rejected.
The contents of this solicitation will become incorporated within any contract signed by the Board and the provider of service. Do not retype this bid. Instead, respond on a separate page and cite the section number for each response. All areas of the request must be addressed in the same sequence cited in the solicitation instructions in order that proper consideration is given to the bid. Bids submitted without information or incomplete content may result in the bid being removed from consideration.
14. Delivery of Bids
Contractors may deliver their sealed bid no later than 4:00 PM on November 16, 2026 at:
Purchasing Department 1 NW MLK Jr. Blvd. Room 323
Evansville, IN 47708
Bids submitted after November 16, 2026 at 4:00 PM CDT must be hand delivered to the Board secretary no later than 9:00 am CDT on November 17, 2026, at:
Levee Authority 1200 Stanley Avenue Evansville, IN 47711
It is the sole responsibility of the vendor to see that their bid is received by the proper time at the proper location described herein. Late bids will not be accepted or considered and will be returned unopened.
15. Evaluation of Bids The City will select the lowest responsive and responsible Vendor whose bid best meets project requirements and offers the most comprehensive and cost-effective approach
16. Right of Refusal The Board reserves the right to reject any one or all bids, or any part of any bid, to waive any irregularities in any bid, and to make award in the best interest of the Board /City. Furthermore, the City reserves the right to hold the bid of the three (3) lowest Vendors for a period of sixty (60) calendar days from and after the time of the bid opening.
17. Award of Contract It is the intent of the Board to enter into a contract with a provider that will emphasize administrative efficiencies, and possess the capacity, infrastructure and organizational competence to perform required functions necessary for managed care under this bid.
Award recommendations made by the purchasing department are contingent upon an initial evaluation of the responsiveness of Contractor’s bid submission. Contractor’s qualifications to determine if the Contractor is a quality service provider. The Contractor’s policies and procedures may be evaluated as a further determination of quality.
The Board reserves the right to make award in the best interest of the Board /City.
The process of evaluating each Contractor’s bid may involve interviews with a random sampling of the Contractor’s current and previous customers. This is not an exclusive criterion for awarding the contract.
It is anticipated that contract(s) will be awarded on or before December 1, 2026.
SECTION 2 – SPECIFICATION & SCOPE OF WORK
1. Project Specification The Evansville Riverfront wall extends approximately 1,760 feet, with sections reaching 25 to 30 feet in height. All prospective bidders are responsible for verifying existing site conditions and confirming actual square footage prior to submitting a bid. Field verification is mandatory to ensure accurate pricing and material estimate
2. Scope of Work Overview The Contractor shall furnish all labor, materials, equipment, and services necessary to complete the full painting and protective coatings scope described below. All work must comply with manufacturer recommendations, industry standards, and City specifications.
Work includes, but is not limited to:
A. Surface Preparation
• Pressure wash all surfaces receiving new finishes.
• Mask and protect adjacent areas, structures, utilities, and landscape elements to prevent overspray, damage, or staining.
B. Concrete Finishes
• Apply two full coats of H&C Color Top Stain for Concrete in two colors, as specified by the city.
C. Handrails
• Spot-prime rusted areas using KEM Bond rust-inhibiting primer.
• Apply two coats of Sherwin-Williams Hi-Solids Polyurethane S/G to all handrails.
D. Galvanized Steel Components
• Spot-prime galvanized gates and steel elements using Macro poxy 626.
• Apply two coats of Hi-Solids Polyurethane S/G to all galvanized steel surfaces.
E. Chain Link Fencing
• Prime as required.
• Apply two coats of finish coating as directed.
F. Light & Speaker Racks
• Prime as needed.
• Apply two coats of Hi-Solids Polyurethane S/G.
G. Cleanup
• Remove and legally dispose of all masking materials, debris, and waste generated by the work.
• Restore all impacted areas to pre-construction conditions.
H. Alternate Work (Additive)
• Pressure wash all concrete seating areas not scheduled to receive new finishes
3. Contractor’s Compliance Acknowledgement
The Contractor shall comply with Indiana Code § 5-16-13, including all requirements governing public works contractor qualifications. Contractors must execute and submit the Contractor’s Acknowledgment form prior to the start of any work
4. Contract Term and Notice to Proceed Upon award, the department will provide:
• A notice of award
• A copy of the agreement
The Contractor must:
• Sign and return the agreement,
• Provide all required insurance documentation, and
• Complete all post-award document submissions within ten (10) calendar days of receiving the agreement.
