This document is a Request for Qualifications (RFQ) issued by the City of San Antonio Public Works Department for a Construction Manager at Risk (CMAR) firm to provide pre-construction and construction services for the renovation and expansion of the existing 11,758 SF Carver Branch Library located in San Antonio, Texas. The project has an approximate construction budget of $8.4 million. The CMAR will provide preconstruction services during the design process and serve as the principal general contractor, assuming the risk of delivering the project within a Guaranteed Maximum Price. Key responsibilities during preconstruction include cost modeling, scheduling, constructability reviews, and value engineering. During construction, the CMAR will be responsible for managing subcontractors, quality control, and coordination with the City and other stakeholders. The City will shortlist up to five CMAR firms based on the responses to this RFQ, and those firms will then be invited to participate in the second phase of the procurement process through a Request for Proposals.
The RFQ outlines the evaluation criteria the City will use to assess the qualifications of respondents, including the CMAR's experience, project approach, experience in the San Antonio region, and compliance with the City's Small Business Economic Development Advocacy (SBEDA) program requirements. The City is subject to the SBEDA program and will establish appropriate subcontracting goals for the project. Respondents must also comply with certain state law requirements, such as not boycotting Israel, certain energy companies, or discriminating against the firearms industry.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| ESBD_File_345502_Addendum II RFQ Final.pdf | ||
| ESBD_File_345502_Addendum I Final.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUEST FOR QUALIFICATIONS
(RFQ)
CONSTRUCTION MANAGER AT RISK
FOR
CARVER BRANCH LIBRARY RENOVATION
RFQ: 2024-042 | WBS: 23-04032
Release Date: December 18, 2023 Submittals Due: February 9, 2024, at 10:00 AM Central Time (CT)
This solicitation has been identified as High-Profile.
PROHIBITED CAMPAIGN CONTRIBUTIONS
Notice Regarding Prohibition on Campaign or Officeholder Contributions for Individuals and Entities Seeking High-Profile Contracts. Under Section 2-309 of the Municipal Campaign Finance Code, the following are prohibited from making a campaign or officeholder contribution to any member of City Council, candidate for City Council or political action committee that contributes to City Council elections beginning on the *10th business day after a contract solicitation has been released through the 30th calendar day following the approval by City Council (“blackout” period):
(1) Any individual seeking a high-profile contract;
(2) Any owner, officer, officer of board, and executive committee member of an entity seeking a high-profile contract, excluding board officers and executive committee members of 501 (c)(3), 501(c)(4) and 501 (c)(6) non-profit organizations not created or controlled by the City whose board service is done strictly as a volunteer with no financial compensation and no economic gain from the non-profit entity;
(3) The legal signatory of the high-profile contract;
(4) Any attorney, lobbyist or consultant hired or retained to assist the individual or entity in seeking a high-profile contract;
(5) Subcontractors hired or retained to provide services under the high-profile contract; and
(6) Any first-degree member of the household of any person listed in (1), (2), (3) or (5) of this subsection.
A high-profile contract cannot be awarded to the individual or entity if a prohibited contribution was made by any of these individuals during the “blackout” period.
*For this solicitation, the first-day contributions are prohibited is Wednesday, January 10, 2024.
The first day contributions may be made is the 31st day after the contract is approved at a City Council “A” Session.
RESTRICTIONS ON COMMUNICATIONS
In accordance with and as authorized by Section 2-61 of the City Code, the following restrictions on communications apply to this solicitation: Respondents are prohibited from contacting 1) City officials, as defined by §2-62 of the City Code of the City of San Antonio, regarding the RFQ or submittal from the time the RFQ has been released until the contract is posted for consideration as an agenda item during a meeting designated as an A session; and 2) City employees from the time the RFQ has been released until the contract is approved at a City Council “A” session.
Restrictions extend to “thank you” letters, phone calls, emails and any contact that results in the direct or indirect discussion of the RFQ and/or submittal submitted by Respondent.
Violation of this provision by Respondent and/or its agent may lead to disqualification of Respondent’s submittal from consideration.
For additional information, see the section of this RFQ entitled “Restrictions on Communication”.
Construction Manager At Risk for Carver Branch Library Renovation
(RFQ: 2024-042)
TABLE OF CONTENTS
Section Section Name Page
I. Background 3 II. Scope of Work, Project Objectives and General Requirements 3 III. Schedule of Events 5 IV. Pre-Submittal Conference 5 V. RFQ Submittal Requirements and Evaluation Criteria 5 VI. Submission Instructions 12 VII. RFP Evaluation Criteria for Shortlisted Firms 12 VIII. Amendments to RFQ 12 IX. Restriction on Communications 13 X. Award of Contract and Reservation of Rights 14
Exhibit # RFQ Exhibits Exhibit A Construction Manager at Risk Contract Template - Exhibit B General Conditions - Exhibit C Insurance Requirements - Exhibit D Wage Decision - Exhibit E SBEDA Solicitation Language -
Form # Required Forms Respondent’s submittal must contain the following documents.
Required Forms must be uploaded individually in CivCast.
