This document is a federal contract clause (ES7034) establishing requirements for rework and repair of nonconforming material, effective January 2012.

The clause defines rework as reprocessing nonconforming material to achieve complete conformance with drawings, specifications, and contract requirements, while repair involves reprocessing to reduce but not eliminate nonconformance, resulting in usable material that still does not fully meet applicable requirements. Contractors must document rework procedures with associated inspection procedures and submit them to the Government Quality Assurance Representative for review prior to implementation, with procedures subject to disapproval. Repair procedures must be documented and submitted on DD Form 1694 (Request for Deviation/Waiver) to the Contracting Officer for written approval before implementation. All submissions for repair or rework procedures must include a description of the nonconformance cause and preventive actions taken or planned. Rework and repair procedures must include reinspection provisions that supersede Technical Data Package requirements and provide government assurance that items meet reprocessing standards. The clause applies as a supply chain flow-down requirement to contractors and their suppliers, vendors, and subcontractors.

View the file

Other files

File Type Posted
FA821326R3052.pdf PDF
EDL_4860.pdf PDF
ID_016504860.pdf PDF
JFQR_3457.pdf PDF
FA821326R3052.pdf PDF
ItemMarkingInstruction.pdf PDF
Statement_of_Objectives_SOO.pdf PDF
SectionMCADPAD_26May2026.pdf PDF
ID_015213457.pdf PDF
EDL_3457.pdf PDF
ADC_SOW.docx DOCX document
CDRLs.pdf PDF
SOW_Packaging.pdf PDF
SectionLCADPAD_26May2026.pdf PDF
JFQR_4860.pdf PDF
Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(ES7034)

REWORK AND REPAIR OF NONCONFORMING MATERIAL

Jan 2012 (version)

(a) Rework and Repair are defined as follows:

(1) Rework - The reprocessing of nonconforming material to make it conform completely to the drawings, specifications or contract requirements.

(2) Repair - The reprocessing of nonconforming material in accordance with approved written procedures and operations to reduce, but not completely eliminate, the nonconformance. The purpose of repair is to bring nonconforming material into a usable condition. Repair is distinguished from rework in that the item after repair still does not completely conform to all of the applicable drawings, specifications or contract requirements.

(b) Rework procedures along with the associated inspection procedures shall be documented by the Contractor and submitted to the Government Quality Assurance Representative (QAR) for review prior to implementation. Rework procedures are subject to the QAR's disapproval.

(c) Repair procedures shall be documented by the Contractor and submitted on a Request for

Deviation/Waiver, DD Form 1694, to the Contracting Officer for review and written approval prior to implementation.

(d) Whenever the Contractor submits a repair or rework procedure for Government review, the submission shall also include a description of the cause for the nonconformances and a description of the action taken or to be taken to prevent recurrence.

(e) The rework or repair procedure shall also contain a provision for reinspection which will take precedence over the Technical Data Package requirements and shall, in addition, provide the

Government assurance that the reworked or repaired items have met reprocessing requirements.

(f) Rework and repair is a supply chain flow-down requirement that applies to contractors and their suppliers, vendors or subcontractors.

(End of clause)