This Request for Qualifications (RFQ) is issued by the City of Phoenix, Arizona Office of the City Engineer for Construction Manager at Risk (CMAR) services for the Estrella Civic Space Branch Library and Road Improvements project. The City seeks a qualified CMAR to provide preconstruction and complete construction services for a combined project involving the City's Parks and Recreation Department and Library Department located at 99th Avenue and Lower Buckeye Road. The project scope includes construction of a new 12,000 square foot branch library, adjacent parking with electric vehicle charging ports for a bookmobile, street improvements (traffic light, medians, bike lanes, turning lanes, sidewalks, and street lighting), landscape improvements, and irrigation relocation. The estimated construction cost is $9.7 million. The pre-submittal meeting is scheduled for 9:00 am on Tuesday, November 17, 2026, at Phoenix City Hall (also available via Microsoft Teams). Statements of Qualifications are due by 12:00 pm on Friday, December 4, 2026, submitted electronically through the City's Procurement Portal in PDF format with a maximum of 20 pages. Finalists will be notified for interviews on December 28, 2026, with interviews scheduled for January 13, 2027. Selection notification is expected in mid-January 2027, followed by a scope meeting in early February 2027. The selected firm will enter into a Guaranteed Maximum Price (GMP) contract and will be responsible for construction means and methods, subcontractor bid solicitation, and quality control.

The CMAR will assume delivery risk through a GMP contract submitted in MAG or CSI format and may self-perform limited work amounts while soliciting bids from prequalified subcontractors using the City's subcontractor selection process. Only firms with physical business locations within Maricopa County are eligible to meet Small Business Enterprise (SBE) subcontracting goals, which will be established prior to construction based on SBE subcontractor availability. The selection process is qualifications-based, with evaluation criteria weighted as follows: General Information (50 points, 11.9%), Experience and Qualifications of the Firm (100 points, 23.8%), Experience of Key Personnel (100 points, 23.8%), Understanding of Project and Approach (150 points, 35.6%), and Reference Checks (21 points, 5%), plus 600 additional points for interviews. Firms must hold appropriate Arizona contractor licenses as determined by the Arizona Registrar of Contractors prior to submittal and must provide current Experience Modification Rate (EMR) ratings and a bonding capacity statement from a Surety Company rated A- or better for the prior four quarters. No Arizona contractor license at the City of Phoenix is required. Arizona Revised Statute 32-1151 governs contractor licensing requirements for this project.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CITY OF PHOENIX, ARIZONA

OFFICE OF THE CITY ENGINEER

DESIGN AND CONSTRUCTION PROCUREMENT

REQUEST FOR QUALIFICATIONS

ESTRELLA CIVIC SPACE BRANCH LIBRARY (GO BOND)

AND ROAD IMPROVEMENTS

CONSTRUCTION MANAGER AT RISK SERVICES

OPENGOV ID NO. PA75200751 & LS71200119

RFQ Rev. 1/25 Page | 2

The City of Phoenix is seeking a qualified Construction Manager at Risk (CMAR) to provide preconstruction services and complete construction services for the ESTRELLA CIVIC SPACE

BRANCH LIBRARY (GO BOND) AND ROAD IMPROVEMENTS CONSTRUCTION MANAGER

AT RISK SERVICES project. The selected CMAR will work as a team with the designer of record and City staff to ensure an efficient design approach for the project. The project site is located at

99th Avenue and Lower Buckeye Road. The estimated construction cost is $9.7 million.

Project Description

This project includes work associated with two City departments: City of Phoenix Parks and

Recreation Department (Parks Department) and City of Phoenix Library Department (Library

Department). The CMAR will work to successfully integrate the two departments project goals under one CMAR agreement and as one project.

The Parks Department is seeking development of ½ street improvements located on north side of road at Lower Buckeye Road and 99th Avenue in Phoenix between Fire Station 62 and the

Pecan Promenade Shopping Center on Lower Buckeye Road. Improvements to include a new traffic light at 95th Avenue, center medians, west bound lanes, bike lane, turning lanes, Right of

Way to tie into park, street lighting, roadway signage and stripping, sidewalks and relocation of private curbing and drainage structure East of the Pecan Promenade entrance. The road leading into the park at 95th Avenue will need to be developed to connect to the entrance of the library parking lot. Within the park adjacent to Lower Buckeye Road and entrance to 95th Avenue, we will need irrigation relocation and landscape improvements.

