Escambia_2025_GCCS_Expansion_Technical_Specifications_SS_9-26-2025.pdf

PDF 537 KB Posted

Attached to
Perdido Landfill 2025 Gas Collection & Control System Expansion
Solicitation number
PD 25-26.004
Issued by
Escambia County, Florida

About this file

The document is a technical specification for the 2025 Landfill Gas Collection and Control System Expansion project for Escambia County, Florida, located at the Perdido Landfill. The project involves expanding the existing landfill gas (LFG) collection system, which includes installing new extraction wells, header and lateral pipes, air supply lines, condensate discharge lines, sumps, pneumatic pumps, and associated appurtenances. The work encompasses comprehensive system components such as HDPE piping, wellheads, dewatering infrastructure, and related site restoration. The project will require construction staking, system layout, surveying, installing underground piping, supplying gas wellheads, connecting to existing systems, system start-up, testing, and providing comprehensive documentation.

The project specifications detail technical requirements for materials and installation, including specific pipe materials (HDPE and PVC), pressure testing protocols, welding procedures, and installation standards. The total estimated quantities include 7 LFG wellheads, 1,100 linear feet of 18-inch header pipe, 520 linear feet of 8-inch lateral pipe, 630 linear feet of 6-inch lateral pipe, 2,250 linear feet each of 3-inch dewatering and 2-inch air supply lines, and 12,500 square yards of sodding. The contract includes provisions for mobilization, surveying, pipe installation, well drilling, condensate management, and site restoration. While a specific total project cost is not directly stated, the specifications suggest a comprehensive approach to expanding the landfill's gas collection infrastructure with detailed technical and procedural requirements.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Perdido Landfill 2025 Landfill Gas Collection and Control System Expansion

Escambia County Waste Services Department 13009 Beulah Road, Cantonment, Florida, 32533

September 2025

Escambia County SUMMARY OF WORK 2025 Landfill Gas Collection and Control System Expansion 01 10 00-1

SECTION 01 10 00

SUMMARY OF WORK

PART 1 – GENERAL

1.01 PROJECT DESCRIPTION

A. The project work to be performed by the Contractor consists of furnishing all labor, materials, equipment, tools, transportation, services, incidentals, and performing all work necessary to complete the project, in place and ready for service in accordance with the Plans and Specifications prepared therefore and entitled “2025 Landfill Gas Collection and Control System Expansion”. The work generally includes but is not limited to the following items:

1. Construction staking/system layout/surveying prior to construction.

2. Installing below grade high-density polyethylene (HDPE) LFG laterals and header, air supply line, and dewatering discharge line. Header appurtenances also to be installed include, but are not limited to, blind flanges, and condensate sumps.

3. Installing dual dewatering discharge line cleanouts.

4. Supplying gas wellheads, including fittings, valves, tubing, hoses, clamps, regulators and filters, and related appurtenances.

5. Installing condensate sump and pump.

6. Existing Dewatering discharge and leachate cleanout tie-in, including excavating, backfill, placement of pipe, wellheads, fittings and related appurtenances.

7. Repairing access roads in areas impacted by construction activities.

8. Grading, seeding & sodding, and restoring site conditions (if applicable).

9. Connection of the GCCS Expansion to the existing GCCS.

10. System start-up and testing.

11. Conformance surveying

12. Providing as-built documentation (record drawings).

1.02 WORK SEQUENCE

Construction work is to be sequenced to accommodate work with any other contractors on site or County forces. Work shall be sequenced so that no existing vertical extraction

2025 Landfill Gas Collection and Control System Expansion 01 10 00-2 wells, or sections of the GCCS, are taken offline for an extended period of time at any time during the Work. Contractor is to install new sections of GCCS prior to disconnecting those limited sections indicated in the Contract Drawings for removal.

1.03 CONTRACTOR USE OF PREMISES

A. Limit use of premises for work, storage, and access to allow work by other contractors, owner occupancy, and normal landfill operations.

B. Work Days: As detailed in the County specifications, allowable work times shall be Monday through Friday from 7:00 a.m. to 5:00 p.m. and Saturdays 7 a.m. to 3 p.m., excluding Sundays and County observed Holidays. Contractor shall request in writing to the County 48 hours’ notice prior to Sunday or County observed Holiday work.

C. Access: No later than 10 days after notice to proceed, the Contractor shall arrange with the County a sequence of procedures, means of access, space for storage of materials and equipment, and use of approaches and roadways.

Contractor’s use of the premises shall be confined to the areas approved by the County.

D. Smoking: Smoking is prohibited at the Perdido Landfill.

E. Contractor shall not dispose any refuse on site without approval of the County and in accordance with Section 02 41 16, Refuse Handling, Storage, and Disposal.

F. Contractor shall coordinate with the County for available area to locate Contractor’s trailer. Non-potable water, septic tank, and electrical services are already available. If using the electrical service, the Contractor is responsible for coordinating with the electric company for any connections and pay for electrical services at no additional cost to the County.

1.04 COUNTY OCCUPANCY AND LANDFILL OPERATIONS

The Contractor shall cooperate with the County during construction operations to minimize conflicts with County work and facilitate County usage. The Contractor shall perform the work so as not to interfere with the County’s operations, maintenance, environmental monitoring, and other County activities at the site.

1.05 SITE CONDITIONS

A. Existing Grades: The existing grades may vary from those indicated on the Plans due to landfill settlement and ongoing filling operations.

