This document is the Technical Specifications for the Hays County IFB 2024-B01 TXCDBG - Cedar Oaks Mesa WSC - Water Improvements project. The project will include the installation of 1,560 linear feet of 6" waterline, 3 fire hydrants, and all necessary supportive work and appurtenances. The contract requires the contractor to prepare a Storm Water Pollution Prevention Plan (SWP3), submit a Notice of Intent (NOI) to the Texas Commission on Environmental Quality, and post the NOI and Construction Site Notice at the project site. The contractor will be responsible for adjusting existing manholes and valve covers within the construction area to meet the finished grade elevation. The contract also outlines requirements for materials, testing, quality control, and other general construction specifications.
The contract states that the contractor's bid prices shall include costs for survey services, water line disinfection, and adjusting existing manholes and valve covers. Separate payment will be made for asphaltic or concrete pavement repair, but not for repair of gravel surfaces. The contractor will be required to comply with any applicable "Buy American" statutes or regulations in effect at the time of performance.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Hays County IFB 2024-B01 TXCDBG – Cedar Oaks Mesa WSC – Water Improvements
Section 12
Technical Specifications
Section 00 72 00 General Information Section 00 73 00 Special Instructions Section 01 50 00 Temporary Facilities and Controls Section 01 57 23 Storm Water Pollution Prevention Plan Section 01 77 00 Closeout Procedures Section 03 30 00 Cast-In-Place Concrete Section 03 40 00 Structural Precast Pretensioned Concrete Section 31 00 00 Earthwork Section 31 23 19.13 Care of Water Section 31 50 00 Excavation Support and Protection Section 32 01 26 Asphalt Pavement Restoration Section 32 92 13 Hydromulching Section 33 05 05.48 Testing of Pipelines Section 33 05 19 Ductile Iron Pipe and Fittings Section 33 05 31.16 Water Main Construction Section 40 91 10 Pressure Reducing Control Valves
00 72 00-1 GENERAL INFORMATION
SECTION 00 72 00
GENERAL INFORMATION
PART 1 - GENERAL
1.01 SCOPE OF PROJECT
A. The work to be done under this contract includes the furnishing of all superintendence, labor, material, transportation, tools, supplies, plant equipment and appurtenances necessary for the complete construction of all improvements herein described and shown on the plans which are made a part of these specifications.
1.02 METHOD OF BIDDING
A. In conjunction with these Instructions to Bidders, OWNER has issued an Advertisement for Bids for this Project. OWNER has identified its decision to utilize competitive sealed bids for this procurement.
B. In addition to the submittal from Offerors in response to the criteria upon which rankings and selection will be based, Offerors are to submit pricing information in accordance with the following instruction:
1. Where the bid consists of various major items of work, Offerors should provide prices for each item in the bid form. Should Offerors have costs for any incidental work, the costs of such work will be reflected in the unit costs of the bid items in the bid form.
1.03 WITHDRAWAL OF BIDS
A. After the specified time, no bid may be withdrawn for a period of ninety (90) days or until a contract is awarded, whichever occurs first.
1.04 ACCESS TO AND INSPECTION OF PROJECT SITE
A. Offerors may arrange for access to the Site by contacting ENGINEER at any time between publication of the publication and the deadline for receipt of bids. Such access will be granted to allow Offerors to make a complete inspection and careful examination of the project site and familiarize themselves with the soil and water conditions to be encountered, construction to be projected, disposal sites for surplus materials not designated to be salvaged materials, method of providing ingress and egress to private properties, and methods of handling traffic during construction of the entire project.
B. By submitting a propos, Offeror acknowledges it has inspected the site, has read and become thoroughly familiar with the plans and contract documents (including all addenda).
1.05 GEOTECHNICAL DATA
A. The locations of the test holes, if applicable, are shown in the Geotechnical Report. Logs of these test holes are included in the Geotechnical Report. Test holes information represents subsurface characteristics to the extent indicated and only for the point location of the test hole. Each Offeror shall make his/her own interpretation of the character and condition of the materials which will be encountered. Each prospective Offeror may, at his/her own expense, make additional surveys and investigations as he may deem necessary to determine conditions which will affect performance of the Work.
00 72 00-2 GENERAL INFORMATION
1.06 REPLACEMENT OF MISCELLANEOUS IMPROVEMENTS
A. The CONTRACTOR shall repair or replace all existing utilities, water and sewer mains, fences, concrete walls, sidewalks, concrete curbs and concrete pavement, signs, culverts, asphalt pavement, building walls and attachments and other miscellaneous improvements damaged by the CONTRACTOR due to his operations on this project, to a condition equal to or better than their condition before construction, at no additional expense to the OWNER. No direct payment will be made for this item.
1.07 CLEAN-UP
A. The CONTRACTOR shall at all times keep the jobsite as free from all material, debris, and rubbish as is practicable and shall remove same from any portion of the job site when it becomes objectionable in the opinion of the OWNER and ENGINEER.
B. After construction work is completed and before final acceptance of improvements by OWNER, CONTRACTOR shall remove all debris from site of project, including all existing debris to an approved place of disposal. Temporary structures, forms, equipment, objectionable rocks, concrete and other debris shall be removed in such manner as to leave the site of work in a neat and presentable condition throughout, and restore in an acceptable manner all property damaged in the progress of this work.
C. No direct payment will be made for clean-up.
D. Materials cleared from project shall not be deposited on adjacent public or private property without written permission of the property owner thereof filed with ENGINEER. Any materials so deposited shall be leveled and left in a condition satisfactory to the OWNER.