The Library Department is seeking construction of a new 12,000 square foot branch library located near the intersection of W. Lower Buckeye Road and S. 99th Avenue in Phoenix, Arizona within the planned Sierra Estrella park. Project scope of work includes new library build, adjacent parking lot to accommodate library patrons, drought-tolerant landscaping and secure covered parking with electrical charging port for the Department’s bookmobile. The civic site is currently used as agricultural land, with a Police substation currently existing on the northwest corner of the site, and a new Fire Station recently completed on the southeast corner of the site along Lower

Buckeye Road to serve the Estrella Community.

The new 12,000 square foot library will provide the Estrella Community with much-needed amenities that include programming areas, meeting areas, study rooms, public computers, and library materials for its collection.

The Parks Department project and the Library Department project will need to be constructed concurrently and in close coordination with one another, as one depends on the other.

Scope of Work

The Construction Manager at Risk will begin with the firm in an agency support role for preconstruction services. The CMAR will assume the risk of delivering the project through a

Guaranteed Maximum Price (GMP) contract. The CMAR will be responsible for construction means and methods, and will be required to solicit bids from prequalified subcontractors to perform the work using the City’s subcontractor selection process. The CMAR may also compete to self-perform limited amounts of work. The GMP must be submitted in MAG or CSI format or it will not be accepted.

Page | 3

A. Preconstruction phase services by the CMAR may include the following:

• Collaborate with the Owner and Design Team during the design phase of the project

• Attend all project and team meetings as necessary to maintain the project objectives

• Support project team efforts for timely submit/retrieval of permits/approvals from various agencies

• Prepare and distribute all daily, monthly and weekly reports to executives and stakeholders

• Perform all preconstruction services for design phase which may consist of multiple package(s)

• Provide pre-construction services team to deliver a complete project including integrated technology specialties

• Collaboration with Owner and Design Team on project directory updates

• Coordinate work with Owner and Design Team to secure all permits and approvals from federal, state, county, and local utility authorities

• Collaborate with Owner and Design Team to validate and synchronize the scope, budget, and schedule

• Investigate and assess existing conditions and project constraints. Recommend additional investigative techniques to further identify and locate unforeseen existing conditions if necessary.

• Develop Guaranteed Maximum Price (GMP) Proposal package strategy and present alternate strategies to optimize sequence of construction

• Develop and implement in-house quality control procedure for review/approval of monthly progress payments by CMAR accounting department before submitting for City review

• Collaborate with the Owner and Design Team to meet project requirements, which include scope, budget, and schedule

• Coordinate with Owner and Design Team on communication plan and studies to lead to solutions for decision making process

• Perform design/constructability review of design documents at milestone review period

• Respond to Stakeholder design/constructability comments from milestone reviews

• Prepare construction cost estimates for all design phases and validate milestone deliverables

• Reconcile with 3rd party construction cost estimate(s) for each design phase milestone

Page | 4

• Perform value engineering / cost reduction efforts to optimize project budget

• Assist Design Team with efforts to identify private and public utility easements

• Perform pre-construction services to assure conformance with requirements of Title 34, Arizona Revised Statutes

• Participate in City process to establish Small Business Enterprise goals and implement process

B. Construction phase services by the CMAR may include:

• Construct new 12,000 square foot branch library and ½ street improvements located near the intersection of W. Lower Buckeye Road and S. 99th Avenue in Phoenix, Arizona within the planned Sierra Estrella park

• Coordinate preparation and print production of construction documents with Design

Team

• Manage process to pick up, scan and distribute copies of the permitted construction documents to prescribed project team members

• Consult with the City to meet all project requirements

• Develop, refine, and implement subcontractor selection plan and Construction

Management Plan

• Prepare time-scaled logic construction schedule, submit for City and Design Team review/comment, and update throughout project course

• Craft and issue with solicitation the subcontractor instructions to bidders

• Solicit subcontractor bid proposals, validate offers, and prepare bid tabulation for review

• Prepare and distribute Guaranteed Maximum Price (GMP) Proposal for City and Design

