ESBD_File_333648_CARRI BLDG ADD2.pdf
PDF 9 MB Posted
- Attached to
- RENOVATION OF CARRI BLDG.
- Solicitation number
- Not on record
- Issued by
- Nacogdoches County, Texas
About this file
This document is an Invitation to Bid (ITB) for a building renovation project at the Center for Applied Research and Rural Innovation (CARRI) facility on the campus of Stephen F. Austin State University (SFASU) in Nacogdoches, Texas. The project includes renovations to the existing CARRI building, such as modifying the existing roofing system, parking lot improvements, drainage work, and other site improvements. The bid is due on October 17, 2023, at 3:00 PM. A pre-bid meeting and site visit is scheduled for August 28, 2023, at 9:00 AM, and all questions related to Addendum No. 2 must be submitted by September 28, 2023. The evaluation of bids and awards is expected to occur between October 18-20, 2023, with the contract expected to be issued on November 17, 2023. The substantial completion date is November 2024, and the facility is expected to be occupied by December 1, 2024.
The ITB includes pricing information, preference claims, and several bid alternates. Bidders must provide pricing for the base bid and several alternates, including adding a covered porch area, a new roof at Building "B", deleting certain office renovations, omitting retractable wall panels, using a different roofing membrane, and adding an on-site septic system. The contract will be awarded based on the best interest of SFASU, and the university reserves the right to reject any and all bid items.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| ESBD_File_333648_ITB CARRI BLDG ADD1.pdf | ||
| ESBD_File_333648_ITB #CARRI BLDG.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
INVITATION TO BID
FAILURE TO SIGN WILL DISQUALIFY BID Bid No.: ITB #CARRI BLDG
ADDENDUM NO. 2
Due Date: October 17, 2023 at 3:00 P.M.
Signature City Zip Show bid opening and bid invitation number in lower left-hand corner of sealed bid envelope and return sealed bids to:
Printed Name
VENDOR NAME AND ADDRESS
PHONE/FAX
Email to: bids@sfasu.edu Mail to: Stephen F. Austin State University P. O. Box 13030, SFA Station 2102 Alumni Drive, Austin Bldg., Room 131 Nacogdoches, Texas 75962-3030 Phone (936) 468-2206
FAX (936) 468-4282
(See 2.3 related to submittal)
Name of Firm
Phone
Mailing Address
FAX
City State Zip
See Instruction 2.10 on Back for Vendor ID Number Is Vendor a State of Texas certified HUB? Yes
Delivery in ______ Days Cash Disc. ________ % _______ Days
Check all that apply if Preference Claimed under Rule 34 TAC 20.38 __ Products of persons with mental or physical disabilities __ Supplies, materials or equipment: produced in TX/offered by TX bidders*
__ Products made of recycled, remanufactured, or environmentally sensitive materials
__ Agricultural products grown in TX __ Energy efficient products __ Agricultural products offered by TX bidders* __ Rubberized asphalt paving material __ USA produced supplies, materials or equipment __ Recycled motor oil and lubricants __ Products produced at facilities located on formerly contaminated property
__ Products and services from economically depressed or blighted areas
*By signing this bid, bidder certifies that if a Texas address is shown as the address of the bidder, bidder qualifies as a Texas resident Bidder as defined in Rule 34 TAC 20.38.
IF QUOTING OTHER THAN THE REFERENCED ITEM(S) BELOW, BROCHURE AND/OR SPECIFICATIONS SHOULD BE ENCLOSED.
ALL BIDS WILL BE CONSIDERED F.O.B. DESTINATION UNLESS OTHERWISE NOTED.
AWARD NOTICE: Stephen F. Austin State University (SFASU) reserves the right to make an award on the basis of low line item bid, low total of line items, or in any other combination that will serve the best interest of SFASU and to reject any and all bid items in the sole discretion of SFASU.
Item No. Description Qty. & Unit Unit Price Extension Quote price on quantity and unit of measure, extend and show total. If error in extension, unit price shall govern.
Items for state use are exempt from state sales and federal excise tax. Do not include tax in your bid.
ADDENDUM NO. 2
THIS ADDENDUM MUST BE ACKNOWLEDGED IN ORDER
FOR THE RESPONSE TO RECEIVE CONSIDERATION.
