This is a Scope of Work document from the Texas Department of Public Safety (TXDPS) for a construction renovation project at the Houston Regional Headquarters located at 12230 West Road, Jersey Village, Texas. The project involves comprehensive renovation of CID Room 345, requiring services including acoustical tile ceiling installation, resilient base and flooring installation, luxury vinyl floor covering, interior painting, and electrical work. The work encompasses multiple specification sections covering surface preparation, quality requirements, cutting and patching, cleaning and waste management, and various finish installations. The contractor is mandated to conduct a scheduled site visit prior to submitting a bid proposal. A preconstruction conference will be held with TXDPS staff, the contractor, and involved trades before work commences, and the contractor's foreman or field representative must attend. Working hours are established between 7:00 AM and 5:00 PM on weekdays, with weekend work available as approved. The contract monitor is Dinah Eghan-Wiafe, Construction Manager for Southeast Texas Region, reachable at 346-244-3360. All work must be completed as a turnkey project with minimal disruption to the occupied facility.
The contractor must provide a minimum one-year warranty on all installation work covering 100 percent of new material and labor costs from the date of Substantial Completion. All workers must have a minimum of three years of experience in their respective fields, and the contractor is responsible for obtaining and paying for all required permits. The facility will remain occupied during construction, requiring contractors to implement appropriate safety measures and minimize disruptions to building operations. Detailed specifications are provided for all work including acoustical tile ceilings (24 by 24 inches, 3/4-inch mineral base with white painted finish), resilient base (Roppe Brown #110, 4 inches high), luxury vinyl floor tile with beveled edges, and interior and exterior painting systems with specific product requirements and dry film thickness specifications. After-hours emergency contact numbers must be provided, with required response within two hours. The contractor must supply documentation of not less than three similar projects, including project names, locations, products installed, completion dates, and owner contact information, along with comprehensive maintenance data and warranty information to be provided upon Substantial Completion.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TEXAS DEPARTMENT OF PUBLIC SAFETY SCOPE OF WORK
The Texas Department of Public Safety (TXDPS) is requesting Bid Solicitations for CID Room 345 Renovation at Houston Headquarters. See the attached scope of work, drawings and specifications for more information.
Services to Include:
1. See Summary of Work.
Project Houston Regional Headquarters, A – CID Suite 12230 West Road Jersey Village, Texas 77065
Department of Public Safety Contract Monitor:
Dinah Eghan-Wiafe Construction Manager Southeast Texas Region
MO: 346-244-3360
Dinah.Eghan-Wiafe@dps.texas.gov
NOTE: Building contacts will be identified to the bidders for the respective locations for site visits and future access. Access times for each phase of construction must be scheduled ahead of actual work.
Table of Contents - Specification Sections Section 01 11 00 Summary of Work Section 01 40 00 Quality Requirements Section 01 50 00 Temp Facilities and Controls Section 01 73 00 Cutting and Patching Section 01 74 00 Cleaning and Waste Management Section 09 51 23 Acoustical Tile Ceilings Section 09 65 13 Resilient Base and Accessories Section 09 65 19 Luxury Vinyl Floor Covering Section 09 91 23 Interior Painting Section 26 05 00 Common Work Results for Electrical
Floor Selection Existing Drawings Drawings Photos
STATEMENT OF WORK 405-26R0019956 Houston Office Renovation
SECTION 01 11 00 – SUMMARY OF WORK
PART 1 - GENERAL
1.01 SCOPE OF WORK
A. This section outlines the scope of work included in the project. Refer to the appropriate drawings and specification sections for further information about installation, preparation methods and components to be provided. The contractor is responsible for including all means and methods necessary to complete this portion of the project. The Contract Documents, otherwise referred to as drawings, shall serve as a part of this scope of work showing more detail on the intent of this project. The Contractor is responsible for including all means and methods necessary to complete this project and to field verify existing conditions and dimensions. In general, the work includes, but is not limited to, the following items:
1. See drawings for additional scope of work.
2. Ensure all applicable codes and ADA/ADAAG/TAS regulations are followed.
3. Provide a minimum one (1) year Warranty on all installation work.
4. Provide turnkey project as indicated on the drawings and as required for complete project.
1.02 QUALITY CONTROL
A. Contractor is responsible for properly disposing of all trash, or construction debris associated with this project.
B. Removal shall not utilize TXDPS dumpster or equipment unless authorized by DPS.
C. TXDPS will identify an exterior staging area/ entry for use by the contractor. This temporary storage must be maintained in a neat orderly manner and restored to original condition upon completion.
D. Any container used as part of this contract is subject to inspection upon being located on DPS property.
E. Contractor shall efficiently schedule all work to ensure work will be done in as few calendar days as possible for optimum installation to meet the manufacturer’s warranty requirements.
All work shall be continuous to insure the facility impact is minimal with limited disruptions.
Every effort shall be made to eliminate down time and get the DPS operations back in service as quickly and safely as possible. The exact dates will be coordinated once the bid award is made.
F. All work will be performed by qualified craft persons with a minimum of (3) three years of experience in the field. It shall be the contractor’s responsibility to provide only skilled qualified workers for this project.
G. The new work shall comply with the state and local codes and ordinances.
1.03 PERFORMANCE REQUIREMENTS
A. The Work requirements of the Contract are summarized by reference to the Bidding Requirements, the Contract forms, the Conditions of the Contract, the Specification, the Drawings, and Addenda and Contract Modifications, including, but not limited to, the printed matter referenced in these requirements. It is recognized that the Work is affected or influenced by governing regulations, natural phenomenon (including weather conditions), unforeseen conditions uncovered by the Work, and other forces outside of the Contract
Documents.