1.08 EXCAVATION
A. Excavation in this Contract shall be unclassified and shall not be included as a separate charge by unit item or scheduled value as all excavation is associated with other work. There is no separate pay item under this Contract for excavation and its cost shall be included in such pay items as are provided in the Contract and bid.
1.09 EXISTING UTILITIES
A. Existing surface and subsurface structures (gas mains, water mains, sewer mains, storm sewers, telephone cables, sprinkler systems, etc.) are shown on the plans if their location has been determined, but it shall be the responsibility of the CONTRACTOR to avoid damaging these existing structures regardless of whether they are shown on the plans. The OWNER assumes no responsibility for failure to show any or all of these structures on the plans or to show them in their exact location. It is mutually agreed that such failure to show these structures will not be considered sufficient basis for claims for additional compensation for extra work or for increasing the pay quantities in any manner whatsoever. The CONTRACTOR expressly assumes responsibility for locating, protecting, and constructing the Project without damage to existing underground utilities and structures. If any structure is damaged by the CONTRACTOR, it shall be his responsibility to repair the damage at his own expense and restore the structure to its intended and fully functional use.
B. CONTRACTOR shall locate and determine (verify if depth is shown on plans) elevation of all existing underground utilities a minimum of 500 feet ahead of trenching. If a utility is found to be in conflict with proposed grades, the ENGINEER shall be contacted and grades adjusted to
00 72 00-3 GENERAL INFORMATION
avoid conflict. CONTRACTOR expressly waives any claims for additional compensation related to measures taken or accommodations and changes made to the Work as a result of such conflict avoidance.
C. The OWNER will provide liaison with property owners and the limited information it has concerning locations, sizes, materials, etc. of existing utilities or structures, but any delays or investigations required of the CONTRACTOR shall be deemed incidental to the project.
D. The CONTRACTOR shall call “One Call” and/or any other locating service or hotline to have all underground utilities marked before beginning any excavation or other activity that may conflict with buried structures.
1.10 NOTICES TO OWNERS AND AUTHORITIES WHEN EXCAVATING
A. Utilities and other concerned agencies shall be notified at least 48 hours prior to excavating near underground utilities or pole lines or in accordance with the utilities, “One Call”, and concerned agencies’ regulations. It shall be the CONTRACTOR’s responsibility to confirm if OWNER’s utilities are on the “One Call” system.
1.11 PRECONSTRUCTION CONFERENCE
A. After award and execution of a contract between the OWNER and CONTRACTOR, a formal preconstruction conference will be held in prior to commencement of the work. This conference will include review of technical specifications in order to insure clarity as to the type of construction machinery to be used, construction methods to be used, and materials to be used, obligations of both the CONTRACTOR and the Owner’s representative, personnel, safety, issues/requirements, permitting requirements, payment requests, construction scheduling, surveying, progress meetings, control of the project, guaranty/warranty, and the method of inspection and decision-making to be used during this project.
1.12 CONSTRUCTION WORKING HOURS
A. The CONTRACTOR shall submit to the OWNER and ENGINEER prior to the preconstruction conference a construction schedule which shall meet the OWNER and ENGINEER's approval before construction can begin.
B. Generally, the CONTRACTOR shall perform all construction activities between 8:00 a.m. to 5:00 p.m., Monday through Friday only. However, the CONTRACTOR may be allowed to work on Saturdays, Sundays, or Legal Holidays upon the OWNER or ENGINEER’s written approval.
CONTRACTOR shall be responsible for paying all costs, fees, etc. related to Owner’s representative during hours on Saturdays, Sundays, or Legal Holidays and outside 8:00 am to 5:00 p.m. Requests must be received from the CONTRACTOR a minimum of 48 hours in advance of work outside that as stated above.
C. The CONTRACTOR shall keep the OWNER and the ENGINEER informed as to his construction progress. Because of traffic congestion, the CONTRACTOR may be required to schedule construction in some areas between the hours of 6:00 p.m. and 7:00 a.m. if the OWNER or ENGINEER determines it to be necessary. CONTRACTOR will be required to perform work in a fashion that will cause the least amount of inconvenience to the general public.
D. The CONTRACTOR may be required to finally complete portions of the project prior to proceeding with other portions. All work scheduling shall be coordinated with OWNER and
00 72 00-4 GENERAL INFORMATION
approved by OWNER before work can proceed. The CONTRACTOR will be required to have someone on call 24 hours per day during the course of the project.
E. The following requirements shall apply to all construction areas:
1. Pavement reconstruction shall be done in half-width road sections unless approved by the
ENGINEER.
2. Residence’s driveways shall be accessible by vehicles at the end of each day (5:00 p.m.).
1.13 COOPERATION AND COORDINATION WITH PUBLIC
A. The CONTRACTOR shall conduct his work so as to cause the least amount of disruption to the public. Closing of any streets or lanes of traffic will be coordinated with OWNER and TxDOT, if applicable. All citizens along each street will be notified by the CONTRACTOR in advance of construction activities. CONTRACTOR shall submit to the OWNER an acceptable notification media such as door hangers, pamphlets, etc.
1.14 SALVAGE RIGHTS
A. Old valves, appurtenances of any kind, street paving materials, etc., excavated, removed, or produced during the project by the CONTRACTOR shall be delivered to the OWNER's yard, if desired by the OWNER. If the OWNER desires not to keep these materials, they shall be disposed of properly and according to current laws. CONTRACTOR shall not be entitled to additional compensation for such delivery or disposal.