B. Existing Features: The Contract Documents require the Contractor to field verify the location of existing features. Existing features include but may not be limited to the following: stormwater drainage structures and underground pipes, stormwater terraces and swales, leachate collection system cleanouts, sumps, 2025 Landfill Gas Collection and Control System Expansion 01 10 00-3 pump stations, electrical panels, forcemain, utilities, roads, guardrails, drainage culverts, monitoring wells and piezometers, fences, and buildings.

C. The Contractor shall enforce safety procedures to minimize hazards to workers, the public, and the environment.

1.06 ERRORS AND/OR OMISSIONS IN PLANS AND SPECIFICATIONS

The intent of the Specifications is to outline or indicate the items of work, or both, which cannot be readily shown on the Drawings and, further to indicate the types and qualities of materials. Drawings and specifications shall be considered as being complimentary and items or work mentioned or indicated in one and not in the other shall be included as if mentioned in both. Should Drawings disagree in themselves or with the Specifications the better quality or greater quantity of work or materials shall be estimated upon, and shall be provided.

PART 2 – PRODUCTS (Not Used)

PART 3 – EXECUTION (Not Used)

END OF SECTION

Escambia County MEASUREMENT & PAYMENT 2025 Landfill Gas Collection and Control System Expansion 01 20 00-1

SECTION 01 20 00

MEASUREMENT AND PAYMENT

PART 1 - GENERAL

1.01 DESCRIPTION

A. The Contractor shall receive and accept the compensation provided in the Contract as full payment for furnishing all labor, equipment, and materials and for performing all construction/operations necessary to complete the work as described in the Contract, and in full payment for all losses or damages incurred during the work, for any discrepancies between actual and estimated quantities, or from any unanticipated difficulties which may arise during the work until final acceptance by the County.

B. Payment for the various items on the Contractor’s Bid Form, as further specified herein, shall include all compensation to be received by the Contractor for furnishing all tools, equipment, supplies, and manufactured articles and for all labor, operations, supervision, overhead, and profit, and incidentals appurtenant to the items of work being described as necessary to complete the various items of the work all in accordance with the requirements of the Contract Documents, including all appurtenances thereto, and including all costs of compliance with the regulations of public agencies having jurisdiction, including Safety and Health Requirements of the Occupational Safety and Health Administration (OSHA) of the U.S. Department of Labor.

C. No separate payment will be made for any item that is not specifically set forth on the Contractor’s Bid Form and all costs therefore shall be included in the prices named on the Contractor’s Bid Form for the various appurtenant items of work.

Payment for complying with the safety requirements for construction on the work site shall be included in the contract unit price paid for the various items of work wherein it is required, and no separate payment will be made therefore.

D. The total Bid Amount shall cover all work required by the Contract Documents.

All costs in connection with the proper and successful completion of the work, including furnishing all materials, equipment, supplies, and appurtenances;

providing all construction equipment and tools; including all costs and expenses for taxes, commissions, transportation charges and expenses, permit fees, patent fees, royalties, handling and tests; and performing all necessary labor and supervision to fully complete the work shall be included in the bid. All work not specifically set forth as a pay item on the Contractor’s Bid Form shall be considered a subsidiary obligation of Contractor and all costs in connection therewith shall be included in the unit prices bid and/or the lump sum prices.

2025 Landfill Gas Collection and Control System Expansion 01 20 00-2

E. The quotations for the various items of work are intended to establish a total price for completing the work in its entirety. Should the Contractor feel that the cost for any item of work has not been established by the Contractor’s Bid Form, Contractor shall include the cost for that work in some other applicable Bid Item, so that his proposal for the project does reflect his total price for completing the work in its entirety.

F. All estimated quantities stipulated on the Contractor’s Bid Form are approximate and are to be used only (a) as a basis for estimating the probable cost of the work and (b) for the purpose of comparing the bids submitted for the work. The actual amounts of work done and materials under unit price items may differ from the estimated quantities. The basis of payment for work and materials will be the actual amount of work done and materials furnished unless it exceeds the estimated quantities in which case a change order must be approved prior to payment for quantities exceeding the estimated quantity.

G. The Contractor shall field verify all quantities and dimensions shown on the Drawings or contained in the Contract Specifications.

H. The Contractor shall be responsible for establishing contracts with its subcontractors, which have a measurement and payment in accordance with this Section. If the Contractor establishes a contract with its subcontractors, which is in conflict with this Section, any additional cost incurred will be borne by the Contractor.

I. Restoration is not a separate pay item but is considered to be an integral part of the work under the contract, and all contract bid prices include the cost of restoration necessitated by the work related to that bid item. Restoration includes existing structure and property, paving, stabilized roads, drainage piping and ditches, catch basins, head walls, yard culverts, driveways, lawns and ground areas, walkways, and irrigation systems, which are altered, removed or damaged during construction. Cleanup is an integral part of restoration.

1.02 COMPUTATION OF QUANTITIES

A. Measurement of quantities expressed as area shall be based upon a horizontal, planimetric projection to the work limits as determined by survey record drawings prepared by a surveyor licensed in the State of Florida. Cost of surveying shall be paid by Contractor, and incorporated into Bid Items, as appropriate.

B. Measurement of linear Items will be for quantities actually field installed to the specified work limits, based upon surveyed stations recorded along the straight or curved centerline of each respective Item. Measurement conducted by survey is to be conducted by the Contractor’s approved surveyor licensed in the State of Florida.