B. All work shall be considered new unless otherwise indicated.
C. All workmanship and materials shall be of the best construction practice. Should a conflict arise between the specification requirements and those of the referenced publications, the better quality or more stringent requirement will prevail. Specification requirements that exceed the minimum requirements of the manufacturer shall be compiled with by the Contractor.
D. The Contractor shall check and verify all dimensions, notes, conditions in the installation area on site before any construction work is started. All discrepancies shall be reported to DPS in writing. No extra charge of compensation will be allowed on account of any difference between actual measurements or dimensions supplied by TXDPS, either verbally or in written form.
E. The Contractor shall assume full responsibility for the accuracy, fit and stability of all parts of the work.
F. All labor, materials and installations must comply with the codes, rules and regulations of local, state and federal authorities having jurisdiction. Any discrepancy which exists between the requirements by the plans, specifications, said codes, rules and regulations, shall be immediately brought to the attention of DPS Facilities Department, in writing for resolution.
G. Applicable publications: Publications listed herein form a part of this Specification to the extent referenced and are indicated in the text by basic designation only. Applicable publications referenced shall be those that were issued and in use at the time of the Bid Submission.
H. The Contractor shall provide all necessary protection of existing work and newly added work.
I. The Contractor shall be responsible for adequately bracing and protecting all work during construction against damage, breakage, collapse, distortion and misalignment according to applicable codes and standards.
J. Working hours will be between 7:00 am and 5:00 pm during the week and as approved during the weekend if necessary. DPS needs to be clean and ready for work as soon as work is complete. If additional time is necessary for the specified products, schedule must be coordinated with DPS before any work begins.
K. The Contractor shall repair and restore to its original condition all work and items damaged as a result of building operations and shall leave the work completed to the true intent of the drawings and specifications and to the satisfaction of DPS.
L. Any disturbance or damage to the existing building, site or utilities resulting from either directly or indirectly from the building operations shall be promptly repaired, restored or replaced to the satisfaction of DPS at no additional cost to DPS.
M. All materials and construction to be incorporated in the work shall be in strict accordance with the latest editions of IBC and shall conform to the standards and recommendations of the various trade institutes where applicable.
N. The Contractor shall coordinate the work of any and all Sub-Contractors and also coordinate with DPS on portions of the work done by DPS employees or sub-contractors.
O. Manufacturer's Instructions:
1. Require compliance with instructions in full detail, including each step in sequence.
Do not omit preparatory steps or installation procedures unless specifically modified or exempted by the SOW.
2. Should instruction conflict with Contract Documents, request clarification from DPS Contact before proceeding.
P. Manufacturer's Certificates:
1. When required in individual specifications section, submit manufacturer's certificate, in duplicate, certifying that products meet or exceed specified requirements, executed by responsible officer.
1.04 PROJECT CONDITIONS
A. The building will be occupied and in use during construction, take necessary precautions to create as little disturbance or disruption to the building and its occupants as possible during work hours.
B. Supply, install, and maintain barriers, protection, warning lines, lighting, and personnel required to segregate the work area(s) from pedestrian or vehicular traffic, as well as to prevent damage to the building, its occupants, and the surrounding landscaped and paved areas. The Contractor shall observe all applicable OSHA requirements.
C. Schedule and execute work without exposing the building interior to the effects of inclement weather. Protect the building and its occupants against such risks and repair/replace work related damage to DPS’s satisfaction.
1.05 PRECONSTRUCTION CONFERENCE
A. A preconstruction conference may be held with DPS Staff as required, Contractor, and involved trades to discuss all aspects of the project. The Contractor's foreman or field representative will attend this conference.
B. DPS shall reserve the right to require an alternate superintendent and/or foreman.
C. Delivery of materials and commencement of construction shall not proceed until the preconstruction conference is held unless authorized by the DPS Contract Monitor.
D. Provide a line item breakdown of construction labor and materials costs for each Specification Section included in these Contract Documents.
1.06 EMERGENCY RESPONSE
A. The Contractor shall provide DPS with after-hours (24 hour) emergency telephone numbers of the Contractor’s superintendent and foreman.
B. The Contractor must respond to emergency situations or calls within two (2) hours.
1.07 SUBMITTALS
A. Provide:
1. Manufacturer’s technical data.
2. Application or installation instructions.
3. Substitution Request Form, if necessary.
B. Provide schedule of installation as part of this requirement.
C. Provide samples and manufacturer’s literature for all products used on this project.
D. Provide certificates signed by the manufacturer certifying that installers comply with specified requirements.
E. All bidders shall submit information of not less than three (3) projects of similar size and complexity to include:
1. Project name and location.
2. Products installed.
3. Date of completion.
4. Owner’s contact name and telephone number.
F. Provide maintenance data for O&M (Operations and Maintenance) Manuals.
G. Provide warranty information to be turned over to the Owner at Substantial Completion.
H. All submittals, samples and documentation required should be sent to DPS Contract Monitor.
1.08 SCHEDULING
A. All field work installations at the listed location shall be scheduled to facilitate continued facility usage as required by DPS.
B. Prior approval must be received from local DPS staff if scheduled project tasks may impact regular DPS facility operational schedule.
C. Proper coordination of all aspects of the work by the Contractor and any sub-trades is critical to ensure proper installation and performance of the work. The Contractor’s Construction Schedule shall clearly outline the coordination between job tasks of all involved disciplines. Subject to review and acceptance by the DPS, this Schedule will be strictly adhered to by the Contractor and sub-trades.