Failure to meet this requirement may result in forfeiture of the bid bond unless the City determines a mutual resolution is appropriate.
Work must begin within ten (10) days of issuance of the Notice to Proceed.
5. Warranty Requirements The Contractor shall guarantee all improvements for two (2) years from the date of final acceptance.
The warranty shall cover defects in materials and workmanship, including, but not limited to, peeling, blistering, flaking, cracking, delamination, loss of adhesion, premature coating failure, and corrosion or substrate exposure resulting from inadequate surface preparation or improper application.
Upon written notification by the Owner of a warranted defect, the Contractor shall, at no additional cost to the Owner, properly prepare the affected areas and repair or recoat the defective work using materials compatible with the existing coating system.
The warranty shall not apply to damage caused by vandalism, impact, structural movement, substrate deterioration not attributable to the Contractor, or other conditions beyond the Contractor's control.
The Contractor shall comply with all coating manufacturer's surface preparation, environmental, application, curing, and dry-film-thickness requirements. The Contractor shall provide the Owner with the manufacturer's product data and warranty documentation prior to application.
If repairs are required, the Contractor must begin remedial work within 10 days of written notice unless additional time is authorized by the department in writing.
If the Contractor fails to begin repairs, the City may perform or procure corrective work and recover associated costs, including supervision and inspection expenses.
The Owner retains 90 days after the warranty period to identify and notify the Contractor of any qualifying defects.
6. Product Substitutions (“Or Equal”)
References to specific manufacturers or brand names are not intended to limit competition. They define the minimum standard of quality and performance. Contractors may submit proposed equivalents, subject to City approval.
7. Budget Constraints
If total project costs exceed available funding, the City reserves the right to either award the project in part or reject all bids.
8. Drug Testing & Licensing Requirements At the time of bid submission, Contractors must provide:
• A copy of the company’s Random Drug Testing Program (per Chapter 3.95 of City Code).
• Applicable Contractor Licenses for all trades participating in the project.
For bids under $10,000, the Contractor must still submit both items.
• If contractor has RBO prequalification for the current fiscal year they may include a copy of their current year prequalification letter issued by the City of Evansville – Vanderburgh County Purchasing Department in place of the drug policy and contractor license(s)
9. Required Insurance Coverage The Contractor must maintain the specified minimum coverage levels, including but not limited to:
• General Aggregate: $2,000,000
• Products & Completed Operations: $2,000,000
• Personal & Advertising Injury: $1,000,000
• Each Occurrence: $750,000
• Fire Damage (any one fire): $50,000
• Medical Expense (any one person): $5,000
Insurance certificates must:
• Name the City of Evansville as an additional insured,
• Be fully executed and submitted before work begins, and
• Comply with additional insurance requirements outlined in Section XI (Scope of Services).
10. Notice to Proceed & Liquidated Damages
If the Contractor fails to meet the required project timeline, the City will assess liquidated damages of $100 per day, unless the Board agrees that the circumstances leading to the delay were unforeseen and outside of contractors control.
11. Final Inspection & Invoicing Requirements
Upon completion, the Contractor must schedule a joint inspection with the City and architect.
The City will provide a list of deficiencies, which must be corrected before another inspection is requested.
Final acceptance occurs only after all deficiencies are resolved.
Only after Final Inspection may the Contractor submit an invoice reflecting approved work and any authorized change orders.
SECTION 3 – CONTRACTOR QUALIFICATIONS & REQUIREMENTS
1. Minimum Qualifications
The Contractor and all employees assigned to this project must conduct themselves in a professional manner at all times. Requirements include:
• Proper attire must be worn at all times; shirts are mandatory.
• Offensive language, inappropriate behavior, or unsuitable clothing will not be tolerated.
• The use of alcohol or illegal drugs is strictly prohibited on the job site.
These behavioral requirements apply throughout the entire duration of the contract.
2. Required Experience Documentation To demonstrate sufficient experience and capability, each Contractor must provide the following with its bid submission:
1. Three (3) local reference letters, documenting relevant project experience.
2. A manpower list identifying all personnel expected to work on the project.
3. A description of the company’s operational history, specifically the number of years the business has performed work similar in scope and complexity to this project.
