ESBD_520044_1780678435528_MOLD REMEDIATION PROTOCOL.pdf
PDF 1 MB Posted
- Attached to
- Mold Remediation Bldg. 802, Rusk State Hospital
- Solicitation number
- HHS0017319
- Issued by
- Schleicher County, Texas
About this file
This is a Mold Remediation Protocol document prepared by ERC Environmental & Construction Services, Inc. for the Texas Health and Human Services Commission (HHSC) at Rusk State Hospital Building 802. The protocol establishes comprehensive procedures for hazardous material remediation addressing mold contamination across seven identified areas, including a restroom, multiple rooms, and common areas totaling approximately 1,338 square feet of affected surfaces requiring removal or cleaning and disinfection. The project is anticipated to commence upon contract award with a completion deadline of August 31, 2026, with an option for one-year extensions at the agency's sole discretion. A mandatory on-site visit is required for bid eligibility, scheduled for May 26, 2026 at 2:00 PM or May 27, 2026 at 10:00 AM at 805 N. Dickinson Drive, Rusk, Texas 75785. Bids are due June 9, 2026 at 10:30 AM Central Time, with questions due by June 2, 2026 at 5:00 PM and responses posted by June 4, 2026. The project duration is a maximum of fifteen consecutive calendar days with up to ten hours per shift.
Pricing must be submitted as firm, fixed prices on the designated pricing sheet, covering all labor, materials, equipment, tools, and associated expenses. Contractors must demonstrate a minimum of five years of relevant mold remediation experience, with assigned personnel holding at least three years of relevant experience and current licenses from the Texas Department of Licensing and Regulation (TDLR). A minimum of three verifiable references from similar contracts completed within the last five years are required. Comprehensive insurance requirements include workers' compensation, commercial general liability of $1 million per occurrence, commercial automobile liability of $1 million per accident, professional liability of $1 million, and umbrella liability of $1 million. Prices are subject to adjustment based on the Bureau of Labor Statistics Consumer Price Index (Region VI) or federal minimum wage increases when applicable. Bidders must submit completed exhibits including HHS Solicitation Affirmations, pricing documentation, bidder reference forms, background checks for all personnel, and financial capability and solvency documentation. Award is contingent upon approval by the HHSC Executive Commissioner, with a response binding period of 240 days.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MOLD REMEDIATION PROTOCOL
Texas Health & Human Services Commission Rusk State Hospital
Building 802
ERC Project No. P-26024.01.02D
March 2, 2026
© Copyright 1991-2025 by ERC Environmental & Construction Services, Inc. (ERC)
DISCLAIMER
The information contained in this report is confidential, privileged, and only for the information of the CLIENT as identified in the Project Directory. This report may be provided to a third party but must be provided in whole; however, ERC’s liability for the information contained in this report does not extend beyond the CLIENT, unless ERC agrees, in writing, to such extension.
The professional opinions expressed in this report are in good faith and while every care has been taken in preparing this document, any decision made based in whole, or in part, on this report should be discussed with ERC prior to implementation. ERC Environmental & Construction Services, Inc., its subsidiaries, the directors, employees, and agents cannot be held liable for decisions made in opposition to the recommendations contained in this report.
TABLE OF CONTENTS
City of Dallas I Cedar Crest Golf Course ERC Project # P-25010.20.12D
PROJECT INFORMATION # of Pages
SECTION I - PROJECT DIRECTORY 1
SECTION II - SUMMARY OF WORK 3
SECTION III - GENERAL CONDITIONS 2
SECTION IV - POST REMEDIATION INSPECTION & CLEARANCE 2
SECTION V - WORKER PROTECTION 4
SECTION VI - RESPIRATORY PROTECTION 5
SECTION VII – DRAWINGS 1
SECTION I
PROJECT DIRECTORY
SECTION I: PROJECT DIRECTORY
THHSC | Rusk State Hospital- Bldg. 802 ERC Project #: P-26024.01.02D
PROJECT: THHSC – Rusk State Hospital Building 802 805 N. Dickinson Drive Rusk, Texas 75785
ERC PROJECT #: P-26024.01.02D
OWNER: Rusk State Hospital
CONTACT: Chad Jones, Assistant Plant Manager
Maintenance Department | Rusk State Hospital 805 N Dickinson Dr | Rusk TX, 75785 Office: 903-683-7568 Cell: 430-244-3139 Email Address: chad.jones@hhs.texas.gov
CONSULTANT: ERC Environmental & Construction Services Inc.