D. DPS shall review the Contractor’s Construction Schedule prior to the start of any work.
After defining the location(s) of the work progress, DPS shall arrange to control occupancy in the building to the greatest extent possible. It shall be the responsibility of the Contractor to supply DPS with written notice, 72 hours in advance, if his work location(s) for a workday is different from the schedule. The Contractor shall update his Construction Schedule weekly and submit a copy to DPS for review.
1.09 SPECIAL CONSIDERATIONS
A. Even if it is not anticipated, the contractor may be required to shut down operations during the project for an unforeseen State of Texas emergency. In this event, the contractor will be required to finish any open work, secure the site staging area, and evacuate his/her personnel as safely but as quickly as possible from the property. Notification to return to work will be issued as soon as possible from authorized DPS personnel.
B. Any Propane tanks, gas cylinders or other flammable/hazardous materials must be secured and stored in a safe industry acceptable manner when in use or when they are being stored for future use at this or any DPS facility. Storage locations and quantities are to be identified to the affected Building Manager for the duration of the contract.
C. Contractor vehicles used for transport of personnel or materials shall be locked with the emergency brake set and the ignition key removed when left unattended. Parking or storage must be located only in approved areas determined by the local building manager.
The Department of Public Safety shall not be responsible for damage by others to contract or Personal vehicles left on the project site. Any vehicle or equipment without an ignition key starter shall be rendered inoperable if left overnight. Also, any Vehicle or large equipment with a common industrial type of ignition source shall be rendered inoperable if left overnight. Security and safety of tools or equipment shall be the responsibility of the contractor during work and after regular business hours. Items such as ladders must be removed and secured prohibiting unauthorized access to the facility.
D. The facility shall not be left open by removal of any building component without prior knowledge of the DPS Building Manager. All removed openings are to be left secure with new products at the end of each work day or reasonably secured with 3/4” plywood or industry standard plugs. Temporary fillers must be cut to size and screwed securely into the opening in the event new component material need to be altered if the first attempt fails to fit an opening.
E. Contractor will be required to provide operation demonstration to the identified staff for future maintenance needs along with other information on warranty, maintenance manuals or other related details. Warranty information is subject to approval by Department of Public Safety’s Legal Section. Counsel may advise as to the warranty details that are not in compliance to state law or must be changed not to violate agency policy.
1.10 DEFINITIONS
A. DPS: Texas Department of Public Safety = Owner.
B. Contractor: Primary party responsible for coordination of their own employees or their respective sub-contractor groups to complete the contract project to meet these specifications.
C. Installer/Applicator/Erector: Entity engaged by Construction Manager as an employee, Subcontractor, or Sub- subcontractor, to perform a particular construction operation, including installation, erection, application, and similar operations.
D. DPS Contact/Contract Monitor: Owner’s primary representative for this project having authority to communicate project details and accept or deny final installation completion.
E. TDLR-TAS: Texas Department of Licensing and Regulation – Texas Accessibility Standards.
1.11 PREFERRED PRODUCTS
A. Pursuant to Texas Government Code 2155.444 and 2155.4441, when quality, availability, and price of materials are comparable, provide those produced within the following distances from the Project site (listed in order of preference): 1. Within the State of Texas and within 500 miles; 2. Within the State of Texas and greater than 500 miles; 3. Within the United States and within 500 miles; 4. Within the United States and greater than 500 miles;
5. Outside the United States and within 500 miles; 6. Outside the United States and greater than 500 miles.
1.12 CONTRACT METHOD
A. Project may be constructed under a single prime contract at the discretion of DPS.
B. Contractor is mandated to make a scheduled site visit prior to sending in their bid proposal.
C. DPS reserves the right to reduce Scope of Work. In such cases, DPS will send out a revised Scope of Work to bidders for a revised bid.
1.13 WARRANTY
A. Installer shall furnish a single, written warranty covering 100% of the new material and labor costs protecting the owner, for a period of one (1) years from date of Substantial Completion.
B. In the event of component damage from the use of incompatible materials, or during installation any accident, mishandling, improper transportation methods or negligence on part of the Contractor or Sub-Contractor forces, the Primary Contractor shall be responsible for replacement at no cost the DPS.
C. Refer to specific sections of the specification for systems and product warranty requirements. Verify with Manufacturer of proposed systems and products that specified warranty requirements are acceptable, without exception, prior to selecting materials for use on this project.
D. Submit a full Contractor's Guarantee of the Work to be free from defect in materials and workmanship upon Substantial Completion, and prior to final payment. This Guarantee shall be for a period of one (1) years from the date of Substantial Completion, and shall be signed by a Principal of the Contractor’s firm, and sealed if a corporation.
E. If requested by DPS, submit a letter from the manufacturer acknowledging that completed
Work is acceptable and that warranty remains in effect.
1.14 FINAL INSPECTION AND PAYMENT
A. Inspections: DPS will conduct inspections of the project to verify work is in general compliance with the project intent, Contract Documents, and specifications prior to issuing payments to the Contractor. Inspections will be done by DPS Contract Monitor or designated representative and may be conducted at any time, prior to payments and at a minimum prior to any payments to the Contractor.
B. Final Inspection: The Contractor and the DPS Contract Monitor or designated representative shall provide a comprehensive final inspection after completion of the project. All application errors shall be addressed and final punch list items completed prior to rendering any final payments.
C. Prior to DPS final acceptance of the project and completion of receiving reports for applications for payment, the contractor shall return all security badges, issued to the contractor and sub-contractors for access to DPS facilities, to the Contract Monitor.
1.15 PERMITS
A. The Contractor will obtain and pay for any and all permits required to perform the work.
1.16 PRE-JOB DAMAGE SURVEY OF FACILITY
A. Perform a thorough pre-job survey of property and all affected and adjacent areas of the building with DPS prior to starting the work in order to document existing damage.