Form 1 Submittal Checklist and Table of Contents - Form 2 RFQ Submittal Cover/Signature Sheet - Form 3 Contracts Disclosure Form - Form 4 Litigation Disclosure Form - Form 5 SBEDA: Subcontractor/Supplier Utilization Commitment Form - Form 6 Key Personnel Commitment Form -
Carver Branch Library Renovation
RFQ: 2024-042 | WBS: 23-04032
I. BACKGROUND
The City of San Antonio (City) Public Works Department is seeking an experienced Construction Manager at Risk (hereafter referred to as “CMAR”) firm with demonstrated technical capabilities and civil construction experience to provide Pre- Construction and Construction services for the Carver Branch Library Renovation. The CMAR firm will be integrated into a city-led team as part of a progressive Construction Manager at Risk delivery method. The operational complexity of this project will require the CMAR to provide specific expertise and specialty technical services for the project to be successful.
This Request for Qualifications (hereafter referred to as “RFQ”) is the first of a two-phase solicitation process. Through the first phase of the solicitation process, the City anticipates shortlisting up to five (5) CMAR firms for project, that submit responses to this RFQ. The City reserves the right to shortlist fewer teams, depending on qualifications and the number of submittals. Only the shortlisted Respondents will be eligible to participate in the second phase of the solicitation process, which will be initiated by the City’s issuance of a request for proposals (RFP) and may include other procurement-related activities as will be described in the RFP.
The City is subject to the City of San Antonio Small Business Economic Development Advocacy (SBEDA) Program.
Competitive bidding of work packages is required.
II. SCOPE OF WORK, PROJECT OBJECTIVES, AND GENERAL REQUIREMENTS
Scope of Work:
This project will consist of the renovation and expansion of the existing 11,758 SF Carver Branch Library, located at 3350 E.
Commerce, SA TX 78220. The construction budget is approximately 8.4 million dollars. The Carver Branch Library was designed by Norcell D. Haywood, the first licensed African-American architect in San Antonio, and a prominent community professional. The original library was constructed in 1973, and was renovated in 1994 and again in 2006. A parking lot expansion and outdoor playscapes were added in 2012. The goal for the current building renovation is to create attractive, user-friendly spaces that respond to the needs of the library users. This improved facility will enhance existing areas of the library and introduce new resources to serve the community.
The CMAR will provide preconstruction services throughout the design process of the Project, the renovation and addition to the Carver Library. The CMAR will serve as the principal general contractor for construction of the Project. The CMAR will assume the risk of delivering the Project within a Guaranteed Maximum Price.
During the pre-construction period, which includes design development, construction documents preparation, procurement and permitting, the CMAR will work with the Public Works Department to provide construction cost modeling of the Project, including but not limited to, updates at major milestones of design; scheduling of all aspects of the Project, including City tasks and outside agencies; constructability reviews; cost trend log updates; and cost savings/value engineering recommendations. The CMAR will support the City in establishing a final construction budget for the Project. The CMAR and Design Consultant will then work collaboratively throughout the remaining design and preconstruction period to ensure that the Project remains within the budget and will regularly report back to the Public Works Department.
The CMAR will be responsible for quality control and the Public Works Department team will be responsible for quality control oversight.
Preconstruction Phase Services: The City anticipates that during the preconstruction design phase, the CMAR will be required to provide certain services, including but not limited to:
A. Developing a critical path method project schedule for each phase of the Project.
B. Submitting a baseline schedule and periodic monthly schedule updates.
C. Participating in weekly coordination meetings and Project workshops with the City and the Design Consultant, and the
Public Works Department.
D. Preparing and maintaining a Project cost model and submitting detailed, open book cost estimates as the design is advanced (including, at a minimum, at the mid-point and completion of design development and 40% construction documents, at 70% and 95% construction documents, and developing a GMP at 100% construction documents or with component GMP’s as warranted based on the requirements of the schedule) and provide other cost information / analysis and knowledge of market conditions to facilitate decision-making.
E. Providing project planning, phasing, and scheduling, including logistics plans as design advances that will minimize interruption to the local businesses, and include schedule reduction opportunities.
F. Providing evaluation of alternates and value engineering recommendations at appropriate times in the design development process.
G. Coordinating and advising the Public Works Department on ways to gain efficiencies in project delivery.
H. Providing long-lead procurement studies and possibly initiating procurement of long-lead items.
I. Developing and maintaining a construction management plan to include a detailed subcontracting plan.
J. Proposing, if needed to maintain schedule, a fast-track approach to executing the work through multiple, interim GMPs prior to acceptance of a final GMP for the complete Project.
K. Assisting in the permitting process.
L. Performing biddability reviews, and design submittal reviews at appropriate times in the design development process to facilitate the design quality and schedule.
M. Analyzing the design, including plans and specifications, to ensure feasibility of the Project design.
N. Developing a comprehensive safety plan for implementation during construction.
O. Determining means and methods for performing the work.
P. Coordinating work plans with various City departments and other agencies, utility companies and similar entities, and other contractors.
Q. Identifying areas with high-cost escalations throughout preconstruction and develop mitigation plans.
R. Developing recommendations to limit Project impacts due to supply chain issues.
S. Providing compliance reviews, such as subcontractor contracts, safety, environmental, labor and quality.
T. Assisting with preparation and delivery of presentations to stakeholders, as required.
U. Developing the scopes of work for subcontractor bid packages.
V. Leading and managing the subcontractor prequalification and bidding process, including a program to maximize subcontractor interest and encourage participation in the bidding process.
W. Bidding, awarding, and managing all construction related contracts in compliance with City solicitation requirements and SBEDA processes and requirements.