CONTACT: Kevin Rezvanipour, MAC
DFW Area Manager DSHS Mold Consultant License No. MAC1077 Expiration Date: 11/12/2026 krezvanipour@erc-tx.com>
2828 Forest Lane, Suite 1147 Dallas Texas 75234 Tel: (972) 243-2177 Fax: (972) 243-2179 www.erc-tx.com http://www.erc-tx.com/
SECTION II
SUMMARY OF WORK
SECTION II: SUMMARY OF WORK
PART 1 – GENERAL
NOT USED
RELATED DOCUMENTS
Drawings and general provisions of Contract, including General and Supplementary Conditions, apply to the Work of this section.
CONTRACT DOCUMENTS
The Contract Documents, as prepared by the CONSULTANT, indicate the Work of the Contract and related requirements and conditions that have an impact on the Project.
Related requirements and conditions include, but are not necessarily limited to the following:
Applicable codes and regulations.
Notices, permits, license fees, taxes.
Existing site conditions and restrictions on use of site.
Work to be performed concurrently by the OWNER.
Requirements for partial OWNER occupancy prior to substantial completion of the Contract Work.
WATER CAUSATION:
It has been determined the cause of mold on the wall is due Water leak from the piping.
Based on information received from the building owner representative, the causations have been addressed and necessary step will be taken to repair the causation.
PROJECT DURATION
Maximum consecutive calendar days..................................................... Fifteen (15) days
Maximum work hours ........................................................... up to ten (10) hours per shift
Note: Work days and hours different than stated above can be arranged upon approval from the consultant.
RELATED DOCUMENTS
Drawings and general provisions of Contract, including General and Supplementary Conditions, apply to the Work of this section.
ABBREVIATED WRITTEN SUMMARY
Briefly and without force and effect upon the Contract Documents, the Work of the Contract can be summarized as including removal and disposal of contaminated materials associated with:
Rusk State Hospital Building 802
Remove and discard mold contaminated Room E369 Restroom Sheetrock Wall four feet from ground (30 ft²);
Remove and discard mold contaminated 3rd Floor Rio Room D328 Sheetrock Ceiling (40 ft²);
Remove and discard mold contaminated 3rd Floor journey Recovery Room C337 Ceiling Tile (8 ft²);
Remove and discard mold contaminated 1st Floor Security Station Sheet Flooring (240ft²);
Clean & Disinfect mold contaminated 1st Floor Room B103 Admin Area Carpet (900 ft²);
Clean & Disinfect mold contaminated 3rd Floor Rio Room D322 Carpet Floor (120 ft²); and
Clean & Disinfect 1st Floor Stair Intake Return Grill, 2nd Floor Room E267 and 2nd Floor Room F201 AC Air Supply Grills.
If moisture content is elevated and more than 15% moisture content. Decontaminating the wall cavities from the work area as access allows.
GENERAL SCOPE
Removal Procedures:
Visual inspection will be conducted after containment preparation (pre-remediation activity), during and before secondary preparation of wall cavities (if necessary) and before collection of final clearance.
Remove all the Mold contaminated wall boards under a controlled environment.
The REMEDIATION CONTRACTOR shall erect a negative pressured containment for remediation. The negative air pressure shall be maintained inside the containment at all times during remediation.