FAILURE TO ACKNOWLEDGE THE ADDENDUM WILL
RESULT IN DISQUALIFICATION OF THE RESPONSE.
STEPHEN F. AUSTIN STATE UNIVERSITY
Invitation To Bid #CARRI BLDG ADD2
CONTINUATION PAGE
CHANGE TO SCHEDULE OF EVENTS (IN RED)
Issuance of Invitation to Bid…………….….…. …. August 18, 2023 Pre-bid meeting/Site visit………….……August 28, 2023, 9:00 am All questions to be submitted………September 8, 2023, 10:00 am Issuance of Addenda No. 2 ………. September 12, 2023, 6:00 pm **Questions related to Addenda No. 2 to be submitted…Sept. 28, Issuance of Addenda No. 3……………. October 5, 2023, 5:00 pm Bid Opening Date……………………October 17, 2023, 3:00pm Evaluation of bids and awards…………. October 18-20, 2023 Compile contract and approval………………Oct 23-Nov 16, 2023 Issue contract………………………………….…November 17,2023 Substantial completion……………………….……November, 2024 Occupy facility……………………………….……December 1, 2024
*Dates are tentative/award contingent upon board approval
**All questions related to Addenda No, 2 should be submitted to Mark Strong, mstrong@glstexas.com
See attachment following this page from GLS dated September 12, 2023 titled ADDENDUM NUMBER TWO (002) – 13 pages total mailto:mstrong@glstexas.com
ADDENDUM NUMBER TWO (002)
Stephen F. Austin State University 1936 North Street Nacogdoches, Texas 75965
Re: Renovation to CARRI Facility
ARCHITECTURE ·ENGINEERING· INTERIORS
LANDSCAPE • SURVEYING
LUFKIN ·BRYAN· TYLER· GROESBECK
September 12, 2023
GLS Job No.: 501154
NOTICE TO BIDDERS:
This addendum shall be considered a part of the contract documents for the above named project and incorporated with the issued documents and specifications dated July 26, 2023, and all addenda issued thereof. This Addendum Number Two (002) dated September 12, 2023, shall govern and take precedence. This Addendum consists of thirteen (13) pages.
The bid date has been changed to be Tuesday, October 17, 2023. The time and location remain unchanged.
CLARIFICATIONS:
1. There is a tank on the NW side of the building near the well house. It is 14' off the building and will be inches from the footing for the new retainer wall. Is this tank to remain, and will water lines have to be relocated in order to install retainer wall?
See revised sheet C1 .00 attached. Tank and well house will remain. Retaining wall is relocated per this drawing.
2. Will the vegetation on the North side of the building and around the existing covered parking need to be removed?
Contractor shall clear all vegetation, brush, etc. within 1 O' of the north, east and south side of the building. All areas between south face off the building and parking shall be clear of existing grass/weeds and resodded.
3. There is a portable building adjacent to the existing covered parking that is to be removed.
Is the portable building to remain? Also, is the fencing that in front of portable building to remain or be removed?
Remove storage building at the south end of the covered parking area down to the slab.
Portable building on north end, along with the covered parking area and fencing in front of covered parking area shall remain.
4. On Sheet C1 .00 there is an offset on the East parking lot where we are to remove 7 SY of concrete. On Sheet C1 .01 it appears the East side of the parking lot is straight. Are we to add additional paving similar to the South parking in order to make parking straight?
See revised sheet C1 .01 attached.
5. Where are the details for the bollards and speed bump?
Omit speed bump and bollard.
1609 S. CHESTNUT • SUITE 202
LUFKIN, TEXAS · 75901
T.B.P.E.L.S. FIRM NO. F-413
T.B.A.E. FIRM NO. BR 351
PHONE: 936-637-4900
FAX: 936-637-6330
T.B.P.E.L.S. FIRM NO. 1011 0900
GLSTEXAS. COM
W 15011501154\Bidding\Addenda\Addendum No. 011501154-Addendum No. 01.docx
0 10 20 40
SCALE: 1"=20'-0"
S
C H
E S
T N
U T S
T
S T E
L
U F K
IN
T E X
A S
-4
C R
O S
S P A
R K
D R
S
T E
B R
Y A
N
T E X
A S
(9
-9
R
IC
E
R O
A D
S T
E
T Y
L E
R
T E
X A
S
-3
C1.00
D :\5
\5
4\
-C D
\C iv il\
-C 1.
