This Statement of Work (SOW) is a deliverables-based, firm-fixed-price contract solicitation from the Texas Military Department (TMD) procured through the Texas Department of Information Resources (DIR) for the design, build-out, configuration, and operational handoff of a complete Impact Level 4 (IL4) Microsoft Azure enterprise environment designated TxNET. The project encompasses network engineering and architecture, identity and access management, cloud platform engineering, database administration, knowledge management, low-code/no-code application development, enterprise asset management, and Agentic AI readiness across four sequential implementation stages: Mobilization & Environment Baseline, Build & Implementation, Optimization & Hardening, and Transition & Handoff. The environment must support an average of 4,850 concurrent enterprise users with surge capacity to 6,700 concurrent users, serve as a governed interoperability bridge between state/civil (IL2) and Department of Defense (IL5) environments, protect Controlled Unclassified Information (CUI), and achieve IL4 Authorization to Operate (ATO) status. The proposed contract structure allows offerors to submit either single-period or multi-year (Base plus Option Years) implementations with clearly delineated milestones, deliverables, and firm-fixed milestone prices. The illustrative milestone timeline spans approximately nine months from mobilization through transition and handoff, though offerors may propose alternative schedules.

Payment is strictly deliverables-based and contingent upon formal written acceptance by designated TMD representatives; no payment is made for hours or time-and-materials. Vendor-internal contract oversight, project management, and quality control costs must be incorporated into milestone pricing and are not separately payable. All contractor personnel must be vetted and authorized to access state and federal IL2/IL4 systems, including U.S. citizenship requirements for those handling CUI, completion of background investigations satisfying DoD Tier 3/Moderate Risk Public Trust standards, and role-based security training. The resulting contract must incorporate Infrastructure-as-Code repositories, comprehensive operational runbooks, automation for routine operations, and a complete transition-out package enabling seamless transfer of sustainment to TMD with minimal ongoing management burden. Service Level Objectives include 99.9% monthly uptime for core enterprise services, 15-minute acknowledgment for critical security incidents, 99% backup success rates, Recovery Time Objective of four hours for critical workloads, and validated scalability to 6,700 concurrent users. Proposals will be evaluated on best-value basis across technical solution completeness (25%), compliance and accreditation capability (20%), turn-key and minimal-management approach (15%), personnel qualifications (10%), Agentic AI readiness (10%), milestone realism (10%), past performance (5%), and price/value (5%).

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Texas Military Department | TxNET IL4 Enterprise Environment

Statement of Work (SOW) TxNET IL4 Enterprise Environment Contracted Support for a Secure, Cloud-Enabled Enterprise Network— Turn-Key Implementation

Prepared for: Texas Military Department (TMD) Procurement Vehicle: Texas Department of Information Resources (DIR) Solicitation Type: Deliverables-Based, Firm-Fixed-Price (Milestone) Document Status: FINAL / Clean Version with Integrated Revisions Date: May 2026

Table of Contents

1. Introduction and Background

2. Project Objectives

3. Scope of Work

3.1 Network Engineering / Architecture

3.2 Identity & Access Management (IAM) Engineering / Architecture

3.3 Azure Cloud Server / Platform Engineering / Architecture

3.4 Database Administration / GRC Management

3.5 Knowledge Management

3.6 Low-Code / No-Code Application Development

3.7 Enterprise Network Asset Management

3.8 AI Solutions Architecture & Agentic AI Readiness

3.9 Vendor Internal Contract Oversight & End-User Enablement

4. Compliance, Security, and Accreditation Requirements

5. Personnel Vetting and Background Requirements

6. Multi-Year Proposal Flexibility

7. Deliverables and Milestones

8. Period and Place of Performance

9. Pricing and Payment Schedule (Deliverables-Based)

10. Acceptance Criteria

11. Transition to Customer Sustainment (Turn-Key Handoff)

12. Assumptions and Constraints

12.1 Assumptions

12.2 Constraints

12.3 Service Level Objectives (SLO) and Service Level Agreements (SLA)

13. Evaluation Criteria and Proposal Instructions

13.1 Proposal Instructions

13.2 Evaluation Criteria

14. Signatures Appendix A — Definitions and Acronyms

1. Project Overview TxNET is a secure, cloud-enabled enterprise environment designed to support collaboration, operational coordination, and information sharing across the Texas Military Department (TMD), Texas state organizations, and federal mission partners. TMD routinely operates across three distinct operational and legal authorities — State Active Duty (SAD), Title 32 (T32), and Title 10 (T10) — and must collaborate seamlessly with civil authorities, state agencies, and Department of War (DoW)/Department of Defense (DoD) components during emergencies, contingencies, and steady-state operations.

Today, this collaboration is constrained by a structural interoperability gap. TMD's information systems operate either at Impact Level 2 (IL2) for state/civil collaboration or must reach into Impact Level 5 (IL5) DoD environments for federal missions, with no governed, accredited intermediate environment to bridge the two. This gap creates fragmented communications, inconsistent security controls, duplicated capabilities, and barriers to enterprise-wide integration — directly degrading mission agility during SAD/T32/T10 operations.