2025 Landfill Gas Collection and Control System Expansion 01 20 00-3

C. Payment will be made to the limits as specified in the Contract Documents. If the constructed limits are less than the specified limit, payment will be made to the actual limits of construction as shown on the Record Drawings. Payment for quantities that exceed the specified contract limits will only be made with the approval of the County with acceptable supporting documentation from the Contractor. Payment for quantities that exceed the Contract quantities can only be obtained through an approved Change Order.

D. No partial payments shall be made for the installation of items which have not been tested and approved by the Engineer.

E. Payment will be made monthly until completion of each unit price item based on quantity completed by Contractor and verified by the Engineer. Final payment will be based on quantity calculated from Record Drawings prepared by a surveyor licensed in the State of Florida and confirmed by field measurement by the Engineer.

F. Payment for Lump Sum items will be made as described for each individual lump sum Bid Item. The Contractor shall not rely on the estimated quantities given, but shall instead estimate all quantities for the item independently for the basis of their bid. No claim shall be made by the Contractor for deviations between the Contractor’s estimated quantity and the Engineer’s estimated quantity including the quantity required to complete the Work. The Contractor shall base their bid solely on the Contractor’s independently estimated quantity.

1.03 VARIATIONS IN ESTIMATED QUANTITIES

A. The quantities given in the Contract Documents are approximate only, and are given as a basis for the uniform comparison of bids. The County does not expressly, or by implication, agree that the actual amount of work will correspond therewith.

B. The Contractor must provide, for unit price work, a proposed contract price determined on the basis of estimated quantities required for each item. The estimated quantities of items are not guaranteed and are solely for the purpose of comparing bids. Each such unit will be deemed to include an amount for overhead, profit and indirect costs for each separately defined item.

1.04 BID FORM

A. The Bid Form for the items contained within this Section can be found in the contract documents.

2025 Landfill Gas Collection and Control System Expansion 01 20 00-4

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

3.01 MEASUREMENT AND PAYMENT

A. Item No. 001 – Mobilization/Demobilization (Lump Sum)

Measurement. Measurement for this item shall be on a lump sum basis based on percentage of work completed.

Payment. Payment for this item shall be on a lump sum basis as described below.

No price adjustments will be made for this item due to changes in the work. Item includes, but not limited to, performance of preparatory paperwork and construction operations, movement of personnel and equipment to the project site, safety equipment, furnishing and installing at the beginning of the project as well as removing and disposing at the conclusion of the project, required facilities to begin work on a substantial phase of the Contract.

The Contract Price for mobilization/demobilization shall be subject to the following provisions:

a. The maximum amount allowed to be bid for mobilization / demobilization is 5 percent of the total bid price

b. Partial payments for mobilization/demobilization will be made in accordance with the following schedule.

Condition or Percent of Total Contract

Amount Earned Allowable Percent of the Lump

Sum Price for the Item

Submittal/completion of items listed in Section 013010 prior to construction

10 percent total contract amount earned 40

25 percent total contract amount earned 60

50 percent total contract amount earned 80

100 percent total contract amount earned 100

The final payment for mobilization/demobilization will not be made until all temporary facilities, excess materials, temporary erosion and sedimentation controls, equipment, and appurtenances used to perform the Work and all remaining construction debris have been removed from the site. Additionally, this shall include the submittal of all final record drawings, record survey project

2025 Landfill Gas Collection and Control System Expansion 01 20 00-5 photos, release of liens, warranties, and other incidentals as specified as requirements of project close-out.

B. Item No. 002 – Project Survey (Lump Sum)

Measurement. Measurement for the Work specified in this item shall be based on the schedule below for payment and all Items related to survey the Work shall be included in the Lump Sum price.

Payment. Payment for this item shall be on a lump sum basis as described below.

No price adjustments will be made for this item due to changes in the work. This item will consist of all surveying and control required by the Contract Documents.

Surveying shall be performed as described in the technical specifications. This work includes establishment of appropriate local site benchmarks, baseline surveys, location of utilities, stakeout of elevation and positional information required to complete the construction, progress payment surveys, and obtaining all survey information required to compile Record (As-Built) Drawings as required by the Contract Documents. As-built drawings must be signed and sealed by a surveyor licensed in the State of Florida.

The Contract Price for Project Survey shall be subject to the following provisions:

a. Partial payments for surveying will be made in accordance with the following schedule.

Condition or Percent of Total Contract

Amount Earned Allowable Percent of the Lump

Sum Price for the Item

Preconstruction Survey 25

LFG System Survey 50

Final Survey - Record Drawings and As- Built signed and sealed survey as required

The following defines complete documents for the surveys notated above:

Preconstruction Survey: The preconstruction survey shall include a survey of the existing conditions within the limits of construction of the Gas Collection and Control System (GCCS) Expansion. The survey shall note all above grade structures, piping, and features which may or will be impacted by the work. The preconstruction survey shall include proposed location of landfill gas header and lateral pipes, stub out locations for future expansions, vertical wells, remote wells, access riser points, isolation valves, air release valves, header, horizontal collector and dewatering collector sumps, road crossings, connection points and tie-in to existing GCCS and dewatering discharge/leachate cleanout, sections to be

2025 Landfill Gas Collection and Control System Expansion 01 20 00-6 abandoned and removed, and any other improvement as part of the GCCS Expansion. Vertical well/boring locations to include Northing, Easting, ground surface elevation to determine any adjustments prior to drilling.