-E xi st in g
C on di tio ns a nd D em o
Pl an
.d w g
/2 1/
:3
PM
REMOVE AND DISPOSE OF EXISTING
COVERED PARKING
REMOVE AND DISPOSE OF
EXISTING CONCRETE STEPS
REMOVE AND DISPOSE OF EXISTING
CONCRETE SIDEWALK - 92 SY
REMOVE AND DISPOSE OF
EXISTING CONCRETE - 39 SY
REMOVE AND DISPOSE OF
EXISTING RETAINING WALL - 2 SY
REMOVE AND DISPOSE OF
EXISTING CONCRETE - 109 SY
REMOVE AND DISPOSE OF
EXISTING CONCRETE STEPS
ADJUST EX CLEANOUT
TO FINAL GRADE
ADJUST EX GAS VALVE
TO FINAL GRADE
REMOVE AND DISPOSE OF
EXISTING DRAIN
REMOVE AND DISPOSE OF
EXISTING DRAIN
REMOVE AND DISPOSE OF
EXISTING SPEED BUMP
REMOVE AND DISPOSE OF
EXISTING CONCRETE - 7 SY
REMOVE AND DISPOSE OF
EXISTING BOLLARDSCAUTION! EXISTING
UNDERGROUND COMMUNICATIONS
EXISTING WELL
HOUSE TO REMAIN
EXISTING ASPHALT TO REMAIN
ADJUST EX WATER
STRUCTURE TO FINAL GRADE
DISCONNECT AND PLUG
EXISTING STORM SEWER
REMOVE AND DISPOSE OF
EXISTING STORM SEWER - 22 LF
REMOVE AND DISPOSE OF
EXISTING STORM SEWER - 8 LF
FF = 467.05 +/-
REMOVE AND DISPOSE OF
EXISTING POST
REMOVE AND DISPOSE OF
EXISTING SIGN
GENERAL NOTES:
1. PAVEMENT TO REMAIN.
2. ALL AREAS DISTURBED FOR SITE GRADING TO REMOVE AND DISPOSE
OF IMPACTED UNDERBRUSH, ROOTS AND DEBRIS.
3. ALL AREAS DISTURBED BY CONSTRUCTION TO BE HYDROMULCHED.
1 1 1
1 1
EXISTING TREE AND ROOTS TO
BE REMOVED AND DISPOSED OF
EXISTING TREE AND ROOTS TO
BE REMOVED AND DISPOSED OF
EXISTING TREE AND ROOTS TO
BE REMOVED AND DISPOSED OF
RE: MEP DRAWING
RELOCATE EX RPZ OFF SIDEWALK (BASE
BID), / FOUNDATION (ALT BID). CONTRACTOR
TO FIELD VERIFY WATER LINE DEPTH AND
LOCATION PRIOR TO CONSTRUCTION.
COORDINATE W / ENGINEER.
EXISTING TANK TO REMAIN
EXISTING WATER VALVES TO REMAIN
DO NOT REMOVE
CLEANOUT
09/08/2023
R5'
R2'
R2'
.9
5'
.0
9'
9'
10'
20'
5'
5'
5'
10'
5'
5'
20'
9'
20'
9'
23'
3'
20'
9'
28.25'
20'
9'
23.4'
.2
5'
35.71'
8'
198'
63.7'
27.71'
.0
9'
4.5 4.5
6 7
11 12
16 17
1.
5.
57.87'
8.16'
6.32'
3.27'
.1
9'
.1
7' 5'
5'
5'
6 7
0 10 20 40
SCALE: 1"=20'-0"
S
C H
E S
T N
U T S
T
S T E
L U
F K
IN
T E X
A S
-4
C R
O S
S P A
R K
D R
S
T E
B
R Y
A N
T E X
A S
(9
-9
R
IC
E
R O
A D
S T
E
T Y
L E
R
T E
X A
S
-3
C1.01
D :\5
\5
4\
-C D
\C iv il\
-C 1.
