Text version

Q: What are considered 50% drawings?

A: See Request For Quote paragraph C. 2. (e)

Q: Can we have the names of the utility provider at both sites?

A: Xcel Energy is the electric utility provider at both sites. One year of utility invoices are included with the amendment.

Q: Can you elaborate on the timeline to start the project---the rfp is stating the work shall begin within 10 calendar days of the award? What is required to “begin work”?

A: We would expect a design/build contractor to begin with a 100% design effort.

Denver Location Q: Has there already been a structural analysis/feasibility study done for the Denver location? If so, may we have a copy of the report that was generated from the study.

A: No.

Q: If a structural analysis/feasibility study hasn’t been done, what is the alternative location in the event the building is deemed unable to support the 40kW roof system?

A: There is no current alternate location.

Q: Concerning the roof at the Denver location:

a. What is the roof material made from?

i. If metal—what is the gauge of the metal

b. What is the purlin/framing spacing for the roof?

c. What are the building dimensions?

i. Width (E-W orientation)

ii. Length (N-S orientation)

iii. Mean roof height

iv. Parapet Height

v. Pitch of the roof

d. Roof protection system

i. Are there specifications for what is to be used?

1. Material

2. Thickness

ii. How long is the expected life span of the protection system required to be?

A: There is no longer a warranty on the existing roof. See Request For Quote documents for roof structural information. For protection system, this is a design/build contract. Material specs should be included in your proposal. UFC 3-110-03, 01 May 2012, Change 2, 1 Jan 2017, UNIFIED FACILITIES CRITERIA (UFC), ROOFING is included with amendment documents for your information.

Ground Mounting Questions Q: Has there been a geotechnical study done, in reference to piers being driven into the ground at this location other than what was included in the initial rfp documents? If so, may we have access to them.

A: No.

Q: Geotextile Fabric

e. Are there preferred specifications for the material to be used?

Q: Is there a minimum ground clearance requirement?

Q: Can the government please confirm the utility provider for each site. (We believe Xcel Energy – please confirm)?

A: Xcel Energy is the electric utility provider at both sites. Copies of utility invoices are included with the amendment.

Q: Has the utility provider been notified of this project?

A: No.

Q: Has a request for a net meter been completed and sent in?

A: No.

Q: Has the power utility provided any information on potential equipment requirements for approval of net metering?

A: No.

Q: (Assuming Xcel Energy is the provider) – Xcel has a $1,000 “study fee” requirement for net metering. Has this study been paid for/completed. If not, please confirm this is the contractor’s responsibility (with costs included in our bid).

A: See Request For Quote paragraph C. 3. b) and e).

Q: Please confirm the age of the building at the Denver Site.

A: The storage building was constructed circa 1984.

Q: Please confirm the age of the roof at the Denver Site.

A: The storage building roof was installed during new construction. A partial roofing inspection report is included with the amendment. There is no longer a warranty on the existing roof.

Q: What is the requested snow load and wind speed requirement for each site.

A: This is a design/build contract. Design criteria are the responsibility of the designer. See Request For Quote paragraph C. 3. i) (4). Design criteria should be included in required calculations.

Q: This project presents a great opportunity to replace the roof at the Denver Site (and will also help reduce the weight load and need for structural upgrades). Will the government entertain proposals that include a roof replacement? Will the additional cost be weighed in a “best value” evaluation, rather than “lowest cost”?

A: Yes, roof replacement proposals will be considered. There is no longer a warranty on the existing roof. UFC 3-110-03, 01 May 2012, Change 2, 1 Jan 2017, UNIFIED FACILITIES CRITERIA (UFC), ROOFING is included with amendment documents for your information.

Q: The current administration is reviewing the implementation of a new solar tariff in January.

There is a potential that this could impact our costs/pricing. When does the government anticipate contract award/notice to proceed?

A: Within 90 days of award.

Q: Can we tie into the existing perimeter security fence, or does a new fence need to be built around the entire ground mount array? If we cannot tie into the existing fence, please provide an acceptable separation/distance that must be maintained between the security fence and array fence.

A: The existing fence may be used as one side of the enclosure. No structural or physical changes may be made to the existing fence.

