This is a technical specification document for the Maryland Aviation Administration (MAA) Erosion Repairs 2024 project at Baltimore/Washington International Thurgood Marshall Airport. The contract (MAA-CO-25-010) involves erosion repair work across multiple sites, including Site 2 (Dorsey Road), Site 3 (Runway 10 Approach), Site 5 (Elkridge Landing Road), Site 7 (Taxiway B), Site 8 (Gold Lot), and Site 9 (28 Hold Block). The project requires clearing, grubbing, excavation, embankment, soil stabilization, drainage installation and repair, riprap protection, pavement and sidewalk repairs, and fence installation. The contract duration is 125 calendar days, with a pre-bid conference and site inspection scheduled for July 9, 2025, and bid submissions due on August 6, 2025, at 1:00 PM.
The project has a Minority Business Enterprise (MBE) participation goal of 20% with no specific subgoal requirements and a Veteran-Owned Small Business Enterprise (VSBE) participation goal of 3%. The contractor must provide a bid guaranty of 5% of the bid price and will be subject to liquidated damages of $1,500 per day for failure to complete the project within the specified duration. The contract includes provisions for security requirements, temporary construction items, and various technical specifications for erosion control, seeding, and infrastructure repairs. Contractors must comply with Maryland prevailing wage rates and obtain necessary permits, with an estimated project budget implied through the comprehensive technical specifications and requirements.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Erosion_Repairs_2024_Addendum_6_Revised_Bid_Form_.pdf | ||
| Prevailing_Wage_Rates.xlsx | XLSX spreadsheet | |
| Erosion_Repairs_2024_Addendum_4_Revised_Bid_Form.xlsx | XLSX spreadsheet | |
| eMMA_Addendum_No._3.pdf | ||
| Pre-Proposal_RSVP.docx | DOCX document | |
| No_Bid_Notice.docx | DOCX document | |
| Standard_Procurement_State_V2.pdf | ||
| Prevailing_Wage_Rates.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TECHNICAL PROVISIONS
Bid Submission
Volume I of II
PARTS I Thru III
STANDARD PROCUREMENT – STATE
MAA-CO-25-010
Erosion Repairs 2024
June 2025
THIS PAGE HAS BEEN INTENTIONALLY LEFT BLANK
TABLE OF CONTENTS
MAA-CO-25-010
Erosion Repairs 2024
VOLUME I
Part I General Information ...................................................................................................................... GI.1
Part II Technical Specifications ......................................................................................................... TP-00.1
Part III Wage Rates.................................................................................................................................. WR.1 DHR Hiring Agreement ............................................................................................... Not-Applicable
APPENDIX A
MTA Office of Safety Management & Risk Control - Insurance Requirements
APPENDIX B
MTA Railroad Protective Liability Application
VOLUME II
Part IV Bid Forms ..................................................................................................................................... BF.1
PART I
General Information
MAA-CO-25-010 State Funded Technical Provisions
Erosion Repairs 2024 General Information at BWI Thurgood Marshall Airport June 2025
GI.1
PART I
GENERAL INFORMATION
GI-1.01 Contract Summary ......................................................................................................................................... GI.1
GI-1.02 Notice to Contractors .................................................................................................................................... GI.2
GI-1.03 Basis of Contract Award .............................................................................................................................. GI.6
GI-1.04 Description of Project ................................................................................................................................... GI.6
GI-1.05 Special Construction Requirements ............................................................................................................. GI.7
GI-1.06 Solicitation and Contract Formation ........................................................................................................... GI.12
GI-1.07 Commercial Non-Discrimination................................................................................................................ GI.14
GI-1.08 Contract Provisions Apprenticeship Training Fund ................................................................................... GI.14
GI-1.09 List of Contract Drawings ........................................................................................................................... GI.20
GI-1.01 Contract Summary
ITEM DESCRIPTION
Contract Title Erosion Repairs 2024
MAA Contract Number MAA-CO- 25-010
AIP Contract Number N/A
Applicable Standard Provisions https://www.airportal.maa.maryland.gov
MBE Participation Goal
20% Total MBE Participation With Sub-Goals of:
0% African American Owned Firms 0% Hispanic American-owned
0% Asian Owned Firms
Veteran-Owned Participation Goal 3% Veteran-Owned Small Business Enterprise Firms
Contractor Self-Performance Goal 50 %
Contract Classification Class D
Wage Rates Required* YES x NO
Project Location BWI Marshall x Martin State
DHR Hiring Agreement Applicable YES NO x
Contract Drawings and Technical Provisions https://emma.maryland.gov/
Contract Duration 125 Calendar Days
Liquidated Damages See GI-1.05, Part K
Pre-Bid Conference
July 9, 2025 at 11:00 AM Via Microsoft Teams (via Microsoft Teams virtual conference)
Click here to join the meeting / 667-262-2962 Conference
ID: 854727350#
Site Inspection July 9, 2025 at 1:30 PM Terminal
Questions Due Date
Must be submitted in writing via email jreese2@bwiairport.com
July 16, 2025 at 3:00 PM
Bids Due Date/Time https://emma.maryland.gov/
August 6, 2025 at 1:00 PM On eMMA
Bid Opening Date/Time https://emma.maryland.gov/
August 6, 2025 at 1:00PM
(via eMMA)
Wage Rates are required for bids in excess of $500,000
GI.2
GI-1.02 Notice to Contractors
The Standard Provisions for Construction Contracts (Volume I: General Provisions and Volume 2:
Special Provisions) and the Technical Provisions are intended to describe and establish all requirements and standards for this construction Contract and shall be binding upon the parties signatory to the Contract. By submitting a bid for this Contract, the Contractor agrees to adhere to the requirements of all of these Provisions.