1.15 DISPOSAL OF EXCAVATED MATERIALS
A. All excavated materials not used in backfilling will be disposed of by the CONTRACTOR at a site obtained by the CONTRACTOR and approved by the OWNER. Disposal of excavated materials shall be in accordance with all rules and regulations of the Texas Commission on Environmental Quality (TCEQ). Any pieces of material such as broken concrete, asphalt, or pipe measuring twelve (12”) inches or larger in any dimension, shall be disposed of by the CONTRACTOR at an approved landfill or as directed by the OWNER. Spoil areas shall be leveled with a motor grader for future mowing. The CONTRACTOR shall include in his bid the cost to dispose of the materials.
B. All trees, stumps, slashings, brush, or other debris removed from the site prior to construction shall be removed from the property and disposed of in a manner approved by the ENGINEER and OWNER.
1.16 SANITARY FACILITIES
A. The CONTRACTOR shall provide sufficient chemical toilet facilities for the use of his forces.
Adequacy of these facilities will be subject to the approval of the ENGINEER and maintenance of same must be satisfactory to the ENGINEER at all times. CONTRACTOR shall provide a maintenance schedule to the OWNER for approval.
1.17 STAKING FOR CONSTRUCTION
A. The CONTRACTOR will provide all construction staking services for the project. The cost of these services will be reflected in the unit price amount in the bid.
00 72 00-5 GENERAL INFORMATION
1.18 EXCAVATION, TRENCHING, AND SHORING
A. All excavation, trenching, and shoring shall conform to the U.S. Department of Labor, Occupational Safety, and Health Administration Guidelines (Subpart P - Excavation, Trenching, and Shoring). The CONTRACTOR will be required to submit an excavation, trenching, and shoring plan to the ENGINEER for approval prior to construction. See SECTION 02260 – TRENCH EXCAVATION SAFETY PROTECTION of these specifications.
1.19 BUY AMERICAN
A. CONTRACTOR agrees to comply with any applicable “Buy American” statutes or regulations in effect at the time for performance of the Project.
1.20 BACKFILL AND PAVEMENT REPAIR
A. Separate payment WILL NOT be made for repair of gravel surfaces crossed or damaged by the CONTRACTOR’s work. However, separate payment WILL be made for asphaltic (or concrete) pavement repair in the bid and as shown on the plans.
1.21 TESTING
A. All concrete work shall be tested by cylinder breaks at an approved testing laboratory. Three
(3) standard test cylinders shall be taken during each continuous pour. Costs for these cylinder breaks will be borne by the CONTRACTOR.
B. Density tests will be taken of the CONTRACTOR’s finished subgrade, each base course lift, and asphalt at 200’ intervals along the length of streets. Costs for the subgrade and base course densities will be per the bid item in the bid form. The cost for the asphalt densities will be borne directly by the CONTRACTOR. Densities by a nuclear density gauge will be accepted for asphalt testing. The cost of retesting cause by failure of initial test will be paid by the CONTRACTOR.
Any other materials, testings and batch designs required by these specifications will be paid by the CONTRACTOR.
C. All testing of materials required under these specifications shall be performed by an approved agency for testing materials. The nomination of the laboratory and the payment for such services shall be made by the CONTRACTOR. The ENGINEER shall approve the laboratory nominated to do the testing of material.
1. Equipment
a. As conditions permit, the CONTRACTOR shall furnish all materials, labor, and equipment required for preliminary field-testing of any equipment to be furnished.
b. Upon completion of the work and prior to final acceptance and payment, all equipment to be furnished shall be tested as specified or required to insure compliance with the Plans and Specifications.
c. Should the equipment tested either for preliminary or final tests not comply with the requirements as set forth on the plans or in the specifications, the CONTRACTOR shall make the necessary changes and adjustments, or replacements as may be required.
d. All costs for testing of equipment shall be borne by the CONTRACTOR.
00 72 00-6 GENERAL INFORMATION
2. Concrete
a. Testing and control of concrete to be used in the work shall be done by a commercial laboratory employed and paid for by the CONTRACTOR.
b. The CONTRACTOR shall furnish the concrete and concrete materials for such testing at his expense, as provided hereinafter in these specifications.
3. HMAC
a. Testing and design of hot mix asphaltic concrete (HMAC) shall be performed by an independent laboratory employed and paid for by the CONTRACTOR.
b. The CONTRACTOR shall furnish all labor and materials necessary for such testing at his expense, as provided in these specifications.
c. As a minimum, the CONTRACTOR shall perform one (1) sample (three (3) test specimens) for determination of Proctor density and stability and one (1) sample for determination of proportioning of materials. These samples shall be daily during HMAC construction activities.
4. Density
a. Testing of subgrade, fill, and/or backfill layers shall be performed by an independent geotechnical testing agency employed and paid for by the CONTRACTOR per the bid item in the bid form.
b. The CONTRACTOR shall furnish all labor and materials necessary for such testing at his expense, as provided in these specifications.
c. CONTRACTOR shall proceed with subsequent work only after test results for previously completed work comply with requirements.
d. All failed tests shall be retested by the CONTRACTOR at the CONTRACTOR’s expense.
1.22 QUALITY CONTROL
A. General
1. CONTRACTOR shall employ and pay for the services of an independent testing laboratory to perform all inspections, tests, or approvals required by the Contract Documents. The CONTRACTOR is solely responsible for maintaining that the quality of work is in accordance with the Contract Documents. The CONTRACTOR shall be responsible for the notification and scheduling required to ensure that a certified technician from the testing laboratory is present during all sampling and testing procedures required in the Contract Documents. The CONTRACTOR shall not proceed with construction work requiring such testing without the presence of the laboratory’s certified technician. The OWNER, at his option, may perform additional tests as quality monitoring. Quality monitoring activities of the OWNER and ENGINEER, or failure on the part of the OWNER or ENGINEER to perform tests on constructed works, in no way relieves the CONTRACTOR of the obligation to perform work and furnish materials conforming to the Contract Documents.