These materials will be used to verify qualifications, assess capacity, and determine overall responsibility.
3. Non-Compliance Procedures If the Contractor fails to comply with any term or condition of the contract, the City will issue a written notice identifying the deficiency.
The Contractor will have four (4) days to correct the issue.
If the deficiency is not corrected within this period, the City may take one or more of the following actions:
• Terminate the contract and compensate the Contractor only for work performed up to the date of termination, minus any amounts owed to the City.
• Use City employees or hire another contractor to complete corrective measures. Costs incurred will be deducted from payments due to the Contractor.
• Pursue any additional remedies allowed by law or equity.
This section emphasizes the Contractor’s obligation to remain compliant and responsive throughout the project.
4. Invoice Submission Requirements All invoices submitted for payment must meet the following requirements:
• The invoice must clearly identify “Evansville Vanderburgh Levee Authority”.
• Invoices must be itemized and include the Contractor’s company name, address, and telephone number.
• Each invoice must include a unique invoice number that does not duplicate any previously submitted invoice.
• Failure to follow invoicing requirements may delay payment processing.
5. Insurance Requirements
The Contractor must maintain, for the full duration of the contract, all insurance coverage required under the specifications, including:
• General liability insurance, providing coverage for personal injury, occupational illness, accidental death, and property damage arising from Contractor or subcontractor operations.
o Minimum combined single limit: $1,000,000 per occurrence.
• Workers’ compensation insurance, as required by Indiana law, covering all employees performing work under the contract.
• The City of Evansville must be listed as an additional insured on all general liability policies.
Certificates of insurance must be submitted to the City’s Board of Public Works or Purchasing Department before work begins.
6. Responsibility for Damage to City or Private Property
If any property—including but not limited to pavement, sidewalks, vehicles, buildings, traffic equipment, or landscaping—is damaged as a result of the Contractor’s operations, the Contractor must:
• Immediately repair the damage at the Contractor’s own expense.
• Maintain a clean and safe work area at all times, free of debris and hazards.
If the Contractor fails to make required repairs promptly, the City or Levee Authority may perform the repairs and recover all associated costs from the Contractor.
18. Taxes The City of Evansville is exempt from federal, state, and local taxes and will not be responsible for any such taxes in connection with the award or performance of this contract.
19. Choice of Law and Venue Any and all actions or proceedings arising out of, or related to, this bid and any resulting contract shall be governed by and construed in accordance with the laws of the State of Indiana. Submissions in response to this solicitation by Vendor constitutes consent and stipulation to jurisdiction and venue in the courts of Vanderburgh County, Indiana, concerning all litigation and proceedings arising out of or related to this solicitation and any resulting contract.
SECTION 4 - GENERAL CONDITIONS
1. DEFINITIONS
The Contract Documents consist of the Contract, the Notice to Respondents, the Request for Bids/Solicitation, the Instructions to Respondents, the General Conditions, the Special Conditions, the Special Provisions, any Project Drawings, the Standard Drawings and the Specifications. The Standard Specifications of the Indiana Department of Transportation (INDOT), Current Edition, are referenced in the Contract Documents, and are incorporated by reference.
The Contract shall consist solely of all written terms of this written agreement, entered into by and between the Owner and by the Contractor in the performance of the Work and the payment therefore and the Contract Documents. This Contract and the Contract Documents supersedes any prior agreements, written or oral, between the Owner and the Contractor.
The following terms are used in these Contract Documents, and are defined as follows:
a) Project The entire improvement proposed by the Owner to be constructed in whole or in part pursuant to the Contract.
b) Owner The City of Evansville, acting by and through the lawful conduct of the appropriate Board or
Commission.
c) Contractor The person, persons, firms or corporations to whom the Contract is awarded by the
Owner, including all agents, employees, workmen or assignees of said Contractor.
d) Subcontractor A person, firm, or corporation other than the Contractor, who supplies labor, workmen and materials, or labor only, or work at the site of the Project at the request of the Contractor.
e) Work All work, including materials, labor, supervision, use of tools, etc., necessary to complete the
Project in full compliance with the terms of the Contract, including work performed by the Contractor and his Subcontractor(s).