LFG System Survey: The LFG system survey shall include survey locations of the landfill gas header and lateral pipes, stub out locations for future expansions, vertical wells, remote wells, access riser points, isolation valves, air release valves, header, horizontal collector and dewatering collector sumps, road crossings, bollards, connection points and tie-in to existing GCCS and dewatering discharge/leachate cleanout, abandoned and removed sections, and any other improvement as part of the GCCS Expansion.

Final Survey - Record Drawings and As-Built: Following completion of the LFG Survey, the final survey will include all features of the project installed as part of the construction project and all existing features within the limits of construction.

The final survey shall include, but not limited to, GCCS components, all above grade structures, piping, sod limits, roadways, stormwater downchutes, and features that were impacted by the work.

The Contractor shall, throughout the project, maintain a redline set of construction drawings noting deviations or actual installed conditions for the GCCS Expansion.

As part of Final Completion, the Contractor must submit a complete set of final Record Drawings based on the redlines maintained throughout the project which identify the actual constructed conditions. These record drawings shall use the construction drawings as a base and show changes by cloud and strikethrough in electronic format (AutoCAD). The record drawings shall incorporate the surveys listed above and any other changes made to the components of the GCCS into the set so to create a single Record Drawing Set for the project. A draft Record Drawing set, in both hardcopy and AutoCAD format in accordance with the specifications, must be submitted to the County and Engineer for review in order to grant Substantial Completion. Final completion cannot be granted until certified Record Drawings (hardcopy and AutoCAD) signed and sealed by a Florida licensed Professional Engineer or Land Surveyor and the Project Record Documentation package is submitted to and approved by the County and Engineer.

The Record Drawings are critical to the County and must be accurate to receive approval by FDEP for operation of the facility.

Partial Surveys of Work: It is understood that the Contractor may elect to survey each section of the GCCS system separately. Partial surveys must be submitted to the Engineer to determine that the section the Contractor is requesting to continue working in meets the design requirements. The Contractor may not continue work until the partial survey is approved. Partial surveys are not required to be signed and sealed at the time of submittal, however, the partial surveys used to compile the complete survey for each of the surveys listed above, must not deviate from the partial survey submitted and the complete survey must be certified for submittal.

Payment for surveys will not be made until the complete, certified survey is submitted and approved. However, partial surveys may be used for payment of

2025 Landfill Gas Collection and Control System Expansion 01 20 00-7 work items such as soil and piping upon review, agreement, and approval by the County, Engineer, and CQA Representative.

C. Item No. 003 – 36-inch Diameter Bore with 8-inch Diameter SCH 80 PVC/HDPE SDR 11 Casing (Linear Foot)

Measurement. Measurement for this item shall be on an installed linear foot basis per specified landfill gas wells from existing ground surface to the bottom of the well bore as measured in the field by the Engineer.

Payment. Payment for this item will be at the contract unit price per linear foot installed. Payment will include all boring, stone, soil, bentonite, geotextile, reinforcement grate, backfilling, waste relocation to working face, health and safety requirements, PVC piping (solid and perforated), HDPE piping (solid), transition PVC/HDPE, connections, and fittings. Payment will also include purchasing and transportation of clean soil to the area of construction. Payment shall constitute full compensation for all material, labor, equipment, and work incidental thereto, necessary to complete this item in accordance with the Contract Documents. Price shall include the above-grade riser pipe at each well.

D. Item No. 004 – Drilling Rig Platform (Each)

Measurement. Measurement for this item shall be on a unit basis per each landfill gas well requiring a platform on the slope.

Payment. Payment for this item will be at the contract unit price per each drilling rig platform constructed for landfill gas well. Payment will include all activities associated with drilling rig platform construction including, excavation, loading, hauling, filling, and compaction of clean soil for the rig platform area near extraction well; and deconstructing the platform following the completion of drilling. Payment will also include purchasing and transportation of clean soil to the area of construction. The grades shall be restored following the removal of the platform. Payment shall constitute full compensation for all material, labor, equipment and work incidental thereto, necessary to complete this item in accordance with the Contract Documents.

E. Item No. 005 – Boring Refusal (Linear Foot)

Measurement. Wells that must be abandoned due to insufficient depth resulting from boring refusal shall be paid on a linear foot basis as measured in the field by the Engineer from existing ground surface to the bottom of the well bore. No boring may be abandoned without approval of the Engineer. Proper backfill of abandoned boreholes will include clean soil to surface.

Payment. Payment for this item will be at the contract unit price per linear foot of boring, and includes boring, and backfilling with clean soil. Payment will also include purchasing and transportation of clean soil to the area of construction.

Payment shall include all material, labor, equipment, waste relocation to working

2025 Landfill Gas Collection and Control System Expansion 01 20 00-8 face, backfill transportation, and work incidental thereto, necessary to complete this item in accordance with the Contract Documents.

F. Item No. 006 – 24-inch HDPE SDR 17 Condensate Sump with Pump Installation (Each)

Measurement. Measurement for this item shall be on a completed and installed unit basis.