00 72 00-7 GENERAL INFORMATION
B. CONTRACTOR’s Responsibilities
1. Control the quality of work produced and verify that the work performed meets the standards of quality established in the Contract Documents.
a. Inspect and verify conformance of all materials furnished and work performed, whether by the CONTRACTOR, its subcontractors or its suppliers.
b. Provide and pay for the services of a testing laboratory approved by Engineer to insure that products proposed for use fully comply with the Contract Documents.
c. Perform tests as indicated in this and other sections of the specifications. Schedule the time and sequence of testing with the OWNER and ENGINEER. Testing is to be observed by the ENGINEER or OWNER.
d. Promptly replace any defective materials and/or construction work incorporating defective materials or workmanship.
e. Provide Certified Test Reports as required. Reports are to indicate that materials and construction are in compliance with the Contract Documents.
2. Assist the OWNER, and OWNER’s testing organization to perform quality monitoring activities.
C. Quality Monitoring Activities by Engineer
1. Quality Monitoring activities of the OWNER through their own forces or through contracts with materials testing laboratories and survey crews are for the OWNER’s use in monitoring the results of the CONTRACTOR’s work and quality control activities, if deemed necessary by the OWNER.
2. The Quality Monitoring activities of the Owner DO NOT relieve the CONTRACTOR of its responsibility to provide testing in accordance with the requirements of the Contract Documents or to provide materials and construction work complying with the Contract Documents.
D. Submittals
1. Submittals shall be in accordance with SECTION 00800 – SPECIAL INSTRUCTIONS and shall include:
a. The name of the proposed primary and secondary testing laboratories along with documentation of qualifications, a list of tests that can be performed, and a list of the certified laboratory technicians and the licensed engineers who will be performing the sampling and testing for the Construction Work along with their certifications and licenses.
b. Test reports per Test Reports Paragraph of this supplementary condition.
E. Standards
1. Provide a testing laboratory that complies with the ASTM (American Society of Testing
Materials) and/or ACIL (American Council of Independent Laboratories)
00 72 00-8 GENERAL INFORMATION
“Recommended Requirements for Independent Laboratory Qualifications”, or other specified testing organizations.
2. Perform tests listed in the specifications.
F. Delivery and Storage
1. Handle and protect test specimens of products and construction materials at the construction site in accordance with ASTM or other applicable testing procedures.
G. Verification Testing
1. Provide verification testing when tests performed by the OWNER indicate that materials or the results of construction activities are not in conformance with Contract Documents.
2. Verification testing is to be provided at the CONTRACTOR’s expense to verify products or constructed works are in compliance after corrections have been made.
3. Tests must comply with recognized methods or with methods recommended by the ENGINEER’s testing laboratory and approved by the ENGINEER and OWNER.
H. Test Reports
1. Test reports are to be prepared for all tests.
a. Tests performed by testing laboratories may be submitted on their standard test report forms. These reports must include the following:
1) Name of the OWNER, project title and number, equipment installer and general contractor.
2) Name of the laboratory, address, and telephone number.
3) Name and signature of the certified laboratory personnel performing the sampling and testing.
4) Date and time of sampling, inspection, and testing.
5) Date the report was issued.
6) Description of the test performed.
7) Weather conditions and temperature at time of test or sampling.
8) Location at the site or structure where the test was taken.
9) Standard or test procedure used in making the test.
10) A description of the results of the test.
11) Statement of compliance or non-compliance with Contract Documents.
12) Interpretations of test results, if appropriate.
00 72 00-9 GENERAL INFORMATION
2. Distribute copies of the test reports to:
No. of Copies
OWNER 2
ENGINEER 1
CONTRACTOR 1
I. Non-Conforming Work
1. CONTRACTOR shall promptly correct any work that is not in compliance with the
Contract Documents and shall immediately notify the ENGINEER and OWNER when the corrective work will be performed.
2. Payment for non-conforming work shall be withheld until such work is corrected or replaced with work complying with the Contract Documents.
1.23 PUMPING, BAILING AND DRAINING
A. The CONTRACTOR shall immediately remove all surface or seepage water from sewers, drains, ditches, and other sources which may accumulate during the excavation and construction work by providing the necessary underdrains or otherwise and by doing the necessary pumping, bailing or draining. The CONTRACTOR shall have available at all times sufficient equipment in proper working order for doing the work herein required. All water removed from excavations shall be disposed of in an approved manner so as to not create unsanitary conditions nor to interfere unduly with the use of streets, private driveways, or entrances. Pumping, bailing, draining, underdrains, ditches, etc., shall be considered as incidental work and will not be paid for as separate items, but their cost shall be included in the contract prices bid in the bid form for the various units of excavation measure.
1.24 BARRICADES AND DANGER SIGNALS
A. Where the work is carried on, in or adjacent to any street, alley, or public place, the CONTRACTOR shall, at his own cost and expense, furnish and erect barricades and/or fences, lights and/or danger signals, and take any other steps necessary, for the protection of persons or property. Barricades shall be painted with a reflectorized paint or scotchlite tape. From sunset to sunrise, the CONTRACTOR shall furnish and maintain lights at each barricade. Barricades shall be erected to endeavor to keep vehicles from being driven on or into any work under construction.