The REMEDIATION CONTRACTOR shall exhaust the negative air pressure to outside of the building if feasible during remediation and shall use negative air machines to scrub the air within containment after the containment passes visual inspection until clearance results are achieved.
The REMEDIATION CONTRACTOR shall HEPA vacuum and wipe down all the exposed walls, studs and other horizontal surfaces with appropriate anti-microbial.
Conduct air and surface testing as needed before removing the Containment and releasing the area back to the construction company.
The REMEDIATION CONTRACTOR shall encapsulate the exposed wall surfaces inside containments with EPA approved biocide after clearance has been achieved.
In case, the containments fail to meet the clearance criteria, the remediation CONTRACTOR shall re-clean the containment before re-testing.
All movable equipment and appliances (Ice machines, refrigerators, vending machines and others) to be removed by Owner.
Containment Preparation for work area isolation
Establish Critical/Construction Barriers;
Cover floors, not to be removed, with one layer of 6 mil as applicable;
Cover walls, not to be removed, with one layer of 4 Mil;
Set up a pup up shower; and
Exhaust Negative Air Pressure machines to the outside if possible. If not, use Air scrubber within the work areas.
********** END OF SECTION **********
SECTION III
GENERAL CONDITIONS
SECTION III: GENERAL CONDITIONS
GENERAL NOTES
1. The CONTRACTOR shall hold a Texas Department of Licensing and Regulation license in Environmental Removal work.
2. The CONTRACTOR shall conduct removal activities as per ERC’s protocol, and best-known industry practices/guidelines.
3. The CONTRACTOR shall hold appropriate licenses/registrations. Personnel engaged in microbial removal shall be trained/licensed in the handling of environmental mold/dust and be equipped with proper respiratory protection.
4. The CONTRACTOR shall be responsible for complying with all OSHA safety standards/approved work practices,
5. The CONTRACTOR shall use local exhaust ventilation equipped with a High
Efficiency Particulate Air (HEPA) filter to provide negative pressurization of the work area.
6. The CONTRACTOR will be brushing/wipe cleaning surfaces, utilizing an E.P.A.
approved anti-microbial cleaning solution.
7. The CONTRACTOR shall restrict access to the work area during removal activities.
8. The Owner/CONTRACTOR shall turn off the air conditioning system to work areas during the removal.
9. Personnel engaged in environmental removal shall be trained in the handling of environmental debris and be equipped with respiratory protection equipped with high efficiency particulate air (HEPA) filters (at least a half-face respirator), disposable full-body protective clothing with head and foot coverings and with gloves.
10. The CONTRACTOR shall bag all contaminated materials in plastic bags and dispose of them as construction debris.
11. The CONTRACTOR shall perform a final inspection of each work area/section for compliance with this Protocol, prior to the consultant’s final inspection.
12. The post-removal visual inspection and collection of work area samples will be provided by an ERC Consultant or a Technician.
13. ERC’s Consultant or Technician will conduct the visual inspection of the work area(s), after containment preparation (pre-remediation activity), during and after detailed cleaning of the removal activities, and prior to final clearance testing.
SECTION III: GENERAL CONDITIONS
14. Post-removal testing shall be a combination of visual inspection and air and surface wipe sampling. ERC’s Consultant or Technician shall randomly select testing locations, at their discretion, to best represent the final product and cleaning procedures efficiently.
15. Laboratory results will be available within three (3) days lab turnaround time.
SECTION IV
POST REMEDIATION
INSPECTION & CLEARANCE
SECTION IV: POST REMEDIATION INSPECTION & CLEARANCE
GUIDELINES
Sample Collection Protocol
Prior to taking post removal samples, the CONTRACTOR shall scrub the air within the containment using a negative air machine. Air scrubbing shall include at least 5 volume changes of containment.
During post removal sampling, all negative air machines will be turned off, unless otherwise noted in Section II SUMMARY OF WORK.