f) Engineer The City Engineer of the City of Evansville, his employees, or assignees or a firm contracted to carry out architectural or engineering duties for a project
g) Surety The person, firm or corporation that has executed, as surety, the Contractor's Performance
Bond, securing the Contractor's performance of the Contract.
h) Affected County Vanderburgh County or an adjacent county.
i) E-Verify Program An electronic verification of work authorization program of the Illegal Immigration
Reform and Immigration Responsibility Act of 1996 (P.L. 104-208), Division C, Title IV, s.403(a), as amended, operated by the United States Department of Homeland Security or successor work authorization program designated by the United States Department of Homeland Security or other federal agency authorized to verify the work authorization status of newly hired employees under the Immigration Reform and Control Act of 1986 (P.L. 99-603).
j) Local Indiana Business A business whose principal place of business is in an Affected County; a business that pays a majority of its payroll (in dollar volume) to residents of Affected Counties; or a business that employees residents of Affected Counties as a majority of its employees.
The Owner, Contractor and Engineer are treated throughout the Contract Documents as if each were of the singular number and masculine gender. When the term Person or Persons is used, it shall be understood to include an Individual, a Firm, a Partnership, an Association, a Corporation, or other business entity.
When the terms Owner or Engineer are used, they shall be understood to mean the Owner and Engineer defined in b) and f) above, unless the wording clearly indicates another meaning.
2. INTENT OF CONTRACT DOCUMENTS
The provisions of the Contract Documents, the Specifications and the Project Drawings are complementary, and what is called for by any one shall be interpreted as being called for in all other writings, composing this Contract. The creation of the Contract Documents is to express the intentions of the parties with respect to the contract price the cost of all labor and materials, water, fuel, tools, plant, equipment, transportation and all other expense necessary for the proper execution and further to express the intent of the parties as to other issues relating to the manner by which the Work shall proceed. Words describing materials or Work which have a well-known technical or trade meaning, unless otherwise specifically defined in the Contract Documents, shall be construed in accordance with their recognized meanings.
Any Work shown on the Project Drawings and not addressed or included in the Contract Documents, or not addressed or included in the Specifications, shall be performed by the Contractor as if this Work was shown on the Project Drawings and included in the Specifications. If the Project Drawings and Specifications should be contradictory in any part, the Specifications shall govern. The Contractor shall advise the Owner in writing of any alleged omissions of Specification(s) prior to the initiation of any Work shown on the Project Drawings or called for in the Contract Documents.
3. CONTRACT DRAWINGS AND SPECIFICATIONS
All Work shall be executed in strict conformity with the Project Drawings and Specifications, and the Contractor shall do no Work without proper Project Drawings and Instructions. The Contractor shall be liable for all claims and costs arising from failure to perform Work without proper Project Drawings and Instructions.
Unless otherwise provided in the Special Conditions, the Owner will furnish to the Contractor, free of charge, all copies of the Project Drawings and Specifications reasonably necessary to carry out the Work.
Figured dimensions on the Project Drawings should be taken as correct but shall be checked by the Contractor before starting construction. Any errors, omissions, or discrepancies shall be brought to the attention of the Engineer, and his decision thereon shall be final.
Correction of errors or omissions on the Project Drawings or in the Specifications may be made by the Engineer when such correction can reasonably be considered necessary for the proper execution and completion of the Work. (See Section 23 "Changes in the Work")
All notes on the Project Drawings shall be followed. The Owner or Engineer shall furnish additional instructions, by means of Project Drawings or otherwise, necessary for the proper execution of the Work. All such Project Drawings and Instructions shall be consistent with the Contract Documents.
The Contractor represents and warrants that he has completely familiarized himself with and understands the terms and provisions of the Contract Documents, Project Drawings and Specifications prior to performing any Work.
4. OWNERSHIP OF DRAWINGS
All Project Drawings, Specifications and copies thereof furnished by the Owner or Engineer are the property of the Owner and are not to be used on any other Project. All Project Drawings and Specifications with the exception of one signed set for each party to the Contract, are to be returned to the Owner on completion of the Project.