X. Identifying sustainable design and ultra-accessibility options.
Construction Phase Services: The CMAR will be responsible for continuous budget monitoring during the duration of the Project and will update the City immediately of any deviations. The City anticipates that the project budget will be set at submission of 40% construction documents.
The City anticipates that the CMAR’s construction phase services will include but not be limited to:
A. Constructing the designed improvements, including managing the means and methods of all self-performed work (if selected through a competitive bidding process) and subcontractors.
B. Coordinating and reporting on status of work with City of San Antonio departments and other agencies, utility companies, similar entities, and other contractors.
C. Managing work to maintain local business operations, efficient traffic flow, and safety of the public.
D. Procuring and managing the subcontractor outreach, bidding and awarding of work on multiple packages, and managing all construction related contracts and subcontracts while meeting the City’s solicitation requirements.
E. Procuring materials and equipment.
F. Scheduling and managing project site operations.
G. Developing and implementing quality management and control procedures, including development of a quality control plan and quality control testing.
H. Developing a site-specific safety plan and maintaining a safe work environment for all participants.
I. Conducting acceptance testing.
J. Providing bonds and insurance, in accordance with the requirements set out in the CMAR contract.
K. Addressing all federal, state, and local permitting requirements.
L. Supporting the City’s efforts related to public information.
M. Conducting and managing site operations in a safe manner.
N. Providing warranty coverage for all constructed work.
O. Preparing and maintaining as-built documents for all work. Use of electronic models is preferred (e.g. Building
Information Modeling (BIM) and the City electronic standards.
P. Mitigating subcontract cost escalation from bidding through construction.
Q. Mitigating supply chain issues.
R. Maintaining continuity of personnel from preconstruction to construction, commissioning and acceptance.
S. Meet or exceed SBEDA requirements.
T. Conducting and documenting regular meetings with the Public Works Department, consultants, and stakeholders.
U. Managing contract closeout and turnover of Project documents (manuals, as-builts, electronic models, etc.).
V. Documenting new assets and coordinating with the City for operational readiness and transition, including commissioning, training, and developing operation and maintenance manuals.
W. Maintaining compliance with all applicable prevailing wage laws/Davis Bacon Act and other relevant local, state and federal laws.
X. Use the City of San Antonio’s program management software Oracle Primavera Unifier to document requests for information (RFIs), submittals, daily logs, change requests, change orders, and invoicing.
III. SCHEDULE OF EVENTS
The following tentative schedule has been prepared for this project:
IV. PRE-SUBMITTAL CONFERENCE
A Pre-Submittal Conference is scheduled for January 10, 2024, at 10:00 a.m. CT in-person via WebEx meeting. Respondents may join the WebEx using the following instructions:
Join by phone: 1-415-655-0001 Meeting number (access code): 2633 772 2668 Meeting password: COSA Join meeting: https://sanantonio.webex.com/sanantonio/j.php?MTID=md7c8719c31dcb2699a54934f3d274d28
Attendance at the Pre-Submittal Conference is optional, but highly encouraged. Respondents who join the WebEx Pre-Submittal Conference are required to sign into the meeting using a QR code provided only during the meeting. This will confirm Respondent’s attendance and participation for the Pre-Submittal meeting through WebEx.
Respondents are encouraged to submit written questions concerning this RFQ through the CivCast website at least five (5) calendar days in advance of the Pre-Submittal Conference, in order to expedite the proceedings. City’s responses to questions received by this due date may be distributed at the Pre-Submittal Conference, as well as being posted on the CivCast website at https://www.civcastusa.com/bids.
Any oral responses provided by City staff at the Pre-Submittal Conference and at the site visit shall be preliminary. A written summary of the Pre-Submittal Conference shall contain City’s official responses to issues raised during the Pre-Submittal Conference and posted on the CivCast website at https://www.civcastusa.com/bids. Any oral response given at the Pre-Submittal Conference/Site Visit that is not confirmed in the posted written summary from the Pre-Submittal Conference/Site Visit or in a subsequent addendum shall not be official or binding on City. Only written responses shall be official. All other forms of communication with any officer, employee or agent of City shall not be binding on City.
V. SUBMITTAL DOCUMENT REQUIREMENTS AND EVALUATION CRITERIA
City will conduct a comprehensive, fair, and impartial evaluation of all submittals received in response to this RFQ. City will appoint a selection committee to perform the evaluation of the received submittals. Each submittal received by City will be analyzed to determine overall responsiveness and qualifications to the RFQ. The selection committee may select Respondents
Request for Qualifications Advertisement December 18, 2023 Pre-Submittal Conference: January 10, 2024, 10:00 AM (CT) Deadline for Submission of Written Questions: January 17, 2024, 4:00 PM (CT) Statement of Qualifications Due: February 9, 2024, 10:00 AM (CT) Notification of Shortlist and RFP Issuance March 15, 2024 Proposal Due Date: April 2, 2024 Shortlisted Respondent Interviews April 4, 2024 Notification of Selection and Negotiation April 8, 2024 Anticipated City Council Consideration / NTP June, 2024 https://sanantonio.webex.com/sanantonio/j.php?MTID=md7c8719c31dcb2699a54934f3d274d28 https://www.civcastusa.com/bids who are judged to be reasonably qualified for interviews, depending on whether further information is needed. Interviews are not an opportunity to change a submission. If the City elects to conduct interviews, Respondents may be interviewed and re-scored based upon the same criteria. City may also request information from Respondents at any time prior to final approval of a selected Respondent deemed reasonably qualified for award. Final approval of a selected Respondent is subject to the action of the San Antonio City Council.