Sealed bids for the State of Maryland (State), Maryland Aviation Administration (MAA) project entitled: Erosion Repairs 2024 at Baltimore/Washington International Thurgood Marshall
Airport, Construction Contract No. MAA-CO-25-010 shall be submitted on emma.maryland.gov. We recommend registering in advance to become acquainted with the site. Bids shall only be accepted via the State’s internet-based electronic procurement system, eMaryland Marketplace Advantage (eMMA).
August 6, 2025 at 1:00PM Local Time
Positively no bids will be received after August 6, 2025 at 1:00PM Local Time. Late bids, late requests for modifications, or late requests for withdrawal, will not be considered. MAA is not responsible for bids received late and will not receive any bids that are late.
In accordance with Code of Maryland Regulations (COMAR) 21.05.02.16, to receive a contract award, a vendor/offeror must be registered on eMaryland Marketplace Advantage (eMMA) as a vendor. To register on eMMA, go to the Department of General Services website at https://emma.maryland.gov.
The work under this contract includes, but is not limited to, clearing and grubbing, excavation and embankment, soil stabilization matting, drainage installation and repair, riprap protection, rock outlet protection, pavement repairs, sidewalk repairs, fence installation, underdrain installation, erosion and sediment controls. See paragraph GI-1.04 for additional description.
This project has been advertised via eMaryland Marketplace Advantage (eMMA). Volume I Technical Specifications and Volume II Bid Documents are available for download via eMMA:
https://emma.maryland.gov. All bids must be submitted on the bid documents provided in Volume II.
A Pre-Bid Conference will be held on:
July 9, 2025 at 11:00AM Local Time
(via Microsoft Teams Virtual Conference).
Please use the following link to access the meeting or phone number to dial in:
Join the meeting now 667-262-2962 Phone Conference ID: 854727350#
Please complete the Pre-Bid RSVP for to confirm your intent to attend.
A Site Inspection will be held on July 9, 2025 at 1:30PM Local Time
GI.3
Contractors interested in attending the Site Inspection must e-mail a list of the following information or send the Site Inspection RSVP form to Joe Reese, Jreese2@bwiairport.com no later than July 8, 2025 at 10:00 AM Local Time:
Company Name Attendee’s Full Name (as shown on Driver’s License) Gender Date of Birth Phone Number
OR
Name and MAA SIDA Badge No
Please Note: If the above information is not received by the date and time specified you may not be cleared by the MAA Office of Airport Security to attend. Only attendees with prior approval from
MAA will be allowed to attend the Site Inspection. This scheduled Site Inspection will be the only time to inspect the site. You must bring valid identification, either a driver’s license / passport or
MAA SIDA Badge.
Attendance at the Pre-Bid Conference and the Site Inspection is not mandatory, but all interested bidders are encouraged to attend in order to facilitate better preparation of their bids. Attendance may also increase the bidder’s understanding of, and ability to, meet the Disadvantaged Business Enterprise (DBE) participation goals.
A representative from the Office of Civil Rights and Compliance will be available to discuss the Disadvantaged Business Enterprise program.
Appropriate auxiliary aids and service for qualified individuals with disabilities will be provided upon request. Please call the Office of Procurement at least five business days in advance of the meeting at 410- 859-7081 or via MD Relay by dialing 7-1-1 or 1-800-201-7165 to advise of any reasonable accommodations required.
The Bid, if over $100,000.00, must be accompanied by a Bid Guaranty in the amount of five percent (5%) of the Bid Price in the name of the "State of Maryland”.
The Bid/Proposal Affidavit shall accompany the bid.
Performance and Payment Bonds in the amount of the Contract Price will be required of the successful Bidders.
Assistance in obtaining Bid, Performance and Payment Bonds may be available to qualifying small businesses through the Maryland Small Business Development Financing Authority (MSBDFA). Questions regarding the bonding assistance program should be referred to: MSBDFA, 826 East Baltimore Street, Baltimore MD 21202, (410) 333-4270 (phone) (410) 333-6931 (fax).
GI.4
Minority Business Enterprise (MBE) Requirements
Bidders shall carefully review all instructions related to MBE requirements under GI-1.06. The Certified MBE Utilization and Fair Solicitation Affidavit and the MBE Participation Schedule must also accompany the bid. Be advised that the documents must be completed in their entirety with accurate information If a bidder fails to submit these documents the MAA will deem the bid as non-responsive.
A summary of factors used to determine the expected degree of minority business enterprise participation, for MAA-CO-25-010 construction project, includes (NAICS code: 238190) Vegetative Stabilization, (NAICS code: 237990) Drainage Structures, Erosion and Sediment Controls and Stone Riprap, (NAICS code: 238910) Site Preparation and Site Clearing
Bidders are hereby notified that in regard to any contract entered into pursuant to this advertisement, MBE firms will be afforded full opportunity to submit bids in response to this notice and will not be subjected to discrimination on the basis of race, color, sex, creed, or national origin. MBE firms are encouraged to respond to this solicitation notice.
It is the goal of the Maryland Department of Transportation (MDOT) that MBE firms participate in all contracts, and the Contractor is encouraged to utilize MBE subcontractors when there is opportunity to do so. Based on the total contract dollar amount, the MAA has established a minimum overall goal and subgoals as follows:
Overall MBE Contract Goal Twenty percent 20%
• African American-owned Business Zero percent 0%
• Hispanic American-owned Business Zero percent 0%
• Asian-owned Business Zero percent 0%
Minority Business Enterprise (MBE) firms may elect to be dually certified as Woman-owned Businesses and as members of an ethnic or racial category. For purposes of achieving any gender or ethnic/racial MBE participation sub goals in a particular contract, an MBE firm that has dual certification may participate in the contract either as a Woman-owned Business or as a business owned by a member of a racial or ethnic minority group, but not both.