This Statement of Work (SOW) directs the design, build-out, configuration, accreditation support, and operational turn-over of a turn-key Impact Level 4 (IL4) Microsoft Azure enterprise environment that serves as the authoritative bridge between IL2 and IL5. This environment will be authorized to store, process, and transmit Controlled Unclassified Information (CUI) and will be engineered to support up to 4,850 concurrent enterprise users on average and surge to 6,700 concurrent users as necessary.

The intent of this engagement is unambiguous: deliver a fully operational, fully optimized IL4 enterprise environment that closes TMD's interoperability gap, maintains IL4 compliance, protects CUI, requires minimal ongoing management by TMD, can be cleanly transitioned to TMD sustainment, and is architected so that Agentic AI capabilities can be introduced whenever TMD elects to do so.

This is an implementation SOW. The Assessment and Recommendation activities common to advisory engagements are intentionally excluded. Vendors are expected to perform any discovery necessary to deliver the end state as part of their own mobilization at no separate charge, and to deliver a working, optimized, accredited environment rather than studies or recommendations.

2. Objectives

Objective Area
Description
Turn-Key Implementation
Design, build, configure, integrate, and operationalize a complete IL4 Azure enterprise environment capable of supporting 4,850 concurrent users on average with surge capacity of up to 6,700 concurrent user.
Interoperability Bridge
Establish governed, accredited connectivity and data-exchange pathways that bridge IL2 (state/civil) and IL5 (DoD) environments to support SAD/T32/T10 missions.
Compliance & CUI Protection
Achieve and document IL4 alignment (DoD Cloud Computing SRG), TxRAMP and FedRAMP authorization, and NIST SP 800-171 controls for CUI protection.
Optimization
Deliver an environment that is fully optimized for performance, cost, resiliency, security, and scalability at the time of handoff.
Minimal Customer Management
Deliver automation, runbooks, and managed-service constructs that minimize the operational burden on TMD.
Seamless Transferability
Structure all artifacts, automation, and documentation so sustainment can be transferred to TMD as easily and seamlessly as possible.
Agentic AI Readiness
Architect the environment so Agentic AI capabilities can be introduced later without re-architecture.
Vendor Contract Oversight & Enablement
Provide vendor-internal project management, governance, training, and adoption support driving milestone completion.
Objective Area
Description
Turn-Key Implementation
Design, build, configure, integrate, and operationalize a complete IL4 Azure enterprise environment capable of supporting 4,850 concurrent users on average with surge capacity of up to 6,700 concurrent user.
Interoperability Bridge
Establish governed, accredited connectivity and data-exchange pathways that bridge IL2 (state/civil) and IL5 (DoD) environments to support SAD/T32/T10 missions.
Compliance & CUI Protection
Achieve and document IL4 alignment (DoD Cloud Computing SRG), TxRAMP and FedRAMP authorization, and NIST SP 800-171 controls for CUI protection.

3. Scope of Work The Contractor shall deliver a complete, turn-key IL4 Azure enterprise environment. The scope is organized into functional areas executed across an implementation lifecycle of four (4) sequential and overlapping stages:

1. Mobilization & Environment Baseline — Stand-up of contractor team, security in-processing, access provisioning, and confirmation of design baseline. Any discovery the Contractor requires is performed here at no separate cost.

2. Build & Implementation — Construction, configuration, integration, and migration into the IL4 environment.

3. Optimization & Hardening — Performance, cost, resiliency, and security optimization; accreditation evidence packaging; validation and testing.

4. Transition & Handoff — Knowledge transfer, documentation, automation handover, and operational turn-over to TMD (or to a TMD-designated sustainment provider).

All implementations shall be performed to satisfy IL4 Authorization to Operate (ATO) requirements and shall protect CUI in accordance with applicable federal and state standards.

3.1 Network Engineering / Architecture

Functional Area
Stage
Activities
Key Outcomes
Network Engineering / Architecture
Mobilization & Baseline
Confirm target-state network design; validate Azure landing zone, hybrid connectivity (ExpressRoute/VPN), DNS, segmentation, and IL2↔IL4↔IL5 bridge pathways.
Approved network build baseline and connectivity plan.
Network Engineering / Architecture
Build & Implementation
Deploy hub-and-spoke/landing-zone architecture, micro-segmentation, Zero Trust network controls, secure cross-domain/cross-IL connectivity, firewalls, and monitoring to support 4,850 concurrent users on average with surge capacity of up to 6,700 concurrent users.
Operational, segmented IL4 network with accredited interoperability pathways.
Network Engineering / Architecture
Optimization & Hardening
Tune performance, redundancy, failover, and DR; harden to DISA STIG/SRG baselines; validate disaster recovery.
Resilient, hardened, performance-optimized network.
Network Engineering / Architecture
Transition & Handoff
Deliver as-built diagrams, IaC templates, runbooks, and DR procedures.
Fully documented, transferable network.