Respondent’s RFQ Submittal shall include the following items in the order set out in the Submittal Checklist & Table of Contents (Form #1) and combined in PDF format:
1. SUBMITTAL CHECKLIST AND TABLE OF CONTENTS (Form #1) (Indexed and labeled as “Tab 1”) – Respondent shall complete this form, which shall be used as the Table of Contents and as a checklist for Respondent’s RFQ submittal.
2. EXECUTIVE SUMMARY (Indexed and labeled as “Tab 2”) – Respondent shall include a two (2) page Executive Summary at the beginning of the Statement of Qualifications. Respondent’s Executive Summary shall state, at a minimum, the number of years Respondent’s team has been in business. If Respondent is a joint venture, provide information for each member of the joint venture.
To correctly submit a response to this RFQ, Respondent shall reveal, disclose, and state the true and correct name of the individual, proprietorship, corporation and/or partnership (clearly identifying the responsible general partner and all other partners who would be associated with the contract, if any) submitting the response. The true and correct name should comport exactly with the corporate and franchise records of the Texas Secretary of State and Texas Comptroller of Public Accounts. Individuals and proprietorships, if operating under other than an individual name, should match with exact Assumed Name filings. Corporate Respondents and limited liability company Respondents shall include the 11-digit Comptroller’s Taxpayer Number on the signature page of the RFQ Submittal.
3. CONTRACT TEMPLATE AND GENERAL CONDITIONS REVIEW (Indexed and labeled as “Tab 3”) –
Respondent shall review the Contract Template and General Conditions, provided hereto and made a part hereof and labeled as Exhibit A & Exhibit B and provide written acknowledgment that Respondent accepts the terms, conditions and requirements of the City’s General Conditions, in Respondent’s submitted proposal under “Tab 3”.
4. LETTERS OF REFERENCE (Indexed and labeled as “Tab 4”) – Respondent shall provide a maximum of five (5) letters of reference.
5. STATEMENT OF QUALIFICATIONS – Respondent shall provide a narrative document, addressing all submittal requirements below considering the Project defined in this RFQ. The following sections include additional submittal requirements and associated evaluation criteria that the City will use to shortlist Respondents who will be invited to participate in the RFP phase of the procurement:
A. Experience, Background, Qualifications of Key Personnel, and Key Sub-Consultants (50 Points)
Respondent shall respond to the following items, as related to Scope of Work outlined in this RFQ:
1. Experience Narrative (Indexed and Labeled as “Tab 5”): Provide a narrative in a maximum of five (5) pages that describes the Respondent’s successful experience constructing projects similar to this Project through construction manager at risk or another collaborative delivery method. As part of this narrative, describe Respondent’s experience providing:
a) Successful preconstruction services in partnership with project teams.
b) Construction phase experience delivering projects of similar scope on schedule, on budget, and with excellent quality and safety performance.
c) Include a discussion of the experience of the team members working together on other comparable projects and the results of that experience, including the number of years working together.
In addition, Respondent’s narrative must:
a. Demonstrate a minimum of ten (10) years’ experience in building projects of similar size, complexity and type. Provide date(s) services were provided. If Respondent is proposing a joint venture for this Project, a minimum of ten (10) years’ experience is required of each joint venture member.
b. Demonstrate success in utilizing comparable preconstruction phase services to establish a plan for execution that provides an executable program on schedule and on budget.
d) Demonstrate success using Primavera P6 and other project management software tools.
e) Demonstrate experience and success of key subcontractors on the team.
2. Project Sheets (Indexed and Labeled as “Tab 6”) – Include the following in support of the above:
Provide 2-page project sheets for three (3) successfully completed projects of similar size, scope and complexity utilizing the construction manager at risk delivery method or another collaborative delivery method. For each highlighted project, the project sheet shall include the following:
a) Description of the project and scope of work;
b) Photograph of the project;
c) Project’s proposed substantial completion date and actual substantial completion date (explain inconsistencies);
d) Project’s original construction contract amount and final construction contract amount (explain inconsistencies);
e) Name of design firm;
f) Project Manager and note whether this person will work on the Project and his/her role planned for the
Project;
g) Project Superintendent and note whether this person will work on the Project and his/her role planned for the Project;
h) Project Estimator and firm for which they were employed and note whether this person will work on the
Project;
i) The owner’s name and the name of the representative who served as the day-to-day liaison for the construction phase of the project in the following format:
Name of Owner:____________________ Name and title of Owner’s representative:_________________ Owner representative’s Phone Number:____________ Owner representative’s E-mail:___________________
3. Organizational Chart (Indexed and Labeled as “Tab 7”) – Provide a one (1) page organizational chart that identifies Respondent’s proposed team organization. Key personnel should be clearly identified. Team roles should be clearly identified. Only include personnel who would perform work under the CMAR contract. The organizational chart can be formatted on an 11” x 17” page, if needed.
At a minimum, the following key personnel must be clearly labeled on the organizational chart and described in the following section:
a) Senior Project Manager (on-site team leader)
b) Project Manager(s)
c) Pre-Construction Manager
d) Sr. General Superintendent (construction phase onsite lead)
e) General Superintendents
4. Organizational Chart Narrative (Indexed and Labeled as “Tab 8”) – Provide a narrative description (up to (2) two pages) of the organization chart describing the proposed assignments, roles and responsibilities, lines of authority, transition of responsibilities from preconstruction to construction phases, and communication for each team member to be directly involved with the Project. The proposed key personnel must have demonstrated experience of projects similar to the scope of the project.