WARNING – PLEASE READ:
� A firm must be listed in the MDOT MBE/DBE Directory with the gender category in order to be used to meet the gender subgoal.
� A firm must be listed in the MDOT MBE/DBE Directory with an ethnic/racial category in order to be used to meet the ethnic/racial subgoal.
� A firm must be listed in the MDOT MBE/DBE Directory with both the gender and ethnic/racial categories in order for a contractor to have the option of selecting which of those categories it will use for the firm on a State contract.
GI.5
� Contractors should designate whether the MBE firm will be used as a woman-owned business or as a business owned by a member of a racial/ethnic group before calculating the percentage of MBE participation goals and subgoals they intend to meet.
Maryland’s MBE/DBE Directory will reflect the dual certification status. You can access the MBE/DBE Directory at http://mbe.mdot.state.md.us. Firms with dual certification will now be listed as follows:
Example:
ABC Corporation, Inc.
123 Corporate Circle Hanover, MD 21076 Female/African American 00-000
By submitting a response to this solicitation the Bidder agrees that this amount of the contract be performed by one or more MBE firms (including the classifications of MBE specified). A Prime contractor, including an MBE prime contractor, must accomplish the MBE subcontract goals with certified MBE subcontractors. A prime contractor comprising a joint venture that includes MBE/DBE partner(s) must accomplish the MBE subcontract goal with certified MBE/DBE subcontractors.
As an option for meeting the MBE/DBE participation goal set out for this procurement in part or in total, the Maryland Aviation Administration strongly encourages joint venture partnerships between the prime and MBEs/DBEs.
In accordance with COMAR 21.11.03.10(E), all contracts containing Minority Business Enterprise Program Goals must include the Liquidated Damages Provision as found in Special Provisions Section
MBE-4.04.
A Veteran-Owned Small Business Enterprise (VSBE) subcontract participation goal of three percent (3.0%) of the total contract dollar amount has been established for this procurement. By submitting a response to this solicitation, the offeror agrees that this percentage of the total dollar amount of the contract will be performed by verified veteran-owned small business enterprises. VSBEs, must be verified by the Center for Veterans Enterprise of the United States Department of Veterans Affairs. The VSBE list is here: http://www.vetbiz.gov]. Questions or concerns regarding the VSBE requirements of this solicitation must be raised before the opening of bids or receipt of initial proposals.]
By submitting a response to this solicitation, the Bidder agrees to accept payments by electronic funds transfer unless the State Comptroller's Office grants an exemption. The selected Bidder shall register with the EFT Registration, General Accounting Division form using the COT/GAD X10 Vendor Electronic Funds (EFT) Registration Request Form, available at http://compnet.comp.state.md.us/gad/pdf/GADX- 10.pdf. Any request for exemption must be submitted to the State Comptroller's Office for approval at the address specified on the COT/GAD X-10 form and must include the reason for exemption.
GI.6
Questions regarding the Electronic Funds Transfer should be referred to Office of the Comptroller, General Accounting Division, 80 Calvert Street, Room 200, Annapolis, Maryland 21401, (410) 260-7375 or mmcmahon@comp.state.md.us.
By submitting a response to this solicitation, a vendor shall be deemed to represent that it is not in arrears in the payment of any obligation due and owing the State of Maryland, including the payment of taxes and employee benefits, and that it shall not become so in arrears during the term of the contract if selected for the contract award.
The MAA reserves the right to reject any and all bids if in its judgment the interest of the Administration may so require.
If there should be any questions regarding this contract, please contact:
Joe Reese Procurement Officer II Office of Procurement and Materials Management Maryland Aviation Administration Maryland Department of Transportation 410-859-7759
GI-1.03 Basis of Contract Award
The Maryland Aviation Administration will award this Contract to the responsible Bidder with the lowest responsive bid based on the Total Base Bid and any combination of Add or Deduct Alternates included in the Contract Documents, whichever is in the best interest of the State.
The apparent low bidder must provide a Schedule of Values in accordance with SP-2.02, Paragraph D.
GI-1.04 Description of Project
The work under this Contract is comprised of the following items:
A. The furnishing of all supervision, labor, materials (including furnishing, delivery, testing, sampling/certifying, storage, handling, installation), equipment, tools, and associated work necessary for the Erosion Repairs 2024 at BWI Thurgood Marshall Airport. The work includes, but is not limited to, the following: clearing and grubbing, excavation and embankment, soil stabilization matting, drainage installation and repair, riprap protection, rock outlet protection, pavement repairs, sidewalk repairs, fence installation, underdrain installation, erosion and sediment controls. All work is to be completed in accordance with the contract drawings and specifications;
all applicable codes, plans, sketches, and other Contract Documents and any addenda thereto, at locations designated by the Engineer. Portions of the work is in the non-movement are inside of the AOA fence, and a portion of the work is outside of the AOA fence and portions of work are in the movement area inside the AOA fence. One site, Site 5, is located adjacent to the MTA Light
Rail and will require coordination with MTA and will need to meet MTA insurance requirements (See Appendix A and Appendix B).
GI.7
B. The Contractor shall be provided an opportunity at pre-bid meeting to visit each site prior to submitting bid to establish the extent of the work and to familiarize him/herself with any existing conditions which may affect the execution of the contract. It is strongly encouraged the Contractor attend.
GI-1.05 Special Construction Requirements
A. MTA Requirements:
One site, Site 5, is located adjacent to the MTA Light Rail and will require coordination with MTA and will need to meet MTA insurance requirements (See Appendix A and Appendix B).
This effort and costs shall be included in the Mobilization bid item.