5. CONTRACT SECURITY
Contractors responding to the solicitation are required to submit a Bid Bond or a Certified Check pursuant to the provisions of I.C. 36-1-12-4.5, in the amount of five percent (5%) of the total bid as a guarantee that all provisions of the specifications shall be met. The bond or certified check shall be made payable to the City of Evansville. All bonds or checks of unsuccessful respondents will be returned to the unsuccessful Contractor(s) after award of purchase by the Owner and to the successful Contractor(s) after the Performance Bond has been received and accepted.
The successful Contractor shall be required to execute a Payment Bond pursuant to the provisions of I.C. 36-1- 12-13.5 for the benefit of the Owner, the subContractors, material suppliers and other service providers in an amount equal to the contract price with such sureties as shall be acceptable to Owner, prior to the beginning of the work. The payment bond shall be binding on the Contractor, the subcontractor(s), and their successors and assigns for the payment of all indebtedness to all persons for labor and services performed, materials furnished or services rendered. The surety of the payment bond may not be released until one (1) year after the board’s final settlement with the Contractor.
The successful Contractor shall furnish and pay for an approved one hundred percent (100%) Performance Bond (Indiana Form 86A) pursuant to the provisions of I.C. 36-1-12-14 covering the faithful performance of the Contract and the payment of all obligations arising thereunder, with such sureties as the Owner may approve, prior to work beginning. The Performance Bond serves as a guarantee that all provisions of the solicitation, the specifications and resulting Contract shall be met. The surety of the performance bond may not be released until one (1) year after the date of the board’s final settlement with the Contractor.
6. OR EQUAL CLAUSE
Whenever, in any section of the Contract Documents, an article, material, or equipment is defined by describing a proprietary product, generic term or by using the name of a manufacturer or vendor, the term "or equal", if not inserted, shall be implied. The specific article, material, or equipment mentioned shall be understood as indicating the type, function, minimum standard of design, efficiency, and quality desired and shall not be construed in such a manner as to exclude manufacturer's products of comparable quality, design and efficiency.
7. CONTRACTOR'S INSURANCE
The Contractor shall not commence any Work under this Contract until he has obtained insurance of the types and in the amounts required by this Section, nor shall the Contractor allow any Subcontractor(s) to commence any Work on his Subcontract until all insurance required of the Subcontractor(s) has been obtained. The Contractor shall be responsible for verifying the acquisition and maintenance of said insurance by any Subcontractor(s) hired by the Contractor. The Contractor shall name the City of Evansville as an additional insured to all insurance contracts procured by the Contractor in accordance with this Section. All insurance procured by the Contractor is to be placed with insurers whom maintain a Best's rating of no less than A: VII. The Contractor shall be solely responsible for the payment of all premiums associated with any insurance required by Owner, and the Contractor shall be solely responsible for the payment of all deductibles to which such policies are subject, whether or not the Owner is an insured under the policy. The Contractor shall advise all Subcontractor(s) of the requirements set forth above.
Commercial General Liability (CGL) Insurance: The Contractor shall furnish and maintain, at the Contractor's expense during the life of the Contract, such Commercial General Liability Insurance as shall protect him, the Owner, as an additional insured, and any Subcontractor(s) performing Work under this Contract, from claims for damage for personal injury, occupational sickness or disease, including accidental death, as well as the claims for property damage, which may arise from operations under this Contract, whether such operations be by himself or by any Subcontractor(s), or by any one directly or indirectly employed by either of them. The amounts of such insurance shall be as required by law. The Owner shall have the right to reject the insurance carrier selected by the Contractor. No Work shall commence prior to the Owner receiving a certificate of insurance verifying the coverages to be provided as defined herein. In the absence of regulations, the amounts of coverage shall be as follows:
General Aggregate: Not Less Than $2,000,000 Products & Completed Not Less Than $2,000,000 Operations Aggregate: Not Less Than $2,000,000 Personal & Advertising Injury: Not Less Than $1,000,000 Each Occurrence: Not Less Than $1,000,000 Fire Damage (Any one fire): Not less Than $300,000 Medical Expense (Any one person): Not Less Than $5,000
Umbrella/Excess Liability: The Contractor shall furnish and maintain Umbrella and/or Excess Liability, over and above the limits noted above in the CGL section of this agreement, with limits of at least $3,000,000 per occurrence with a corresponding $3,000,000 Aggregate limit. This limit shall be reflected on a submitted Certificate of Insurance with all Additional Insured and Indemnification language to correspond and follow all underlying terms and conditions of the CGL policy.