3.2 Identity & Access Management (IAM) Engineering / Architecture

Functional Area
Stage
Activities
Key Outcomes
IAM Engineering / Architecture
Mobilization & Baseline
Confirm identity architecture (Entra ID / Azure AD), federation, conditional access, and Zero Trust identity model.
Approved IAM build baseline.
IAM Engineering / Architecture
Build & Implementation
Implement least-privilege RBAC/ABAC, PIM/privileged access management, MFA/phishing-resistant authentication (FIDO2/PIV/CAC where applicable), conditional access, and lifecycle automation (JML — Joiner/Mover/Leaver).
Enterprise IAM supporting 4,850 concurrent user identities on average with surge capacity up to 6,700 concurrent users and automated lifecycle.
IAM Engineering / Architecture
Optimization & Hardening
Implement identity governance (access reviews, entitlement management), privileged identity monitoring, and just-in-time access.
Hardened, governed identity fabric.
IAM Engineering / Architecture
Transition & Handoff
Deliver IAM runbooks, policy-as-code, and administrator training.
Transferable, self-sustaining IAM.

3.3 Azure Cloud Server / Platform Engineering / Architecture

Functional Area
Stage
Activities
Key Outcomes
Azure Cloud Server Engineering / Architecture
Mobilization & Baseline
Confirm subscription/management-group hierarchy, policy framework, and compute baseline.
Approved cloud platform baseline.
Azure Cloud Server Engineering / Architecture
Build & Implementation
Deploy compute, storage, scaling, availability zones, Infrastructure-as-Code (Bicep/Terraform), Azure Policy guardrails, and provisioning automation.
Scalable, automated, policy-governed compute platform.
Azure Cloud Server Engineering / Architecture
Optimization & Hardening
Optimize cost (FinOps), right-size, harden to STIG, implement autoscaling and advanced monitoring (Azure Monitor/Sentinel).
Cost- and performance-optimized, hardened platform.
Azure Cloud Server Engineering / Architecture
Transition & Handoff
Deliver IaC repositories, cost dashboards, and operational runbooks.
Transferable, automated platform operations.

3.4 Database Administration / GRC Management

Functional Area
Stage
Activities
Key Outcomes
Database (Azure SQL) Administration / GRC
Mobilization & Baseline
Confirm database architecture, data classification, encryption, and compliance framework.
Approved data and GRC baseline.
Database Administration / GRC
Build & Implementation
Deploy databases with encryption at rest/in transit, backup/restore, HA/DR, CUI data tagging, and GRC tooling mapped to NIST 800-171/IL4 controls.
Secure, compliant, resilient data tier.
Database Administration / GRC
Optimization & Hardening
Optimize performance, implement continuous compliance monitoring, and produce control evidence.
Optimized, continuously monitored compliance posture.
Database Administration / GRC
Transition & Handoff
Deliver DBA runbooks, GRC control matrices, and POA&M templates.
Transferable data administration and GRC operations.

3.5 Knowledge Management

Functional Area
Stage
Activities
Key Outcomes
Knowledge Management
Mobilization & Baseline
Confirm KM platform (e.g., SharePoint/M365 GCC High–aligned), taxonomy, and content migration plan.
Approved KM baseline.
Knowledge Management
Build & Implementation
Deploy centralized KM, records management, content migration, and search; enforce CUI marking and handling.
Operational, compliant KM environment.
Knowledge Management
Optimization & Hardening
Optimize information architecture, lifecycle/retention policies, and AI-ready content structuring.
Governed, AI-ready knowledge base.
Knowledge Management
Transition & Handoff
Deliver KM governance guides and end-user/administrator training.
Transferable KM operations.

3.6 Low-Code / No-Code Application Development

Functional Area
Stage
Activities
Key Outcomes
Low-Code/No-Code Application Development
Mobilization & Baseline
Confirm Power Platform (or equivalent) governance, environments, DLP policies, and ALM approach.
Approved app platform baseline.
Low-Code/No-Code Application Development
Build & Implementation
Deploy governed low-code/no-code environments, citizen-developer guardrails, prioritized applications/workflows, and CI/CD/ALM.
Operational, governed low-code platform with delivered apps.
Low-Code/No-Code Application Development
Optimization & Hardening
Harden DLP, secure connectors, and API governance; optimize for reuse.
Secure, scalable, reusable app platform.
Low-Code/No-Code Application Development
Transition & Handoff
Deliver app catalogs, ALM pipelines, and maker/admin training.
Transferable, self-sustaining app development capability.

3.7 Enterprise Network Asset Management

Functional Area
Stage
Activities
Key Outcomes
Enterprise Network Asset Management
Mobilization & Baseline
Confirm asset/CMDB approach, licensing model, and lifecycle processes.
Approved asset management baseline.
Enterprise Network Asset Management
Build & Implementation
Deploy automated asset discovery/inventory, CMDB, license management, and lifecycle tracking.
Complete, automated asset accountability.
Enterprise Network Asset Management
Optimization & Hardening
Integrate with monitoring/SIEM; optimize utilization and compliance reporting.
Optimized, auditable asset posture.
Enterprise Network Asset Management
Transition & Handoff
Deliver CMDB, reporting dashboards, and processes.
Transferable asset management operations.