Q: Do the installations have a requirement for hydro-excavation at both sites?

A: No.

Q: At both sites, there appears to be little space in the electrical rooms for additional equipment.

Would the government entertain proposals to mount equipment on the exterior wall and secure it with fencing at both sites?

A: This is a design/build contract. Include equipment locations in proposals.

Q: As these locations are both on Federal property, please confirm we will NOT be required to pull any permits with the city.

A: No city permits are required.

Q: At the site visit (and a review from an engineer), the roof at the Denver site appears to be maxed out for weight loads for the existing structure. Will we be required to retrofit the existing trusses or building to accept the additional weight of the new PV system? If this is the contractor’s responsibility, please specify what structural/roof submittals will be required with the proposal.

A: If the proposal includes structural reinforcement of the roof, full structural plans and details describing the work are required. Roof submittal should include, at a minimum, roofing system materials, details and warranty information.

Q: Will the government accept emailed (electronic) proposals?

A: Yes.

Q: Can the solar panels at 2320 Ursula St. be located on the roof of an existing building rather than on the ground?

A: No.

Q: Is it possible to locate the solar panels at 2320 Ursula St. in a location other than the area originally identified?

A: Yes, it is possible. The location provided is preferred.

A: Can the solar panels at 12211 E 56th Ave be located on the building south of the originally identified building?

A: No.

Q: Is it possible to locate the solar panels at 12211 E 56th Ave on the ground or in another location?

A: No.

Q: Is there any structural study done before on the roof? If yes, please provide us the data(load calculation) for the same.

A: Original structural calculations for building construction are not available.

Q: For the ground mount array: is there anytime geo-tech survey has been done before? If yes, please provide us the report for the same.

A: Some geotechnical information was included in the information documents with the Request For Quote. No other information is available.

Q: I have asked about the battery location at the roof top system when I was on the site. Since you told me that they can arrange some space over there, please advice if that has changed and penned down to some particular location.

A: Battery storage is not required. See Request For Quote paragraph C. 1. b) (1).

Q: Please advice whether we can mount the sub-combiner panel right outside the meter at the next building besides the rooftop site.

A: This is a design/build contract. Include equipment locations in proposals.

Q: Is there any limitations on the location of where we can enter the building/s with the electrical connection at either site?

A: This is a design/build contract. Include equipment locations in proposals.

Q: Do you have the engineering for the roof at Joe P Martinez Site from the roof installation or original structural design you could share?

A: Original structural calculations for building construction are not available. Structural drawings for original construction were included in the Request For Quote.

Q: Do you have as built electrical drawings for the Joe P Martinez Site that show the electrical panels in the building in which the installation will be?

A: A site electrical plan and full power plans from original construction were included in the Request For Quote. A GIS plan showing known utilities is included with the amendment. Any further required information should have been collected during the bidder walk through.

Q: Can we use the fence on the north side of the Army Reserve Center PV location as part of the fencing for the solar array?

A: The existing fence may be used as one side of the enclosure. No structural or physical changes may be made to the existing fence.

Q: Can you provide the electrical drawings for the Army Reserve Center showing transformer, meter location and electrical gear?

A: A site electrical plan and full power plans from original construction were included in the Request For Quote. A GIS plan showing known utilities is included with the amendment. Any further required information should have been collected during the bidder walk through.

Q: Is there an in-state preference?

A: Question lacks the necessary clarification required for an answer.

Q: Will the utility bills for both properties be provided to allow for submittal of an application in Xcel's Solar Rewards Program?

A: One year of utility invoices are included with the amendment.

Q: Are there any special security requirements to work onsite outside of providing employee?

A: Refer to CONTRACTOR'S RESPONSIBILITY - Personnel access and identity verification.

Q: Are there any specification/standards for the construction of the facility that exceed national standard IBC and NEC codes?

A: See Request For Quote paragraph C. 3.

Q: What is the process for Permitting the project and who is the Permitting authority for the site?

A: See Request For Quote paragraph C. 3. No city permits are required.

Q: Could we do an overhead line option for running electrical to the buildings at the ground mount site?

A: An overhead line is not preferred.

File details come from the government source that posted it.