Team review and approval

• Evaluate operational impacts and work with stakeholders to minimize or eliminate disruptions

• Conduct CMAR construction progress meetings and other project meetings to prosecute the work

• Develop clear and concise Requests For Information (RFI) with corresponding construction documents as backup which clearly defines the nature of the request(s)

• Develop construction submittal schedule in coordination with Design Team and

Stakeholders consolidate input and prepare master submittal log for project

• Provide support role related to Design Team preparation of Construction Change

Directives (CCD) and Proposal Requests (PR) as needed and provide cost proposals

Page | 5

• Upload and archive of all project related documentation into the City’s Project

Management System – Unifier – which shall be used for ALL project record keeping and file transferring and sharing of record.

• Obtain required As-Built documentation to establish existing conditions and conduct field surveys, as needed

• Perform field inspection and prepare reports to ensure compliance with the project plans and specifications

• Perform reviews and provide input on sustainability evaluation criterion relative to City standards.

• Perform field inspection and prepare reports to ensure compliance with the project plans and specifications

• Prepare and submit progress payments in line with the monthly progress of the work

• Provide itemized cost detail as required in support of proposed potential change notifications and change orders and submit recommendations to City

• Prepare and submit punch list and record documents for Design Team review/approval

• Prepare Closeout submittal Log with metrics, as directed by the City, to provide comprehensive list of closeout documentation for City record archive

• Participate in the 11 ½ month warranty inspection.

• Maintain site safety personnel from preconstruction through project closeout and notify

City of any unsafe conditions observed at the construction site(s)

• Provide quality controls and maintain a safe work site for all project participants

• Maintain all project records in electronic format

Use of UNIFIER, an Application Service Provider (ASP) web-based project management database, may be required. The following information provides a guideline for utilization. Any questions related to the requirements of UNIFIER should be directed to the Project Manager.

• The CMAR will be required to maintain all project records in electronic format.

• The City provides an ASP web-based project management database which the CMAR will be required to utilize in the fulfillment of the contract requirements.

• The CMAR shall provide a computerized networked office platform with broadband internet connectivity.

• UNIFIER training will be provided through the City of Phoenix to firms under contract.

Small Business Enterprise (SBE) Requirements

Page | 6

Only firms whose physical business is located within Maricopa County are eligible to meet the

SBE subcontracting goal, which will be set prior to construction of this project. The final goal will be based on SBE subcontractor availability.

Pre-Submittal Meeting

A pre-submittal meeting will be held at 9:00 am, Phoenix time on Tuesday, November 17, 2026, at Phoenix City Hall, 200 West Washington Street, Phoenix, AZ 85003, Conference Room 5 West, 5th Floor AND via Teams. At this meeting, City staff will discuss the scope of work, general project requirements, and respond to questions from the attendees. It is strongly recommended that interested firms attend the pre-submittal meeting. Inquiries regarding the project scope outside of this pre-submittal meeting must be directed to the Contracts Specialist.

Pre-Submittal Meeting Teams Information:

https://teams.microsoft.com/meet/2579211929358800?p=yTryEOVPCprbpk7YhT

Meeting ID: 257 921 192 935 880 0

Passcode: yq6EN7YH

Statement of Qualifications Evaluation Criteria

A firm will be selected through a qualifications-based selection process based on the criteria below. Subcriteria are listed in order of importance in relation to project services. City of Phoenix project experience is not required.

No. Evaluation Criteria Scoring Method Weight (Points) https://teams.microsoft.com/meet/2579211929358800?p=yTryEOVPCprbpk7YhT

Page | 7

1. General Information

A. Provide a general description of the firm that is proposing to provide construction management services and general construction services.

Explain the legal organization of the proposed firm or team. Provide an organization chart showing key personnel.

B. Provide the following information:

1. List the Arizona contractor licenses held by the firm and the key personnel who will be assigned to this project.

Provide the contractor license number.

Reference the appropriate licenses held, if needed. In order to be considered for this project, the contractor must hold the correct license as deemed appropriate by the

Arizona Registrar of

Contractors prior to submitting a Statement of Qualifications (SOQ) for this project in accordance with

Arizona Revised Statute

§32-1151.