3.8 AI Solutions Architecture & Agentic AI Readiness

Functional Area
Stage
Activities
Key Outcomes
AI Solutions Architecture
Mobilization & Baseline
Confirm AI-ready data architecture, governance, and the foundational landing zone for future AI/Agentic AI workloads.
Approved AI-ready baseline.
AI Solutions Architecture
Build & Implementation
Implement AI-ready data pipelines, secure model-hosting foundations (e.g., Azure OpenAI/AI services within IL4 boundary), API/identity scaffolding for agents, and guardrails (responsible AI, logging, human-in-the-loop hooks).
Foundational AI platform pre-wired for Agentic AI.
AI Solutions Architecture
Optimization & Hardening
Harden AI data governance, access controls, and auditability; document the activation path for Agentic AI.
Secure, governed, Agentic-AI-ready foundation.
AI Solutions Architecture
Transition & Handoff
Deliver AI readiness package, agent-activation playbook, and governance framework.
TMD able to introduce Agentic AI on demand without re-architecture.

Agentic AI Readiness Requirement (Mandatory): The environment shall be architected so that Agentic AI (autonomous/semi-autonomous AI agents) can be introduced at a time of TMD's choosing without re-architecture. At minimum this includes: (a) AI-ready, well-governed and classified data; (b) identity scaffolding for non-human/agent identities with least-privilege and full auditability; (c) secure, IL4-bounded model hosting and API integration patterns; (d) logging, observability, and human-in-the-loop control points; and (e) a documented activation playbook.

3.9 Enterprise Network Asset Management

Functional Area
Stage
Activities
Key Outcomes
Contract Oversight (Vendor Internal)
All Stages
Maintain integrated master schedule, milestone/deliverable tracking, risk/issue management, weekly status reporting, and quality control. Performed at vendor cost; not a separately payable deliverable.
All workstreams managed to schedule and milestone acceptance.
End-User Enablement
All Stages
Develop and execute communications, stakeholder management, training plans, and training materials supporting adoption.
Trained users and administrators; sustained adoption.

4. Compliance, Security, and Accreditation Requirements The Contractor shall design, build, and deliver the environment in compliance with the following. Where standards conflict, the most restrictive applicable control shall govern.

DoD Impact Level 4 (IL4): The environment shall be engineered to satisfy IL4 requirements per the DoD Cloud Computing Security Requirements Guide (SRG) and shall support an IL4 Authorization to Operate (ATO). The Contractor shall produce all security artifacts (SSP, control implementation, POA&M, etc.) necessary to support TMD/sponsoring authority accreditation.

The environment shall be licensed and architected to support up to 24,000 named users. The architecture must sustain an average of 4,850 concurrent users with surge capacity to 6,700 concurrent users during peak operations without performance degradation beyond agreed baselines. The Contractor shall conduct and document high-load/stress testing validating performance at scale, specifically simulating and confirming system stability and responsiveness with 6,700 concurrent users.

IL2↔IL4↔IL5 Bridging: The environment shall provide governed, accredited connectivity/data-exchange pathways enabling interoperability across IL2 (state/civil) and IL5 (DoD) for SAD/T32/T10 missions.

TxRAMP: Solution and underlying services shall be TxRAMP certified at the appropriate level for the data handled.

FedRAMP: Underlying cloud services shall be FedRAMP authorized (Moderate or High as appropriate to IL4); the Contractor shall identify the FedRAMP authorization status of all proposed services.

CUI Protection: The environment shall protect CUI in accordance with NIST SP 800-171 (and NIST SP 800-172 enhanced controls where directed), 32 CFR Part 2002, and applicable DFARS 252.204-7012 safeguarding and incident-reporting requirements.

CMMC Readiness: The environment and the Contractor's handling practices shall support CMMC readiness commensurate with CUI handling.

NIST SP 800-53: Security controls shall align to NIST SP 800-53 at the FedRAMP/IL4 Moderate-High baseline as applicable.

CJIS: Where Criminal Justice Information may traverse or reside in the environment, FBI CJIS Security Policy requirements shall be met.

State of Texas Requirements: Compliance with DIR standards, Texas Administrative Code (TAC) §202, and applicable Texas Government Code provisions.

Hardening: Systems shall be hardened to applicable DISA STIGs and CIS Benchmarks.

User Scale: The enterprise network and all supporting services shall be designed, tested, and validated to support 4,850 concurrent users on average with surge capacity up to 6,700 concurrent users with appropriate performance, availability, and scalability.

5. Personnel Vetting and Background Requirements All Contractor personnel performing work under this SOW must be vetted and authorized to meet both federal and state requirements to work within state agency networks and within DoW/DoD networks classified at IL2 and IL4. At a minimum:

Background Investigations: All personnel shall undergo background checks satisfying State of Texas agency requirements and the standard required for access to DoD IL2/IL4 systems (e.g., favorable Tier 3 / Moderate Risk Public Trust (MBI) or higher; IT-I / IT-II (ADP-I/ADP-II) position-sensitivity equivalents based on system access).

