ESBD_368984_1721425241097_bwd electric sow.docx

DOCX document 14 KB Posted

Attached to
FY25_bwd_wh_electrical
Solicitation number
FY25_bwd_wh_electrical
Issued by
Brown County, Texas

About this file

This document is a Scope of Work (SOW) for a state and local government contract opportunity in Texas. The SOW outlines the work required to install a new 50 kW diesel generator, an automatic transfer switch, a new electrical panel board, and associated conduit and wiring at a secure correctional facility warehouse. The project includes pouring a concrete pad for the generator, installing a fence around the generator, and connecting the new panel board to various equipment such as a walk-in freezer, cooler, and pallet lift. All work must meet state and local electrical codes.

The contract opportunity is named "FY25_bwd_wh_electrical" and is for a new generator, wiring, and panel box installation at a warehouse facility. The SOW provides detailed specifications and requirements for the electrical work, but does not include any information about pricing, set asides, incumbents, funding sources, or contract terms and renewals.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Brownwood Electrical SOW

1. Install a 50 KW Diesel generator 120-208-volt 3 phase.

2. Install 200-amp ATS, ATS to be mounded next to new panel board in storage area.

3. Pour a concrete pad for generator. Pad must be per spec by manufacture instructions.

4. Run a feeder conduit and copper feeders from generator to ATS.

5. Build a fence per spec around generator with a walk gate, 6’ tall with 3 strands of barbwire at top 45 outward, also allow 4’ clearance around generator.

6. Run a feeder conduit and copper feeders from main panel to a 42-space panel board to be located in the storage area. Approximately 45’ away.

7. Run feeder conduits from new panel for a walk-in freezer, cooler, and pallet lift. Approximately 70’ to pallet lift from new panel.

8. Center lights in storage room will be disconnected from main panel and reconnected into new panel.

9. Please refer to building drawing or visit site for more details.

10. All wiring shall be copper.

11. Install disconnects for LOTO at each piece of equipment.

12. Generator will power new panel only.

13. All work shall meet all state and local codes per the NEC.

File details come from the government source that posted it. Updated .