About this file
This is an equipment list exhibit for a high voltage switchgear maintenance contract at Richmond State Supported Living Center in Texas. The document details bi-annual preventive maintenance requirements for high voltage switchgear systems scheduled for January and July across multiple facility locations. The equipment inventory includes Powell brand switchgear units and a Westinghouse unit distributed across several buildings: locations 502-DPC, 504-Angelina, 508-Brazos, 509-Colorado, 505-Gym, and 512-Power Plant. The switchgear specifications vary by location, with primary voltage configurations of 120-208v (3-phase, 4-wire) and 12,470v (3-phase, 3-wire) systems, amperage ratings ranging from 600A to 3000A, and multiple switchboard and transformer designations per location. Most locations contain two Powell units with complementary voltage configurations, while some locations feature additional units to support the facility's electrical infrastructure needs.
No pricing information, contract term details, set-asides, incumbent vendor information, or funding sources are specified in this equipment list exhibit. The document serves solely as a reference inventory of the high voltage switchgear assets requiring maintenance support at the Richmond State Supported Living Center, establishing the scope and frequency of work to be performed by the successful bidder under the contract opportunity for high voltage repair services.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Manufacturer Description Location PM Frequency
Powell #1: 120-208v | 3phase 4W | S.W. BD 02 | S.O
33795 502-DPC
Bi-Annual: January & July
Powell #2: PRI. 12,470v | 3phase 3W | 600A SW.BD. 02 |
S.O 33795 | SW-6 | T-502 502-DPC
Bi-Annual: January & July
Westinghouse Unavailable 525-Neches outside
Bi-Annual: January & July
Unavailable Unavailable 526-Leon outside
Bi-Annual: January & July
Unavailable Unavailable 527-Trinity outside
Bi-Annual: January & July
Unavailable Unavailable
528-San Antonio outside
Bi-Annual: January & July
Powell #1: 120-208v | 3phase 4W | 800A | S.O 33795 504-Angelina Bi-Annual: January & July
Powell #2:12,470v | 3phase 3W | S.O 33795 | SW-6 | T- 504 504-Angelina
Bi-Annual: January & July
Powell #1: 120-208v | 3phase 4W | 800A | SW.BD.08 | S.O 33795 508-Brazos
Bi-Annual: January & July
Powell #2: 12,470v | 3phase 3W | 600A | SW.BD.08 | S.O 33795 508-Brazos
Bi-Annual: January & July
Powell #1: 12,470v | 3phase 3W | 600A | SW.BD.09 | S.O
33795 | SW-3 | T-509
509- Colorado
Bi-Annual: January & July
Powell #2: 120-208v | 3phase 4W | 800A | SW.BD.09 509- Colorado
Bi-Annual: January & July
Powell #1: 120-208v | 3phase 4W | 800A | Blgd.05 | S.O 33795 505-Gym
Bi-Annual: January & July
Powell #2: 12,470v | 3phase 3W | S.O 33795 | T-505 505-Gym Bi-Annual: January & July
Bi-Annual preventive maintenance at Richmond SSLC Switchgear - Alternating Current A/C Voltage | 12,500 volts
Powell #1: 12,470 | 255-44v | 3phase 4W | 3000A | S.O 33795
512-Power Plant
Bi-Annual: January & July
Powell #2: 12,470v | 3phase 3W | 600A | S.O 33795 512-Power Plant
Bi-Annual: January & July
Powell #3 Powell 12.47Kv 3phase 3W 600A S.O 48913
512-Power Plant
Bi-Annual: January & July
Switchgear