Payment. Payment for this item will be at the contract unit price per installed condensate sump with pneumatic pump, including excavation, stone base support, backfilling, clean soil backfill material, dewatering efforts, fittings, sump and piping installation and connections, monitoring ports, supplied pump, placement and testing of the pump, pump data modules, pump air and discharge hoses, check and ball valves, connectors for air and condensate discharge line, testing and, connection to header pipe. Payment will also include purchasing and transportation of clean soil to the area of construction. Payment shall constitute full compensation for all material, labor, equipment, and work incidental thereto, necessary to complete this item in accordance with the Contract Documents.

G. Item No. 007 – 18-inch HDPE SDR 17 Landfill Gas Header Pipe (Linear Foot)

Measurement. Measurement for this item shall be on an installed linear foot basis per specified pipe size wherein measurement will be made in plan view from the LFG System Survey.

Payment. Payment for this item shall be at the contract unit price per horizontal linear foot of installed 18-inch HDPE SDR 17 header piping. Payment includes excavation, loading, hauling, and unloading of excavated waste from GCCS expansion trenches and disposing of at the active face; loading, hauling, and unloading of clean soil from adjacent construction activities and placed into GCCS expansion trenches; placing pipe bedding, clean soil backfill, soil compaction, fittings, piping, connections, pipe location markings, quality control surveying, testing, repairing stormwater swale and incidentals. Payment will also include purchasing and transportation of clean soil to the area of construction. Payment shall constitute full compensation for all material, labor, equipment and work incidental thereto, necessary to complete this item in accordance with the Contract Documents.

H. Item No. 008 – 18-inch Header Blind Flange (Each)

Measurement. Measurement for this item shall be on a completed and installed unit basis.

Payment. Payment for this item will be at the contract unit price per supplied unit.

Payment shall constitute full compensation for all material, labor, equipment, and

2025 Landfill Gas Collection and Control System Expansion 01 20 00-9 work incidental thereto, necessary to complete this item in accordance with the Contract Documents.

I. Item No. 009 – 8-inch HDPE SDR 17 Landfill Gas Lateral Pipe (Linear Foot)

Measurement. Measurement for this item shall be on an installed linear foot basis per specified pipe wherein measurement will be made in plan view from the LFG System Survey.

Payment. Payment for this item shall be at the contract unit price per horizontal linear foot of installed 8-inch HDPE SDR 17 lateral piping. Payment includes excavation, loading, hauling, and unloading of excavated waste from GCCS expansion trenches and disposing of at the active face; loading, hauling, and unloading of clean soil from adjacent construction activities and placed into GCCS expansion trenches; placing pipe bedding, clean soil pipe backfill material, soil compaction, fittings, piping, connections, pipe location markings, quality control surveying, testing, and incidentals. Payment will also include purchasing and transportation of clean soil to the area of construction. Payment shall constitute full compensation for all material, labor, equipment and work incidental thereto, necessary to complete this item in accordance with the Contract Documents.

J. Item No. 0010 – 6-inch HDPE SDR 17 Landfill Gas Lateral Pipe (Linear Foot)

Measurement. Measurement for this item shall be on an installed linear foot basis per specified pipe wherein measurement will be made in plan view from the LFG System Survey.

Payment. Payment for this item shall be at the contract unit price per horizontal linear foot of installed 6-inch HDPE SDR 17 lateral piping. Payment includes excavation, loading, hauling, and unloading of excavated waste from GCCS expansion trenches and disposing of at the active face; loading, hauling, and unloading of clean soil from adjacent construction activities and placed into GCCS expansion trenches; placing pipe bedding, clean soil pipe backfill material, soil compaction, fittings, piping, connections, stub-ups for connections at wellheads, pipe location markings, quality control surveying, testing, and incidentals. Payment will also include purchasing and transportation of clean soil to the area of construction. Payment shall constitute full compensation for all material, labor, equipment and work incidental thereto, necessary to complete this item in accordance with the Contract Documents.

K. Item No. 011 – 3-inch HDPE SDR 11 Dewatering Discharge Line in Common Trench (Linear Foot)

Measurement. Measurement for this item shall be on an installed linear foot basis per specified pipe size wherein measurement will be made in plan view from the LFG System Survey.

2025 Landfill Gas Collection and Control System Expansion 01 20 00-10

Payment. Payment for this item shall be at the contract unit price per horizontal linear foot of installed 3-inch HDPE SDR 11 Dewatering Discharge line in a common trench with the air supply line and header or lateral pipe. Payment includes fittings, piping, connections, stub-ups for connection at wellheads and isolation valves, stub-ups for connections at condensate sumps, pipe location markings, quality control surveying, testing, and incidentals. Payment will also include purchasing and transportation of clean soil to the area of construction.

Payment shall constitute full compensation for all material, labor, equipment and work incidental thereto, necessary to complete this item in accordance with the Contract Documents.

L. Item No. 012 – 2-inch HDPE SDR 9 Air Supply Line in Common Trench (Linear Foot)

Measurement. Measurement for this item shall be on an installed linear foot basis per specified pipe size wherein measurement will be made in plan view from the LFG System Survey.

Payment. Payment for this item shall be at the contract unit price per horizontal linear foot of installed 2-inch HDPE SDR 9 Air Supply Line in a common trench with the dewatering discharge line and header or lateral pipe. Payment includes fittings, piping, connections, stub-ups for connections at wellheads and isolation valves, stub-ups for connections at condensate sumps, pipe location markings, quality control surveying, testing, and incidentals. Payment will also include purchasing and transportation of clean soil to the area of construction. Payment shall constitute full compensation for all material, labor, equipment and work incidental thereto, necessary to complete this item in accordance with the Contract Documents.