Post removal samples will be collected after a period of eight (8) hours (minimum) following the final visual inspection.
The number of samples collected within each contained area will be at the discretion of the CONSULTANT.
Visual Inspection
Prior to the collection of samples, a visual inspection shall be carried out within the contained areas (work areas). The following criteria shall be followed.
All surfaces within the work areas should be free of visible debris.
All work areas should be visibly free of dust and debris.
Spore Trap Samples (When Applicable)
Air samples from the Work Areas (contained areas) will have species concentrations of one half or less (<1/2) of the air outside the Work Areas and/or the outdoors (individually as well as collectively).
Air samples from the Work Areas shall have the same species composition as compared to the samples collected outside the Work Areas and/or the outdoors.
Surface Samples
To determine if environmental removal is complete the CONSULTANT may collect and interpret surface sample results in accordance with the following criteria.
Surface samples may include tape samples, swab sample and/or bulk samples.
SECTION IV: POST REMEDIATION INSPECTION & CLEARANCE
SCHEDULE OF SAMPLES
General: Sample quantities and analytical methodologies may vary and will be at the discretion of the CONSULTANT.
Release Criteria: Decontamination of the Work Area is complete when every Work Area sample is within the guidelines stated above.
Re-cleaning: If the results of analysis of the Work Area samples fails to meet the release criteria, Decontamination is incomplete, re-cleaning is required, and re-testing is required until release criteria is met.
SECTION V
WORKER PROTECTION
SECTION V: WORKER PROTECTION
SUMMARY
This Section describes clothing, equipment and procedures for protection of workers during removal activities.
WORKER TRAINING
Provide worker training for workers on the Project in accordance with applicable regulations. Worker training shall be maintained current for the Project Duration.
MEDICAL EXAMINATIONS
Provide medical examinations for workers on the Project in accordance with applicable regulations, including OSHA requirements as set forth in 29 CFR 1926 1001 (m). Worker medical examinations shall be maintained current for the Project Duration.
LICENSING / REGISTRATION
Provide appropriate licensing\registration, including photo identification, for workers on the Project in accordance with applicable regulations. Worker licensing\registration shall be maintained current for the Project Duration.
SUBMITTALS
General: Submit the following documentation to the CONSULTANT for review. Submit in a timely fashion to allow completed review of documentation prior to start of Work.
List of Workers: Submit a list of CONTRACTOR's personnel (typewritten or neatly printed) for the Project. Only CONTRACTOR's personnel on the list will be permitted on the Project site. Post a copy of the list at the entry to the Work Area. Update the list on a daily basis.
Certificate of Worker's Acknowledgment: Submit an original signed copy of the Certificate of Worker's Acknowledgment, found at the end of this section, for each person on the List of Workers.
Worker Training Certificate: Submit evidence of required Worker Training.
Medical Examination Results: Submit copy of required Medical Examination results.
Worker Registration Certificate: Submit evidence of required Worker Licensing and Registration.
Respiratory Fit Test Certificate: Submit evidence of Respiratory Fit Test for the type of respirator proposed for Work, and in accordance with applicable regulations.
PROTECTIVE CLOTHING AND EQUIPMENT
General: Provide protective clothing and equipment as required by applicable regulations for anticipated type of Work.
Coveralls: Provide disposable full-body coveralls, foot covers, and disposable head covers of polyolefin or polypropylene. Require that personnel in the Work Area wear the above continuously. Provide a sufficient number for required changes for workers, the CONSULTANT and visitors in the Work Area. Non-disposable or cloth protectives will not be permitted.
Gloves: Provide durable waterproof work gloves to workers and require that personnel in the Work Area wear gloves continuously. Do not remove gloves from work area;
dispose as contaminated waste.
Boots and Shoes: Provide waterproof boots or shoes to be used in the Work Area.
Provide boots or shoes with non-skid soles and hard toes.