Worker's Compensation Insurance: The Contractor shall furnish certificates from the Worker's Compensation Board of Indiana, or its successor, that he is fully covered by Worker's Compensation and Occupational Diseases insurance, on all Employees on the Project. The Contractor shall maintain said coverage for the life of the Contract. The same requirements pertain to any Subcontractor(s). The Contractor shall be responsible for verifying that all Subcontractor(s) have Workmen's Compensation and Occupational Insurance Coverage. No Work shall commerce prior to the Owner receiving a certificate of insurance verifying the coverages provided herein. For any work to be conducted or performed on or over navigable waters, the Workers Compensation certificate must include proof of coverage to include related to the United States Longshore and Harbor (USL&H) Workers Compensation Act as defined in U.S. Code 33, Chapter 18.
Errors & Omissions (E&O) Liability for Specified Contractor Types: In addition to provision of General Liability and Workers Compensation Insurance, for work to be performed by “professional” services entities (i.e. – Architects, Engineers, Surveyors, Inspection Services), proof should be provided indicating coverage for Professional Liability indicating limits of not less than $1,000,000 per occurrence with a corresponding $1,000,000 Aggregate limit.
Automobile Liability: The Contractor shall furnish and maintain, at his expense during the life of the Contract, automobile liability insurance, covering claims for damages because of bodily injury, death or property damage arising from the use of all motor vehicles engaged in operating within the terms of this Contract. The amounts of combined single limit coverage shall be not less than ($ 1,000,000) for any one occurrence, including hired and non-owned vehicles. All Subcontractor(s) of the Contractor shall have similar automobile liability insurance. The Contractor shall be responsible for verifying that all Subcontractor(s) have said automobile liability insurance.
Coverage 1 shall apply. No Work shall commence prior to the Owner receiving a certificate of insurance verifying the coverage provided herein.
Special Hazards: Special Hazards, as determined by the Owner, shall be covered by rider or riders in amounts to be agreed upon, to the Liability Insurance policy or policies required to be furnished by the Contractor, and all Subcontractor(s) employed by the Contractor, or by separate policies of insurance in the amounts as defined in the Special Conditions of the Contract Documents. All such special Hazards insurance coverage shall have the Owner as an additional insured. No Work requiring special hazard coverage shall commence until the Owner has received a certificate of insurance verifying the coverage required herein.
Builder's Risk Insurance: The Contractor, and all Subcontractor(s) employed by the Contractor, shall maintain Builder's Risk Insurance, "all risk" coverage, on the Project for the benefit of the Owner. The Contractor shall be responsible for verifying that all Subcontractor(s) have the required Builder's Risk Insurance coverage.
However, this provision shall not release the Contractor from his obligation to complete the Project, and the Contractor and his Surety shall be obligated to full performance of the Contract.
Subcontractor(s) Insurance: The Contractor shall require all Subcontractor(s) to secure and maintain in force during the term of this Contract, all such insurance coverages defined above. The Contractor shall verify the existence of all said insurance policies and coverages. No Work by a Subcontractor(s) shall commence prior to the Owner receiving a certificate of insurance verifying the coverage required herein.
Other Provisions: Any failure to comply with reporting provisions of the policies shall not affect coverage provided to the Owner, its officers, officials, employees and volunteers by the Contractor and Subcontractor(s).
The Contractor's and Subcontractor’s insurance shall apply separately to each insured against whom claim is made or suit is brought except with respect to the limits of the insurer's liability. The insurer shall agree to waive all rights of subrogation against the Owner, its officers, officials, employees and volunteers for losses arising from Work performed by the Contract for the Owner. The Contractor shall be responsible for notifying all insurance carriers of this contract provision and shall be liable to the Owner for any failure to so notify and advise any insurance carrier of this provision.
8. PROOF OF INSURANCE
The Contractor shall furnish the Owner with satisfactory proof of coverage of the insurance required, in a reliable company or companies to be approved by the Owner, licensed to do business in the State of Indiana, before commencing any Work. Such proof shall consist of certificates executed by the respective insurance companies, filed with the Owner. The certificates of insurance shall show the name and address of the Company, expiration date or dates, and the policy number or numbers. The Owner reserves the right to require complete, certified copies of all required insurance policies at any time.