A request for a Right of Entry to perform erosion repairs near the BWI Business District Light Rail Station has been made and the contact for this project is:
Jill N. Dunham Real Property Specialist
Maryland Transit Administration Office of Real Estate 401 E. Pratt Street, Suite 1500, Baltimore, MD 21202 Office: 410-856-4314 Fax: 410-333-3289 jdunham@mdot.maryland.gov
Insurance requirements and RRPL application have been incorporated into the specifications and will need to be purchased through MTA’s program. The Contractor shall send the Certificate of Insurance and form, to the above contact to work with MTA Risk Management for coverage approval. ‘MTA RE No. 1372 MAA Erosion Repairs at BWI Business District LR Station’ will need to appear on any checks, COI’s, etc. related to this project.
A copy of the contract/agreement with a contractor, a list of contractor employees (full legal names that reflect their government issued ID) that need to attend the Railroad Worker Protection (RWP) training will need to be provided to the MTA representation. At least one Contractor individual will need On-Site Coordinator (OSC/RWP2) training. If anyone has previously completed the training(s), please send copies of their badges even if they’re expired. If an interpreter is needed, the Contractor shall send one, as interpreters are not provided by the training division. The trainings are a full day. Once MTA has the list, they will provide additional information.
B. Phasing
Phasing sequence for this project will not be dictated. Certain phase relationships are included in the phasing plans that contractor shall become familiar with during bidding. Work area limits are
GI.8
identified on specific contract drawings by location, with an anticipated construction duration.
As required by the Standard Provisions, the Contractor is required to submit a fully detailed schedule for the entire work that shall include all phase milestones, relationships, and tasks required to achieve those milestones. This phasing schedule shall include specific descriptions of each phase, with sequences and sub-phases, anticipated off-work hours and any other information necessary to clearly describe and delineate the intention of work. The Contractor’s proposed construction schedule must be approved per SP-8 before NTP is issued.
C. Time Restrictions
Time restrictions are subject to change as required to accommodate airline, tenant, TSA and airport operations.
All work within Sites 3 that is located inside of Runway 10-28 RSA must be performed at night between the hours of 11:00 pm and 6:00 am. All work within Site 7 that is located inside active TOFA and TSA must be performed at night between the hours of 11:00 pm and 6:00 am. All work within Site 8 that is located inside of Runway 15R-33L RSA must be performed at night between the hours of 11:00pm and 6:00am. The remaining work within these sites outside of these restrictions can be constructed during normal Airport Operations Area time restrictions.
All work within Sites 2, and 9, that are located in the Airport Operations Area is assumed to be completed during weekday daylight hours of 7:00 am to 5:00 pm. Actual work hours are subject to the Contractors discretion. The work schedule must be approved by the Construction Manager to accommodate the needs of the stakeholders listed above.
All work within Sites 5, that are not located in the Airport Operations Area is assumed to be completed during weekday daylight hours of 7:00 am to 5:00 pm. Actual work hours are subject to the Contractors discretion. The work schedule must be approved by the Construction Manager to accommodate the needs of the stakeholders listed above.
D. Deliveries/Haul Route
The contractor shall have access to the site as shown on the drawings. The entire project site, including haul routes, shall be kept free and clean of debris at all times and shall be maintained in good repair by the Contractor. All damages to the project site caused by the actions of the Contractor or its agents shall be immediately repaired to the satisfaction of the Engineer.
E. Site Restrictions
Contractor’s access to the work site may be restricted by airport operations.
Work Under Escort: Due to current TSA restrictions, the Contractors shall comply with the security requirements in the Contract Documents and specifically in the Technical Specifications.
GI.9
F. Access to the Site
All persons entering upon airport property must have the proper identification and vehicle registration specified in applicable articles of the Standard Provisions for Construction Projects.
Routing within the Airfield Operations Areas (AOA) shall be subject to proper approval by the Engineer.
Airport Security, BWI Airport Access Badges, Airfield Vehicle Ramp Permits and Temporary Airfield Vehicle Registration: Comply with the security requirements in the Contract Documents and specifically in the Technical Specifications.
The Contractor’s employees shall be required to park personal vehicles in the designated parking lot. Personal vehicles of employees and vehicles operated by vendors of goods or services will not be permitted beyond the Contractor’s designated parking area.
G. Staging Area
The Contractor will be given authorization to utilize an area or areas that will be available for the duration of this project as staging and mobilization areas. Staging area to be used shall be as shown on contract documents. Contractor will be required to relocate trailer staging and mobilization areas as directed by the Engineer.
During the course of the work the Contractor shall maintain his staging and work areas in a clean and usable condition.
The MAA reserves the right to discontinue use of these staging areas at any time during the work.
H. Load & Height Restrictions
The Contractor shall comply with all legal load restrictions imposed by the State Department of Transportation, MAA, or other authorities having jurisdiction, in the hauling of materials on public roadways and bridges beyond the limits of the work.
Special permits will not relieve the Contractor of its liability for damages resulting in the moving of materials, spoil, or equipment.
I. Permits, Licensing, and Crane Height Restrictions
The Contractor is required to meet all requirements of AC 150/5370-2 “Operations Safety on Airports during Construction,” current edition, and FAR Part 77 “Objects affecting Navigable Airspace,” current edition. The Contractor is required to obtain all permits and licenses required for the project work at his own expense.
J. Contract Duration
The duration for this contract shall be for a period of 125 calendar days from the date determined after completion of the approved construction schedule in conformance with the
GI.10
Standard Provisions. Contractor shall note that each phase and sub-phase, as shown in the construction documents, has its own corresponding duration. The Contractor shall be responsible for completing the work within the stated durations. Should the Contractor request a winter shut-down, those days will not count against contract duration.