Damaged items identified during the survey will not be the responsibility of Contractor unless further damaged by the Contractor during execution of the project.
B. Documentation recorded during this meeting (pictures and videos) will be sent to DPS in order to review at the end of the project. It is the responsibility of the contractor to provide this documentation.
PART 2 – NOT USED
PART 3 - EXECUTION
3.01 EXAMINATION
A. Contractor shall check and verify all dimensions, notes, conditions and location of existing poles, cables or equipment in the installation area on site before any construction work starts. All discrepancies shall be reported to DPS Contact. No extra charge of compensation will be allowed on account of any difference between actual measurements and measurements or dimensions supplied by DPS, either verbally or in written form.
B. Examine substrates and conditions under which Work is to be performed. Do not commence work over unsatisfactory conditions detrimental to proper and timely execution of Work.
C. Do not proceed with Work until unsatisfactory conditions have been corrected.
D. Commencement of installation constitutes acceptance of conditions and cost of any corrective measures are the responsibility of the Contractor.
E. The Contractor is responsible for notifying the DPS Contact should there be a discovery of asbestos during the demolition process. In such cases, Work will cease until there is a resolution and permission from DPS Contract Monitor to commence work.
F. Ensure preparatory works are correctly done prior to main work.
END OF SUMMARY OF WORK
SECTION 01 40 00 - QUALITY REQUIREMENTS
PART 1 – GENERAL
1.01 SUMMARY
A. This Section includes administrative and procedural requirements for quality assurance and quality control.
B. Requirements for Contractor to provide quality-assurance and -control services required by TXDPS
Contract Monitor or authorities having jurisdiction are not limited by provisions of this Section.
C. See specific specification sections for testing and inspection requirements.
1.02 DEFINITIONS
A. Quality-Assurance Services: Activities, actions, and procedures performed before and during execution of the Work to guard against defects and deficiencies and substantiate that proposed construction will comply with requirements.
B. Quality-Control Services: Tests, inspections, procedures, and related actions during and after execution of the Work to evaluate that actual products incorporated into the Work and completed construction comply with requirements.
C. Preconstruction Testing: Tests and inspections that are performed specifically for the Project before products and materials are incorporated into the Work to verify performance or compliance with specified criteria.
D. Product Testing: Tests and inspections that are performed by an NRTL, an NVLAP, or a testing agency qualified to conduct product testing and acceptable to authorities having jurisdiction, to establish product performance and compliance with industry standards.
E. Source Quality-Control Testing: Tests and inspections that are performed at the source, i.e., plant, mill, factory, or shop.
F. Field Quality-Control Testing: Tests and inspections that are performed on-site for installation of the Work and for completed Work.
G. Testing Agency: An entity engaged to perform specific tests, inspections, or both. Testing laboratory shall mean the same as testing agency.
H. Installer/Applicator/Erector: Contractor or another entity engaged by Contractor as an employee, Subcontractor, or Sub-subcontractor, to perform a particular construction operation, including installation, erection, application, and similar operations.
I. Experienced: When used with an entity, "experienced" means having successfully completed a minimum of five previous projects similar in size and scope to this Project; being familiar with special requirements indicated; and having complied with requirements of authorities having jurisdiction.
1.03 CONFLICTING REQUIREMENTS
A. If compliance with two or more standards is specified and the standards establish different or conflicting requirements for minimum quantities or quality levels, comply with the most stringent requirement. Refer uncertainties and requirements that are different, but apparently equal, to TXDPS Contract Monitor for a decision before proceeding.
B. The quantity or quality level shown or specified shall be the minimum provided or performed. The actual installation may comply exactly with the minimum quantity or quality specified, or it may exceed the minimum within reasonable limits. To comply with these requirements, indicated numeric values are minimum or maximum, as appropriate, for the context of requirements. Refer uncertainties to TXDPS Contract Monitor for a decision before proceeding.
1.04 SUBMITTALS
A. If required and for TXDPS's records, submit copies of permits, licenses, certifications, inspection reports, releases, jurisdictional settlements, notices, receipts for fee payments, judgments, correspondence, records, and similar documents, established for compliance with standards and regulations bearing on performance of the Work.
1.05 QUALITY ASSURANCE
A. General: Qualifications paragraphs in this Article establish the minimum qualification levels required;
individual Specification Sections specify additional requirements.
B. Installer Qualifications: A firm or individual experienced in installing, erecting, or assembling work similar in material, design, and extent to that indicated for this Project, whose work has resulted in construction with a record of successful in-service performance.
C. Manufacturer Qualifications: A firm experienced in manufacturing products or systems similar to those indicated for this Project and with a record of successful in-service performance, as well as sufficient production capacity to produce required units.
D. Fabricator Qualifications: A firm experienced in producing products similar to those indicated for this
Project and with a record of successful in-service performance, as well as sufficient production capacity to produce required units.
E. Specialists: Certain sections of the Specifications require that specific construction activities shall be performed by entities who are recognized experts in those operations. Specialists shall satisfy qualification requirements indicated and shall be engaged for the activities indicated.
1. Requirement for specialists shall not supersede building codes and regulations governing the
Work.
F. Testing Agency Qualifications: An NRTL, an NVLAP, or an independent agency with the experience and capability to conduct testing and inspecting indicated, as documented according to ASTM E 548; and with additional qualifications specified in individual Sections; and where required by authorities having jurisdiction, that is acceptable to authorities.
1. NRTL: A nationally recognized testing laboratory according to 29 CFR 1910.7.
2. NVLAP: A testing agency accredited according to NIST's National Voluntary Laboratory
Accreditation Program.
