ESBD_459157_1760651854735_Addendum NO. 1 Bid NO. 25-43 Dawson Lake Dam Reconstruction .pdf
PDF 170 KB Posted
- Solicitation number
- NO.25-43
- Issued by
- Van Zandt County, Houston City, Texas
About this file
This is an Addendum No. 1 to Bid No. 25-43 for the Dawson Lake Dam Reconstruction Project #24-10-05, issued by the City of Huntsville, Texas for work in Van Zandt County and Houston City. The project encompasses complete dam reconstruction including stormwater structure installation, spillway reconstruction, permanent erosion control measures, removal of existing trees and storm infrastructure, and comprehensive regrading of the dam. A non-mandatory pre-bid conference is scheduled for Tuesday, October 14, 2025, at 10:00 a.m., with sealed bid submissions due on Thursday, October 23, 2025, at 2:00 p.m. Central Time. The contract duration is 180 calendar days from the Notice to Proceed. Project documents are available through the City of Huntsville website, Electronic State Business Daily, CIVCASTUSA, and PublicPurchase, as well as for examination at no charge through the City Engineer's Office and James C. Dulac, P.E.'s office in Dallas. The legal advertisement will be published on October 4, 2025, and October 11, 2025.
The total project budget is estimated at approximately $2,400,000. The addendum represents clarifications or modifications to the original bid documents and should be carefully reviewed by all prospective bidders to ensure compliance with updated requirements. The City of Huntsville reserves the right to adopt the most advantageous bid interpretation or reject any or all submitted bids. Potential bidders should thoroughly review all technical specifications, as the project requires significant civil engineering expertise and capabilities in dam and stormwater management infrastructure. Vendor registration may be required on certain platforms to access project documents.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Page 1 of 3 Bid # 25-43
ADDENDUM #1
Title Bid Number Closing Date Issued Date
Dawson Lake Dam Reconstruction
25-43
October 23, 2025, at 2:00 P.M.
Central Standard Time
October 16, 2025
TO ALL PROSPECTIVE BIDDERS:
The information contained in this Addendum supersedes information contained in the Contract Documents to the extent indicated. All information contained in the Contract Documents remain in full force and effect unless specifically modified herein. All Respondents shall acknowledge the receipt of the Addendum in the space provided on this Addendum Form and submit this form with your bid packet. Failure to do so will result in
Respondent disqualification.
The attention of all prospective Respondents is directed to the following modifications for the above referenced project.
Questions and Answers Question No. 1: What is the duration of the grant as this will affect completion date for construction?
Answer: 24 months from June 2025. Closing documents will be prepared by December 2026 for actual closing June 2027.
Question No. 2: Can you clarify the size of the pad around the riser and the rebar spacing (one sheet shows 8x8 and another sheet shows 10x10; the rebar spacing is not noted)?
Answer: The pad is an 8’x8’ concrete pad that is 8” thick with #4 Rebar at 12” On Center Each
Way. It is only intended to be constructed on one side of the riser, not around it. This is included in the riser pay item.
Question No. 3: Is construction testing to be provided by the City?
Answer: Yes, the City is providing construction testing.
Question No. 4. Is there a place to spoil dirt and onsite?
Answer: Clear area for access and staging within the site is limited to existing open areas outside of the right-of-way and floodplain and within the City’s property. The contractor is required to provide the City with the proposed access and staging plan for review and approval prior to the start of construction. Offsite staging and storage of any equipment and materials, employee parking etc. will require written authorization by the corresponding property owner(s) prior to start of construction. Temporary SWPPP will need to be provided during the construction period of time.
City of Huntsville
448 State Highway 75 N
Huntsville, TX 77320
Lucy Gonzalez, CTCD
Procurement Manager
Telephone: (936) 291-5495
Email: purchasing@huntsvilletx.gov mailto:purchasing@huntsvilletx.gov
Page 2 of 3 Bid # 25-43
Question No. 5. Can woody debris be burned onsite?
Answer: City clarified that this would need to be addressed with the Fire Marshal. For the purpose of bidding this project, no burning of woody construction debris is allowed. If at the time of construction, the burning of woody debris is considered permissible, a change order may be considered by the owner to allow it to be performed and realize any savings it may provide.
Question No. 6. Will there be adequate traffic control and construction signage along Veterans
Memorial?
Answer: Other than a stabilized construction entrance on Veterans Memorial, no temporary or permanent lane closers were considered necessary. If a contractor expects their means and methods to require the temporary or permanent lane closure for deliveries and hauling of materials etc. into or out of the site, the contractor must include all cost associated with traffic control, including but not limited to securing the necessary right-of-way permits, traffic control plans and devices etc., in their bid, subsidiary to the most appropriate bid items accordingly. No additional bid items will be provided for traffic control.
Question No. 7. What is the timing of the contract award and NTP?
Answer: The contract is expected to be awarded in November or the first part of December after
Council approval, with Notice To Proceed immediately following the contract execution.
Construction is expected to begin in January at the latest.
Question No. 8. What is the bid date?
Answer: October 23rd, 2025
Question No. 9. Who will do the construction inspections?
Answer: These will be done by the City staff on requested dates and times from the contractor.
Question No. 10. Will control points be provided?
Answer: This is noted in the plans. A Control Points Table is provided on sheet 7 of 10 in the drawings. The planned addendum will provide labeling of key control points on in the drawing for reference as well.
Question No. 11. Will there be requirements for permits?
Answer: Permits will be obtained from the City to commence construction, but these will not be paid permits.
Question No. 12. Is it possible to do much of the necessary erosion and sediment control on the land downstream of the dam?
Answer: Yes, but the stream will need to be protected and there is a house adjacent to Autumn
Road (east of the channel) which is subject to flooding. In addition, sediment control will likely be carefully monitored by residents downstream of the dam.
Question No. 13. Will there be an addendum to the plan set?
Answer: An addendum is expected to be issued that will provide the geotechnical engineering report and make minor corrections and notations to the drawings.
Page 3 of 3 Bid # 25-43
Please include signed copy of Addendum with submitted Solicitation Packet.
Responder Name: ___________________________________________________________________
Address: ___________________________________________________________________________
Telephone Number: ________________________ ________________________________
Printed Name of Contact
Fax Number: _____________________________
Email Address: ____________________________ ________________________________
Authorized Signature