K. Liquidated Damages
Failure by the Contractor to complete work on the Project within the time specified will impact airport operations and increase construction inspection costs. Therefore, the Contractor and his surety will be liable for liquidated damages as follows:
Pursuant to General Provisions Articles GP-8.02 and GP-8.03, commence Work on or Before the date specified in the Notice to Proceed and complete the specified portions of the work within the contract durations specified above. In the event the Contractor fails to complete the specified Work within the specified number of days after the Notice to Proceed (either for the total Contract duration or any of the phase milestone duration, with the exception of extensions granted by Change Orders), liquidated damages (not as a penalty) will be assessed pursuant to General Provisions Article GP-8.09 and as specified herein for each calendar day the completion of the specified work is delayed.
1. For failure to substantially complete the Project within the defined Duration, the Contractor and his Surety will be liable for liquidated damages in the amount of $1,500 per day/part of day for each calendar day beyond allotted overall duration.
2. For reopening of runway, $1,000 per quarter-hour/part of quarter-hour beyond scheduled openings.
L. Project Coordination
Contractor shall not mobilize until necessary shop drawings, cut sheets, etc. are approved or as directed / approved by the engineer.
Coordinate scheduling, submittals, and Work of the various Sections of the Technical Specifications to assure timely and orderly sequence of installation of interdependent construction elements.
Where scale of Contract Drawings is too large to show details clearly prepare small scale coordination drawings and submit to the Engineer for approval.
Coordinate completion and cleanup of the work of separate Sections in preparation of the Final Acceptance Review Inspection.
The Contractor shall cooperate and coordinate its work with all tenants, other contractors, and utilities companies as necessary.
GI.11
Other construction contracts may be underway during the life of this project. These other projects may occur adjacent to and, at times, within the Contract limit of work for this project. These projects include but are not limited to:
1. Taxiway T Reconstruction Phases 2 & 3
2. DX-DY Apron Construction
M. Shop Drawings
The Contractor shall submit complete shop drawing packages for each item of work as required in the applicable Technical Specification Sections. Delays caused by incomplete submittals by the Contractor will not be accepted and the Contractor will be required to recover lost time at no expense to the MAA.
N. Designated Subcontractors
A portion of the work under this contract may involve modifications to or extensions of existing systems that are maintained by designated contractors under contract to the MAA. The bidder is required to solicit a bid from and, if awarded the contract, to contract with these firms as Subcontractors to the Contract for work involving these systems. Work to be performed by these Subcontractors is indicated in the Specifications and on the Drawings. Systems work to be performed by designated Subcontractors includes any and all of the following systems work affected by the work of this Contract:
1. Building Automation System (BAS): Johnson Controls, Inc. (JCI) Contract Person: Erick Badders Telephone: 410-527-2607
2. Paging System: Washington Professional Sound (WPS) Contact Person: Dave Leister Telephone: 301-370-4746
3. Integrated Access Security Systems (IASS): M. C. Dean Contact Person: Charlie Gibson Telephone: 410-599-3700 Email: Charlie.gibson@mcdean.com
4. Video Surveillance System: Tyco Integrated Security (Tyco) Contact Person: Neal Mitchell Telephone: 703-898-1365
5. Fire Alarm System: Honeywell Contact Person: John Collins Telephone: 410-682-8213
GI.12
6. Visual Paging System Monitors: Comnet Software Contact Person: Steve Rohrig Telephone: 937-859-6323
O. No Substitution Procurement
Not Applicable.
P. Personal Protective Equipment (PPE)
In order to promote workplace safety, to mitigate and minimize risk to employees who may be exposed to various hazards related to their work responsibilities, the Employer shall provide personal protective equipment to employees in the performance of their job duties and train on the use of PPE.
The Contractor must ensure that the Contractor’s Personnel make full use of such equipment as the circumstances demand. This includes but is not limited to safety helmets, eye protection, faces shields, safety shoes, gloves, mask, etc. Where it is a site/facility rule that such items of equipment must be worn, the owner has the right to request removal from the Premises of any Personnel not complying with this rule. For the purposes of this section, personal protective equipment shall mean equipment required under applicable federal and state laws, rules, and/or regulations (including Occupational Safety and Health Administration regulations) or required by Employer policy.
GI-1.06 Solicitation and Contract Formation
A. A Bidder must include with its Bid:
1. A completed Certified Minority Business Enterprise (MBE) Utilization and Fair Solicitation Affidavit (Section 3) whereby the Bidder or offeror:
a. Acknowledges the certified MBE participation goal, commits to make a good faith effort to achieve the goal, and affirms that MBE subcontractors were treated fairly in the solicitation process.
b. A completed MBE Participation Schedule (Section 3) whereby the Bidder or offeror responds to the expected degree of MBE participation as stated in the solicitation, by identifying the specific commitment of certified MBE at the time of submission.
2. If a Bidder or offeror fails to submit Section 3 as required, the Procurement Officer shall deem the bid non-responsive. This includes failure to complete the forms or failure to provide accurate information on the forms.
GI.13
B. Within 10 working days from notification that it is the apparent awardee or from the date of the actual award, whichever is earlier, the apparent awardee must provide the following documentation to the Procurement Officer:
1. Outreach Efforts Compliance Statement (Section 3).
2. Subcontractor Project Participation Statement (Section 3).
3. In the rare event that the apparent awardee believes a waiver (in whole or in part) is necessary of the overall MBE goal or of any subgoal by MBE classification, it must submit a fully documented waiver request that complies with COMAR 21.11.03.11.
4. If a waiver is requested, MDOT MBE/DBE Form E – Good Faith Efforts Guidance and Documentation Part 1 – Part 5 must be submitted.
C. Any other documentation required by the Procurement Officer to ascertain Bidder or offeror responsibility in connection with the certified MBE Participation goal. If the apparent awardee fails to return each completed document within the required time, the Procurement Officer may determine that the apparent awardee is not responsible and therefore not eligible for Contract award.
If the Contract has already been awarded, the award is voidable.