2. Identify the location of the firm’s principal office

Points Based 50

(11.9% of Total)

Page | 8 and the home office location of key staff on this project.

3. Identify any contract or subcontract held by the firm or officers of the firm, which has been terminated within the last five years. Identify any claims arising from a contract which resulted in litigation or arbitration within the last three years. Briefly describe the circumstances and the outcomes.

Page | 9

2. Experience and Qualifications of the Firm

A. Identify at least three comparable projects in which the firm served as either CMAR, agency

Construction Manager during design and construction phases

(without providing construction services), or

General Contractor. Special consideration will be given to firms that have provided

Construction Manager at

Risk services on similar successful projects. For each project identified, provide the following:

1. Description of the project

2. Role of the firm (specify whether Construction

Manager at Risk, Construction Manager or General Contractor. If

CMAR or General

Contractor, identify the percent of work self-performed. Also specify services provided during design phase, i.e. cost estimating, scheduling, value engineering, etc.)

3. Project’s original contracted construction cost and final construction cost

4. Construction dates

Points Based 100

(23.8% of Total)

Page | 10

5. Project owner

3. Experience of Key Personnel to be Assigned to This Project

A. For each key person identified, list their length of time with the firm and at least two comparable projects in which they have played a primary role. If a project selected for a key person is the same as one selected for the firm, provide just the project name and the role of the key person. For other projects provide the following:

1. Description of project

2. Role of the person

3. Project’s original construction cost and final construction cost

4. Construction dates

5. Project owner

B. List any proposed consultants, including key staff names and the experience and qualifications of these individuals.

Points Based 100

(23.8% of Total)

Page | 11

4. Understanding of the Project and Approach to Performing the

Required Services

A. Discuss the major issues your team has identified on this project and how you intend to address those issues.

B. Attached to this Request for

Qualifications is the City of

Phoenix general subcontractor selection plan

(see Exhibit A). Describe how you intend to implement this subcontractor selection plan including your recommendations for subcontractor trades to be selected by qualifications only vs. qualifications and bids; and discuss the benefit that your subcontractor selection plan provides to the project.

C. Describe your team’s project management approach and team organization during design and construction phase services. Describe systems used for planning, scheduling, estimating, and managing construction.

Briefly describe the firm’s experience on quality control, dispute resolution, and safety management.

Points Based 150

(35.6% of Total)

Page | 12

5. Reference Checks

Use the form provided in the

Attachments section to obtain at least three references. It is preferred no more than one be a

City of Phoenix project. If your firm has not completed prior projects with other agencies, you will not be penalized. It is recommended there be references outside the City of

Phoenix.

*These points are in addition to the

400 points for the SOQ.

Interviews are an additional 600 points. Scores from the SOQ evaluations carry over to

Interviews.

Points Based 21

(5% of Total)

Submittal Requirements

Electronic Submittal Process: Firms interested in this project must submit a Statement of

Qualifications (SOQ) electronically through the City's Procurement Portal at https://procurement.opengov.com/portal/phoenix.

Submittal requirements are as follows:

Vendor Information: All firms must be registered in the City’s Vendor Management System prior to submitting a proposal. The vendor number should be included on the cover of the

SOQ. Information on how to register with the City is available at:

https://www.phoenix.gov/financesite/Pages/EProc-help.aspx

If your firm is already registered with the City of Phoenix’s Procurement system, visit https://procurement.opengov.com/portal/phoenix to login and access the electronic solicitation.

Submittals:

• Experience Modification Rate (EMR) – provide current rating; the awarded company will be asked to provide verification upon contract execution.

• Submit only one SOQ electronically, in .PDF format only, addressing all evaluation criteria. No hard copies will be accepted.

• Clearly display the firm legal name, vendor number, project title, and project number on the cover of the SOQ.

https://procurement.opengov.com/portal/phoenix https://www.phoenix.gov/financesite/Pages/EProc-help.aspx https://procurement.opengov.com/portal/phoenix

Page | 13

• A maximum of 20 pages is permitted to address all content in the SOQ submittal.

(Maximum page limit includes evaluation criteria and all additional content. It does not include information sheet.)

• Submit electronically the Statement of Qualifications by 12:00 pm, Phoenix time, on

Friday, December 4, 2026.