5. Resumes (Indexed and Labeled as “Tab 9”) – Not included in the page count for Section B – Include the following in support of the above. Respondent shall provide a two (2) pages maximum resume for each of the key personnel listed above.
a) Resumes should link back to project sheets submitted in accordance with Section 3.A.2 and may reference additional previously completed relevant projects not highlighted in the project sheets, where applicable.
If a person did not work on any project included in the project sheets, then the resume should reference projects where the person performed roles similar to the role proposed for this Project.
b) Resumes shall include: 1) license type (if applicable) and number of years licensed; 2) certification or other role specific recognitions, and number of years, including LEED Accreditation, if any; 3) number of years employed with the Respondent or subcontractor; 4) number of years of experience in proposed role identified on the Organizational Chart.
B. General Proposed Work Plan/Approach (30 Points) – Submit a description of the Respondent team’s philosophy and proposed approach to the work and availability of labor resources (capacity to perform) in executing the team’s effort. Submit information in a brief narrative plan of up to three (3) pages (exclusive of the plans described below) that clearly and concisely describes the approach to the Project, as well as other information you feel is critical to the success of the Project. In addition, provide information on the items below:
1. Subcontractor Selection Plan/Process (Indexed and Labeled as “Tab 10”) – Provide a maximum three (3) page narrative that describes the selection process you will use to select qualified subcontractors for the Project.
a) Provide an understanding of how you will determine best value in the subcontractor procurement process, as well as criteria used to evaluate the ability of subcontractors to successfully perform the work.
b) If subcontractors are already identified as a part of Respondent’s team, provide a teaming rationale narrative and proven past experience, if applicable.
2. Pre-Construction Phase Work Plan (Indexed and Labeled as “Tab 11”)– Limit response to the following items to five (5) pages maximum:
a) Describe Respondent’s management approach and how the team organization/approach for the pre-construction scope of work outlined in this RFQ will facilitate an improved construction phase.
b) Describe Respondent’s approach to working with the design team to identify opportunities for cost and schedule assurance in the Project design.
c) Describe Respondent’s approach to providing timely design reviews and input to improve the constructability and biddability of the Project.
3. Construction Phase Work Plan (Indexed and Labeled as “Tab 12”) – Limit response to the following items to five (5) pages maximum:
a) Describe Respondent’s construction management approach and plan for coordination with stakeholders.
b) Describe Respondent’s methodology to plan, oversee, coordinate and manage the implementation of the work, including site management, logistics, and subcontractor management.
c) Describe Respondent’s approach to managing project documentation and communications, such as requests for information, shop drawings, design bulletins/updates, potential changes and other coordination of construction progress meetings with the City, designer(s), and other contractors on site.
C. Experience with San Antonio Region and Past Performance – (10 Points) (Indexed and Labeled as “Tab
13”)
1. The City is interested in evaluating Respondent’s team (including Sub-consultants(s), if applicable) experience with local processes and practices, as may be evidenced by work in San Antonio and/or the surrounding area, during the past five (5) years. In narrative form, using a maximum of two (2) pages for Respondent’s response and one (1) page for Subcontractor(s) response, if applicable, briefly describe Respondent’s team experience in the areas listed below, referencing projects relating to that experience. (Note:
Respondent may reference projects included in the project sheets under Criteria A above, but no additional project sheets shall be provided for this criterion, as the response shall be in narrative form.)
a. Construction costs and practices.
b. Environmental conditions and constraints.
c. Involvement in project development as it relates to public awareness in the project’s local area.
d. Respondent’s experience with private and public utilities in the San Antonio or surrounding area including
SAWS and CPS.
e. Municipality Design Guidelines
2. More than one (1) project may be referenced per page, and projects should be discussed in reverse chronological order. (Note: Respondent may reference projects by project name included in the project sheets under Criteria A above or include other projects, but no additional project sheets shall be provided for this criterion, as the response shall be in narrative form.) If Respondent is referencing a project that is not included in the project sheet section, please include the following information:
a. Project name and description of scope.
b. Respondent’s project role and work performed.
c. Names of Respondent’s team members who worked on the project, if applicable.
d. The contact information of the project’s owner or representative (if different) including name, email, and phone number.
Note a portion of the scoring for this Section C may be based on City’s Contractor’s/Consultants’ Scorecard, experience with City projects and/or other documentation generated by City staff and previous City Consultants on other City projects. City shall consider the history of Respondent in complying with project programs, schedules and budgets on previous City projects. No items shall be submitted by Respondent for this criterion. Respondent shall not be penalized if it has not done work on City of San Antonio projects. Specific items used for consideration may include, but are not limited to:
a. Timely completion of City projects.
b. Cooperative working relationship with City.
c. Prompt payment of Sub-consultants at all levels.
d. Compliance with other City contract terms.
e. Compliance with City Ordinances on substitution/addition/deletion of Sub-consultants.
f. Compliance with City standards.
g. Conformance to City budget requirements.
3. Reference checks may be performed with Owners indicated on the submitted project sheets submitted as Tab
“6” and considered as part of this criteria.
