This document is an Addendum to a Request for Qualifications (RFQ) issued by the Texas Water Development Board (TWDB) for services to study two brackish aquifers in Texas. The RFQ is for Project 1, a study on the Ellenburger-San Saba and Hickory aquifers, and Project 2, a study on the Yegua-Jackson Aquifer. The RFQ states that the maximum total project cost for each of the two studies will not exceed $400,000.00. The RFQ includes a schedule of events with a proposal submission deadline of 5:00 pm CST. Respondents are required to submit separate Statements of Qualifications for each of the two projects, but are not required to pursue both.
The addendum provides clarification that the $400,000.00 project cost applies separately to each of the two studies, not a combined total. It also confirms that respondents can request a copy of the Estepp 1998 report mentioned in the RFQ. The contract opportunity is funded by the state of Texas and impacts the jurisdictions of Travis County and the City of Austin.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions & Answers Addendum Solicitation No. 580-24-RFQ-0018
If two or more similar questions are submitted (i.e., redundant questions), it is best practice to either provide the exact same answer to both questions or answer the first question and then include a cross reference to the first answer when responding to the second question.-
REQUEST FOR QUALIFICATIONS NO. 580-24-RFQ-0018
FOR
SERVICES TO STUDY BRACKISH AQUIFERS IN TEXAS
ADDENDUM 1 – QUESTIONS AND ANSWERS
1. Question: The cover of the RFQ lists 5pm and the schedule on page 14, section 4.2 Proposal Submission, lists 4pm. Can you confirm the time the submittal is due?
TWDB Response: Please see the corrected solicitation in ESBD. The time has been changed in the schedule of events to 5:00 pm CST.
2. Question: Page 8, section 2.5 Compensation. “The maximum total project cost will not exceed $400,000.00.” Can you clarify if the $400,000.000 project cost is per aquifer or both combined?
TWDB Response: Each of the two projects 1) the Llano Uplift aquifers and 2) the Yegua-Jackson Aquifer has a project cost not to exceed $400,000.00.
3. Question: On page 38 of Attachment 1: Bracs Database, Section: Interpreting total dissolved solids from geophysical well logs. “A number of geophysical well log interpretation techniques are described in, a copy of which is available upon request:
Estepp, J.D., 1998, Evaluation of ground-water quality using geophysical logs: Texas Natural Resource Conservation Commission, unpublished report, 516p.” Can we request a copy of the Estepp report?
Questions & Answers Addendum Solicitation No. 580-24-RFQ-0018
If two or more similar questions are submitted (i.e., redundant questions), it is best practice to either provide the exact same answer to both questions or answer the first question and then include a cross reference to the first answer when responding to the second question.-
TWDB Response: Yes. Please email kristie.laughlin@twdb.texas.gov to request a copy of the Estepp 1998 report.
4. Question: RFQ No. 580-24-RFQ-0018 references two (2) Brackish Aquifer studies referred to as "Project". The RFQ states that the maximum total project cost will not exceed $400,000. Can you kindly confirm whether this is per study or a total combined project cost for both studies?
TWDB Response: Each of the two projects 1) the Llano Uplift aquifers and 2) the Yegua-Jackson Aquifer has a project cost not to exceed $400,000.00.