Hard Hats: Provide head protectives (hard hats) for workers as applicable for anticipated type of Work. Provide four (4) spare hard hats for use by the CONSULTANT and visitors.
Label hats with same warning labels as used on disposal bags. Require hard hats to be worn when Work is in progress. Provide hard hats with plastic strap style of suspension.
Require hats to remain in the Work Area throughout the Work. Decontaminate Prior to removing from Work Area or dispose of hard hats as contaminated waste.
Goggles: Provide eye protectives (goggles) for workers involved in chipping, scraping, spraying, or other activity that may potentially cause eye injury.
WORKER PROTECTION
General: Provide for protection of workers and other authorized personnel on the Project site as required by applicable regulations for anticipated type of Work.
The following procedures are to be considered minimum regardless of air monitoring results within the Work Area.
Require that protective clothing and equipment be worn continuously in Work Area.
Replace damaged or torn items immediately.
ENTERING WORK AREA
Each time Work Area is entered, remove street clothes in the Changing Room of the Personnel Decontamination Unit and don new disposable coverall, head and foot covers and gloves. Tape gloves to the sleeves of coveralls.
Fit proper respiratory protection (respirator).
Proceed through Shower Room to Equipment Room. Don work boots or shoes, hard hat, goggles, etc. in Equipment Room.
Proceed to Containment area.
WITHIN WORK AREA
Workers shall not eat, drink, smoke, and chew gum or tobacco in the Work Area.
Workers shall not remove protective clothing or equipment within the Work Area.
EXITING WORK AREA
Decontamination Procedures: Require personnel to adhere to the following decontamination procedures when exiting the Work Area.
Remove disposable clothing and equipment (except respirator) in the Equipment Room.
Proceed to Shower Room still wearing respirator. Showering is mandatory. Care must be taken to follow reasonable procedures in removing the respirator to avoid fungi (mold) contamination while showering.
Thoroughly wet body including hair and face.
If using PAPR, exercise care to prevent water from entering canisters, blower unit and battery pack.
If using half or full-face cartridge type respirator (non-powered), exercise care to prevent water from entering cartridges at this point.
With respirator remaining in place, thoroughly wash body, hair, and parts of the respirator with soap/shampoo.
Carefully wash seal between face and respirator and under straps.
Take a deep breath, hold and/or exhale slowly, completely wet hair, face, and respirator. While still holding breath, remove respirator away from face before breathing.
Carefully wash respirator inside and out. Dispose of wet filters as contaminated waste.
If using PAPR: Shut down in the following sequence; first, cap inlets to filter cartridges;
then turn off blower unit (this sequence will help keep debris which has collected on the inlet side of filter from dislodging and contaminating the outside of the unit). Thoroughly wash blower unit and hoses. Carefully wash battery pack with wet rag. Use caution to prevent water entering the battery pack.
Rinse body and respirator thoroughly.
Rinse Shower Room walls and floor prior to exit.
Proceed from shower to Changing Room and change into street clothes or into new disposable work items.
SECTION VI
RESPIRATORY PROTECTION
SECTION VI: RESPIRATORY PROTECTION
SUMMARY
This Section describes respiratory protection during environmental removal.
STANDARDS
Comply with the following as applicable:
OSHA U.S. Department of Labor Occupational Safety and Health Administration, Safety and Health Standards 29 CFR 1910, Section 1001 and Section
1910.134, 29 CFR 1926.
CGA Compressed Gas Association, Inc., New York, Pamphlet G-7, "Compressed
Air for Human Respiration", and Specification G-7.1 "Commodity Specification for Air".
CSA Canadian Standard Association, Rexdal, Ontario, Standard Z180.1-1978, "Compressed Breathing Air".
ANSI American National Standard Practices for Respiratory Protection, ANSI
Z88.2-1980.
