Amendment No. 1.pdf

PDF 19 KB Posted

Attached to
Architect-Engineer Services for the USEPA in Regions 6 through 10 Federal contract opportunity
Solicitation number
EPA-CPOD-022
Issued by
Environmental Protection Agency Cincinatti Procurement Operations Division

About this file

Amendment No. 1 to Announcement EPA-CPOD-022 Architect-Engineer Services for the USEPA in Regions 6 through 10 March 17 2011

View the file

Other files for this federal contract opportunity

Other files attached to Architect-Engineer Services for the USEPA in Regions 6 through 10, newest first.
File Type Posted
Justification_for_Exception_3_23_16.docx DOCX document
Amendment No. 2.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Amendment No. 1 to Announcement EPA-CPOD-022 Architect-Engineer Services for the USEPA in Regions 6 through 10

March 17, 2011

Q1. Would past experience projects that went though the LEED design process, but not finally certified (due to owner budget cut), qualify as eligible LEED project examples?

A1. LEED certified projects would receive more favorable consideration, but any LEED experience can be documented and would receive consideration.

Q2. If a prime contractor is an architectural firm, not an engineering firm, would that be considered as unqualified in your search? Please assume the sub-consulting team engineers would meet all the other requirements and certifications desired in the sources sought by the

EPA.

A2. There is no ban on submittals by architectural firms.

Q3. Do all of our consultants/subcontractors need to be certified small businesses in order for us to qualify, or does only the Prime firm need to fulfill this requirement?

A3. Only the prime is required to be a small business concern.

Q4. One of my subs submitted me multiple Part II’s (one for each branch office that is supporting the contract). Will it be acceptable to submit each branch office or should I request on Part 2 for the entire company.

A4. A separate Part II may be submitted for each branch office which is expected to be used during contract performance.