M. Item No. 013 – Dual 3-inch Dewatering Discharge Line Cleanout (Each)

Measurement. Measurement for this item shall be on a completed and installed unit basis.

Payment. Payment for this item will be at the contract unit price per installed unit, including excavation, backfilling, flanges, valves, pressure gauge, fittings, spacers, piping installation and connections, testing, and other incidentals. Payment will also include purchasing and transportation of clean soil to the area of construction.

Payment shall constitute full compensation for all material, labor, equipment, and work incidental thereto, necessary to complete this item in accordance with the Contract Documents.

N. Item No. 014 – Tie-in to Existing System (Each)

Measurement. Measurement for this item shall be on a lump sum basis based on percentage of work completed for header, air, and dewatering discharge pipe connections to existing system. All other general connections are covered under respective pipe line item.

2025 Landfill Gas Collection and Control System Expansion 01 20 00-11

Payment. Payment shall include tie-in to existing GCCS as shown on the drawings at V-12. Payment includes excavation to expose flange tie-in to the existing 18-inch flange, 2-inch air and 3-inch dewatering discharge line as shown on the drawings. Payment includes excavation, pipe bedding, backfilling, soil compaction, fittings, piping, connections, quality control surveying, testing, and incidentals. Payment will also include purchasing and transportation of clean soil to the area of construction. Payment shall constitute full compensation for all material, labor, equipment and work incidental thereto, necessary to complete this item in accordance with the Contract Documents.

V. Item No. 015 – Leachate Riser Tie-in (Each)

Measurement. Measurement for this item shall be on a completed and installed unit basis.

Payment. Payment for this item shall be at the contract unit price per leachate cleanout location (2 locations total: LCR-4 and LCR-5) that is proposed to be connected to with LFG collection and/or dewatering discharge. Payment includes excavation, exposing all existing cleanouts and gas pipes, header and/or dewatering discharge pipe connections to existing leachate cleanout risers (LCR-4 and LCRS-5) as specified in the drawings, clean soil backfill material, pipe bedding, backfilling, soil compaction, branch saddle fittings, fittings, piping, pipe location markings, quality control surveying, testing, incidentals and repairs/testing to any damaged existing bottom liner system and piping (at no cost to the County).

Payment will also include purchasing and transportation of clean soil to the area of construction. Payment shall constitute full compensation for all material, labor, equipment and work incidental thereto, necessary to complete this item in accordance with the Contract Documents.

W. Item No. 016 – LFG Wellheads (Each)

Measurement. Measurement for this item shall be on a completed and installed unit basis.

Payment. Payment for this item shall be at the contract unit price per supplied unit, including new QED type orifice plate wellheads with fine tune control valve and all required connections, QED well caps, Solarguard flex hose, steel clamps, fittings, identification markings, monitoring/sample port covers, and HDPE reducers. Payment shall constitute full compensation for all material, labor, equipment, and work incidental thereto, necessary to complete this item in accordance with the Contract Documents.

X. Item No. 017 – Sodding (Square Yard)

Measurement. Measurement for this item shall be on a square yard basis wherein measurement will be made in plan view from the Final Survey. The area has been estimated to include a 50-foot wide section following the alignment of the LFG header, lateral, air, and dewatering discharge pipes along the side slopes. Areas

2025 Landfill Gas Collection and Control System Expansion 01 20 00-12 disturbed by the Contractor that are not required as part of the performance of the work, as determined by the Client and Engineer, will not be included in the quantity of payment.

Payment. Payment for this item shall be on a square yard basis for areas which have been disturbed by the Contractor estimating a 50-foot wide section following the alignment of the LFG header, lateral, air, and dewatering discharge pipes along the side slopes as shown on the Contract Drawings and in accordance with the Specifications. The pay item includes addition of topsoil, conditioning the topsoil with fertilizer and/or lime application, soil testing, fine grading, supplying and installing sod, anchoring/netting of sod, watering, mowing, replanting, repair of erosion, maintaining areas sodded through final acceptance of the work, and any other work necessary to produce a uniform stand of grass. No payment will be made for sod placed outside of the limits of construction shown on the Contract Drawings without prior approval of the Engineer. Payment of sod shall not relieve the Contractor of the need to maintain sod throughout warranty period.

Item No. Description Unit Estimated Quantity Unit Price ($) Amount ($)

001 Mobilization/Demobilization (Maximum of 5% of Total Bid Price) LS 1

002 Project Survey LS 1

003 36-inch Diameter Bore with 8-inch Diameter HDPE SDR 11 Casing LF 236

004 Drilling Rig Platform EA 5

005 Boring Refusal LF 25

006 24-inch HDPE SDR 17 Condensate Sump with Pump Installation EA 1

007 18-inch HDPE SDR 17 Landfill Gas Header Pipe LF 1,100

008 18-inch Header Blind Flange EA 2

009 8-inch HDPE SDR 17 Landfill Gas Lateral Pipe LF 520

010 6-inch HDPE SDR 17 Landfill Gas Lateral Pipe LF 630

011 3-inch HDPE SDR 11 Dewatering Discharge Line in Common Trench LF 2,250

012 2-inch HDPE SDR 9 Air Supply Line in Common Trench LF 2,250

013 Dual 3-inch Liquid Conveyance Line Cleanout EA 2

014 Tie-in to Existing System LS 1

015 Leachate Riser Tie-in EA 2

016 LFG Wellheads EA 7

017 Sodding SY 12,500

SUBTOTAL BID COST

Authorized Contingency (10% of Subtotal Cost)

TOTAL BID COST

2025 Landfill Gas Collection and Control System Expansion Escambia County - Perdido Landfill

Individual Costs for each item are a compiled average value based on recent bids, SCS's construction division pricing and estimated labor rates and completion time for each item. This is a preliminary cost estimate with a tolerance of +/- 20%.