NIOSH National Institute for Occupational Safety and Health
MSHA Mine Safety and Health Administration
AIR PURIFYING RESPIRATORS
Respirator Bodies: Provide half-face or full-face type respirators; negative pressure or powered (PAPR). Equip full-face respirators with a nose cup or other anti-fogging device as would be appropriate for use in air temperatures less than 32 degrees Fahrenheit.
Provide an extra battery pack for each PAPR.
Filter Cartridges: Provide, at a minimum, HEPA type filters labeled with NIOSH and MSHA Certification for "Radionuclides, Radon Daughters, Dust, Fumes, Mists including Dusts and Mists" and color coded in accordance with ANSI Z228.2 (1980).
In addition, a chemical cartridge section may be added, if required, for solvents, etc., in use. In such case, provide cartridges that have each section of the combination canister labeled with the appropriate color code and NIOSH/MSHA Certification.
Non-Permitted Respirators: Do not use single use, disposable or quarter face respirators.
SUPPLIED AIR RESPIRATOR SYSTEMS (TYPE "C")
General: Provide equipment capable of producing air of quality and volume required as applied to the Project conditions and crew size.
Air Quality: Provide air used for breathing in Type "C" supplied air respiratory systems that meets or exceeds standards set for C.G.A. type 1 (Gaseous Air) Grade D.
Face piece and Hose: Provide full Face piece and hose by same manufacturer, certified by NIOSH/MSHA as an approved Type "C" respirator assembly operating in pressure demand mode with a positive pressure Face piece.
Auxiliary Backup System: In atmospheres, which contain sufficient oxygen (greater than or equal to 19.5% oxygen), provide a pressure-demand full Face piece supplied air respirator equipped with an emergency backup HEPA filter.
Escape Air Supply: In atmospheres, which are oxygen deficient (less than 19.5% oxygen), provide a pressure-demand full Face piece supplied air respirator incorporating an auxiliary self-contained breathing apparatus (SCBA), which automatically maintains an uninterrupted air, supply in pressure demand mode with a positive pressure Face piece.
Backup Air Supply: Provide a reservoir of compressed air located outside the Work Area which will automatically maintain a continuous uninterruptible source of air automatically available to each connected Face piece and hose assembly in the event of compressor shut-down, contamination of air delivered by compressor, power loss or other failure.
Provide sufficient capacity in the backup air supply to allow a minimum escape time of one-half hour times the number of connections available to the Work Area. Air requirement at each connection is the air requirement of the respirators in use plus the air requirement of an average sized adult male engaged in moderately strenuous activity.
Warning Device: Provide a warning device that will operate independently of the building's power supply. Locate so that alarm is clearly audible throughout the Work Area and at the compressor with a volume above the noise level produced by equipment and work procedures in use. Connect alarm to warn of:
Compressor shut-down or other fault requiring use of backup air supply, Carbon Monoxide (CO) levels in excess of 10 PPM/V.
Carbon Monoxide (CO) Monitor: Continuously monitor and record on a strip chart recorder Carbon Monoxide (CO) levels. Place monitors in the airline between compressor and backup air supply and between backup air supply and workers. Connect monitors so that they also sound an alarm as indicated under "Warning Devices".
Compressor Shut-Down: Interconnect monitors, alarms and compressor so that compressor is automatically shut down and the alarms sounded if any of the following occur:
Carbon Monoxide (CO) concentrations exceed 10 PPM/V in the airline between the filter bank and backup air supply.
Compressor temperature exceeds normal operating range.
Compressor Motor: Provide a compressor driven by an electric motor. Ensure that electrical supply available is adequate to energize motor.
If building power supply is inadequate or as other factors may necessitate, provide gasoline or diesel compressor motor as follows.
Compressor Location: Locate compressor outside of building in location that will not impede access to the building, and that will not cause a nuisance by virtue of noise or fumes to occupied portions of the building.
Air Intake: Locate air intake remotely from source or automobile exhaust or exhaust from motors, or buildings.