G. Factory-Authorized Service Representative Qualifications: An authorized representative of manufacturer who is trained and approved by manufacturer to inspect installation of manufacturer's products that are similar in material, design, and extent to those indicated for this Project.
1.06 QUALITY CONTROL
A. Inspections are Contractor's responsibility. Unless otherwise indicated, provide quality-control services specified and those required by authorities having jurisdiction. Perform quality-control services required of Contractor by authorities having jurisdiction, whether specified or not.
1. Where services are indicated as Contractor's responsibility, engage a qualified testing agency to perform these quality-control services.
a. Contractor shall not employ same entity engaged by TXDPS, unless agreed to in writing by
TXDPS.
2. Notify testing agencies at least 24 hours in advance of time when Work that requires testing or inspecting will be performed.
3. Where quality-control services are indicated as Contractor's responsibility, submit a certified written report, in duplicate, of each quality-control service.
4. Testing and inspecting requested by Contractor and not required by the Contract Documents are
Contractor's responsibility.
5. Submit additional copies of each written report directly to authorities having jurisdiction, when they so direct.
B. Manufacturer's Field Services: Where indicated, engage a factory-authorized service representative to inspect field-assembled components and equipment installation, including service connections. Report results in writing to the TXDPS Contract Monitor.
C. Retesting/Re-inspecting: Regardless of whether original tests or inspections were Contractor's responsibility, provide quality-control services, including retesting and re-inspecting, for construction that replaced Work that failed to comply with the Contract Documents.
D. Testing Agency Responsibilities: Cooperate with TXDPS Contract Monitor and Contractor in performance of duties. Provide qualified personnel to perform required tests and inspections.
1. Notify TXDPS Contract Monitor and Contractor promptly of irregularities or deficiencies observed in the Work during performance of its services.
2. Determine the location from which test samples will be taken and in which in-situ tests are conducted.
3. Conduct and interpret tests and inspections and state in each report whether tested and inspected work complies with or deviates from requirements.
4. Submit a certified written report, in duplicate, of each test, inspection, and similar quality-control service through Contractor.
5. Do not release, revoke, alter, or increase the Contract Document requirements or approve or accept any portion of the Work.
6. Do not perform any duties of Contractor.
E. Associated Services: Cooperate with agencies performing required tests, inspections, and similar quality-control services, and provide reasonable auxiliary services as requested. Notify agency sufficiently in advance of operations to permit assignment of personnel. Provide the following:
1. Access to the Work.
2. Incidental labor and facilities necessary to facilitate tests and inspections.
F. Coordination: Coordinate sequence of activities to accommodate required quality-assurance and -control services with a minimum of delay and to avoid necessity of removing and replacing construction to accommodate testing and inspecting.
PART 2 – PRODUCTS - Not applicable.
PART 3 – EXECUTION
3.01 REPAIR AND PROTECTION
A. On completion of testing, inspecting, and similar services, repair damaged construction and restore substrates and finishes.
1. Provide materials and comply with installation requirements specified in other Specification
Sections. Restore patched areas and extend restoration into adjoining areas with durable seams that are as invisible as possible.
B. Protect construction exposed by or for quality-control service activities.
C. Repair and protection are Contractor's responsibility, regardless of the assignment of responsibility for quality-control services.
END OF SECTION
SECTION 01 73 00 - CUTTING AND PATCHING
1.1 SUMMARY
A. Provisions as established in the General Requirements of the Scope of Work.
1.2 SUBMITTALS
A. Submit written request in advance of cutting or alteration, which affects:
1. Structural integrity of any element of the Project.
2. Integrity of weather-exposed or moisture-resistant element.
3. Efficiency, maintenance, or safety of any operational element.
4. Visual qualities of sight-exposed elements.
5. Work of Owner or separate contractor.
B. Include in request:
1. Identification of Project.
2. Location and description of affected work.
3. Necessity for cutting or alteration.
4. Description of proposed work, and products to be used.
5. Alternatives to cutting and patching.
6. Effect on work of Owner or separate contractor.
7. Written permission of affected separate contractor.
8. Date and timework will be executed.
1.3 PAYMENT FOR COSTS
A. Costs resulting from ill-timed or defective work, or work not conforming to Contract Documents, including costs for additional services of other consultants shall be borne by the party responsible for ill-timed, rejected or non-conforming Work.
PART 2 – PRODUCTS
2.1 MATERIALS
A. Products: Those required for original installation.
3.1 GENERAL
A. Execute cutting, fitting, and patching including excavation and fill, to complete the Work, and to:
1. Fit the several parts together, to integrate with other work.
2. Uncover work to install ill-timed work.
3. Remove and replace defective and non-conforming work.
4. Remove samples of installed work for testing.
5. Provide openings in elements of Work for penetrations of mechanical and electrical work.
3.2 INSPECTION
A. Inspect existing conditions, including elements subject to damage or movement during cutting and patching.
B. After uncovering, inspect conditions affecting performance of work.
C. Beginning of cutting or patching means acceptance of existing conditions.
3.3 PREPARATION
A. Provide temporary supports to assure structural integrity of surroundings; devices and methods to protect other portions of the Project from damage.
B. Provide protection from elements for areas, which may be exposed by uncovering work;
maintain excavations free of water.
3.4 CUTTING AND PATCHING
A. Execute cutting, fitting, and patching (including excavation and fill) to complete work.
B. Fit products together, to integrate with other work.
C. Uncover work to install ill-timed work.
D. Remove and replace defective or non-forming work.
E. Remove samples of installed work for testing when requested.
F. Provide openings in the work for penetration of mechanical and electrical work.
3.5 PERFORMANCE
A. Execute work by methods to avoid damage to other work, and which will provide proper surfaces to receive patching and finishing.