Citizenship: Personnel with access to CUI and to IL4 environments shall be U.S. persons / U.S. citizens as required by the applicable authorizing official; no foreign nationals shall have access absent explicit written authorization.

Texas-Specific Vetting: Personnel shall meet TMD/DIR onboarding, fingerprint-based criminal history checks (including CJIS fingerprinting where applicable), and any TMD-specific suitability requirements.

CUI Training & Acknowledgment: All personnel shall complete CUI handling training and sign required non-disclosure and rules-of-behavior agreements prior to access.

Security Awareness & Role-Based Training: Annual security awareness training and role-based privileged-user training as required by NIST 800-171/IL4.

Drug Screening: Where required by TMD or applicable authority.

Continuous Vetting / Insider Threat: Personnel shall be subject to continuous evaluation and removal upon any disqualifying determination.

Personnel Roster & Replacement: The Contractor shall maintain a current roster of cleared personnel and shall ensure any replacement personnel are fully vetted prior to assignment, at no impact to milestone schedules or cost.

Key Personnel: The Contractor shall designate key personnel (e.g., Program Manager, Lead Cloud/Security Architect, Lead IAM Engineer, ISSO/Security Lead) and shall not substitute key personnel without TMD approval.

The Contractor is encouraged to identify any additional certifications or vetting it deems necessary (e.g., DoD 8570/8140 baseline certifications such as Security+, CISSP, CCSP; Microsoft Azure certifications such as AZ-104, AZ-305, AZ-500, SC-100) and to describe how its workforce exceeds these minimums.

6. Multi-Year Proposal Flexibility This procurement may or may not result in a multi-year contract. To allow Offerors to propose the approach they believe best achieves the desired end state, the following applies:

Offerors may propose a single-period turn-key implementation or a multi-year, phased approach (e.g., Base Period plus Option Years) if the Offeror believes a multi-year structure best achieves a fully operational, optimized, and transferable IL4 environment.

Multi-year proposals shall clearly delineate each period's milestones, deliverables, firm-fixed milestone prices, and the operational capability achieved at the end of each period.

Any multi-year proposal must preserve the deliverables-based payment model (Section 9) and must include a defined path to seamless transition to TMD sustainment.

Offerors are invited to "sell themselves" to TMD — to differentiate their solution, accelerators, IL4/CUI experience, managed-service constructs, automation, and ability to minimize TMD's ongoing management burden. TMD will evaluate the degree to which each proposal delivers a truly turn-key, low-management, transferable, and AI-ready environment.

7. Deliverables and Milestones Payment is tied to formal acceptance of milestone deliverables (Section 9). Milestones may be decomposed into sub-deliverables to enable intermittent payment across the life of the contract. Timelines below are illustrative; Offerors shall propose their own milestone schedule (single- or multi-year).

Milestone
Representative Deliverables
Illustrative Timeline
M1 – Mobilization & Build Baseline
Cleared personnel onboarded; confirmed build baseline; Project Management Plan; Integrated Master Schedule; design/build baseline package (incl. any contractor discovery).
Months 0–1
M2 – Core Landing Zone & Network
Accredited IL4 landing zone; segmented network; hybrid/IL2-IL4-IL5 connectivity pathways; IaC.
Months 1–3
M3 – Identity & Security Fabric
Entra ID/IAM, RBAC/PIM/MFA, conditional access, lifecycle automation; security tooling (Sentinel/Defender).
Months 2–4
M4 – Data, Database & GRC
Secure databases; CUI classification/tagging; GRC tooling; control evidence and POA&M.
Months 3–5
M5 – Collaboration, KM & Low-Code
Centralized KM; content migration; governed Power Platform; delivered priority apps/workflows.
Months 4–6
M6 – Asset Management & Monitoring
CMDB/asset inventory; enterprise monitoring; reporting dashboards.
Months 5–6
M7 – AI-Ready & Agentic-AI Foundation
AI-ready data estate; agent identity scaffolding; secure model-hosting foundation; Agentic AI activation playbook.
Months 5–7
M8 – Optimization & Hardening
Performance/cost optimization; STIG hardening; DR validation; scale validation to 6,700 concurrent users; accreditation evidence package.
Months 7–8
M9 – Transition & Handoff
As-built documentation; IaC repositories; runbooks; administrator/end-user training; transition-out package; operational turn-over to TMD.
Months 8–9

8. Period and Place of Performance

Period of Performance (PoP)
To be proposed by Offeror (single-period or Base + Option Years).
Place of Performance
Remote, with any on-site/escorted activity at TMD-designated facilities as required by IL4/CUI access controls.
Core Hours
8:00 AM – 5:00 PM Central Time (may flex to meet milestone deliverable timelines and maintenance windows).

9. Pricing and Payment Schedule (Deliverables-Based) This is a firm-fixed-price, deliverables-based engagement. The contract is not labor-hour or time-and-materials based. TMD pays for accepted deliverables, not for hours.

