About this file

This Emergency Purchase Final Cost document reports the completion of an emergency procurement declared under reference B-51437 by the State of Illinois Chief Procurement Office for General Services, in coordination with the Central Management Services agency. The emergency contract, awarded to F.E. Moran, Inc. Fire Protection, involved fire pump replacement services for a facility located at 300 W. Jefferson in Springfield, Illinois. Martha Blackwell, Facilities Portfolio Manager, authorized and signed the final cost report on July 7, 2026, certifying completion of the emergency services procured under the authority of 30 ILCS 500/20-30(b).

The final total cost for the emergency purchase of supplies and services was $74,999.33. This document serves as official public notice of the final cost and represents the actual expenditure for the emergency declared contract, with the cost being reported to both the Chief Procurement Office and the Auditor General as required by Illinois law. The vendor, F.E. Moran, Inc. Fire Protection, is located at 818 N Main Street in Morton, Illinois 61550.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

EMERGENCY PURCHASE FINAL COST

Page 1 of 1State of Illinois Chief Procurement Office for General Services Emergency Purchase Final Cost v.26.1

Pursuant to 30 ILCS 500/20-30(b), the actual final cost shall be published.

Zip: 61550State:IlCity:MortonAddress: 818 N Main St

Vendor: F.E. Moran, Inc. Fire Protection

Zip: 62702State: ILCity:SpringfieldAddress: 300 W. Jefferson

Division: Bureau of Strategic SourcingAgency: Central Management Services

Final Cost Original BidBuy Reference #: B- B-51437

Final Cost BidBuy Reference # B- 53153

Final total cost ($) of supplies and services: $74,999.33

Printed Name: Martha Blackwell

Title: Facilities Portfolio Manager

Agency Representative Signature:

Date: 07/07/2026

I am reporting the final cost for the referenced emergency contract to the CPO and the Auditor General.

Page of

EMERGENCY PURCHASE FINAL COST

State of Illinois Chief Procurement Office for General Services Emergency Purchase Final Cost and Term v.25.1

EMERGENCY PURCHASE FINAL COST

Page of State of Illinois Chief Procurement Office for General Services Emergency Purchase Final Cost v.26.1 Pursuant to 30 ILCS 500/20-30(b), the actual final cost shall be published.

Final Cost I am reporting the final cost for the referenced emergency contract to the CPO and the Auditor General.

11.0.0.20130303.1.892433.887364

PageCount:
CurrentPage:
VendorZip: 61550
VendorState: Il
VendorCity: Morton
VendorAddress: 818 N Main St
Vendor: F.E. Moran, Inc. Fire Protection
AgencyZip: 62702
AgencyState: IL
AgencyCity: Springfield
AgencyAddress: 300 W. Jefferson
AgencyDivision: Bureau of Strategic Sourcing
AgencyUniversity: Central Management Services
CurrentMasterPage:
MasterPageCount:
ReferenceNumber: B-51437
TextField1: 53153
FinalTotalCost: $74,999.33
PrintedName: Martha Blackwell
TitleField: Facilities Portfolio Manager
AuthorizedSignature:
Date: 07/07/2026