D. Small Business Economic Development Advocacy (SBEDA) – (10 Points) (Indexed and Labeled as “Tab 12”)
SBE Prime Contract Program – 5 pts.
Certified SBE firms (see Small Business Enterprise definition) headquartered or having a Significant Business Presence within the San Antonio Metropolitan Statistical Area responding to this solicitation as Prime Contractors proposing at least 51% SBE participation (Prime and/or Subcontractor) will receive five (5) evaluation criteria points, and
M/WBE Prime Contract Program – 5 pts.
Certified M/WBE firms (see Minority/Women Business Enterprise definition) headquartered or having a Significant Business Presence within the San Antonio Metropolitan Statistical Area responding to this solicitation as Prime Contractors proposing at least 51% M/WBE participation (Prime and/or Subcontractor) will receive five
(5) evaluation criteria points.
Additionally, the City has determined that subcontracting opportunities will arise during the construction phase of this Project; however, the specific scopes of work and the magnitude of the scopes of work cannot be determined until the design for the Project has been completed. When the design documents are sufficiently completed, the City will establish appropriate SBEDA goals, and the Construction Manager at Risk (CMAR) firm shall submit a SBEDA Change of Utilization Form meeting the goals.
Information on programs such as the City’s Ready to Work Program and the City’s Mentor-Protégé program will be included in the RFP Phase.
Below is the Evaluation Criteria Summary:
Evaluation Criteria Summary Maximum Points
A. Experience, Background, & Qualifications of Key Personnel, and Key Sub-Consultants 50
B. General Proposed Work Plan/Approach 30
C. Experience with San Antonio Region and Past Performance 10
D. Small Business Economic Development Advocacy (SBEDA) SBE Prime Contract Program – 5 Points M/WBE Prime Contract Program – 5 Points
Total Maximum 100 Points
For each evaluation criterion above, City will review the submittals and any other information corresponding to the criterion and will provide a score within the maximum allotted points that reflects the extent to which the information provided demonstrates in a comprehensive and credible way the Respondent team’s ability to deliver the Project while meeting the City’s project-related goals and objectives.
Required Forms (to be uploaded individually):
City shall conduct due diligence and analysis of the following required forms:
1. RFQ SUBMITTAL COVER/SIGNATURE SHEET (Form #2) – Respondent shall include the completed
Submittal Cover/Signature Sheet with the other required forms. The Submittal Cover/Signature Sheet shall be signed by a person (or persons) authorized to bind Respondent and the entity/entities submitting the response.
Signature pages signed by a person other than an officer of the company or partner of the firm shall be accompanied by evidence of authority. Joint ventures submittals require signatures from all firms participating in the joint venture. Submitting joint ventures are required to provide legal proof of the joint venture, such as a joint venture agreement. Respondent is required to enter the Texas Secretary of State Filing Number and the System of Award Management (SAMS) DUNS and/or CAGE number.
2. CONTRACTS DISCLOSURE FORM (Form #3) – Respondent shall complete the form online at:
https://webapp1.sanantonio.gov/ContractsDisclosure/, print a copy of the completed form and include in the packet of required forms. If Respondent is proposing as a team or joint venture, each party to that team or joint venture shall complete and submit a separate Contracts Disclosure Form.
3. LITIGATION DISCLOSURE FORM (Form #4) – Respondent shall complete a Litigation Disclosure
Form, utilizing additional pages for explanation, if necessary, and submit the completed form. If Respondent is proposing as a team or joint venture, each party to that team or joint venture shall complete and submit a separate Litigation Disclosure Form.
4. SMALL BUSINESS ECONOMIC DEVELOPMENT UTILIZATION COMMITMENT FORM (Form
#5) – Respondent must submit a completed and signed Subcontractor/Supplier Utilization Plan Indicating Respondent’s firm commitment to satisfy the established (18%) subcontracting goal to a Minority/Women Business Enterprise (M/WBE) and (3%) African American Business Enterprise (AABE) for this Project. If Respondent believes they cannot meet the subcontracting goal, Respondent must also submit a Waiver Request Form as part of the required forms. The Waiver Request Form may be download at https://www.sanantonio.gov/SBO/Form.
5. KEY PERSONNEL COMMITMENT FORM (Form #6) – Respondent shall include the completed Key
Personnel Commitment Form with the other required forms to confirm Respondent’s commitment to utilize the key personnel it identifies in the RFQ Submittal.
6. FINANCIAL STATEMENT – Due to the anticipated investment and length of resultant contract between the parties, audited financial statements are preferred. In the event audited financial statements are not available, state the reason why. If audited financial statements are not available, respondents may submit other financial statement(s) or documentation, such as a Trial Balance Income Statement along with the most recent Annual https://webapp1.sanantonio.gov/ContractsDisclosure/ https://www.sanantonio.gov/SBO/Form
Tax Submission that validates and ensures the long-term financial viability of the organization. Failure to provide requested information may impact your firm’s final score.
7. PROOF OF INSURABILITY – Respondent shall submit a copy of its current insurance certificates for builder’s risk, general liability, and professional liability.
8. CERTIFICATE OF INTERESTED PARTIES TEC FORM 1295 – The Texas Government Code §2252.908, and the rules issued by the Texas Ethics Commission found in Title 1, Chapter 46 of the Texas Administrative Code, require a business entity to submit a completed Form 1295 to the City before the City may enter into a contract with that business entity:
Form 1295 must be completed online. It is available from the Texas Ethics Commission by accessing the following web address: https://www.ethics.state.tx.us/whatsnew/elf_info_form1295.htm.