Engineer's Estimate

Escambia County CONTRACTOR SUBMITTALS 2025 Landfill Gas Collection and Control System Expansion 01 30 10-1

SECTION 01 30 10

CONTRACTOR SUBMITTALS

1.01 PRE-CONSTRUCTION MEETING SUBMITTALS

A. At the pre-construction meeting, the Contractor shall submit the following items to the Engineer for review:

1. A preliminary schedule of Shop Drawings submittals and target dates for the project prior to start of construction.

2. Schedule of values that will be used for payment applications.

3. A list of any and all permits and licenses the Contractor shall obtain indicating the agency required to grant the permit and the expected date of submittal for the permit and required date for receipt of the permit.

4. Insurance certificates.

5. Health and Safety Plan.

1.02 SHOP DRAWINGS

A. Wherever called for in the Contract Documents, or where required by the Engineer, the Contractor shall furnish to the Engineer for review, one (1) copy of each submittal. The term “submittal” as used herein shall be understood to include detail design calculations, shop drawings, fabrication and installation drawings, lists, graphs, operating instructions, catalog sheets, data sheets, samples, and similar items. Unless otherwise required, said submittals shall be submitted to the Engineer, 15 days minimum prior to planned work activity to allow review of same by the Engineer, and to accommodate the rate of construction progress required under the Contract. Should any submittal be a part of any schedule milestone and is considered to be unacceptable by the County, the appropriate milestone shall be considered as not having been met until a complete and properly detailed submittal is received.

B. Attach to the front of each submittal a title sheet stating the pertinent product information submitted and reference the appropriate Specification Section and Paragraph. Apply stamp, signed or initialed, certifying that all quantities, dimensions, field construction criteria, materials, catalog numbers, and specified performance criteria has been reviewed in accordance with the requirements of the Work and the Contract Documents.

If this information is not provided with each submittal, the submittal shall be

2025 Landfill Gas Collection and Control System Expansion 01 30 10-2 returned to the Contractor without action taken by the Engineer, and any delays caused thereby shall be the total responsibility of the Contractor.

C. All shop drawings or other submittals shall be accompanied by the County’s standard submittal transmittal form, or other form mutually agreed upon at the pre-construction meeting. Any submittal not accompanied by the approved form or if all applicable items on the form are not completed, the submittal will be returned to the Contractor without action taken by the Engineer.

D. Normally, a separate transmittal form shall be used for each specific unrelated item or class of material or equipment for which a submittal is required.

Transmittal of a submittal of various items using a single transmittal form will be permitted only when the items taken together constitute a manufacturer’s “package” or are so functionally related that this helps speed the review of the group or package as a whole. A multiple-page submittal shall be collated into sets, and each set shall be stapled or bound, as appropriate, prior to transmittal to the Engineer.

E. Except as may otherwise be provided herein, the Engineer will return prints of each submittal to the Contractor, with comments noted thereon, within 15 calendar days following their receipt by the Engineer. It is considered reasonable that the Contractor shall make a complete and acceptable submittal to the Engineer by the second submission of a submittal item. The County reserves the right to withhold monies due the Contractor to cover additional costs of the Engineer’s review beyond the second submittal.

F. If a submittal is returned to the Contractor marked “NO EXCEPTIONS TAKEN,” formal revision and resubmission of said submittal will not be required.

G. If a submittal is returned to the Contractor marked “MAKE CORRECTIONS NOTED,” formal revision and resubmission of said submittal will not be required. However, Contractor shall address the comments/corrections in the final Work. Revisions indicated on submittals shall be considered as changes necessary to meet the requirements of the Contract Documents and shall not be taken as the basis of claims for extra work.

H. If a submittal is returned to the Contractor marked “AMEND - RESUBMIT,” the Contractor shall revise said submittal per Engineer’s comments and shall resubmit the required number of copies of said revised submittal to the Engineer.

I. If a submittal is returned to the Contractor marked “REJECTED - RESUBMIT,” the Contractor shall revise said submittal and shall resubmit the required number of copies of said revised submittal to the Engineer.

J. Fabrication of an item shall not commence before the Engineer has reviewed the pertinent submittals and returned copies to the Contractor marked either “NO EXCEPTIONS TAKEN” or “MAKE CORRECTIONS NOTED.” Revisions

2025 Landfill Gas Collection and Control System Expansion 01 30 10-3 indicated on submittals shall be considered as changes necessary to meet the requirements of the Contract Documents and shall not be taken as the basis of claims for extra work.

K. All Contractor submittals shall be carefully reviewed by an authorized representative of the Contractor prior to submission to the Engineer. Each submittal shall be dated, signed, and certified by the Contractor as being correct.

Contractor shall use the County-approved shop drawing stamp agreed upon at the pre-construction meeting. No consideration for review by the Engineer of any Contractor submittals will be made for any items which have not been so certified by the Contractor. All non-certified submittals will be returned to the Contractor without action taken by the Engineer, and any delays caused thereby shall be the total responsibility of the Contractor.