D. Liquidated Damages. This contract requires the contractor to make good faith efforts to comply with the Minority Business Enterprise (“MBE”) Program and contract provisions. The State and the Contractor acknowledge and agree that the State will incur damages, including but not limited to loss of goodwill, detrimental impact on economic development, and diversion of internal staff resources, if the Contractor does not make good faith efforts to comply with the requirements of the MBE Program and MBE contract provisions. The parties further acknowledge and agree that the damages the State might reasonably be anticipated to accrue as a result of such lack of compliance are difficult to ascertain with precision.
Therefore, upon a determination by the State that the Contractor failed to make good faith efforts to comply with one or more of the specified MBE Program requirements or contract provisions, the Contractor agrees to pay liquidated damages to the State at the rates set forth below. The Contractor expressly agrees that the State may withhold payment on any invoices as a set-off against liquidated damages owed. The Contractor further agrees that for each specified violation, the agreed upon liquidated damages are reasonably proximate to the loss the State is anticipated to incur as a result of such violation.
a. Failure to submit each monthly payment report in full compliance with COMAR 21.11.03.13B (3): $23.00 per day until the monthly report is submitted as required.
b. Failure to include in its agreements with MBE subcontractors a provision requiring submission of payment reports in full compliance with COMAR 21.11.03.13B (4): $82.00 per MBE subcontractor.
c. Failure to comply with COMAR 21.11.03.12 in terminating, canceling, or changing the scope of work/value of a contract with an MBE subcontractor and/or amendment of the MBE
GI.14
participation schedule: the difference between the dollar value of the MBE participation commitment on the MBE participation schedule for that specific MBE firm and the dollar value of the work performed by that MBE firm for the contract.
d. Failure to meet the Contractor’s total MBE participation goal and subgoal commitments: the difference between the dollar value of the total MBE participation commitment on the MBE participation schedule and the MBE participation actually achieved.
Notwithstanding the use of liquidated damages, the State reserves the right to terminate the contract and exercise all other rights and remedies provided in the contract or by law.
GI-1.07 Commercial Non-Discrimination
As a condition of entering into this Agreement, Contractor represents and warrants that it will comply with the State’s Commercial Nondiscrimination Policy, as described under Title 19 of the State Finance and Procurement Article of the Annotated Code of Maryland. As part of such compliance, Contractor may not discriminate on the basis of race, color, religion, ancestry or national origin, sex, age, marital status, sexual orientation, or on the basis of disability or other unlawful forms of discrimination in the solicitation, selection, hiring, or commercial treatment of subcontractors, vendors, suppliers, or commercial customers, nor shall Contractor retaliate against any person for reporting instances of such discrimination. Contractor shall provide equal opportunity for subcontractors, vendors, and suppliers to participate in all of its public sector and private sector subcontracting and supply opportunities, provided that this clause does not prohibit or limit lawful efforts to remedy the effects of marketplace discrimination that have occurred or are occurring in the marketplace. Contractor understands that a material violation of this clause shall be considered a material breach of this Agreement and may result in termination of this Agreement, disqualification of Contractor from participating in State contracts, or other sanctions. This clause is not enforceable by or for the benefit of, and creates no obligation to, any third party.
As a condition of entering into this Agreement, upon the Maryland Human Relations Commission’s request, and only after the filing of a complaint against Contractor under Title 19 of the State Finance and Procurement Article, as amended from time to time, Contractor agrees to provide within 60 days after the request a complete list of the names of all subcontractors, vendors, and suppliers that Contractor has used in the past 4 years on any of its contracts that were undertaken within the state of Maryland, including the total dollar amount paid by Contractor on each subcontract or supply contract. Contractor further agrees to cooperate in any investigation conducted by the State pursuant to the State’s Commercial Nondiscrimination Policy as set forth under Title 19 of the State Finance and Procurement Article of the Annotated Code of Maryland, and to provide any documents relevant to any investigation that is requested by the State. Contractor understands that violation of this clause is a material breach of this Agreement and may result in contract termination, disqualification by the State from participating in State contracts, and other sanctions.
GI-1.08 Contract Provisions Apprenticeship Training Fund
Effective October 1, 2009, State Law requires all contractors and subcontractors working on State prevailing wage projects with prevailing wage determinations to register (Apprenticeship Training Fund
GI.15
Site) with the Division of Labor and Industry Prevailing Wage Unit prior to the commencement of work and to make certain contributions toward improving and expanding apprenticeship programs in the State.
In addition, registered apprenticeship programs and organizations that have registered apprenticeship programs that have been selected by contractors and subcontractors for contributions also are required to register with the Division of Labor and Industry Prevailing Wage Unit.
The following information concerning the requirements of the apprenticeship training fund program is being provided for informational purposes only. It is the contractor’s responsibility to contact the Maryland Department of Labor, Licensing and Regulation (DLLR), prior to commencement of any work, to determine how these provisions are being implemented and enforced by DLLR.
Definitions. The following terms have the meanings indicated.
A. Terms Defined.
1. “Approved apprenticeship program” means an apprenticeship program or an organization with an apprenticeship program which has been registered with, and approved by, the Maryland Apprenticeship and Training Council or the United States Department of Labor.
2.“Commissioner” means the Commissioner of Labor and Industry.
3. “Covered craft” means a classification of workers listed in the prevailing wage determination applicable to a prevailing wage project.
4.“Fund” means the State Apprenticeship Training Fund.
5. “Monthly Certified Verification Report” means the monthly report that details contractor and subcontractor contributions for that month available on the Division of Labor and Industry’s website.
6. “Public body” means a unit of State government as defined in § 17-201(l), State Finance and
Procurement Article, Annotated Code of Maryland.
7. “Unit” means the Division of Labor and Industry, Prevailing Wage Unit and the public body that awarded the procurement contract.