Print your completed Form 1295. Submit your signed Form 1295 with your response to this solicitation.
Where requested to provide the name of the public entity with whom you are contracting, insert “City of San Antonio”. Where requested to provide the contract number, provide the solicitation number shown on the cover page of this solicitation (e.g. RFQ: AV122122DR, RFO: 6100001234 or RFCSP:
PW051822DR).
The following definitions found in the statute and Texas Ethics Commission rules may be helpful in completing Form 1295.
“Business entity” includes an entity through which business is conducted with a governmental entity or state agency, regardless of whether the entity is a for-profit or nonprofit entity. The term does not include a governmental entity or state agency. (NOTE: The City of San Antonio should never be listed as the “Business entity”.)
“Controlling interest” means: (1) an ownership interest or participating interest in a business entity by virtue of units, percentage, shares, stock, or otherwise that exceeds 10 percent; (2) membership on the board of directors or other governing body of a business entity of which the board or other governing body is composed of not more than 10 members; or (3) service as an officer of a business entity that has four or fewer officers, or service as one of the four officers most highly compensated by a business entity that has more than four officers.
Subsection (3) of this section does not apply to an officer of a publicly held business entity or its wholly owned subsidiaries.
“Interested party” means: (1) a person who has a controlling interest in a business entity with whom a governmental entity or state agency contracts; or (2) an intermediary.
“Intermediary,” for purposes of this rule, means a person who actively participates in the facilitation of the contract or negotiating the contract, including a broker, adviser, attorney, or representative of or agent for the business entity who:
(1) receives compensation from the business entity for the person’s participation;
(2) communicates directly with the governmental entity or state agency on behalf of the business entity regarding the contract; and
(3) is not an employee of the business entity or of an entity with a controlling interest in the business entity.
Publicly traded business entities, including their wholly owned subsidiaries, are exempt from this requirement and are not required to submit Form 1295.
City shall review Form 1295 as part of the Minimum Requirements Review performed upon all submittals received. Deficiencies in or missing Form 1295 shall not be a disqualifying error. Instead, City shall notify a Respondent of any requirements to cure the deficiency and/or to submit/re-submit Form 1295 within two (2) days of notice to remain eligible to be considered for a contract award. If applicable, City shall include the selected Respondent’s Form 1295 in its package prepared for the San Antonio City Council’s consideration for contract award.
https://www.ethics.state.tx.us/whatsnew/elf_info_form1295.htm
VI. SUBMISSION INSTRUCTIONS
Online submission will be via CivCast at https://www.civcastusa.com/bids. Online submission services will open for submitting statement of qualifications on December 18, 2023, and close on February 9, 2024, at 10:00 a.m. CT. Follow submittal instructions on https://www.civcastusa.com/. Hard copies and submittals sent by facsimile or email will not be accepted.
Please adhere to the following criteria:
• “Page” means one electronic page
• Sheets are 8.5”x11” unless otherwise stated
• No smaller than 11-point font.
• Be succinct and clear.
• Keep your submittal relevant to the target project.
• Each submittal shall include the sections and attachments in the sequence listed in the Section V, Submittal
Document Requirements & Evaluation Criteria, with each section divided by tabs and indexed, as indicated in this
RFQ.
• All pages shall be numbered, and all sections shall adhere to page limits. If a section does not have a page limit specified, there are no page limits for that section.
To correctly submit a response to this RFQ, Respondent shall reveal, disclose and state the true and correct name of the individual, proprietorship, corporation and/or partnership (clearly identifying the responsible general partner and all other partners who would be associated with the contract, if any) submitting the response. The true and correct name shall comport exactly with the corporate and franchise records of the Texas Secretary of State and Texas Comptroller of Public Accounts. Individuals and proprietorships, if operating under other than an individual name, shall match with exact Assumed Name filings. Corporate Respondents and limited liability company Respondents shall include the 11-digit Comptroller's Taxpayer Number on the signature page of the Submittal.
Respondent must comply with the Restrictions on Communication section of this RFQ and shall not provide full or partial copies of its submission to City officials or City employees, as defined by that section. Failure to submit a submittal in accordance with the prescribed process will result in Respondent’s proposal being disqualified from consideration.
VII. RFP EVALUATION CRITERIA FOR SHORTLISTED FIRMS
Based on the evaluation process of Phase I, the selection committee shall qualify up to a maximum of five (5) Respondents to participate in Phase II of the solicitation process. Phase II of the solicitation process shall include requests for additional information from the short-listed firms and shall include an invitation for an interview. Additional information requested may include more detailed information from Respondent regarding demonstrated competence and qualifications, the ability of Respondent to meet the Project schedule and other information, as appropriate. During the Phase II of the solicitation process, the selection committee will evaluate and rank the short-listed firms based on the published evaluation criteria set forth below:
RFP Phase Submittal Evaluation Criteria Summary (For Information Only):
Maximum Points
A. Detailed Proposed Work Plan and Approach to Quality Control 50 B. Overall Evaluation of the Firm/Team and its Ability to Provide Required
Services 20
C. Proposed Costing Methodology 20 D. Small Business Economic Development Advocacy (SBEDA)
SBE Prime Contract Program – 5 Points M/WBE Prime Contract Program – 5 Points
TOTAL
100 Points https://www.civcastusa.com/
VIII. AMENDMENTS TO RFQ
Changes, amendments, or written responses to questions received in compliance with Section IX, Restrictions on Communication herein, will be posted on the CivCast website at https://www.civcastusa.com/bids. It is Respondent’s responsibility to review this site and ascertain whether any amendments have been made prior to submission of its submittal. If Respondent does not have access to the Internet, Respondent shall notify City, in accordance with Section IX, Restrictions on Communication, that it wishes to receive copies of changes, amendments or written responses to questions by mail or facsimile.