• Page size must meet requirements of 8½” x 11”.

• Font size must not be less than 10 point.

• Content count:

o Each side of a page containing evaluation criteria and additional content will be counted toward the maximum page limit noted above.

o Pages that have project photos, charts and/or graphs will be counted towards the maximum page limit noted above.

o Front and back covers, information sheet, Table of Contents pages, and divider (tab) pages will NOT be counted toward the maximum page limit noted above, unless they include evaluation criteria and additional content that could be considered by the selection panel.

Information Sheet: Provide an information sheet that includes project title, OpenGov ID number, legal firm name (not a trade name), address, phone number, vendor number, and the name, title, email address and signature of your contact person for the project. Do not include any additional information.

Evaluation Criteria: Address the SOQ evaluation criteria.

Bonding Statement: As a separate PDF attachment, include a statement of the firm’s bonding capacity from a Surety Company (A- or better for the prior four quarters). This bond statement will not be counted towards the maximum number of pages.

Additional Content: Resumes and other information may be included (content shall be included within the permitted maximum page limit).

Note: All pages exceeding the specified maximum page limit will be removed from the submittal and not considered in evaluating a submitted SOQ.

Grounds for Disqualification

Please be advised that the following will be grounds for disqualification, and will be strictly enforced:

• Submitting a Statement of Qualifications for a different project.

• Violating the “Contact with City Employees” policy contained in this RFQ.

• Failure to provide additional documents due at time of submittal.

• Failure to provide bonding statement.

Page | 14

Selection Process and Schedule

The successful firm will be selected through a qualifications-based selection process. Interested firms will submit a Statement of Qualifications (SOQ). A Selection Panel will evaluate each SOQ according to the criteria set forth in Statement of Qualifications Evaluation Criteria above. Finalists from the SOQ evaluation will be invited to participate in detailed interviews. An invitation letter to each finalist will provide the evaluation criteria to be used during the interview presentation.

Interview evaluations to select the highest qualified firm include scores from the SOQ evaluation process. The City may conduct a due diligence review on the firm receiving the highest evaluation.

The City expects to create a final list of at least one, but not more than three firms for this project.

The City will enter into negotiations with the selected firm and execute a contract upon completion of negotiation of contract terms for City Council approval.

The following tentative schedule has been prepared for this project. Firms interested in this project must be available on the interview date specified below. The Pre-submittal meeting is not mandatory.

Pre-submittal Meeting 9:00 am on Tuesday, November 17, 2026

SOQs Due 12:00 pm on Friday, December

4, 2026

Firms Notified for Interview December 28, 2026

Interview January 13, 2027

Selection Notification Mid-January 2027

Scope Meeting Early February 2027

If the City is unsuccessful in negotiating a contract with the best-qualified firm, the City may then negotiate with the next most qualified firm until a contract is executed, or the City may decide to terminate the selection process. Once a contract is executed with the successful firm, the procurement is complete.

Firm(s) on the short list for interviews for this project will be notified directly by the City. Notification to all other firms on the status of a short list for this project will be posted on the City of Phoenix’s

Procurement Portal:

https://procurement.opengov.com/portal/phoenix

The firm selected for this project will be notified directly by the City. Notification to all other firms on the status of a selection on this project will be posted on the City of Phoenix’s Procurement

Portal:

https://procurement.opengov.com/portal/phoenix https://procurement.opengov.com/portal/phoenix/projects/316605/document?section=2997214

Page | 15

General Information

Citywide Capital Improvement Projects. Consulting and contractor services supporting the

City’s Capital Improvement Projects are procured under the authority of the City Engineer, currently located within the Street Transportation Department. Design and Construction

Procurement coordinates the citywide consulting and construction contracting procurement processes.

Changes to Request for Qualifications. Any changes to this Request for Qualifications

(RFQ) will be in the form of a Notification. The City of Phoenix shall not be held responsible for any oral instructions. Notifications are available on both the Current Opportunities and City's eProcurement Portal at https://procurement.opengov.com/portal/phoenix.

It shall be the responsibility of the registered RFQ holder to determine, prior to the submittal of the Statement of Qualifications, if a Notification has been issued. Registered

RFQ holders may refer to the web page or call the Contracts Specialist (listed below) to ascertain if a Notification has been issued for this project.