8. “Yearly Certified Verification Report” means the yearly report that details contractor and subcontractor contributions for the preceding year available on the Division of Labor and Industry’s website.
Contractor/Subcontractor Registration. Contractors and subcontractors awarded a procurement contract on a public work contract subject to the Maryland Prevailing Wage Law shall register on the Division of Labor and Industry’s website at www.dllr.state.md.us/labor prior to the commencement of work.
GI.16
Contractor/Subcontractor Project Management. Upon registration under Contractor/Subcontractor Registration of this Chapter, contractors and subcontractors are required to provide information to the Division of Labor and Industry on its website at www.dllr.state.md.us/labor about each public work contract including the following:
A. The prevailing wage project number for each prevailing wage project the contractor or subcontractor is performing work on; and
B. The contract value for each prevailing wage project the contractor or subcontractor is performing work on.
Contractor/Subcontractor Notification to Subcontractors. Contractors and subcontractors who hire subcontractors on a public work contract subject to the Maryland Prevailing Wage Law shall provide all subcontractors with written notice of the following requirements:
A. Subcontractors are required to register on the Division of Labor and Industry’s website at www.dllr.state.md.us/labor prior to the commencement of work;
B. After registration, subcontractors are required to enter certain information about each prevailing wage project on the Division of Labor and Industry’s website; and
C. Subcontractors performing work on a prevailing wage project valued at $100,000 or more are required to make payments to approved apprenticeship programs or to the Fund for workers in classifications listed on the prevailing wage determination, or both.
Contractors and subcontractors shall retain a copy of the written notice required in §A of this Regulation that was provided to all subcontractors for inspection and review by the Commissioner for three years.
Contributions to the Fund.
A. A contractor or a subcontractor that makes contributions to the Fund shall do so in the amount of 25 cents per hour for each employee in each covered craft on the prevailing wage project on a monthly basis.
B. A contractor or a subcontractor that makes contributions to the Fund, who is performing work under a prevailing wage determination for a covered craft that includes a fringe benefit contribution that exceeds 25 cents, shall pay to the employee in wages the amount the fringe benefit contribution exceeds 25 cents.
Contributions to Approved Apprenticeship Programs. If a contractor or a subcontractor makes contributions to an approved apprenticeship program in an amount less than 25 cents per hour for each employee in each covered craft on the prevailing wage project, the contractor or subcontractor shall make payments to the Fund in the amount of the difference between 25 cents and its contribution on a monthly basis.
GI.17
Contractor/Subcontractor Obligations Relating to Approved Apprenticeship Program.
A. Contractors and subcontractors are required to complete and to file on the Division of Labor and Industry’s website at www.dllr.state.md.us/labor the Monthly Certified Verification Report which shall include the following:
1. A list of the contributions to each approved apprenticeship program during the last month;
2. A statement signed by the contractor or subcontractor that the information is correct and that the contractor or subcontractor has complied with the requirements of Subtitle 6, Title 17, State Finance and Procurement Article, Annotated Code of Maryland.
B. Contractors and subcontractors are required to submit the Monthly Certified Verification Report by the 30th calendar day of each month for the previous month.
C. Contractors and subcontractors are required to complete and to file on the Division of Labor and Industry’s website at www.dllr.state.md.us/labor the Yearly Certified Verification Report which shall include the following:
1. A summary of monthly contributions with total annual contributions; and
2. A statement signed by the contractor or subcontractor that the information is correct and that the contractor or subcontractor has complied with the requirements of Subtitle 6, Title 17, State Finance and Procurement Article, Annotated Code of Maryland.
D. Contractors and subcontractors shall post a copy of their Yearly Certified Verification Report in a prominent and easily accessible place in the workplace near where work is performed.
Notification to Division of Labor of Changes to Designated Approved Apprenticeship Programs or Fund. Contractors and subcontractors shall provide the Commissioner with written notice of each approved apprenticeship program or the Fund to which it will make contributions. If a contractor or subcontractor changes their designation, it shall notify the Division of Labor and Industry 30 days prior to the change in designation.
Approved Apprenticeship Program Obligations. Upon notification from the Division of Labor and Industry that the approved apprenticeship program has been designated for contributions by a contractor or subcontractor, the approved apprenticeship program shall register on the Division of Labor and Industry’s website at www.dllr.state.md.us/labor.
After registering under §A of this Regulation, an approved apprenticeship program will receive a summary of contractor and subcontractor contributions from the Division of Labor and Industry on a monthly basis and shall comply with the following:
A. Review and certify that the contribution amounts are correct;
GI.18
B. Certify that all funds received are used solely for the purpose of improving or expanding apprenticeship training in the State; and
C. File a response within 30 days of receipt of the Division of Labor and Industry’s summary.
Enforcement Procedures.
A. The Commissioner may investigate whether Subtitle 6 of Title 17 of the State Finance and
Procurement Article, Annotated Code of Maryland, has been violated:
1. On the Commissioner’s own initiative;
2. On receipt of a written complaint; or
3. On referral from another State agency.
B. The Commissioner may require a contractor, subcontractor, or an approved apprenticeship program to produce records as part of its investigation.
C. The Commissioner may enter a place of business to:
1. Interview individuals; or
2. Review and copy records.
D. If after an investigation, the Commissioner determines that there is a violation of Subtitle 6, Title 17 or a regulation adopted to carry out the title, the Commissioner shall issue a citation that shall:
1. Describe in detail the nature of the alleged violation;
2. Cite the provision of law or regulation that is alleged to have been violated; and
3. State the penalty, if any.
E. Within a reasonable amount of time after the issuance of the citation, the Commissioner shall send a copy of the citation to the alleged violator by certified mail with notice of the opportunity to request a hearing.
F. Within 15 days after the alleged violator receives the citation, the employer may submit a written request for a hearing on the citation and proposed penalty.
