ESBD_File_331451_RFQ-903-1470CM- Addendum no 1.pdf
PDF 12 MB Posted
- Attached to
- REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGER-AT-RISK The University of Texas Rio Grande Valle
- Solicitation number
- RFQ-903-1470CM
- Issued by
- Hidalgo County, East Columbia CDP, Texas
About this file
This document is an Addendum to a Request for Qualifications (RFQ) issued by The University of Texas Rio Grande Valley for a Construction Manager-at-Risk contract. The RFQ is for construction services within the jurisdictions of Hidalgo County and East Columbia CDP in Texas. The addendum provides clarification on the solicitation documents, which can be accessed on the University's procurement website. The addendum does not appear to contain details about the specific products or services requested, project overviews, response dates, due dates, site visits, bidder's meetings, award dates, or the term of the contract.
The addendum also does not provide information on pricing terms, set asides, incumbents, funding requirements and sources, or any other salient details about the contract opportunity. The document appears to be a supplemental communication providing administrative clarification to interested parties regarding the RFQ process and accessing the solicitation documents.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ADDENDUM #001 PAGE 1 OF 2 AUGUST 9, 2023
ADDENDUM #001
REQUEST FOR QUALIFICATIONS FOR
CONSTRUCTION MANAGER AT RISK
The University of Texas Rio Grande Valley New Student Housing RFQ No.: 903-1470CM
Due Date: August 25, 2023
Prepared By:
Jerry Lopez – Project Manager
Project Control
(956) 684-6384 glopez@projectcontrol.com
ADDENDUM #001 PAGE 2 OF 2 AUGUST 9, 2023
REQUEST FOR QUALIFICATIONS FOR
CONSTRUCTION MANAGER AT RISK
The University of Texas Rio Grande Valley
New Student Housing RFQ No.: 903-1470CM
Addendum #001
The following information is issued to change, clarify, supplement or further explain the above referenced RFQ. This information shall supersede and take precedence over the information contained in the RFQ in the event of a conflict.
ITEM #001: 08/08/2023 Pre-submittal Conference Documents:
1. Attached is the Pre-submittal sign-in sheet 08/08/2023
2. Attached is the Pre-submittal Conference presentation on 08/08/2023 (19 slides)
ITEM #002: 08/08/2023 Clarification to questions received via email:
1. Clarification on question asked via email:
Question: How are the Commission services being handled for this project? Is the Commissioning provider to be part of the CMAR’s Team or to be procured by some other method?
Answer: Refer to the Owner’s Front End Documents Section 01 91 00 General Commissioning Requirements
End of Addendum #001
Meeting:
Date : 8/08/2023 x
Stephen Mikolaitis UT System smikolaitis@utsystem.edu
Jason Hartley UT System jason.hartley@utrgv.edu
Moses Ahmadi Project Control mahmadi@projectcontrol.com
Jerry Lopez Project Control glopez@projectcontrol.com
Merrill Stanley Project Control mstanley@projectcontrol.com
Name Company Email Phone
Project Name :
UT Project No. :
CM Pre- submittal ConferenceNew Student Housing
903-1470
Amanda Bishop SpawGlass Contractors (956) 412-9880 Laurel Ehasi SpawGlass Contractors laulel.ehsai@spawglass.com (817) 716-0146 Sam Saldana SpawGlass Contractors samuel.saldana@spawglass.com (956) 535-2028 Emmanuel Mena SpawGlass Contractors emmanuel.mena@spawglass.com (956) 266-4959
Jon Hermann Mechanical Reps, Inc. jonh@mechreps.com Walt Ferguson White Construction Company waltf@whiteconst.com Sam Saldana SpawGlass Contractors samuel.saldana@spawglass.com Joseph Gozalez Broaddus Construction jgonzalez@broaddususa.com (956) 688-2307
AUGUST 08, 2023
THE UNIVERSITY OF TEXAS RIO GRANDE
VALLEY
NEW STUDENT HOUSING
903-1470 CM
CMAR Pre-Submittal Conference
Agenda
• Introductions
• Project Overviews, Scope, and Schedule
• RFQ Overview
• HUB Requirements and Contact
• Questions
Introductions
• UTRGV Campus Staff
• The Office of Capital Projects
• Project Control Staff
• UTS HUB Staff
Project Overview
• New Student Housing
– 500 Suite Style Beds
– Dining Hall
• Two Project Deliveries
– 350 Beds in July 2025
– 150 Beds in April 2026
• CMAR Project Delivery Method
• Budget – CCL: $46,900,000
New Student Housing Site
West Bird's Eye View South Bird's Eye View
West View
North View
Project Schedule Owner approves Schematic Design Documents 12/14/23 Owner approves Design Development Documents 03/18/24 Owner approves Construction Documents 06/17/24 Owner issues Notice to Proceed for Construction 05/16/24 Partial Substantial Completion (350 Beds) 07/02/25 Full Substantial Completion (150 Beds) 04/29/26
RFQ Overview
• CMAR Selection Process
– RFQ Submittal Due Date, Time and Location
• August 25, 2023/ 2:00 PM (CST)
• Link: https://tinyurl.com/34czwmcz
• RFQ Schedule for Selection
– Anticipated Shortlist Notification Date: September 04, 2023
– Anticipated Interview Date: September 29, 2023
– Anticipated Executed Agreement: October 10, 2023
Historically Underutilized Business (HUB) Overview
What is a "Historically Underutilized Business"…
• is a for-profit entity that has not exceeded the size standards prescribed by 34 TAC §20.23, and has its principal place of business in Texas, and
• is at least 51% owned by an Asian Pacific American, Black American, Hispanic American, Native American, American woman and/or Service Disabled Veteran, who reside in Texas and actively participate in the control, operations and management of the entity's affairs.
