ES7034.docx
DOCX document 18 KB Posted
- Attached to
- B-1 Handles - FA821326R3006
- Solicitation number
- FA821326R3006
About this file
This is a contract clause attachment defining procedures for rework and repair of nonconforming material applicable to the B-1 Handles solicitation (FA821326R3006) issued by the Department of the Air Force Materiel Command Lifecycle Management Center at Hill Air Force Base. The clause establishes distinctions between rework and repair operations: rework involves reprocessing nonconforming material to achieve complete conformance with drawings, specifications, and contract requirements, while repair involves reprocessing to bring material into usable condition without eliminating all nonconformances.
The clause imposes mandatory procedural and approval requirements on the contractor. Rework procedures and associated inspection procedures must be documented and submitted to the Government Quality Assurance Representative (QAR) for review prior to implementation and are subject to QAR disapproval. Repair procedures require submission on DD Form 1694 (Request for Deviation/Waiver) to the Contracting Officer for written approval before implementation. All submissions for rework or repair procedures must include a description of the root cause of nonconformances and preventive action measures. The rework or repair procedure must include a reinspection provision that supersedes Technical Data Package requirements and provides Government assurance that items meet reprocessing standards. The clause applies as a supply chain flow-down requirement to contractors and all subcontractors, suppliers, and vendors.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SPI_F012077089.pdf | ||
| REPSHIP.pdf | ||
| FA8213-26-R-3006.pdf | ||
| JHCS_1377012077091.pdf | ||
| Item Description 1377012077090.pdf | ||
| AIR SPEC.pdf | ||
| Item Description 1377012077091.pdf | ||
| JFQR B-1 B Type III Hatch Jettison Handle.pdf | ||
| JFQR B-1 B Type II Hatch Jettison Handle.pdf | ||
| Packaging SOW.pdf | ||
| ADC SOW Jan 2018.docx | DOCX document | |
| CDRLs.pdf | ||
| CADPAD Item Marking Instruction Ver 1.6.pdf | ||
| JHCS_1377012077090.pdf | ||
| EDL_1377012077090.pdf | ||
| EDL_1377012077091.pdf |
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment 5
(ES7034)
REWORK AND REPAIR OF NONCONFORMING MATERIAL
Jan 2012 (version)
(a) Rework and Repair are defined as follows:
(1) Rework - The reprocessing of nonconforming material to make it conform completely to the drawings, specifications or contract requirements.
(2) Repair - The reprocessing of nonconforming material in accordance with approved written procedures and operations to reduce, but not completely eliminate, the nonconformance. The purpose of repair is to bring nonconforming material into a usable condition. Repair is distinguished from rework in that the item after repair still does not completely conform to all of the applicable drawings, specifications or contract requirements.
(b) Rework procedures along with the associated inspection procedures shall be documented by the Contractor and submitted to the Government Quality Assurance Representative (QAR) for review prior to implementation. Rework procedures are subject to the QAR's disapproval.
(c) Repair procedures shall be documented by the Contractor and submitted on a Request for Deviation/Waiver, DD Form 1694, to the Contracting Officer for review and written approval prior to implementation.
(d) Whenever the Contractor submits a repair or rework procedure for Government review, the submission shall also include a description of the cause for the nonconformances and a description of the action taken or to be taken to prevent recurrence.
(e) The rework or repair procedure shall also contain a provision for reinspection which will take precedence over the Technical Data Package requirements and shall, in addition, provide the Government assurance that the reworked or repaired items have met reprocessing requirements.
(f) Rework and repair is a supply chain flow-down requirement that applies to contractors and their suppliers, vendors or subcontractors.
(End of clause)