-S ite P la n.
dw g
/2
1/
:3
PM
ADA PARKING SPACES W / WHEELSTOPS
AND SIGN - TYPICAL 4 LOCATIONS
22 SPACES
SP
AC
ES
S
PA
C
ES
S
PA
C
ES
PROPOSED CONCRETE
SIDEWALK - 262 SY TOTAL
GUARDRAIL - 32 LF
9 STEPS
6" RISE
12" TREAD
7 STEPS
6.6" RISE
12" TREAD
SP
AC
ES
WHEEL STOPS - 10 EAASPH TO ASPH TIE-IN
FF = 467.05 +/-
PROPOSED CONCRETE ALT BID - 23 SY TOTAL
SIDEWALK ALTERNATE BID
ADDITIONAL PAVING W / SURFACE
TREATMENT - 71 SY TOTAL
ADJUST EX CLEANOUT TO
FINAL GRADE
CAUTION! EXISTING
UNDERGROUND
COMMUNICATIONS
CAUTION! EXISTING
OVERHEAD ELECTRIC
ADJUST EX GAS VALVE
TO FINAL GRADE
ADA PARKING SPACE W /
WHEELSTOP AND SIGN
PROPOSED 5" CONCRETE - 108 SY
TOTAL
12" HDPE STORM SEWER CULVERT @ 0.5% - 65 LF
W / FILL DEPTH STRUCTURE BACKFILL
PRE-CAST HEADWALL RE: DETAIL
( 2 LOCATIONS)
PRE-CAST HEADWALL RE: DETAIL
( 2 LOCATIONS)
PROPOSED RETAINING WALL
CAUTION! EXISTING
WELL HOUSE
GENERAL NOTES:
1. EXISTING ASPHALT TO BE CLEANED AND ALL CRACKS CRACK
SEALED.
2. CRACK SEAL PARKING LOT. THE SEALANT SHALL BE CRAFCO
POLYFLEX 3 OR APPROVED EQUAL THAT MEETS ALL THE
REQUIREMENTS OF ASTM-D-6690.
3. TWO COURSE SURFACE TREATMENT TO BE APPLIED AFTER CRACK
SEAL AND CONSTRUCTION COMPLETED.
4. PARKING LOT STRIPING TO BE REDONE AFTER CRACK SEALING.
5. PAVEMENT STRIPING FOR PARKING TO BE WHITE.
RAMP 7.40 %
PROPOSED 5" CONCRETE - 115 SY TOTAL
EXISTING RETAINING WALL
4" WIDE PARKING LOT STRIPING (WHITE)
AFTER SURFACE TREATMENT IS COMPLETED
NOTES:
32 SY OF SIDEWALK REMOVED FROM BASE BID
HANDRAIL - 37 LF
HANDRAIL - 33 LF
END OF GUARDRAIL/START
OF HANDRAIL
HANDDRAIL - 31 LF
END OF HANDRAIL/START
OF GUARDRAIL
GUARDRAIL - 90 LF
ALT BID 7
BASE BID
RE: MEP DRAWING
ALT BID 6 BASE BID
ALTERNATE BID 6 - CRACK SEAL AND 2 COURSE SURFACE
TREATMENT - 1155 SY AND RESTRIPE PARKING LOT
ALTERNATE BID 7 - CRACK SEAL AND 2 COURSE SURFACE
TREATMENT - 1237 SY AND RESTRIPE PARKING LOT
BASE BID - CRACK SEAL AND 2 COURSE SURFACE
TREATMENT - 1083 SY AND RESTRIPE PARKING LOT
FIBER OPTICS CONDUIT TO BUILDING "B"
SEE ELECTRICAL SHEET E9.11
ADDITIONAL PAVING W / SURFACE
TREATMENT - 27 SY TOTAL
RELOCATE EX RPZ OFF SIDEWALK (BASE
BID), / FOUNDATION (ALT BID). CONTRACTOR
TO FIELD VERIFY WATER LINE DEPTH AND
LOCATION PRIOR TO CONSTRUCTION.
COORDINATE W / ENGINEER.
RELOCATE EX RPZ OFF SIDEWALK (BASE
BID), / FOUNDATION (ALT BID). CONTRACTOR
TO FIELD VERIFY WATER LINE DEPTH AND
LOCATION PRIOR TO CONSTRUCTION.
COORDINATE W / ENGINEER.