No payment shall be made until the associated milestone deliverable(s) are completed and formally accepted in writing by the designated TMD representative.

Milestones may be decomposed into sub-deliverables so that the Contractor may invoice and be paid intermittently as discrete sub-deliverables are accepted throughout the life of the contract.

Vendor-internal contract oversight, project management, and quality control are not separately payable; these costs shall be incorporated into milestone pricing.

The Offeror shall propose a milestone-based payment schedule mapping each payment to a specific accepted deliverable or sub-deliverable.

Contract Modifications: The SOW and resulting contract are structured to minimize modifications. Because payment is deliverables-based and discovery is the Contractor's responsibility, scope is fixed to the delivered end state. Any change shall be processed only through formal, mutually agreed change control with corresponding deliverable/price adjustment.

10. Acceptance Criteria Acceptance of deliverables shall be based on successful completion of agreed milestone tasks and operational outcomes. Deliverables will be reviewed by designated TMD/TxNET stakeholders and accepted when they meet functional, technical, security, and operational requirements. Acceptance criteria include, but are not limited to:

Completion of all Build, Optimization, and Transition activities for the milestone;

Delivery of required documentation: as-built architecture, SSP and control implementation statements, SOPs/runbooks, IaC repositories, POA&M, and training materials;

Successful implementation and validation of configurations, integrations, automation, monitoring, and security controls within the IL4 environment;

Verified compliance with IL4 (DoD SRG), TxRAMP, FedRAMP, NIST SP 800-171 (CUI), CJIS (where applicable), NIST 800-53, DISA STIG, DIR/TAC §202, and applicable DoD/State policies;

Demonstrated functionality, performance, resiliency, and validated scalability to 6,700 concurrent users;

Demonstrated Agentic AI readiness per Section 3.8;

Completion of knowledge transfer, administrator training, and operational handoff enabling seamless TMD sustainment;

Submission and approval of test results, validation reports, and operational readiness documentation;

Formal written acceptance by an authorized TMD representative.

Deficiencies will be documented for remediation; deliverables are accepted upon written TMD approval or completion of mutually agreed corrective actions.

11. Transition to Customer Sustainment (Turn-Key Handoff) To ensure sustainment can be transferred to TMD as easily and seamlessly as possible with minimal ongoing TMD management, the Contractor shall deliver a Transition-Out / Turn-Key Handoff Package, including at minimum:

Complete as-built documentation and architecture diagrams;

Infrastructure-as-Code (IaC) repositories and policy-as-code enabling full environment reproducibility;

Operational runbooks and SOPs for all functional areas (network, IAM, platform, data/GRC, KM, low-code, asset management, AI foundation);

Automation for routine operations, patching, scaling, backup/DR, and monitoring/alerting to minimize manual administration;

Administrator and end-user training with recorded sessions and reference materials;

Accreditation/ATO sustainment package (SSP, control evidence, POA&M, continuous monitoring plan);

Agentic AI activation playbook (Section 3.8);

A 30/60/90-day post-handoff support/warranty period (Offeror to propose) and an optional sustainment proposal, at TMD's discretion;

Intellectual Property & Licensing Plan: A comprehensive document detailing the ownership of all custom-developed components (which shall transfer to TMD) and a complete inventory and transfer/re-assignment plan for all third-party proposed solutions required for TMD to sustain and operate the system independently.

12. Assumptions and Constraints

12.1 Assumptions

TMD will provide timely access to required personnel, facilities, accreditation authorities, and technical environments necessary for build, testing, and transition;

TMD will identify POCs with decision-making authority for technical approvals and deliverable acceptance;

Required access approvals, administrative permissions, and security authorizations will be granted per policy to allow vetted personnel to perform authorized tasks;

TMD will support scheduled maintenance windows and testing periods required for implementation;

Underlying enterprise licensing and cloud subscriptions will be available or procured as specified in the resulting contract;

TMD will secure and provide formal Data Sharing Agreements (DSAs) or equivalent authorizations with all designated civil-partner source-system owners to guarantee Contractor access for integration, where required.

12.1 Constraints

Work touching IL5 or other restricted environments may require additional coordination, escort, or access approvals;

Procurement lead times and licensing constraints may affect schedule and must be reflected in the Offeror's milestone plan;

Production-impacting changes must follow established change management;

AI/Agentic AI capabilities are delivered as a ready foundation; full agent deployment occurs at TMD's election;

Scope changes after award require formal change control (Section 9).

13. Service Level Objectives (SLO) and Service Level Agreements (SLA) The following SLOs/SLAs apply during the Optimization & Hardening stage, the post-handoff support/warranty period, and any proposed sustainment period. Offerors shall confirm their ability to meet or exceed these targets and may propose enhanced levels as a differentiator. Where the Contractor proposes a managed-service or sustainment option, these SLAs shall be binding for that period.