Alternate Format. For more information or a copy of this publication in an alternate format, contact O'cie Hendricks (602) 534-1423 - Voice or TTY 711. Requests will only be honored if made within the first week of the advertising period.

Release of Project Information/Public Records Request. The City shall provide the release of all public information concerning the project, including selection announcements and contract awards. Those desiring to release information to the public must receive prior written approval from the City. To submit a Public Records Request, visit phoenix.gov/prr.

City Rights. The City of Phoenix reserves the right to reject any or all Statements of

Qualifications, to waive any informality or irregularity in any Statement of Qualifications received, and to be the sole judge of the merits of the respective Statements of Qualifications received.

Contact with City Employees. This policy is intended to create a level playing field for all

Proposers, assure that contracts are awarded in public, and protect the integrity of the selection process. OFFERORS THAT VIOLATE THIS POLICY WILL BE DISQUALIFIED.

Beginning on the date the RFQ is issued and until the date the contract is awarded or the RFQ withdrawn, all persons or entities that respond to the RFQ, including their authorized employees, agents, representatives, proposed partner(s), subcontractor(s), joint venture(s), member(s), or any of their lobbyists or attorneys (collectively the Proposer), will refrain from any direct or indirect contact with any person (other than the designated Contract Specialist) who may play a part in the selection process, including members of the evaluation panel, the City Manager, Assistant

City Manager, Deputy City Managers, Department heads, the Mayor and other members of the

Phoenix City Council. As long as the RFQ solicitation is not discussed, Proposers may continue to conduct business with the City and discuss business that is unrelated to this RFQ solicitation with City staff.

Commencing on the date and time a solicitation is published, potential or actual proposers

(including their representatives) will only discuss matters associated with the solicitation with the

Mayor, any members of City Council, the City Manager, any Deputy City Manager, or any department director directly associated with the solicitation (including in each case their assigned staff, except for the designated procurement officer) at a public meeting, posted under the Arizona https://phoenix.gov/prr

Page | 16

Revised Statutes, until the resulting contract(s) are awarded or all offers or responses are rejected and the solicitation is cancelled without any announcement by the procurement officer of the City’s intent to reissue the same or a similar solicitation.

Proposers may discuss their proposal or the RFQ solicitation with the Mayor or one or more members of the Phoenix City Council, provided such meetings are scheduled through the

Contract Specialist (listed above), conducted in person at 200 W. Washington, Phoenix, Arizona

85003, and are posted as open meetings with the City Clerk at least twenty-four (24) hours prior to the scheduled meetings. The City Clerk will be responsible for posting the meetings. The posted notice shall identify the participants and the subject matter, as well as invite the public to participate.

Conflict of Interest. The City reserves the right to disqualify any Proposer on the basis of any real or apparent conflict of interest that is disclosed by the proposal submitted or any other data available to the City. This disqualification is at the sole discretion of the City. Any Proposer submitting a proposal herein waves any right to object now or at any future time, before any body or agency, including but not limited to, the City Council of the City of Phoenix or any court.

Protest Procedures. Firms responding to disqualification or a procurement outcome are referred to the Code of the City of Phoenix Chapter 2, Article XII, Section 2-187 to 2-190.4, which governs protest procedures utilized throughout the selection process. The procedures may be reviewed through the City of Phoenix website at:

http://www.codepublishing.com/az/phoenix/

A copy of the Protest Policy is also available online at:

https://www.phoenix.gov/administration/departments/streets/careers/business-opportunities.html

Questions - Questions pertaining to this selection process or contract issues should be submitted via the Procurement Portal.

Vendor Questionnaire

*Response required

*Response required http://www.codepublishing.com/az/phoenix/ https://www.phoenix.gov/administration/departments/streets/careers/business-opportunities.html

REQUEST FOR QUALIFICATIONS
Project Description
Scope of Work
Small Business Enterprise (SBE) Requirements
Pre-Submittal Meeting
Statement of Qualifications Evaluation Criteria
Submittal Requirements
Grounds for Disqualification
Selection Process and Schedule
General Information
Vendor Questionnaire

File details come from the government source that posted it. Updated .