ADJUST EX CLEANOUT TO
FINAL GRADE
ADJUST EX CLEANOUT TO
FINAL GRADE 1
CAUTION! EXISTING
WATER TANK
ADJUST EX WATER VALVES
TO FINAL GRADE (2)
09/11/2023
BS 462.45BS 462.45
TS 466.95
P 466.98
TS 466.95
P 466.48
SW 466.94P 466.63
P 466.77
P 462.35
MATCH EX
P 462.24
MATCH EX
FL 466.50
FL 463.33
FL 465.60
P 466.90
P 466.72
P 466.57
P 465.93
MATCH EX
P 466.72
SW 467.02
464465466467468469470
FL 463.91
MATCH EX
FL 465.84
FL 466.90FL 469.51
TW 470.50TW 469.00
TW 467.00
BW 466.00
BW 468.50 BW 470.15
P 466.90
P 466.92
P 466.13
P 466.27
P 466.03
MATCH EX
P 465.68
MATCH EX
P 467.05
P 467.05
FL 463.00
465 464
SW 467.05SW 467.05SW 467.05P 466.41
P 460.04
MATCH EX
P 459.94
P 466.67
P 461.44
MATCH EX
P 461.40
BW 466.32 BW 466.50
SW 466.97
SW 467.02
P 466.75
466 P 466.55
P 466.48
P 466.55
P 466.90
P 466.97P 466.97
P 466.90
P 461.96
MATCH EX
P 463.00
MATCH EX
P 461.88
P 462.97
P 462.96
MATCH EXP 463.53
P 466.87
P 466.90
TS 466.87
BS 463.02
BS 463.02
SW 466.87
FG 465.20
P 466.98
P 462.82
MATCH EX
P 466.98
BR 463.81
SW 465.99 TR 466.03
SW 466.14
SW 466.18
SW 466.69
TR 466.11
SW 466.74
SW 463.23
SW 466.47SW 466.61 SW 466.47
SW 466.55
SW 467.05
P 463.15
SW 467.05SW 467.05
SW 466.55
BR 463.88
SW 467.05SW 467.05
P 463.85
SW 464.40
TS 466.87
FG 466.32
SW 466.96
FG 465.25
SW 466.69
P 463.75
MATCH EX
P 463.58 P 463.52
P 463.39 P 463.25
P 463.12 P 463.00
SW 466.66
P 462.98
MATCH EX
SW 466.07
P 466.97
P 466.96
P 467.05
P 466.07
MATCH EX
P 466.14
MATCH EX
P 466.75
MATCH EX
P 466.72
MATCH EX
P 466.25
P 466.33
P 466.25
P 466.67P 466.63
0 10 20 40
SCALE: 1"=20'-0"
S
C H
E S
T N
U T S
T
S T E
L U
F K
IN
T E X
A S
-4
C R
O S
S P A
R K
D R
S
T E
B
R Y
A N
T E X
A S
(9
-9
R
IC
E
R O
A D
S T
E
T Y
L E
R
T E
X A
S
-3
C1.02
D :\5
\5
4\
-C D
\C iv il\
-C 1.
-G ra di ng P la n.
dw g
/2
1/
:3
PM
12" HDPE STORM SEWER CULVERT @ 0.5% - 65 LF
W / FILL DEPTH STRUCTURE BACKFILL
FF = 467.05 +/-
RE: INSET "A"
INSET "A"
1" = 10' - 0"
PROP SWALE
PROP SWALE
REGRADE AREA TO ENSURE
DRAINAGE AWAY FROM BUILDING
CONTRACTOR TO VERIFY ELEVATIONS OF
EXISTING PAVEMENT TO ENSURE
POSITIVE DRAINAGE TRANSITION OF
CONCRETE FROM ADA PARKING SPACES
TO EXISTING ASPHALT PAVEMENT
SIDEWALK ALTERNATE BID
ALT BID 7
BASE BID
RE: MEP DRAWING
ALT BID 6 BASE BID
FIBER OPTICS CONDUIT TO BUILDING "B"
SEE ELECTRICAL SHEET E9.11
09/11/2023
C A
Roof Area B: Existing metal roof approx. 4050 SF. install specified flute fill sarnafil system.
Roof Area C: Approx. 13,000 SF. existing roof is light weight concrete deck over light weight metal deck. Built up gravel roof is applied over concrete deck and over that system is 1/2" perlite, then 1/2" densdock with membrane surface. Tear off down to built up gravel roof. Remove/vaccum any loose gravel then install specified deck board and sarnafil system as specified.