#
Metric
Target / Threshold
Measurement
Remedy / Note
1
Environment Availability (core enterprise services)
≥ 99.9% monthly uptime (excluding approved maintenance windows)
Azure Monitor / platform telemetry; monthly availability report
Service credits or remediation per resulting contract; root-cause analysis (RCA) for any breach
2
Critical (Sev 1) Incident Response
Acknowledge ≤ 15 minutes; begin remediation ≤ 30 minutes
Ticketing/ITSM timestamps
RCA within 5 business days; recurring breaches trigger corrective action plan
3
High (Sev 2) Incident Response
Acknowledge ≤ 1 hour; remediation plan ≤ 4 hours
Ticketing/ITSM timestamps
Documented in monthly service review
4
Medium/Low (Sev 3/4) Incident Response
Acknowledge ≤ 1 business day
Ticketing/ITSM timestamps
Tracked to closure
5
Security Incident / Suspected CUI Spillage Reporting
Report to TMD ≤ 1 hour of detection; DFARS 252.204-7012 reporting ≤ 72 hours
Incident records; SIEM (Sentinel) alerts
Mandatory; failure is a material breach
6
Critical Vulnerability Remediation
Patch/mitigate critical vulnerabilities ≤ 15 days; high ≤ 30 days (or per IL4/STIG timelines)
Vulnerability scans (e.g., Defender, ACAS-equivalent)
POA&M entries for exceptions
7
Backup Success Rate
≥ 99% successful scheduled backups
Backup logs/reports
Failed backups remediated within 24 hours
8
Recovery Time Objective (RTO)
≤ 4 hours for critical workloads (Offeror may propose better)
DR test validation
Validated during M8 and annually
9
Recovery Point Objective (RPO)
≤ 1 hour for critical data (Offeror may propose better)
DR test validation
Validated during M8 and annually
10
Scalability / Performance
Sustain up to 4,850 concurrent users on average with surge capacity to 6,700 concurrent user with no degradation beyond agreed performance baselines
Load/performance testing reports
Validated prior to acceptance
11
Patch & Configuration Compliance
≥ 95% of assets STIG/CIS-compliant at any time
Compliance scanning dashboards
Drift remediated per timelines above
12
Monthly Reporting & Service Review
Delivered within 5 business days of month-end
Report delivery records
Reviewed in recurring service meeting
13
Continuous Monitoring (ConMon)
Continuous (24x7) security monitoring and alerting
SIEM/SOAR telemetry
Aligned to IL4 ConMon requirements

Maintenance Windows: Approved, scheduled maintenance shall be excluded from availability calculations and coordinated with TMD in advance. Service Credits: Offerors shall propose a service-credit or remediation framework for SLA breaches applicable to any managed-service/sustainment period.

14. Evaluation Criteria and Proposal Instructions

14.1 Proposal Instructions

Offerors shall submit a proposal that demonstrates a complete, turn-key solution and a clear path to a fully operational, optimized, accredited, transferable, and AI-ready IL4 environment. Proposals shall include, at minimum:

Technical Solution Narrative — How the Offeror will design, build, integrate, optimize, harden, and transition the IL4 environment across all functional areas in Section 3, including the IL2↔IL4↔IL5 interoperability bridge;

Compliance & Accreditation Approach — How the Offeror will achieve and document IL4 (DoD SRG), TxRAMP, FedRAMP, NIST SP 800-171/CUI, CMMC readiness, CJIS (if applicable), NIST 800-53, and DISA STIG compliance, including the accreditation/ATO evidence package;

Personnel & Vetting Plan — Key personnel, certifications (e.g., DoD 8570/8140, Azure AZ-104/AZ-305/AZ-500/SC-100, CISSP/CCSP), and how all personnel will meet federal and state IL2/IL4 vetting requirements (Section 5);

Milestone & Deliverables Plan — Proposed milestones/sub-deliverables, schedule, and deliverables-based payment mapping (Section 9), including any single- or multi-year structure (Section 6);

Turn-Key & Minimal-Management Approach — Automation, IaC, managed-service constructs, and runbooks that minimize TMD's ongoing management burden;

Transition / Transferability Plan — How sustainment will be transferred to TMD as seamlessly as possible (Section 11);

Agentic AI Readiness Approach — How the architecture will be pre-wired so TMD can introduce Agentic AI on demand without re-architecture (Section 3.8);

Pricing — Firm-fixed milestone pricing consistent with Section 9;

Past Performance — Relevant experience delivering IL4/CUI/FedRAMP/TxRAMP environments of comparable scale (up to 6,700 concurrent users);

Differentiators ("Sell Yourself") — Accelerators, tooling, references, and value-adds. Offerors are expressly invited to differentiate themselves and demonstrate why their approach best achieves TMD's desired end state.