B. Employ original installer to perform cutting and patching for weather-exposed and moisture-resistant elements and sight-exposed surfaces.
C. Cut rigid materials using masonry saw or core drill. Pneumatic tools are not allowed without prior approval.
D. Restore work with new products in accordance with requirements of the Contract
Documents.
E. Fit work tight to pipes, sleeves, ducts, conduit, and other penetrations through surfaces.
F. Refinish surfaces to match adjacent finishes. For continuous surfaces, refinish to nearest intersection; for an assembly, refinish entire unit.
SECTION 01 74 00 – CLEANING AND WASTE MANAGEMENT
1.1 SUMMARY
A. Provisions as established in the General Requirements of the Scope of Work.
B. Section Includes:
1. Cleaning during construction.
2. Final cleaning of project and related site work.
1.2 CLEANING DURING CONSTRUCTION
A. Control accumulation of waste materials and rubbish; dispose of off-site daily.
B. Keep site and construction areas clean on a daily basis.
C. Maintain areas free of dust and other contaminants during finishing operations.
1.3 FINAL CLEANING
A. Execute cleaning prior to inspection for Substantial Completion of the Work.
2.1 CLEANING MATERIALS
A. Use materials which will not create hazards to health or property, and which will not damage surfaces.
B. Use only materials and methods recommended by manufacturer of material being cleaned.
3.1 CLEANING
A. In addition to removal of debris and cleaning specified in other sections, clean exposed-to-view surfaces.
B. Remove waste, foreign matter, and debris from access ways.
C. Maintain cleaning until Final Completion.
D. Final Cleaning: In addition to cleaning during construction, prior to Substantial Completion provide the following:
1. Remove temporary protection and labels not required to remain.
2. Remove waste, debris, and surplus materials from site daily. Clean grounds; remove stains, spills, and foreign substances from paved areas and sweep clean. Rake clean other exterior surfaces.
TEXAS DEPARTMENT OF PUBLIC SAFETY TEXAS CITY AREA OFFICE
DPS Project No. 20220214000 HVAC Upgrade
ACOUSTICAL TILE CEILINGS 09 51 23 - Page 1 of 6
SECTION 09 51 23 - ACOUSTICAL TILE CEILINGS
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section Includes:
1. Acoustical tiles for interior ceilings.
B. Related Requirements:
1.3 ACTION SUBMITTALS
A. Product Data: For each type of product.
B. Sustainable Design Submittals:
1. Product Data: For recycled content, indicating postconsumer and preconsumer recycled content and cost.
2. Product Data: For adhesives, indicating VOC content.
C. Samples: For each exposed product and for each color and texture specified, 6 inches in size.
D. Samples for Verification: For each component indicated and for each exposed finish required, prepared on Samples of sizes indicated below:
1. Acoustical Tiles: Set of full-size Samples of each type, color, pattern, and texture.
1.4 CLOSEOUT SUBMITTALS
A. Maintenance Data: For finishes to include in maintenance manuals.
1.5 MAINTENANCE MATERIAL SUBMITTALS
A. Furnish extra materials, from the same product run, that match products installed and that are packaged with protective covering for storage and identified with labels describing contents.
1. Acoustical Ceiling Units: Full-size tiles equal to 2 percent of quantity installed.
1.6 DELIVERY, STORAGE, AND HANDLING
A. Deliver acoustical tiles, suspension-system components, and accessories to Project site and store them in a fully enclosed, conditioned space where they will be protected against damage from moisture, humidity, temperature extremes, direct sunlight, surface contamination, and other causes.
B. Before installing acoustical tiles, permit them to reach room temperature and a stabilized moisture content.
http://www.arcomnet.com/sustainable_design.aspx?topic=7 http://www.arcomnet.com/sustainable_design.aspx?topic=11
ACOUSTICAL TILE CEILINGS 09 51 23 - Page 2 of 6
1.7 FIELD CONDITIONS
A. Environmental Limitations: Do not install acoustical tile ceilings until spaces are enclosed and weathertight, wet-work in spaces is complete and dry, work above ceilings is complete, and ambient temperature and humidity conditions are maintained at the levels indicated for Project when occupied for its intended use.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. Source Limitations:
1. Suspended Acoustical Tile Ceilings: Obtain each type of acoustical ceiling tile and its suspension system from single source from single manufacturer.
2.2 PERFORMANCE REQUIREMENTS
A. Verify ceiling products comply with the requirements of the California Department of Public Health's "Standard Method for the Testing and Evaluation of Volatile Organic Chemical Emissions from Indoor Sources Using Environmental Chambers."
B. Surface-Burning Characteristics: Comply with ASTM E84; testing by a qualified testing agency.
Identify products with appropriate markings of applicable testing agency.
1. Flame-Spread Index: Class A according to ASTM E1264.
2. Smoke-Developed Index: 50 or less.
C. Fire-Resistance Ratings: Comply with ASTM E119; testing by a qualified testing agency.
Identify products with appropriate markings of applicable testing agency.
1. Indicate design designations from UL or from the listings of another qualified testing agency.
2.3 ACOUSTICAL TILES GENERAL INTERIOR (NEW & REPLACEMENT)
A. Acoustical Tile Standard: Provide manufacturer's standard tiles of configuration indicated that comply with ASTM E1264 classifications as designated by type, form, and pattern, unless otherwise indicated.