Roof Area A: Approx 2260 SF. Existing roof is light weight concrete deck over light weight metal deck. Deck is covered with wood fiber board and modified bitumen roof surface. Remove roof surface and wood fiber board, cover with specified deck board and sarnafil system as specified.
B
N
T.B.P.E.L.S FIRM NO. F-413 T.B.A.E.
FIRM NO. BR 351 T.B.P.E.L.S FIRM NO.
10110900 T.B.P.E.L.S FIRM NO. 10110901
ARCHITECTURE - ENGINEERING - INTERIORS
LANDSCAPE - SURVEYING
1609 S. CHESTNUT ST. STE. 202 - LUFKIN, TEXAS 75901 - (936) 637-4900
4077 CROSS PARK DR. STE. 100 - BRYAN, TEXAS 77802 - (979) 776-9700
455 RICE ROAD STE. 107 - TYLER, TEXAS 75701 - (903) 581-3805
AS01
Roofing Notes Nacogdoches, Texas Stephen F. Austin State University CARRI Facility Renovations
Alternate #9: State in proposal the amount to be added to install new roof over section A & C as described above. Base bid shall be to reroof section B only.
AutoCAD SHX Text
D:\501\501154\06-CD\501154-AS01.DWG
AutoCAD SHX Text
9/8/2023 11:48 AM
AutoCAD SHX Text
DATE
AutoCAD SHX Text
DRAWN BY:
AutoCAD SHX Text
JOB NUMBER
AutoCAD SHX Text
SHEET NO.
AutoCAD SHX Text
APPV'D BY:
AutoCAD SHX Text
SCALE
AutoCAD SHX Text
D:\501\501154\06-CD\501154-AS01.DWG
AutoCAD SHX Text
9/8/2023 11:48 AM
AutoCAD SHX Text 2023 ALL RIGHTS RESERVED BY GOODWIN-LASITER, INC. UNAUTHORIZED USE OR UNAUTHORIZED USE OR REPRODUCTION IS PROHIBITED WITHOUT WRITTEN CONSENT FROM GOODWIN-LASITER, INC. GOODWIN-LASITER, INC.GOODWIN-LASITER, INC.
AutoCAD SHX Text 501154
AutoCAD SHX Text N.T.S.
AutoCAD SHX Text
MS
AutoCAD SHX Text
LE
AutoCAD SHX Text 9/11/23
GLS 9/16 00460-1 ALTERNATES
SECTION 00460
ALTERNATES
ALTERNATE No.1: State in proposal the amount to be added for furnishing and installing covered porch area as shown on detail 4/S2.11 and 5/A4.21.
ALTERNATE No. 2: State in proposal the amount to be added for new roof at Building “B” as shown on sheet A4.52.
ALTERNATE No. 3: State in proposal the amount to be deducted for deleting all work to create offices
113, 114, 115, 118, 119, 120, Corridor 117 and porch 116. If alternate is accepted, this area will remain as it currently exists.
ALTERNATE No. 4: State the proposal the amount to be deducted to omit retractable panels wall in panels between Conference 139, 140 and 144 and related structure as shown on A4.11, S2.11 and detail A4.63.
ALTERNATE No. 5: State in the proposal the amount to be deducted for using Sarnafil Sika Plan 60 mil nominal membrane, in leu of Sarnafil full 60 mil membrane as specified.
ALTERNATE No. 6: State in proposal the amount to be deducted for deleting seal coat and restriping of existing parking at east end of site as shown on Civil drawing.
ALTERNATE No. 7: State in proposal the amount to be deducted for deleting seal coat and restriping of existing parking at west end of site as shown on Civil drawing.
ALTERNATE No. 8: State in proposal the amount to be added for the following: On-site septic system: Provide and install as required (Design Load: 3,900 gallons/day based on TCEQ Table B1, Chapter 217.32, 260 occupants). Coordinate with a Sanitarian Engineer. (A Texas-registered Sanitarian shall design, permit, and install the system).
ALTERNATE No. 9: State in proposal the amount to be added to install new roof over section A & C as described on attached sheet AS01. Base bid shall be to reroof section B only per attached sheet AS01.
| 501154-Addendum No. 02-GLS.pdf |
| 501154-AS01.pdf |
| Sheets and Views |
| Oce 24x36 |
| SECTION 00460.pdf |
| SECTION 00460 |
| ALTERNATES |
File details come from the government source that posted it. Updated .