This document is Addendum No. 3 to the Request for Proposals (RFP) issued by the Texas State University System on behalf of Sam Houston State University for the Belvin Buchanan Hall Renovation project, Project No. 753-25-95900. The scope of work includes the replacement of cast iron piping, a new roof, and interior finish upgrades to the Belvin Buchanan Hall on the Sam Houston State University campus in Huntsville, Texas. The RFP was originally posted on October 10, 2024, and the deadline for submitting proposals has been extended from October 31, 2024 to November 6, 2024 at 2:00 p.m. Central Time. A mandatory pre-proposal conference was held on October 16, 2024, and the deadline for submitting written questions is October 23, 2024 at 12:00 p.m. The Owner plans to select the General Contractor by November 18, 2024, and the contract will be executed on November 20, 2024, with a notice to proceed for material procurement and the start of onsite construction also on November 20, 2024. The project is scheduled for substantial completion by June 30, 2025, and final completion by August 1, 2025.

The contract will be awarded as a lump-sum contract, and the Owner will select the respondent offering the "best value" based on 50% pricing and 50% qualifications. The RFP requires the submission of a Historically Underutilized Business (HUB) Subcontracting Plan. The Owner reserves the right to divide the project, reject any and all proposals, or temporarily or permanently abandon the project. The exact award value is not provided, but the project has an estimated construction budget.

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(i)

(ii)

REQUEST FOR PROPOSALS

FOR

GENERAL CONTRACTOR

FOR

SAM HOUSTON STATE UNIVERSITY

HUNTSVILLE, TEXAS

Belvin Buchanan Hall Renovation

RFP No.:

753-25-95900

Notice To All Respondents:

The following is Addendum No. 3 to the Request for Proposals (RFP)

ESBD Posting No. 753-25-95900 which was posted on October 10, 2024

Prepared By:

Chuck Jones

Director, Facilities Planning and Construction

Sam Houston State University

2424 S. Sam Houston Ave.

Addendum No. 3 Issued October 30, 2024

Date REVISIONS listed below:

2.1 PROJECT PLANNING SCHEDULE: Key Project planning schedule milestones are:

2.4.1 RFP Issued .................................................................................................. 10/10/24

2.4.2 Mandatory Pre-Proposal Conference (2:00 pm) ......................................... 10/16/24

2.4.3 Deadline for submission of written questions (12:00 pm) .......................... 10/23/24

2.4.4 Deadline for submittal of Proposals (2:00 pm) ............................ 10/31/24 11/06/24

2.4.5 Deadline for submittal of HSP (2:00 pm) .................................... 10/31/24 11/06/24

2.4.6 Read Respondents name aloud .................................................... 10/31/24 11/06/24

2.4.7 Read Respondents Pricing Proposal aloud .................................. 11/06/24 11/12/24

2.4.8 Interview shortlisted firms (if required) ....................................... 11/11/24 11/15/24

2.4.9 Owner selects General Contractor ............................................... 11/13/24 11/18/24

2.4.10 Execute General Contractor Agreement ..................................................... 11/20/24

2.4.11 Notice to Proceed with procurement of material ........................................ 11/20/24

2.4.12 Onsite construction to start ........................................................................ 11/20/24

2.4.13 Substantial Completion ............................................................................... 06/30/25

2.4.14 Final Completion ........................................................................................ 08/01/25