B. The CONTRACTOR will be held responsible for all damage to the work due to the failure of barricades, signs, lights, and watchmen to protect it, and whenever evidence is found of such damage, the ENGINEER may order the damaged portion immediately removed and replaced by the CONTRACTOR at his cost and expense. The CONTRACTOR’s responsibility for the maintenance of barricades, signs, and lights and for providing watchmen shall not cease until the project has been accepted by the ENGINEER.
C. The CONTRACTOR shall meet all applicable local, state, and federal regulations for barricades and danger signals.
1.25 SAFETY
A. CONTRACTOR shall place the highest priority on health and safety, and shall maintain a safe working environment during performance of the Work. The site shall be considered to be drug
00 72 00-10 GENERAL INFORMATION
and alcohol free and such policy will be strictly enforced. All employees shall adhere to these policies while on site. CONTRACTOR shall comply, and shall secure compliance by its employees, agents, and lower-tier CONTRACTOR’s, with all applicable health, safety, and security laws and regulations including, without limitation, federal, state and local laws and regulations, any health and safety plans issued by the ENGINEER as well as all policies and regulations of the OWNER. Compliance with such requirements shall represent the minimum standard required of CONTRACTOR. CONTRACTOR will be performing Work on the OWNER’s property.
B. CONTRACTOR agrees to furnish protective devices and clothing as required by applicable laws, regulations, health and safety plans and OWNER rules and regulations, and to ensure that such devices or clothing are properly used by its employees, agents, lower-tier Contractors and other invitees of CONTRACTOR at the jobsite. Safety protection is required at all times while working onsite including a hardhat and a high visibility, tear-off reflective vest.
1.26 PROJECT MAINTENANCE
A. The CONTRACTOR shall maintain and keep in good repair the improvements covered by these plans and specifications during the life of his contract. Existing improvements shall at all times be protected by the CONTRACTOR during the construction of the work as specified herein. All such improvements shall be left in a condition equal to that prior to start of construction.
1.27 PROPERTY LINES AND MONUMENTS
A. The CONTRACTOR shall protect all property corner markers, and when any such markers or monuments are in danger of being disturbed, they shall be properly referenced and if disturbed, shall be reset at the expense of the CONTRACTOR.
1.28 OFF-SITE STORAGE
A. Off-site storage for any materials and equipment not incorporated into the Work but included in the Applications for Payment shall not be allowed.
1.29 CONNECTIONS TO EXISTING FACILITIES
A. Unless otherwise specified or indicated, the CONTRACTOR shall make all necessary connections to existing facilities, including structures, drain lines, and utilities such as water, sewer, gas, telephone and electric. The CONTRACTOR shall give the OWNER or owning utility written notice seven (7) days in advance of making all connections. In each case, the CONTRACTOR shall receive written permission from the OWNER or the owning utility prior to undertaking connections. The CONTRACTOR shall protect facilities against deleterious substances and damage.
B. Connections to existing facilities which are in service shall be thoroughly planned in advance, and all required equipment, materials, and labor shall be on hand at the time of undertaking the connections. Work shall proceed continuously (around the clock) if necessary to complete connections in the minimum time. Operation of valves or other appurtenances on existing utilities, when required, shall be by or under the direct supervision of the owning utility.
1.30 CONNECTIONS TO EXISTING PIPELINES
A. All connections to existing piping shall be made using joints and/or fittings suitable for the conditions encountered. The CONTRACTOR shall field-verify the location, pipe material, and
00 72 00-11 GENERAL INFORMATION
connection requirements of all existing pipe before ordering any new piping to be installed under this contract.
1.31 DEWATERING
A. The CONTRACTOR shall at his own expense remove any water that may be encountered during the course of the work, by pumping, well pointing, or other approved methods. The water shall be stored in a storage tank provided by the CONTRACTOR and disposed of in accordance with all applicable State rules and regulations. Newly placed concrete or grout shall be adequately protected from possible damage resulting from groundwater or from handling and disposal of water.
B. All surface drainage or natural waterways shall be controlled by dikes or ditches without damage to adjacent property or structures and without interference with the right of either public or private owners.
1.32 EXISTING STRUCTURES/EQUIPMENT
A. Exact dimensions of existing structures, buildings, equipment roads, utility locations, etc. shown on the plans have not been field verified by the ENGINEER. Prior to submittal preparation by the CONTRACTOR, or construction activities as applicable, all dimensions of these existing items shall be verified by the CONTRACTOR in the field. It shall be the CONTRACTOR’s responsibility to field verify all field dimensions.
1.33 MANUFACTURER'S CERTIFICATES
A. All manufacturers’ certificates required herein are to be furnished by the CONTRACTOR at his own expense.
1.34 DETAIL PLANS
A. Detail plans for construction are furnished herewith and made a part of these specifications, the same as if they were written herein.
1.35 TREE DAMAGES
A. The protection of existing trees within the right-of-way and on private property is the essence of the contract. For each tree that any work shall damage or destroy, the amount per tree shall be $500.00. This will be deducted from the monies due the CONTRACTOR, not as a penalty but as liquidated damages. In addition the CONTRACTOR shall replace the tree with a caliper- inch to caliper-inch replacement.
B. This sum of money thus deducted for such failure to protect the trees is not to be considered as a penalty, but it shall be deemed, taken and treated as reasonable liquidated damages, since it would be impractical and extremely difficult to fix the actual damages and the OWNER may withhold from the CONTRACTOR's compensation such sum as liquidated damages.
1.36 MATERIALS
A. The CONTRACTOR shall furnish all materials for a complete job as shown on the plans and as required by the specifications.
00 72 00-12 GENERAL INFORMATION
1.37 COPIES OF PLANS AND SPECIFICATIONS
A. Four (4) sets of the Plans and the Specifications shall be furnished to the CONTRACTOR, without charge, for construction purposes. Additional copies may be obtained from the ENGINEER at actual reproduction cost. One (1) additional set of plans shall be marked and returned to the ENGINEER as "RECORD" drawings.
1.38 MATERIALS AND WORKMANSHIP
A. The CONTRACTOR shall furnish all materials for a complete job as shown on the plans and as required by the specifications.
B. No material which has been used by the CONTRACTOR for any temporary purpose whatever is to be incorporated in the permanent structure without written consent of the ENGINEER.
C. Where materials or equipment are specified by a trade or brand name, it is not the intention of the
OWNER to discriminate against an equal product or another manufacturer, but rather to set a definite standard of performance and to establish an equal basis for the evaluation of bids. Where the words "equivalent", "proper", or "equal to" are used, they shall be understood to mean that the article or process is equal, in the opinion or judgment of the ENGINEER, to the article or process specified by name. Unless otherwise specified, all materials shall be the best of their respective kinds and shall be in all cases fully equal to approved samples. Notwithstanding that the words "or equal to" or other such expressions are used in the specifications, the material, manufactured article or process specifically designated shall be used unless a substitute shall be approved in writing by the ENGINEER, and the ENGINEER shall have the right to require the use of such specifically designated material, article or process.
D. The CONTRACTOR should note that his bid will be based on the material, manufactured article or process specifically designated in the specifications.
1.39 ABBREVIATIONS
A. Wherever the abbreviations defined herein occur on the plans, in the specifications, contract, bonds, advertisement, bid, or in any other document or instrument herein contemplated or to which the specifications apply or may apply, the intent and meaning shall be as follows:
A.A.S.H.O. American Association of State Highway
Officials Lin. Linear
A.S.T.M. American Society for Testing Materials Lb. Pound A.W.W.A. American Water Works Association M.H. Manhole Asph. Asphalt Max. Maximum Ave. Avenue Min. Minimum Blvd. Boulevard Mono. Monolithic D.I. Ductile Iron No. Number C.L. Centerline % Percent C.O. Cleanout P.S.I. Pounds square inch per Conc. Concrete P.V.C. Polyvinyl Chloride Cond. Conduit Reinf. Reinforced Corr. Corrugated Rem. Remove Cu. Cubic Rep. Replace Culv. Culvert R/W. or
ROW
Right-of-Way
00 72 00-13 GENERAL INFORMATION
Dia. Diameter Sani. Sanitary Dr. Drive or Driveway Sq. Square Elev. Elevation Std. Standard F. Fahrenheit St. Street or Storm Ft. or ' Foot or Feet Str. Strength Gal. Gallon Vol. Volume In. or " Inch or Inches Yd. Yard
B. In reference to such abbreviations as A.S.T.M., A.W.W.A., etc. where a specification number is referred to, the latest revision of said specification shall apply.\
1.40 REFERENCE SPECIFICATIONS
A. Where reference is made in these specifications to specifications compiled by other agencies, organizations, or departments, such reference is made for expediency and standardization from the material suppliers' point of view, and such specifications referred to are hereby made a part of these specifications.
B. Whenever reference is made to the furnishing of materials or testing thereof to conform to the
Standards of any technical society, organization, or body, it shall be construed to mean the latest standard, code, specification, or tentative specification adopted and published at the time of advertisement for bids, even though reference has been made to an earlier standard, and such standards are made a part hereof to the extent which is indicated or intended.
C. The following are names and abbreviations of such groups:
1. AASHO American Association of State Highway Officials
2. ACI American Concrete Institute
3. AGMA American Gear Manufacturers Association
4. AIEE American Institute of Electrical Engineers
5. AISC American Institute of Steel Construction
6. API American Petroleum Institute
7. AREMA American Railway Engineering and Maintenance-of-Way
Association
8. ASCE American Society of Civil Engineers
9. ASA American Standards Association
10. ASHE American Society of Heating & Ventilating Engineers
11. ASTM American Society for Testing Materials
12. ASME American Society of Mechanical Engineers
13. AWSC American Welding Society Code
00 72 00-14 GENERAL INFORMATION
14. AWPA American Wood Preservers Association
15. AWWA American Water Works Association
16. FED. SPEC. Federal Specification
17. NAVY SPEC. Navy Department Specification
18. NEC National Electric Code
19. NEMA National Electrical Manufacturer's Association
20. SAE Society of Automotive Engineers Standards
21. SHBI Steel Heating Boiler Institute
22. U.L., INC. Underwriters' Laboratories, Incorporated
D. Where no reference is made to a code, standard, or specification, the Standard Specifications of the ASTM, the ASA, the ASME, the AIEE, or the NEMA shall govern.
1.41 INCIDENTAL ITEMS
A. CONTRACTORS are especially notified that no incidental items of work will be paid for unless there appears an item in the bid form for such work. It must be strictly understood that the prices bid are for complete and acceptable work.
1.42 PUBLIC UTILITIES AND OTHER PROPERTY
A. In case it is necessary to change or move the property of OWNER or of a public utility, such property shall not be moved or interfered with until ordered to do so by the ENGINEER and OWNER. The right is reserved to the ENGINEER of public utilities to enter upon the limits of the project for the purposed of making such changes or repairs of their property that may be made necessary by performance of this contract.
1.43 USE OF EXPLOSIVES
A. Use of explosives will not be allowed.
1.44 TOOLS AND ACCESSORIES
A. The CONTRACTOR shall, unless otherwise stated in the detailed specifications, furnish with each type, kind, or size of equipment, one (1) complete set of suitably marked high grade tools and appliances which may be needed to adjust, operate, maintain, or repair the equipment.
B. Such tools and appliances shall be furnished in approved painted steel cases, properly labeled and equipped with good grade cylinder locks and duplicate keys.
C. Spare parts shall be furnished as specified in the specific provisions or contract items.
D. Each piece of equipment shall be provided with a substantial name plate securely fastened in place and clearly inscribed with the manufacturer's name, year of manufacture, and principal rating data.
00 72 00-15 GENERAL INFORMATION
1.45 REFERENCE STANDARDS
A. Reference to standards, specifications, manuals or codes of any technical society, organization, or association, or to the laws or regulations of any governmental authority, whether such reference be specific or by implication, shall mean the latest standard specification, manual code, or laws or regulations in effect at the time of opening of Bids (or on the Effective Date of the Agreement if there were no Bids), except as may be otherwise specifically stated. However, no provision of any referenced standard, specification, manual, or code, (whether or not specifically incorporated by reference in the Contract Documents) shall be effective to change the duties and responsibilities of the OWNER, CONTRACTOR, or ENGINEER, or any of their Consultants, agents, or employees from those set forth in the Contract Documents, nor shall it be effective to assign to ENGINEER and OWNER, or any of the their consultants, agents, or employees, any duty or authority to supervise or direct the furnishing or performance of the Work.
1.46 PUBLIC UTILITIES AND OTHER PROPERTY
A. In case it is necessary to change or move the property of the OWNER or of a public utility, such property shall not be moved or interfered with until authorized by the utility company, OWNER, or ENGINEER.
B. It will be the CONTRACTOR’s responsibility to contact the proper authority, and set up a field meeting to verify by uncovering of the utility and determine the location and elevation of each major utility described above, at least two weeks prior to crossing the utility. If field conditions vary from those shown on the contract plans, the CONTRACTOR shall notify the ENGINEER immediately of field conditions to be encountered, so sufficient time exists to make any necessary adjustments in line or grade. Failure by the CONTRACTOR to make proper and timely verification of the above described utilities shall be justification for rejection of claim for extra cost by the CONTRACTOR.
C. If, after field verification, it is necessary to change or move the property of a property owner or of a public utility, seven (7) days notice shall be given before such change, and such property shall not be moved or interfered with until authorized by the property owner or the utility company. The right is reserved to the property owner or public utilities to enter upon the limits of the project for the purpose of making such changes or repairs of their property that may be made necessary by the performance of this contract.
1.47 CONSTRUCTION IN PUBLIC ROADS
A. CONTRACTOR will be responsible for complying with all federal, State, County and City regulations pertaining to construction in public roadway and traffic safety. No public road shall be entirely closed overnight. It shall be the responsibility of the CONTRACTOR to build and maintain all weather bypasses and detours, if necessary, and to properly light, barricade and mark all bypasses and detours that might be required on and across the roads involved in the work included in this contract.
B. The CONTRACTOR shall make every effort to complete construction and allow immediate access to adjacent property at driveway entrances located along the roads. Owners or tenants of improvements where access and/or entrance drives are located shall be notified at least twenty-four (24) hours prior to the time the construction will be started at their drive-ins or entrances, and the CONTRACTOR shall provide temporary ingress to entrance drives where necessary. The CONTRACTOR shall be responsible for all road and entrance reconstruction and repairs and maintenance for same for a period of one year from the date of acceptance of the project.
00 72 00-16 GENERAL INFORMATION
C. In addition to roads and entrances cut by construction excavation, if any other roads or streets in the area are used by the CONTRACTOR or Subcontractors during the progress of construction and are damaged by the CONTRACTOR in the opinion of the Engineer, the Contractor, when directed by the OWNER, shall immediately repair such damage. In the event the repairs and maintenance are not made in a reasonable period of time and it becomes necessary for the County, City, OWNER or ENGINEER to make such repairs, the CONTRACTOR shall reimburse the County, City, OWNER or ENGINEER for the cost of such repairs.
D. The CONTRACTOR shall, at all times, keep a sufficient width of the roadway clear of dirt and other materials to allow the free flow of traffic on the project site. The CONTRACTOR shall assume any and all responsibility for damage, personal or otherwise, that may be caused by the construction along roads or private drives.
1.48 PRELIMINARY FIELD TESTS
A. As soon as conditions permit, the CONTRACTOR shall furnish all labor, materials, and instruments and shall make preliminary field tests of equipment. If the preliminary field tests disclose any equipment furnished under this contract which does not comply with the requirements of the contract documents, the CONTRACTOR shall, prior to the acceptance tests, make all changes, adjustments, and replacements required.
B. Equipment which is subject to a “start-up” will be paid at ninety-five percent (95%) of the schedule of values amount, less retainage, when construction of the equipment is complete. The remaining five percent (5%) will be paid when the equipment is placed in service. Retainage will be released as per the Final Payment terms.
1.49 FINAL FIELD TESTS
A. Upon completion of the work and prior to final payment, all items installed under this contract shall be subjected to acceptance tests as specified or required to comply with the contract documents.
B. The CONTRACTOR shall furnish labor, fuel, energy, water, and all other materials, equipment and instruments necessary for all acceptance tests, at no additional cost to the OWNER.