Proof of insurance shall be maintained up to date, and failure to maintain adequate coverage and proof shall be deemed sufficient reason for cancellation of the Contract. All insurance shall provide that the policy shall not be canceled, terminated or modified unless thirty (30) days prior to such cancellation, termination or modification written notice is given to the Owner. No policy may be modified, terminated or canceled by the Contractor without the prior written approval of the Owner.
9. SHOP DRAWINGS AND SAMPLES
The Contractor shall submit, in a prompt manner, at least two copies of all shop or Project Drawings and schedules for every item of equipment or material to be incorporated in the Work, which is fabricated or manufactured off site, including those pertaining to structural and reinforcing steel, electrical, plumbing, carpentry, heating and ventilation. The Contractor shall make any corrections required by the Owner or Engineer and resubmit the required revised Project Drawings without delay. The Engineer's review of such Drawings shall extend only to determining the conformity of such equipment and materials with the general features of the Project Drawings and Specifications prepared by the Engineer
It shall be the responsibility of the Contractor to determine the correctness of all Specifications and dimensions and minor details of such equipment and materials so that they will fit into the completed Work, and so that when incorporated in the Work, correct operation will result. The Contractor shall furnish for approval all samples required by the Specifications. The Work shall be in accordance with approved samples.
10. PERMITS, SURVEYS AND COMPLIANCE WITH LAWS
The Contractor shall keep fully informed of Federal, State and Municipal laws, ordinances, regulations, codes and standards, or any other bodies having jurisdiction or authority, which in any manner may affect the conduct of the Work or the Work of any employee. The Contractor shall at all times observe and comply with all such laws, ordinances, regulations, codes and standards. The Contractor shall protect, indemnify, and exculpate the Owner and its representatives, against any civil claim or civil liability arising from or based on the violation or any such laws, ordinances, regulations, codes and standards whether by himself or his employees, even if such violation is due wholly or in part to violation of said laws, ordinances, regulations, codes or standards by the Owner or its representatives.
The Contractor shall give all notices, and procure and pay for all permits, licenses and bonds, necessary for the prosecution of the Work, as required by Municipal, State and Federal ordinances, regulations, codes and laws, unless specifically provided otherwise in the Special Conditions or the Specifications. If the Contractor observes that the Project Drawings and Specifications are at variance with rules, codes or laws, he shall promptly notify the Owner or Engineer in writing, and any necessary changes shall be made as provided in the Contract for changes in the Work. If the Contractor performs any Work knowing it to be contrary to such laws, ordinances, rules and regulations, and gives no notice to the Owner or Engineer, he shall bear all costs and damages, including but not limited to attorney's fees, arising from said Work.
The Owner will furnish all site surveys, unless otherwise provided. The Contractor shall provide construction staking, unless otherwise provided.
11. ROYALTIES AND PATENTS
The Contractor shall pay all royalties and license fees for any patented product used by him or incorporated in the Work. The Contractor shall defend all suits or claims for infringement of any patent right brought against himself or the Owner, and shall save the Owner harmless from liability or loss or damage of any nature or kind, including costs, expenses and attorney's fees arising from the infringement or allegation of infringement of any patent or patent right, or because of any royalty, fee or license for the use, arrangement or operation of any tools, machinery, appliances, devices or materials which may be used by the Contractor or furnished by him in fulfillment of the requirements of this Contract.
12. PROTECTION OF WORK AND PROPERTY
The Contractor shall continuously maintain adequate protection and security of the Project site and shall indemnify the property of the Owner and any adjacent property from injury, damage, loss or claim, including a claim for attorney's fees, arising in connection with this Contract. The Contractor shall exercise due diligence at all times in protection of persons and property from injury. The Contractor shall promptly notify the Owner of any accidents arising in the course of operations under the Contract causing bodily injury or property damage.
The Contractor and any Subcontractor(s) employed by the Contractor, will be responsible for any and all damage to person(s) or property, public or private, that may be caused by his operation in the performance of this Contract, and the Contractor shall defend any suit that may be brought against himself or the Owner on account of damage inflicted by his operations, and shall be liable for any attorney's fees incurred by the Owner, and any judgments awarded against the Owner, Contractor or Subcontractor(s) employed by the Contractor arising from such damage.