B. Acoustical ratings:
1. NRC: ≥ 0B8D per ASTM C423.
2. CAC: ≥ 3D per ASTM E1414.
3. Sound Masking: 45-48 dBA per ASTM E1130.
4. Reverberation Time: less than 0.8 seconds.
C. Light reflectance: ≥ 85%.
D. Recycled Content: Postconsumer recycled content plus one-half of preconsumer recycled content not less than 20 percent. Product shall be Recyclable in a closed Loop process back to manufacturer.
E. Classification: Provide tiles as follows:
1. Type and Form: Type III, mineral base with painted finish.
2. Pattern: CD (perforated, small holes and fissured.
http://www.arcomnet.com/sustainable_design.aspx?topic=65 http://www.arcomnet.com/sustainable_design.aspx?topic=30
ACOUSTICAL TILE CEILINGS 09 51 23 - Page 3 of 6
F. Color: White
G. Edge/Joint Detail: Square, kerfed, and rabbeted.
H. Thickness: 3/4 inch.
I. Modular Size: 24 by 24 inches.
J. Antimicrobial Treatment: Manufacturer's standard broad spectrum, antimicrobial formulation that inhibits fungus, mold, mildew, and gram-positive and gram-negative bacteria and showing no mold, mildew, or bacterial growth when tested according to ASTM D3273, ASTM D3274, or ASTM G21 and evaluated according to ASTM D3274 or ASTM G21.
2.4 METAL SUSPENSION SYSTEM
A. Metal Suspension-System Standard: Provide manufacturer's standard, direct-hung, fully concealed, metal suspension system and accessories of type, structural classification, and finish indicated that complies with applicable requirements in ASTM C635/C635M.
B. Direct-Hung, Double-Web Suspension System: Main and cross runners roll formed from and capped with cold-rolled steel sheet, prepainted, electrolytically zinc coated, or hot-dip galvanized, G30 coating designation.
1. Structural Classification: Heavy-duty system.
2.5 ACCESSORIES
A. Attachment Devices: Size for five times the design load indicated in ASTM C635/C635M, Table 1, "Direct Hung," unless otherwise indicated. Comply with seismic design requirements.
1. Anchors in Concrete: Anchors of type and material indicated below, with holes or loops for attaching hangers of type indicated and with capability to sustain, without failure, a load equal to five times that imposed by ceiling construction, as determined by testing according to ASTM E488/E488M or ASTM E1512 as applicable, conducted by a qualified testing and inspecting agency.
a. Type: Postinstalled expansion or Postinstalled bonded anchors.
b. Corrosion Protection: Carbon-steel components zinc plated according to
ASTM B633, Class SC 1 (mild) service condition.
2. Power-Actuated Fasteners in Concrete: Not permitted.
B. Wire Hangers, Braces, and Ties: Provide wires as follows:
1. Zinc-Coated, Carbon-Steel Wire: ASTM A641/A641M, Class 1 zinc coating, soft temper.
2. Size: Wire diameter sufficient for its stress at three times hanger design load
(ASTM C635/C635M, Table 1, "Direct Hung") will be less than yield stress of wire, but not less than 0.135-inchdiameter wire.
C. Hanger Rods: Mild steel, zinc coated or protected with rust-inhibitive paint.
D. Flat Hangers: Mild steel, zinc coated or protected with rust-inhibitive paint.
2.6 METAL EDGE MOLDINGS AND TRIM
A. Roll-Formed, Sheet-Metal Edge Moldings and Trim: Type and profile indicated or, if not indicated, manufacturer's standard moldings for edges and penetrations complying with seismic design requirements; formed from sheet metal of same material, finish, and color as that used for of suspension-system runners.
ACOUSTICAL TILE CEILINGS 09 51 23 - Page 4 of 6
1. For circular penetrations of ceiling, provide edge moldings fabricated to diameter required to fit penetration exactly.
2. Finish: Match suspension system.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine substrates, areas, and conditions, including structural framing and substrates to which acoustical tile ceilings attach or abut, with Installer present, for compliance with requirements specified in this and other Sections that affect ceiling installation and anchorage and for compliance with requirements for installation tolerances and other conditions affecting performance of the Work.
B. Examine acoustical tiles before installation. Reject acoustical tiles that are wet, moisture damaged, or mold damaged.
C. Proceed with installation only after unsatisfactory conditions have been corrected.
3.2 PREPARATION
A. Measure each ceiling area and establish layout of acoustical tiles to balance border widths at opposite edges of each ceiling. Avoid using less-than-half-width tiles at borders unless otherwise indicated, and comply with layout shown on reflected ceiling plans.
B. Layout openings for penetrations centered on the penetrating items.
3.3 INSTALLATION OF SUSPENDED ACOUSTICAL TILE CEILINGS
A. Install suspended acoustical tile ceilings according to ASTM C636/C636M and manufacturer's written instructions.
B. Suspend ceiling hangers from building's structural members and as follows:
1. Install hangers plumb and free from contact with insulation or other objects within ceiling plenum that are not part of supporting structure or of ceiling suspension system.
2. Splay hangers only where required to miss obstructions; offset resulting horizontal forces by bracing, countersplaying, or other equally effective means.
3. Where width of ducts and other construction within ceiling plenum produces hanger spacings that interfere with location of hangers at spacings required to support standard suspension-system members, install supplemental suspension members and hangers in form of trapezes or equivalent devices.
4. Secure wire hangers to ceiling suspension members and to supports above with a minimum of three tight turns. Connect hangers directly to structure or to inserts, eye screws, or other devices that are secure and appropriate for substrate and that will not deteriorate or otherwise fail due to age, corrosion, or elevated temperatures.