G. If a hearing is not requested within fifteen days, the citation, including any penalties, shall become a final order of the Commissioner.
GI.19
H. If there is a request for a hearing, the Commissioner may delegate the hearing to the Office of Administrative Hearings in accordance with Title 10, Subtitle 2 of the State Government Article, Annotated Code of Maryland.
I. A proposed decision of an administrative law judge shall become a final order of the Commissioner unless, within 15 days of the issuance of the proposed decision:
1. The Commissioner orders review of the proposed decision; and
2. The alleged violator submits to the Commissioner a written request for review of the proposed decision.
J. After review of the proposed decision under Subsection I, with or without a hearing on the record, the Commissioner shall issue an order that affirms, modifies or vacates the proposed decision.
GI.20
GI-1.09 List of Contract Drawings
SHEET
NUMBER
DRAWING
NUMBER
SHEET TITLE
1 G.001 COVER SHEET
2 G.002 INDEX OF DRAWINGS
3 G.003 LEGEND, ABBREVIATIONS, AND SUMMARY OF QUANTITIES
4 G.004 GENERAL CONSTRUCTION AND SAFETY NOTES 1 - SIDA
5 G.005 GENERAL CONSTRUCTION AND SAFETY NOTES 2 - SIDA
6 G.006 GENERAL PROJECT LAYOUT
7 G.007 SURVEY CONTROL PLAN
8 G.008 BORING LOCATION PLAN
9 G.009 SECURITY BID PLAN
10 G.010 CONSTRUCTION PHASING PLAN - SITE 2 - DORSEY ROAD AT HAWKINS DRIVE
11 G.011 CONSTRUCTION PHASING PLAN - SITE 3 - EMBANKMENT FAILURE AT THE RUNWAY 10 APPROACH
12 G.012 CONSTRUCTION PHASING PLAN - SITE 5 - ELKRIDGE LANDING ROAD SITE
13 G.013 CONSTRUCTION PHASING PLAN - SITE 7 - TAXIWAY B SITE
14 G.014 CONSTRUCTION PHASING PLAN - SITE 8 - GOLD LOT SITE
15 G.015 CONSTRUCTION PHASING PLAN - SITE 9 - 28 HOLD BLOCK SITE
16 G.016 CONSTRUCTION SAFETY AND PHASING DETAILS
17 G.017 MAXIMUM EQUIPMENT HEIGHT PLAN
18 C.001 EXISTING CONDITIONS PLAN - SITE 2 - DORSEY ROAD AT HAWKINS DRIVE
19 C.002 REPAIR PLAN - SITE 2 - DORSEY ROAD AT HAWKINS DRIVE
20 C.003 EROSION AND SEDIMENT CONTROL PLANS - SITE 2 - DORSEY ROAD AT HAWKINS DRIVE
21 C.004 EROSION AND SEDIMENT CONTROL PLANS - SITE 2 DA MAP 1- DORSEY ROAD AT HAWKINS DRIVE
22 C.005 EROSION AND SEDIMENT CONTROL PLANS - SITE 2 DA MAP 2- DORSEY ROAD AT HAWKINS DRIVE
23 C.006 SITE 2 - CROSS SECTIONS - DORSEY ROAD AT HAWKINS DRIVE
24 C.007 STORM DRAIN PIPE PROFILES - SITE 2 - DORSEY ROAD AT HAWKINS DRIVE
25 C.008 EXISTING CONDITIONS PLAN - SITE 3 - EMBANKMENT FAILURE AT THE RUNWAY 10 APPROACH
26 C.009 REPAIR PLAN - SITE 3 - EMBANKMENT FAILURE AT THE RUNWAY 10 APPROACH
27 C.010 EROSION AND SEDIMENT CONTROL PLANS - SITE 3 - EMBANKMENT FAILURE AT THE RUNWAY 10 APPROACH
28 C.011 SITE 3 - CROSS SECTIONS - EMBANKMENT FAILURE AT THE RUNWAY 10 APPROACH
29 C.012 EXISTING CONDITIONS PLAN - SITE 5 - ELKRIDGE LANDING ROAD SITE
30 C.013 REPAIR PLAN - SITE 5 - ELKRIDGE LANDING ROAD SITE
31 C.014 EROSION AND SEDIMENT CONTROL PLANS - SITE 5 - ELKRIDGE LANDING ROAD SITE
32 C.015 SITE 5 - CROSS SECTIONS 1 - ELKRIDGE LANDING ROAD SITE
33 C.016 SITE 5 - CROSS SECTIONS 2 - ELKRIDGE LANDING ROAD SITE
34 C.017 SITE 5 - CROSS SECTIONS 3 - ELKRIDGE LANDING ROAD SITE
35 C.018 STORM DRAIN PIPE PROFILES - SITE 5 - ELKRIDGE LANDING ROAD SITE
36 C.019 EXISTING CONDITIONS PLAN - SITE 7 - TAXIWAY B SITE
37 C.020 REPAIR PLAN - SITE 7 - TAXIWAY B SITE
38 C.021 EROSION AND SEDIMENT CONTROL PLANS - SITE 7 - TAXIWAY B SITE
39 C.022 SITE 7 - CROSS SECTIONS - TAXIWAY B SITE
40 C.023 STORM DRAIN PIPE PROFILES - SITE 7 - TAXIWAY B SITE
41 C.024 EXISTING CONDITIONS PLAN - SITE 8 - 1 - GOLD LOT SITE
42 C.025 EXISTING CONDITIONS PLAN - SITE 8 - 2 - GOLD LOT SITE
43 C.026 REPAIR PLAN - SITE 8 - 1 - GOLD LOT SITE
44 C.027 REPAIR PLAN - SITE 8 - 2 - GOLD LOT SITE
45 C.028 EROSION AND SEDIMENT…