About this file

This document is an Addendum No. 2 to a Request for Qualifications and Proposals (RFQ/P) for a Construction Manager-at-Risk (CMR) firm to perform the Madison Monroe Educational Building Renovation project at Lamar State College-Port Arthur in Port Arthur, Texas. The Texas State University System is soliciting Qualifications and Pricing/Delivery Proposals from prospective CMR firms. The project involves the renovation of the existing Madison Monroe Educational Building on the Lamar State College-Port Arthur campus. The RFQ/P was originally posted on December 7, 2023, and Addendum No. 1 was posted on January 9, 2024. This Addendum No. 2 provides the final question and answer regarding utility costs during construction, with the owner paying for the utilities currently serving the existing building, while the CMR will be responsible for utilities for their own job site trailer or temporary facilities.

The contract opportunity involves the selection of a CMR firm to perform the renovation project. The project will be funded by the owner, and the CMR's utilities costs for their own temporary facilities will be paid out of the General Conditions Fee as outlined in the CMR Agreement template. The solicitation is open to qualified CMR firms, with Respondents required to submit their Qualifications, Proposals, and HUB Commitment Letter in separate, sealed packages.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(i)

(ii)

REQUEST FOR QUALIFICATIONS & PROPOSALS

FOR

CONSTRUCTION MANAGER-AT-RISK

FOR

LAMAR STATE COLLEGE-PORT ARTHUR

PORT ARTHUR, TEXAS

MADISON MONROE EDUCATIONAL

BUILDING RENOVATION

RFQ/P No.:

758-24-04019

Notice To All Respondents:

The following is Addendum No. 2 to the Request for Qualifications & Proposals (RFQ/P)

Addendum No. 1 was posted January 9, 2024 ESBD Posting No. 758-24-04019 was posted on December 7, 2023

Prepared By:

Donna Bryce, Senior Contract Administrator

The Texas State University System

601 Colorado Street

Austin, TX 78701 - 512-463-1808

Donna.Bryce@tsus.edu

Addendum No. 2 Issued January 9, 2024

Addendum No. 2 - RFQ/P for Construction Manager-At-Risk (posted 01/09/2024) Madison Monroe Educational Building Renovation at Lamar State College-Port Arthur

RFQ/P No. 758-24-04019

I. GENERAL:

A. Below is the final question with answer as of January 9, 2024, 12:00 p.m.:

1. Question: Will the utility cost (electricity, water, etc.) during construction be paid for by the General Contractor or by LSCPA as it is an existing building and independent metering may not be possible?

Answer: All the utilities currently serving the Madison Monroe Educational Building will be paid by the owner due to the separate submetering challenges that are being raised. Utilities serving a job site trailer or other temporary facilities provided by the CM will be the CM’s responsibility, but paid out of the General Conditions Fee, per Exhibit C of the template CMR Agreement.

- END OF ADDENDUM NO. 2 -