13. MATERIALS AND WORKMANSHIP
Unless otherwise stipulated, in writing and approved by the Owner, the Contractor shall provide and pay for all material, labor, water, tools, equipment, light, power, heat transportation and other facilities necessary for the execution and completion of the Work.
Unless otherwise stipulated in the Specifications, all workmanship, equipment, materials and articles incorporated in the Work shall be new and of the best grade of their respective kinds. When required by the Owner, the Contractor shall furnish satisfactory evidence as to the kind and quality of materials.
The Contractor shall at all times enforce strict discipline and good order among his employees and shall not employ on the Project any unfit person, or anyone not skilled in the Work assigned to him.
When required by the Specifications, or when called for by the Owner, the Contractor shall obtain the Owner's approval of the materials or articles to be used in the Work. The Contractor in obtaining this approval shall furnish the Owner full information concerning the materials or articles which he contemplates incorporating in the Work. Samples of materials shall be submitted for approval when so directed. Machinery, equipment, materials and articles installed or used without such approval shall be used at the risk of the Contractor. All materials and workmanship shall be guaranteed by the Contractor and the Surety for a period of three years from the date of final acceptance. The Contractor further guarantees the materials and workmanship of all Work performed by any Subcontractor(s) employed on the Project by the Contractor for a period of three (3) years from the date of final acceptance of the Work.
No material of any kind shall be installed in the Project until it has been inspected and accepted by the Engineer.
All material rejected shall be immediately removed from the site of the Work and not again offered for inspection. Any materials or workmanship found at any time to be defective shall be remedied at once regardless of previous inspections.
At any time during the course of construction of the Project, when, in the opinion of the Engineer, provisions of the Contract Documents are being violated by the Contractor, its employees, or any Subcontractor(s) hired by the Contractor, the Engineer will have the right and authority to order all construction to cease and require the removal and replacement of all defective Work. In the event the Engineer orders a cessation of any Work, the Contractor shall not proceed until arrangements satisfactory to the Engineer are made by the Contractor for resumption of the Work in compliance with the provisions of the Contract Documents. It shall not be construed as a waiver of defects if the Engineer shall not order the Work stopped or material removed, as the case may be.
The Contractor shall be liable for the cost of any defective Work performed by the Contractor or any Subcontractor(s) employed by the Contractor.
14. INSPECTION OF WORK AND TESTING OF MATERIALS
The Owner and Engineer shall at all times have access to the Work, and the Contractor shall provide proper facilities for access and for inspection of the Work. All material to be incorporated in the Work, all labor performed, and all tools, appliances and methods used, shall be subject to the inspection and approval or rejection of the Owner. Any Work rejected by the Owner by reason of defective materials, workmanship or that said Work fails to comply with the Contract Documents shall be repaired at the expense of the Contractor.
The Contractor, and any Subcontractor(s) hired by the Contractor, shall execute the Work only in the presence of the Engineer or his Inspector during normal Working hours unless provision has been made for Work on other shifts. The presence of the Engineer or inspector shall in no way relieve the Contractor of the responsibility of his Contract or be any warrant for the furnishing of bad materials or poor workmanship.
The inspection and supervision of the Work by the Engineer is intended to aid the Owner in determining whether the labor, materials, and workmanship being provided by the Contractor or a Subcontractor(s) hired by the Contractor are in compliance with the Contract Documents. Any inspection and supervision by the Engineer shall not operate to release the Contractor from any of his Contract obligations or be deemed as the acceptance of such Work.
All laboratory tests shall be made by a testing laboratory employed by the Contractor and approved by the Engineer. The cost of tests shall be paid by the Contractor. Unless otherwise provided in the Special Conditions, the Contractor shall furnish the materials to be tested, and incidental material and labor required at the site in connection with the tests, the costs of which shall be considered to be included in the price or prices for the Contract items.
Where in Contract Documents, laws, ordinances, codes, or the Engineer's instructions require any Work to be specially tested or approved, the Contractor shall give the Owner or Engineer timely notice of the readiness of the Work for inspection, and if the inspection…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .