ESBD_File_335074_New Tower Requirement Ch.1.pptx

PPTX presentation 10 MB Posted

Attached to
Communications Tower
Solicitation number
RFQ-23-144
Issued by
Bexar County, San Antonio City, Texas

About this file

The document provided appears to be a PowerPoint file related to a communications tower project being requested by the Alamo Area Council of Governments (AACOG) on behalf of the 149th Fighter Wing, Texas Air National Guard, Joint Base San Antonio (JBSA). The project involves the installation of a 100' communications tower on JBSA-Lackland AFB located in San Antonio, Texas. Construction is expected to begin no later than December 1, 2023, with a completion date of April 30, 2024. The project is being funded through a Defense Economic Adjustment Assistance Grant from the Texas Military Preparedness Commission.

The project will take place within the jurisdictions of Bexar County and the City of San Antonio. No other specific pricing terms, set asides, incumbents, funding requirements, or other salient information is provided in the document.

View the file

Other files

File Type Posted
ESBD_File_335074_Picutres of current tower.docx DOCX document
ESBD_File_335074_Addendum 2 doc.doc DOC document
ESBD_File_335074_RFQ DEAAG Communications Tower.pdf PDF
ESBD_File_335074_917 Utilities.pdf PDF
ESBD_File_335074_Addendum 1.doc DOC document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Install new 100’ tower next to existing tower base as highlighted in blue.

Install a wave guide bridge as required to transition cables from new tower to the existing wave guide bridge

Tower needs to be designed to hold:

5xUVU-200 antennas 1xTACO D2218 antenna (UHF/VHF/VHF) 1xTACO D2213 (1xUHF / 1xVHF) 1xSADL antenna 1xLINK-16 (MIDS-JTRS) antenna 1xADSB antenna 1xDPV108v RRU antenna 3xL1G1A-STD GPS antennas for the RRU, ADSB and for the SADL radio/Comm radio time reference.

Install new tower next to existing tower base as highlighted in blue

Install a wave guide bridge as required to transition cables from new tower to the existing wave guide bridge

Need to install cable brackets next to existing brackets to allow for up to 8 additional radio cables (as highlighted)

Need to install 2 more wall penetrations to allow for up to 8 cables to penetrate the building (as highlighted)

Need to install an additional grounding bar on the inside of the building (in the ceiling of the gym) to ground up to 8 additional cables

Current requirement is for 4 additional cables but planning for 8 cables provides room for growth

Remove existing tower once new tower is installed and BSE has moved the antennas and cables from the existing tower

Must get FAA approval to use a crane and to build a permanent tower Step 1 is to go to Obstruction Evaluation / Airport Airspace Analysis (OE/AAA) (faa.gov) and get a login Step 2 is to fill out a 7460-1 application on that website for the crane to construct the tower and one for the permanent tower. The coordinates for the tower must be NAG 83 format which are N 29 23 3.982, W 98 35 49.972 and 669 feet. This process takes about 4-6 weeks to get approval for each request and will let you know if obstruction lighting is required for the tower. You can contact the FAA at the below numbers (Andrew Hollie was my POC for the last tower we did):