L. The Engineer’s review of the Contractor submittals shall not relieve the Contractor of the entire responsibility for the correctness of details and dimensions. The Contractor shall assume all responsibility and risk for any misfits due to any errors in the Contractor submittals. Any fabrication or other work performed in advance of the receipt of approved submittals shall be entirely at the Contractor’s risk and expense. The Contractor shall be responsible for the dimensions and the design of adequate connections and details.

M. Product Data

1. Submit only pages which are pertinent; mark each copy of standard printed data to identify pertinent products, reference it to Specification Section and Paragraph number. Show reference standards, performance characteristics, and capacities; dimensions; and required clearances.

2. Modify manufacturer’s standard schematic drawings and diagrams to supplement standard information and to provide information specifically applicable to the Work. Delete information not applicable.

3. Failure to follow the guidelines in paragraphs 1 and 2 above shall be grounds for rejection of Contractor submittals.

N. Contractor shall notify Engineer in writing, at time of submittal, of proposed deviations from requirements of Contract Documents.

1.03 CONTRACTOR’S PROJECT SCHEDULES

A. The schedule shall be comprehensive, covering both activities at the site of the Work and offsite activities such as design, procurement, and fabrication. The schedule shall be orderly and realistic and shall be revised as necessary to meet this requirement. The Contractor shall promptly advise the County and Engineer of any occurrence that may impact the schedule. No revision to the schedule can be made without approval from the County and Engineer.

2025 Landfill Gas Collection and Control System Expansion 01 30 10-4

B. The detailed schedule and each revision thereof shall be subject to approval by the County and Engineer for conformity with the requirements of the Contract Documents. The Contractor shall assist the County and/or Engineer in reviewing and evaluating each schedule furnished. Disapproved schedules returned to the Contractor shall be revised to correct the defects noted and shall be resubmitted to the County within five (5) calendar days after receipt.

C. When required to perform and complete the changed Work in accordance with the revised schedule, the Contractor shall provide additional labor, materials, equipment, or other factors of production in excess of those in use before the changed Work was ordered.

1.04 SAMPLES

A. Unless otherwise specified, whenever in the Specifications samples are required, the Contractor shall submit one (1) sample of each such item or material to the Engineer for approval at no additional cost to the County.

B. Samples, as required herein, shall be submitted for approval a minimum of fifteen

(15) working days prior to ordering such material for delivery to the job site and shall be submitted in an orderly sequence so that dependent materials or equipment can be assembled and reviewed without causing delays in the Work.

C. All samples shall be individually and indelibly labeled or tagged, indicating thereon all specified physical characteristics and manufacturer’s names for identification and submittal to the Engineer for approval.

D. Unless otherwise specified, all colors and textures of specified items will be selected by the County from the manufacturer's standard colors and standard product lines.

1.05 RECORD DRAWINGS

A. Contractor’s Record Drawings shall be maintained in accordance with this Section. The Contractor shall keep and maintain at the job site one set of draft Redline Drawings.

1. On these, the Contractor shall mark all project conditions, locations, configurations, and any other changes or deviations which may vary from the details represented on the original Contract Drawings, including buried or concealed construction and utility features which are revealed during the course of construction.

2. Special attention shall be given to recording the horizontal and vertical location of all buried utilities that differ from the locations indicated or which were not indicated on the Contract Drawings.

2025 Landfill Gas Collection and Control System Expansion 01 30 10-5

3. Redline Drawings shall be supplemented by any detailed sketches or typewritten changes to the specifications, as necessary or directed, to indicate fully the Work as actually constructed.

4. These master Redline Drawings shall be the Contractor’s representation of as-built conditions, including all revisions made necessary by addenda, change orders, and the like.

5. Redline Drawings shall be maintained up-to-date during the progress of the Work and available for inspection by the Engineer.

B. The Contractor shall include a survey site plan and pipe route survey table with the Redline Drawings showing coordinates and elevations of all wells, condensate traps, valves, etc., and piping installed.

1. Piping shall be located every 50 feet and at grade breaks and changes in pipe slope and direction, fittings, tie-ins, appurtenances, etc., as required for the conformance survey.

2. For pipe runs of 100 feet or less, the pipe shall be located a minimum of every 20 feet.

3. Coordinates and elevations shall be included in the survey for pipe fittings, changes in pipe slope and direction, valves, buried flanges, appurtenances and other similar connections to the header piping, and the ground surface at each well and appurtenance, and for all pipe location shots.

4. All locations shall be shown in the coordinate system identical to that used for the Construction Drawings.

5. A Florida Licensed Professional Surveyor shall certify all survey work pertaining to the Record Drawings.

C. Redline Drawings shall be accessible to the Engineer at all times during the construction period and shall be delivered to the Engineer upon Substantial Completion of the Work.

D. Requests for partial payments will not be approved if the Redline Drawings are not kept current and not until the completed Redline Drawings showing all variations between the Work as actually constructed and as originally shown on the Contract Drawings or other Contract Documents have been inspected by the Engineer.

E. Final payment will not be approved until the Contractor -prepared Record Drawings have been approved by the Engineer.

F. Upon Substantial Completion of the Work and prior to final acceptance, the Contractor shall complete and deliver a preliminary set of Record Drawings and

2025…