This document is a contract clause titled "REWORK AND REPAIR OF NONCONFORMING MATERIAL" that defines the requirements for reworking and repairing nonconforming material on a federal contract. The clause outlines the definitions and procedures for rework and repair, including the requirement for the contractor to document and submit rework and repair procedures to the Government Quality Assurance Representative (QAR) or Contracting Officer for review and approval prior to implementation. The clause also requires the contractor to provide a description of the cause of the nonconformance and the action taken to prevent recurrence when submitting a rework or repair procedure. The rework or repair procedure must include a provision for reinspection that takes precedence over the Technical Data Package requirements.
The related federal contract opportunity is for "UWARS Battery Kits" and is a restricted solicitation limited to the following qualified sources: Stratus Systems (Cage: 3AX04) and Mission Systems Davenport (Cage: 99251). The solicitation is being issued by the Department of the Air Force Materiel Command Lifecycle Management Center at Hill Air Force Base.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| FA821324R3024_______0001 amendment 1.pdf | ||
| REPSHIP.docx | DOCX document | |
| PHST_SOW.pdf | ||
| ITEM_DESCRIPTION_5022.pdf | ||
| FA821324R3024.pdf | ||
| ADC_SOW.docx | DOCX document | |
| ITEM_DESCRIPTION_5244.pdf | ||
| CDRL.pdf | ||
| CADPAD_Item_Marking_Instruction.pdf | ||
| AIR_SPEC.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(ES7034)
REWORK AND REPAIR OF NONCONFORMING MATERIAL
Jan 2012 (version)
(a) Rework and Repair are defined as follows:
(1) Rework - The reprocessing of nonconforming material to make it conform completely to the drawings, specifications or contract requirements.
(2) Repair - The reprocessing of nonconforming material in accordance with approved written procedures and operations to reduce, but not completely eliminate, the nonconformance. The purpose of repair is to bring nonconforming material into a usable condition. Repair is distinguished from rework in that the item after repair still does not completely conform to all of the applicable drawings, specifications or contract requirements.
(b) Rework procedures along with the associated inspection procedures shall be documented by the Contractor and submitted to the Government Quality Assurance Representative (QAR) for review prior to implementation. Rework procedures are subject to the QAR's disapproval.
(c) Repair procedures shall be documented by the Contractor and submitted on a Request for
Deviation/Waiver, DD Form 1694, to the Contracting Officer for review and written approval prior to implementation.
(d) Whenever the Contractor submits a repair or rework procedure for Government review, the submission shall also include a description of the cause for the nonconformances and a description of the action taken or to be taken to prevent recurrence.
(e) The rework or repair procedure shall also contain a provision for reinspection which will take precedence over the Technical Data Package requirements and shall, in addition, provide the
Government assurance that the reworked or repaired items have met reprocessing requirements.
(f) Rework and repair is a supply chain flow-down requirement that applies to contractors and their suppliers, vendors or subcontractors.