No oral statement of any person shall modify or otherwise change or affect the terms, conditions or specifications stated in this RFQ and all changes to this RFQ – if any – shall be made by City only in writing.
IX. RESTRICTION ON COMMUNICATIONS
Respondents are prohibited from contacting 1) City officials, as defined by §2-62 of the City Code of the City of San Antonio, regarding the RFQ or submittal from the time the RFQ has been released until the contract is posted for consideration as an agenda item during a meeting designated as an A session; and 2) City employees from the time the RFQ has been released until the contract is approved at a City Council “A” session.
Restrictions extend to “thank you” letters, phone calls, emails and any contact that results in the direct or indirect discussion of the RFQ and/or submittal submitted by Respondent.
Violation of this provision by Respondent and/or its agent may lead to disqualification of Respondent’s submittal from consideration.
As used herein, City Official is defined as the Mayor; members of City Council; Municipal Court Judges and Magistrates; City Manager; Deputy City Manager; City Clerk; Deputy City Clerk; Assistant City Clerk; Assistant City Managers; Assistants to City Manager; all City department heads and assistant department heads; Internal Auditor and Assistant Internal Auditors;
Compliance Auditor; Assistant to City Council; Assistants to City Council, including contract personnel; Assistant to Mayor;
Assistants to the Mayor, including contract personnel; Executive Secretaries; Public Utilities Supervisor; members of bid committees; members of the Historic and Design Review Commission; Zoning Commission; and members of any board or commission that is more than advisory in nature.
Exceptions to the restrictions on communication with City employees include:
1. Respondent may ask verbal questions concerning this RFQ at the Project’s Pre-Submittal Conference.
2. Respondent may ask verbal questions concerning this RFCSP at the Project’s Site-Visit Meeting if one is scheduled.
3. Respondent must submit questions concerning this RFQ through the CivCast website at https://www.civcastusa.com/bids until January 17, 2024, at 4:00 p.m. CT. Questions received after the stated deadline shall not be answered.
4. Respondents and/or their agents are encouraged to contact the Small Business Office of the Economic Development Department for assistance or clarification with issues specifically related to the City’s Small Business Economic Development Advocacy (SBEDA) Program policy and/or completion of the required SBEDA forms. The point of contact may be reached by telephone at (210) 207-3932 or by e-mail at SBEDAdocs@sanantonio.gov. After the solicitation closing date, there is no contact permitted to the Small Business Office regarding this solicitation
5. Respondent must provide responses to any questions asked of it by City’s Staff Contact Person and/or his/her designee about City’s SBEDA Program both before and after responses are received and opened. During interviews, if any, verbal questions and explanations will be permitted.
6. If Respondent is invited for an interview and/or demonstration, the City requests Respondents limit the size of their team to no more than six (6) people of Respondent’s choosing and subject to City’s approval. Attorneys and/or lobbyists are strictly prohibited from attendance. If you are utilizing a subcontractor, a subcontractor representative should be included. The City reserves the right to exclude any persons from interviews as it deems in its best interest.
City reserves the right to contact any Respondent to negotiate if such is deemed desirable by City. Such negotiations, initiated by City staff persons, shall not be considered a violation by Respondent of this section.
X. AWARD OF CONTRACT, RESERVATION OF RIGHTS AND MISCELLANEOUS
A. A CMAR contract, if awarded, shall be awarded to the Respondent determined to be the most qualified to successfully complete the Project based on the criteria set out in the RFP, as determined by the selection committee and upon the approval by the San Antonio City Council.
B. City may accept any RFQ Submittal in whole or in part. If subsequent contract negotiations are conducted, such negotiations shall not constitute a rejection or alternate RFQ on the part of City. However, final selection of a Respondent is subject to San Antonio City Council approval.
C. City reserves the right to accept one or more RFQ Submittals or reject any or all RFQ Submittals received in response to this RFQ, accept and review a non-conforming RFQ Submittal, permit clarifications or supplements to an RFQ Submittal, and to waive informalities and irregularities in any RFQ Submittal received. City also reserves the right to terminate this RFQ, reissue a subsequent solicitation and/or remedy technical errors in the RFQ process without incurring any cost obligations or liabilities.
City reserves the right to issue addenda to the RFQ and to modify all dates set or projected in this RFQ.
D. By executing the RFQ Submittal Cover/Signature Sheet, Respondent agrees to be bound by the terms therein. Further, by executing the RFQ Submittal Cover/Signature Sheet, Respondent acknowledges it has received all addenda and agrees to be bound by the terms, conditions and requirements of this RFQ, the enabling City Ordinance and all of the associated documentation that form the entire CMAR contract to which Respondent, if ultimately selected for the Project, shall be bound, upon the approval of the San Antonio City Council. All CMAR contract documents are not binding on City until approved by the San Antonio City Council.