After Cooler: Provide an after cooler at entry to filter system, which is capable of reducing temperatures to outside ambient air temperatures.
SELF-CONTAINED BREATHING APPARATUS (SCBA)
Configure system to permit the recharging of ½ hour 6220-PSI SCBA cylinders.
GENERAL
Respiratory Protection Program: Comply with ANSI Z88.2 - 1980 "Practices for Respiratory Protection" and OSHA 29 CFR 1910 and 1926, and other applicable regulations.
Instruct and train workers in proper care and use of respiratory protection equipment
Require that respiratory protection be used in the Work Area from the start of Work, which may cause fungi (mold) spores until the Work Area is completely decontaminated. Use respiratory protection appropriate for the concentration encountered and anticipated or as required for other toxic or oxygen-deficient situations encountered.
Require that respiratory protection be used during the possibility of disturbance of fungi (mold) spores’ materials whether intentional or accidental.
Regardless of Airborne Fiber Concentrations: Require that the minimum level of respiratory protection used be half-face air-purifying respirators with high efficiency filters.
RESPIRATORY PROTECTION FACTOR
Use the following respiratory protection factors in determining the degree of protection offered by the indicated respirator type between air inside and outside the respirator.
RESPIRATOR TYPE
PROTECTION
FACTOR
Air purifying:
Negative pressure respirator High efficiency filter Half Face piece
Air purifying:
Negative pressure respirator High efficiency filter Full Face piece
Powered-air purifying (PAPR):
Positive pressure respirator High efficiency filter Half or Full-Face piece
Type C supplied air:
Positive pressure respirator Continuous flow Half or Full-Face piece
Type C supplied air:
Positive pressure respirator Pressure demand Full Face piece
Type C supplied air:
Positive pressure respirator Pressure demand Full Face piece Equipped with an auxiliary positive pressure Self-contained breathing apparatus (SCBA)
Over 1000
Self-contained breathing apparatus (SCBA):
Positive pressure respirator Pressure demand filter Full Face piece
Over 1000
MINIMUM TYPE OF RESPIRATORY PROTECTION REQUIRED
Provide at a minimum the following respiratory protection unless otherwise indicated:
Preparatory, Pre-cleaning, Temporary Containment construction Work: Utilize half-face, negative pressure, and air-purifying respirator with high efficiency filters.
Removal Work: Utilize half-face, negative pressure, and air-purifying respirator with high efficiency filters.
SUPPLIED AIR RESPIRATOR SYSTEMS (TYPE "C")
General: Carefully set up and control supplied air respirator systems to prevent hazards for workers due to difficulty of handling the attached hoses, including on scaffolding and other equipment.
Air Systems Monitor: Monitor the air system operation including compressor operation, filter system operation, backup air capacity and warning and monitoring devices continuously during system operation.
AIR PURIFYING RESPIRATORS
General: Store respirators and filters in the Changing Room. Store respirators in individual, clean plastic bags. Maintain a sufficient quantity of respirator filters for the Work.
Half or Full-Face Negative Pressure Respirators: Require that filters be discarded and that new filters be installed each time a worker exits and re-enters the Work Area.
Powered Air Purifying Respirators (PAPR): Require that filters be discarded and that new filters be installed when flow through the face-piece decreases to the level at which the manufacturer recommends filter replacement. Require that regardless of flow, filters be replaced after forty (40) hours of use. Maintain one spare battery charged or being charged for each PAPR provided.
SECTION VII
DRAWINGS
SECTION VII: DRAWINGS
1. View of Water Damage over carpet at Room
B103 Admissions Office
2. View of Damaged vinyl Sheet Floring at Room
D101
1. View of Wet carpet Flooring at Room D322. 2. View of Damaged Wall Sheetrock at Room E369 Restroom Wall.
1. View of Restroom Air Supply grill at Room
F201.
2. View of Damaged Ceiling Tile at Room D337.
File details come from the government source that posted it. Updated .