ESBD_549011_1786714965013_ATTACHMENT G.6 Mandatory Pricing Schedule.xlsx

XLSX spreadsheet 24 KB Posted

Attached to
Austin Bergstrom International Airport (ABIA) Foam Systems Repairs
Solicitation number
TMD26-FMO-0044573
Issued by
Texas

About this file

This is a mandatory pricing schedule attachment for a competitive bid solicitation issued by the Texas Military Department Procurement and Contract Services for fire protection equipment foam system repairs at Austin Bergstrom International Airport (ABIA). The project encompasses four hangars (9530, 9535, 9540, and 9550) located at 5102 Emma Browning Avenue, Austin, Texas 78719. Work at each facility includes capturing and preserving existing Jet-X foam concentrate using 55-gallon drums, removing and disposing of existing tank bladders, installing new tank bladders of specified capacities, reinstalling foam from drums into new bladders, replacing one electronic valve per hanger, and repairing minor leaks on fire sprinkler risers. Hanger 9530 requires work on two 300-gallon tanks, while hangars 9535, 9540, and 9550 each require work on two 800-gallon tanks. Testing of the foam concentrate will be completed by TMD's existing fire protection vendor. The solicitation is classified under NIGP Class 936-33 for fire protection equipment and systems inspection, maintenance, and repair services.

The pricing schedule requires contractors to submit unit prices and extended prices for each of the four line items representing work at each hanger facility. All cells in the pricing template are locked except for data entry fields highlighted in yellow, and contractors are prohibited from adding, deleting, or modifying any other cells under penalty of proposal disqualification. Bidders must provide company name, point of contact information, phone number, and email address. All pricing submissions must reflect work that meets the requirements outlined in Section C—Statement of Work of the solicitation. The document does not indicate specific response deadlines, award dates, contract terms, or renewal options.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Pricing Schedule

Texas Military Department
Procurement and Contract Services (P&CS)
TMD26-FMO-0044573 Austin Bergstrom International Airport Foam Repair, Austin
ATTACHMENT G.6 Mandatory Pricing Schedule
Company Name:
Company Point Of Contact:
Contact Phone #:
Contact Email:

Items proposed below must meet the Statement of Work described in SECTION C - Statement of Work. Cells highlighted in yellow permit data entry. Please DO NOT add, delete or change any other cells. Doing so may subject your proposal to disqualification.

Line Item Details

Item #NIGP Class and ItemItem Description
QuantatyUnit of Measure (UOM)Estimated Days To Completion AROUnit PriceExtended Price
1936-33 Fire Protection Equipment and Systems Including Fire Hydrants, Fire Sprinkler Systems, Smoke Detectors, Jaws of Life, Fire Protection Material Treatment, Firestop and Fire Barriers, etc. Inspection, Maintenance and RepairThe Texas Military Department (TMD) is seeking competitive bids from highly qualified Contractors for the Fire Protection Equipment Foam System Repairs.

Location: Austin Bergstrom International Airport (ABIA), hanger numbers 9530, 9535, 9540 and 9550 located at 5102 Emma Browning Avenue, Austin, Texas 78719.

A. Hanger 9530

1. Hanger 9530 holds two (2) 300-gallon foam tanks.

2. Contractor must capture the existing Jet-X foam concentrated by utilizing the 55-gallon drums. Drums being used will be inspected prior to being used to ensure there is no contamination. Drums will be stored in the affected hanger pump room.

3. Contractor must remove and dispose of the two (2) 300-gallon tank bladders.

4. Contractor must install two (2) 300-gallon tank bladders.

5. Contractor must reinstall foam from drums into the two (2) new tank bladders.

6. Contractor must replace one (1) 799D 02C11 6” 152-112A Inbal valve with one (1) electronic valve including labor and repair minor leak on fire sprinkler riser.

7. Testing of the foam concentrate:

a. Completed by TMD’s vendor who is currently providing services for fire protection.

1JOB$0
2936-33 Fire Protection Equipment and Systems Including Fire Hydrants, Fire Sprinkler Systems, Smoke Detectors, Jaws of Life, Fire Protection Material Treatment, Firestop and Fire Barriers, etc. Inspection, Maintenance and RepairB. Hanger 9535:

1. Hanger 9535 holds two (2) 800-gallon foam tanks.

2. Contractor must capture the existing Jet-X foam concentrated by utilizing the 55-gallon drums. Drums being used will be inspected prior to being used to ensure there is no contamination. Drums will be stored in the affected hanger pump room.

3. Contractor must remove and dispose of the two (2) 300-gallon tank bladders.

4. Contractor must install two (2) 300-gallon tank bladders.

5. Contractor must reinstall foam from drums into the two (2) new tank bladders.

6. Contractor must replace one (1) 799D 02C11 6” 152-112A Inbal valve with one (1) electronic valve including labor and repair minor leak on fire sprinkler riser.

7. Testing of the foam concentrate:

a. Completed by TMD’s vendor who is currently providing services for fire protection.1JOB$0
3936-33 Fire Protection Equipment and Systems Including Fire Hydrants, Fire Sprinkler Systems, Smoke Detectors, Jaws of Life, Fire Protection Material Treatment, Firestop and Fire Barriers, etc. Inspection, Maintenance and RepairC. Hanger 9540:

1. Hanger 9540 holds two (2) 800-gallon foam tanks.

2. Contractor must capture the existing Jet-X foam concentrated by utilizing the 55-gallon drums. Drums being used will be inspected prior to being used to ensure there is no contamination. Drums will be stored in the affected hanger pump room.

3. Contractor must remove and dispose of the two (2) 800-gallon tank bladders.

4. Contractor must install two (2) 800-gallon tank bladders.

5. Contractor must reinstall foam from drums into the two (2) new tank bladders.

6. Contractor must replace one (1) 799D 02C11 6” 152-112A Inbal valve with one (1) electronic valve including labor and repair minor leak on fire sprinkler riser.

7. Testing of the foam concentrate:

a. Completed by TMD’s vendor who is currently providing services for fire protection.1JOB$0
4936-33 Fire Protection Equipment and Systems Including Fire Hydrants, Fire Sprinkler Systems, Smoke Detectors, Jaws of Life, Fire Protection Material Treatment, Firestop and Fire Barriers, etc. Inspection, Maintenance and RepairD. Hanger 9550

1. Hanger 9550 holds two (2) 800-gallon foam tanks.

2. Contractor must capture the existing Jet-X foam concentrated by utilizing the 55-gallon drums. Drums being used will be inspected prior to being used to ensure there is no contamination. Drums will be stored in the affected hanger pump room.

3. Contractor must remove and dispose of the two (2) 800-gallon tank bladders.

4. Contractor must install two (2) 800-gallon tank bladders.

5. Contractor must reinstall foam from drums into the two (2) new tank bladders.

6.Contractor must replace one (1) 799D 02C11 6” 152-112A Inbal valve with one (1) electronic valve including labor and repair minor leak on fire sprinkler riser.
7.Testing of the foam concentrate:
a.Completed by TMD’s vendor who is currently providing services for fire protection.1JOB$0
Total:$0

File details come from the government source that posted it. Updated .