14.2 Evaluation Criteria

Proposals will be evaluated on a best-value basis. TMD reserves the right to weight criteria as set forth in the solicitation. The following criteria and illustrative weights apply (final weights to be confirmed in the solicitation):

#
Evaluation Factor
Description
Illustrative Weight
1
Technical Solution & Architecture
Completeness, soundness, and turn-key nature of the proposed IL4 environment and interoperability bridge across all functional areas.
25%
2
Compliance, Security & Accreditation
Demonstrated ability to deliver and document IL4, TxRAMP, FedRAMP, CUI/NIST 800-171, CMMC readiness, CJIS, and STIG compliance.
20%
3
Turn-Key, Minimal-Management & Transferability
Strength of automation, managed-service constructs, runbooks, and the transition-out approach enabling seamless TMD sustainment with minimal management.
15%
4
Personnel Qualifications & Vetting
Quality of key personnel, certifications, and ability to meet federal/state IL2/IL4 vetting.
10%
5
Agentic AI Readiness
Quality and credibility of the AI-ready foundation and Agentic AI activation path.
10%
6
Milestone/Deliverables Plan & Schedule Realism
Realism, clarity, and risk management of the milestone/deliverables plan (including any multi-year structure).
10%
7
Past Performance
Relevance and success of comparable IL4/CUI/large-scale engagements.
5%
8
Price / Best Value
Reasonableness and value of firm-fixed milestone pricing relative to proposed capability.
5%

Total

100%

TMD may conduct oral presentations, demonstrations, or clarifications. TMD reserves the right to make award without discussions and to select the proposal representing the best overall value.

15. Signature The DIR signature below serves solely to verify that the scope of services outlined in the Solicitation falls within the scope of the DIR contract being utilized. The DIR signature does not make DIR a party to the Contract or to any constituent document.

TMD Representative

Name:

Title:

Date:

Respondent Representative

Name:

Title:

Date:

DIR Representative

Name:

Title:

Date:

Appendix A — Definitions and Acronyms

Term / Acronym
Definition
ACAS
Assured Compliance Assessment Solution — DoD vulnerability scanning capability (or equivalent).
Agentic AI
Autonomous or semi-autonomous AI agents capable of taking actions toward goals with limited human intervention, operating under defined guardrails and human-in-the-loop controls.
ATO
Authorization to Operate — formal accreditation decision permitting a system to operate.
CIS Benchmark
Center for Internet Security configuration hardening standards.
CJIS
Criminal Justice Information Services — FBI security policy governing criminal justice information.
CMDB
Configuration Management Database.
CMMC
Cybersecurity Maturity Model Certification — DoD framework for protecting FCI/CUI.
ConMon
Continuous Monitoring.
CUI
Controlled Unclassified Information — information requiring safeguarding per 32 CFR Part 2002.
DFARS
Defense Federal Acquisition Regulation Supplement (e.g., 252.204-7012 safeguarding/reporting).
DIR
Texas Department of Information Resources.
DISA
Defense Information Systems Agency.
DLP
Data Loss Prevention.
DoD
Department of Defense.
DoW
Department of War (as referenced by TMD).
DR
Disaster Recovery.
Entra ID
Microsoft Entra ID (formerly Azure Active Directory).
ExpressRoute
Azure private, dedicated network connectivity service.
FedRAMP
Federal Risk and Authorization Management Program.
GRC
Governance, Risk, and Compliance.
IaC
Infrastructure as Code (e.g., Bicep, Terraform).
IAM
Identity and Access Management.
IL2 / IL4 / IL5
DoD Cloud Computing Impact Levels (per the DoD Cloud Computing SRG) defining data sensitivity and required controls. IL2 = public/non-critical; IL4 = CUI; IL5 = higher-sensitivity CUI/National Security Systems.
ISSO
Information System Security Officer.
IT-I / IT-II
Information Technology position sensitivity designations (formerly ADP-I/ADP-II) tied to system access and required investigations.
JML
Joiner / Mover / Leaver identity lifecycle process.
KM
Knowledge Management.
MBI
Moderate Background Investigation (Public Trust).
MFA
Multi-Factor Authentication.
NIST SP 800-53
NIST security and privacy controls catalog.
NIST SP 800-171 / 800-172
NIST standards for protecting CUI in nonfederal systems / enhanced controls.
PIM
Privileged Identity Management.
POA&M
Plan of Action and Milestones.
RBAC / ABAC
Role-Based / Attribute-Based Access Control.
RCA
Root Cause Analysis.
RPO
Recovery Point Objective.
RTO
Recovery Time Objective.
SAD
State Active Duty — National Guard service under state authority and funding.
SIEM / SOAR
Security Information and Event Management / Security Orchestration, Automation and Response.
SLA / SLO
Service Level Agreement / Service Level Objective.
SOW
Statement of Work.
SRG
(DoD Cloud Computing) Security Requirements Guide.
SSP
System Security Plan.
STIG
Security Technical Implementation Guide (DISA).
TAC §202
Texas Administrative Code, Title 1, Chapter 202 (Information Security Standards).
T10 (Title 10)
Federal active duty service under U.S. Code Title 10.
T32 (Title 32)
National Guard service under U.S. Code Title 32 (federally funded, state-controlled).
TMD
Texas Military Department.
TxNET
The secure, cloud-enabled enterprise environment being delivered under this SOW.
TxRAMP
Texas Risk and Authorization Management Program.
Zero Trust
Security model based on never trust always verify with continuous validation.""