1.50 FENCES, IMPROVEMENTS, AND DRAINAGE CHANNELS
A. Fences or other improvements removed to permit construction shall be replaced in the same location and left in a condition as good as, or better, than that in which they were found. There shall be no separate pay item for fences removed or damaged beyond the limits shown in the plans.
B. Temporary fencing for maintenance of site security shall be provided by the CONTRACTOR at his expense. Temporary fencing, with gates, to restrain livestock shall be provided through areas where livestock are pastured, unless the CONTRACTOR makes satisfactory arrangements with the land owner and/or tenant. The temporary fence shall be installed on the easement lines and shall be removed after the trench has been backfilled.
C. Where surface drainage channels or drainage structures are disturbed or altered during construction, they shall be restored to their original condition of grade and cross section as soon as possible.
00 72 00-17 GENERAL INFORMATION
D. Temporary channels required to provide adequate drainage during construction shall be provided and maintained by the CONTRACTOR. No separate payment shall be allowed.
1.51 DUST CONTROL
A. CONTRACTOR shall take responsible measures to prevent unnecessary dust. Earth surfaces subject to dusting shall be kept moist with water or by application of a chemical dust suppressant.
Dusty materials in piles or in transit shall be covered when practical to prevent blowing. Dust control shall be provided on all days within the contract period regardless of work taking place or not. CONTRACTOR shall allow at least four times per day as required. No separate pay shall be provided.
B. Buildings or operating facilities which may be affected adversely by dust shall be adequately protected from dust. Existing or new machinery, motors, instrument panels or similar equipment, shall be protected by suitable dust screens. Proper ventilation shall be included with dust screens.
1.52 ENVIRONMENTAL PROTECTION REQUIREMENTS
A. The CONTRACTOR shall provide and maintain, during the life of the contract, environmental protection as defined herein:
1. Plan for and provide environmental protective measures to control pollution that develops during normal construction practice.
2. Plan for and provide environmental protective measures required to correct conditions that develop during the construction of permanent or temporary environmental features associated with the project.
3. Comply with Federal, State, and local regulations pertaining to the environment, including water, air, solid waste, hazardous waste and substances, oily substances, and noise pollution. Obtain all construction and disposal permits as required.
1.53 ENVIRONMENTAL PROTECTION PLAN
A. All of the CONTRACTOR’s employees shall be trained on the site Environmental Protection
Plan requirements. The CONTRACTOR shall meet all requirements of the OWNER’s Environmental Protection Plan described herein.
1. Land Resources: Except in areas to be cleared, DO NOT remove, cut, deface, injure, or destroy trees or shrubs without the OWNER’s permission. DO NOT fasten or attach ropes, cables, or guys to existing nearby trees for anchorages unless authorized by the OWNER.
Where such use of attached ropes, cables, or guys is authorized, the CONTRACTOR shall be responsible for any resultant damage.
2. Replacement: Trees and other landscape features scarred or damaged by equipment operations, and replace with equivalent, undamaged trees and landscape features. Obtain OWNER approval before replacement.
3. Oily and Hazardous Substances: Prevent oil or hazardous substances from entering the ground, drainage areas, or navigable waters. In accordance with 40 CFR §112, surround all temporary fuel oil or petroleum storage tanks with a temporary berm or containment of sufficient size and strength to contain the contents of the tanks, plus ten percent (10%)
00 72 00-18 GENERAL INFORMATION
freeboard for precipitation. The berm shall be impervious to oil for seventy-two (72) hours and be constructed so that any discharge will not permeate, drain, infiltrate, or otherwise escape before cleanup occurs.
4. Storm Water Drainage: There shall be no discharge of excavation groundwater to the sanitary sewer, storm drains, or to drainage ditches without prior specific authorization by required regulatory agencies and OWNER in writing. Discharge of hazardous substances will not be permitted under any circumstances. Construction site runoff shall be prevented from entering any storm drain or the drainage ditch directly by the use of straw bales or other method suitable to the ENGINEER. CONTRACTOR shall provide erosion protection of the surrounding soils. CONTRACTOR shall be responsible for payment and receipt of a stormwater permit if necessary. CONTRACTOR shall maintain stormwater controls of said permit per state, local agencies or ENGINEER and OWNER.
5. Fish and Wildlife Resources: DO NOT disturb fish and wildlife. DO NOT alter water flows or otherwise significantly disturb the native habitat adjacent to the project and critical to the survival of fish and wildlife, except as indicated or specified.
6. Burn-off: Burn-off of the ground cover is not permitted.
7. Protection of Erodible Soils: Immediately finish the earthwork brought to a final grade, as indicated or specified. Immediately protect the side slopes and back slopes upon completion of rough grading. Plan and conduct earthwork to minimize the duration of exposure of unprotected soils.
8. Temporary Protection of Erodible Soils: Use the following methods to prevent erosion and control sedimentation:
a. Mechanical Retardation and Control of Runoff: Mechanically retard and control the rate of runoff from the construction site. This includes construction of diversion ditches, benches, berms, and use of silt fences and straw bales to retard and divert runoff to protected drainage courses.
b. Vegetation and Mulch: Provide temporary protection on sides and back slopes as soon as rough grading is completed or sufficient soil is exposed to require erosion protection. Protect slopes by accelerated growth of permanent vegetation, temporary vegetation, mulching, or netting. Stabilize slopes by hydro-seeding, anchoring mulch in place, covering with anchored netting, sodding, or such combination of these and other methods necessary for effective erosion control.
c. Provide new seeding where ground is disturbed. Include topsoil or nutrients during the seeding operation necessary to…