Completing the HUB Sub-Contracting Plan (HSP)
• UT System Policy #137 requires a “good-faith effort” to include minority and woman-owned businesses in all of our procurement opportunities.
• All firms or individuals, both HUB and non-HUB, in-state or out-of-state, who propose on UT System opportunities, valued over $100,000 are required to submit a HUB Subcontracting Plan with their RFQ.
• Responses that do not include an HSP will be rejected as a material failure to comply with advertised specifications in accordance with the request for proposal.
• HUB Goal for this RFQ is 21.1%
HSP for CMAR RFQ Response: Self-Performing
Pg. 5
• Letter of HUB Commitment (Signature Required)
SEC 1.
• Respondent and Requisition Information
SEC 2a.
• A. No, I will not be subcontracting any portion of the contract, and I will be fulfilling the entire contract with my own resources.
SEC 3.
• Self Performance Justification
SEC 4.
• Affirmation (Signature Required) complete the following sections
• Sections 1-4
• Letter of HUB CommitmentSubmit.
Suggested language for Section 3
[Your Company] has the resources to complete pre-construction for this RFQ with our own equipment, supplies, materials and personnel. If sub contracting opportunities are identified at a future date, we will immediately contact the project manager and HUB Coordinator and commit to perform a Good Faith Effort through solicitation of HUB firms and submit an amended HUB Subcontracting Plan.
HSP FAQ’s
• Question: I am certified as a State of Texas HUB. Do I still have to fill out the HSP?
– Answer: Yes, every Proposer must complete the HSP or their Proposal will be disqualified.
• Question: If my company is based outside of the State of Texas, do I have to complete an HSP?
– Answer: Yes, your company’s place of business is not considered in determining who completes an HSP.
• Question: What are the cases that would exempt a company from filling out a HSP for this RFQ?
– Answer: None. Every Proposer must complete an HSP or their Proposal will be disqualified.
• Question: What is the biggest reason a Proposal may be disqualified during the RFQ process?
– Answer: HSP was not received or the Good Faith Effort was performed and documented.
Before Proposal Submission
You may send the HSP to Cynthia Booker for a courtesy draft review.
*Through Wednesday, August 23rd at 4:00 p.m. CST o For a courtesy draft review of your HUB Plan, you must submit it by August 23rd at 4:00 PM CDT/CST o HUB Plan MUST be submitted under separate cover per RFQ instructions in Section 1.5.3 & 1.13.4.
o Responses that do not include a HUB Plan will be rejected as a material failure to comply with advertised specifications in accordance with the request for proposals.
UT System HUB Program Contact Cynthia Booker
UT System Administration Office of HUB Programs Office: 512-322-3779 cbooker@utsystem.edu
Technical Aspects of the RFQ
Section 1
Section 2
Section 3
Section 4
Section 5
Questions?
| cover |
| 903-1470CM New Student Housing CM RFQ - Addendum No 01 08.09.23 |
| New Student Housing CM RFQ - Addendum No 01 08.09.23 |
| 903-1470 New Student Housing Pre-Submittal Conference Sign-in Sheet |
| Presubmittal Conference Presentation 08.08.23 |
File details come from the government source that posted it. Updated .