5. Secure flat, angle, channel, and rod hangers to structure, including intermediate framing members, by attaching to inserts, eye screws, or other devices that are secure and appropriate for both the structure to which hangers are attached and the type of hanger involved. Install hangers in a manner that will not cause them to deteriorate or fail due to age, corrosion, or elevated temperatures.
6. Do not support ceilings directly from permanent metal forms or floor deck. Fasten hangers to postinstalled mechanical or adhesive anchors, that extend into concrete.
7. When steel framing does not permit installation of hanger wires at spacing required, install carrying channels or other supplemental support for attachment of hanger wires.
8. Do not attach hangers to steel deck tabs.
ACOUSTICAL TILE CEILINGS 09 51 23 - Page 5 of 6
9. Do not attach hangers to steel roof deck. Attach hangers to structural members.
10. Space hangers not more than 48 inches o.c. along each member supported directly from hangers unless otherwise indicated; provide hangers not more than 8 inches from ends of each member.
11. Size supplemental suspension members and hangers to support ceiling loads within performance limits established by referenced standards.
C. Secure bracing wires to ceiling suspension members and to supports with a minimum of four tight turns. Suspend bracing from building's structural members as required for hangers without attaching to permanent metal forms, steel deck, or steel deck tabs. Fasten bracing wires into concrete with cast-in-place or postinstalled anchors.
D. Install edge moldings and trim of type indicated at perimeter of acoustical ceiling area and where necessary to conceal edges of acoustical tiles.
1. Apply acoustical sealant in a continuous ribbon concealed on back of vertical legs of moldings before they are installed where indicated on drawings.
2. Screw attach moldings to substrate at intervals not more than 16 inches o.c. and not more than 3 inches from ends. Miter corners accurately and connect securely.
E. Install suspension-system runners so they are square and securely interlocked with one another. Remove and replace dented, bent, or kinked members.
F. Install acoustical tiles in coordination with suspension system and exposed moldings and trim.
Place splines or suspension-system flanges into kerfed edges of tiles so tile-to-tile joints are interlocked.
1. Fit adjoining tiles to form flush, tight joints. Scribe and cut tiles for accurate fit at borders and around penetrations through ceiling.
2. Protect lighting fixtures and air ducts according to requirements indicated for fire-resistance-rated assembly.
3.4 ERECTION TOLERANCES
A. Suspended Ceilings: Install main and cross runners level to a tolerance of 1/8 inch in 12 feet, non-cumulative.
B. Moldings and Trim: Install moldings and trim to substrate and level with ceiling suspension system to a tolerance of 1/8 inch in 12 feet, non-cumulative.
3.5 ADJUSTING
A. Clean exposed surfaces of acoustical tile ceilings, including trim and edge moldings. Comply with manufacturer's written instructions for cleaning and touchup of minor finish damage.
B. Remove and replace tiles and other ceiling components that cannot be successfully cleaned and repaired to permanently eliminate evidence of damage.
END OF SECTION 09 51 23
ACOUSTICAL TILE CEILINGS 09 51 23 - Page 6 of 6
THIS PAGE LEFT BLANK
SECTION 09 65 13 - RESILIENT BASE AND ACCESSORIES
1.01 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions apply to this Section.
1.02 SUMMARY
A. Section Includes:
1. Resilient base.
2. Resilient molding accessories.
1.03 SUBMITTALS
A. Product Data: For each type of product.
B. Samples: For each exposed product and for each color and texture specified, not less than 12 inches long.
1.04 MAINTENANCE MATERIAL SUBMITTALS
A. Furnish extra materials that match products installed and that are packaged with protective covering for storage and identified with labels describing contents.
1. Furnish not less than 10 linear feet for every 500 linear feet or fraction thereof, of each type, color, pattern, and size of resilient product installed.
1.05 DELIVERY, STORAGE, AND HANDLING
A. Store resilient products and installation materials in dry spaces protected from the weather, with ambient temperatures maintained within range recommended by manufacturer, but not less than 50 degrees F or more than 90 degrees F.
1.06 FIELD CONDITIONS
A. Maintain ambient temperatures within range recommended by manufacturer, but not less than 70 degrees F or more than 95 degrees F, in spaces to receive resilient products during the following time periods:
1. 48 hours before installation.
2. During installation.
3. 48 hours after installation.
B. After installation and until Substantial Completion, maintain ambient temperatures within range recommended by manufacturer, but not less than 55 degrees F or more than 95 degrees F.
C. Install resilient products after other finishing operations, including painting, have been completed.
2.01 PERFORMANCE REQUIREMENTS
A. Low-Emitting Materials: Flooring system shall comply with the testing and product requirements of the California Department of Public Health's "Standard Method for the
Testing and Evaluation of Volatile Organic Chemical Emissions from Indoor Sources Using Environmental Chambers."
2.02 THERMOSET-RUBBER BASE RB-1
A. Product Standard: ASTM F 1861, Type TS (rubber, vulcanized thermoset), Group I (solid, homogeneous).
1. Style and Location:
a. Style B, Cove.
b. Thickness: 0.125 inch.
c. Height: 4” High unless otherwise noted.
d. Lengths: Coils in manufacturer's standard length.
e. Outside Corners: Job formed
f. Inside Corners: Job formed
g. Color: Roppe Brown, #110
2.03 INSTALLATION MATERIALS
A. Trowelable Leveling and Patching Compounds: Latex-modified, Portland cement based or blended hydraulic-cement-based formulation provided or approved by resilient-product manufacturer for applications indicated.
B. Adhesives: Water-resistant type recommended by resilient-product manufacturer for resilient products and substrate conditions indicated.
1. Adhesives shall have a VOC…