This request for proposal outlines requirements for an emergency chiller redundancy project at the Miami VA Medical Center. The project requires furnishing and installing three new outdoor chillers, two to serve air handling units 1 and 2 and a third to serve units 1 and 7. The chillers must be approved for outdoor use with NEMA 3R enclosures and high saltwater/rust protection. Bidders must provide design and construction services including preparing schematic drawings, specifications, conducting site surveys, inspections and testing to ensure all work meets applicable codes and VA standards. The project has a 120-day design phase and 145-day construction phase, with work to be scheduled to minimize disruption to hospital operations. Submissions are due within specified timeframes and must adhere to formatting and technical requirements detailed in the RFP.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DESIGN-BUILD
Emergency Chiller Redundancy for AHU-1, AHU-2 and AHU-7 Serving all Operating Rooms Project No. 546-23-128
I. DEFINITIONS AND ACRONYMS:
A. Air handling Unit (AHU):
B. Design-Build (DB): as defined by the Department of Veterans Affairs (DVA) is the procurement by the Government, under one contract, with one firm (which may be a joint venture) for both design and construction services on a specific project.
C. Contracting Officer (CO): The services to be performed under this contract are subject to the general supervision, direction, control and approval of the Contracting Officer.
D. Chiller Motor Control Center (CMCC3): Located in existing Mechanical Room MEA-43 roof at 3rd floor roof level on Building 1.
E. Project Manager (PM)/Contracting Officers Representative (COR): The Contracting Officer's representative responsible for administering contracts under the immediate direction of the Contracting Officer.
F. Design Build Contract: This term, as used herein, refers to the Contract(s) to perform the design and construction of the project.
G. Contractor: This term, as used herein, refers to the contractor under this contract.
H. A/E: This term, as used herein, refers to the ArchitectEngineer firm(s) that are a part of the DB team, also referred to as DB A/E.
I. Design-Build Team A/E: This term, as used herein, to refer to the entire Design-Build Team (Contractor, A/E and any sub-contractors) all inclusive.
J. Pre-Construction Risk Assessment (PRCA): Used to identify potential risks associated with the renovation, construction and some maintenance & repair activities and to develop risk mitigation strategies to minimize these risks. Prior to beginning work this assessment will be completed.
K. Interim Life Safety Measures (ILSM): Measures that are instituted to compensate for significant hazards posed by existing life safety (fire) code deficiencies or construction/renovation activities.
L. Certified Independent Third-Party Safety Professional (CITP): Certified Independent Third-Party Safety Professional for the review of the design documents for compliance with national and local codes, standards, federal and state regulations.
M. National Fire Protection Association (NFPA): The world's leading advocate of fire prevention and an authoritative source on public safety, NFPA develops, publishes, and disseminates codes and standards intended to minimize the possibility and effects of fire and other risks.
N. National Electrical Manufacturer’s Association (NEMA): Develops ratings and standards to ensure enclosures with the right level of protection.
O. The Joint Commission (TJC): The Joint Commission provides evaluation, accreditation and disease-specific certification programs for healthcare facilities.
P. Veterans Affairs Medical Center (VAMC): Specifically, the Bruce W. Carter Department of Veterans Affairs Medical Center.
Q. Competent Person (CP): One who is capable of identifying existing and predictable hazards in the surroundings or working conditions which are unsanitary, hazardous, or dangerous to employees, and who has authorization to take prompt corrective measures to eliminate them.
II. SCOPE OF WORK:
General Requirements:
Provide all labor, materials, tools and equipment, and design-build services necessary for the design and construction of the project described herein and other specific tasks as further defined by this Request for Proposal (RFP). All proposals are to provide both design and construction services for this project. Contractor shall not match existing materials but shall use hospital grade materials as designated in the Department of Veterans Affairs (DVA) technical information library (TIL) and/or industry standards for healthcare facilities relevant to space usage. Reference section VII, Resources, below.
Introduction:
Project requires three (3) back u chillers for the existing Chiller 4 and Chiller 5 supplying chilled water to all existing OR Rooms, located on the existing roof at the 3rd floor of the Miami VA Medical Center, building 1. The condition of the existing Chillers 4 and 5 are critical right now. There is no redundancy and if the MVAMC lose any of the exiting chiller, the hospital will lose all the Operating Rooms. Losing any of these existing Chillers will automatically force to shutdown Patient Care Services, preventing the Main Hospital form performing OR procedures.
Project Overview:
Contractor shall be required to furnish three (3) new Chillers Outdoor type. Two (2) for AHU-1 and AHU-2 and another Chiller for AHU-1 and AHU-7. Since most of the Chillers are manufactured by Trane, the MVAC Operations preference is to continue with TRANE Manufacturer with a 5 Year warranty on the compressor OR approved equal. Chillers shall be approved for Outdoor type NEMA 3R enclosure with high saltwater/rustproof protection.
Existing Substation SUBBN-3AC shall feed the two new chillers using two 300 A/3P amp breaker for the 250 Ton chiller and one 200 A/3P circuit breaker for the other 200 Ton chiller. A new cubicle will be added to the existing Substation SUBN-3AC for these breakers. Provide two (2) ea. 300A/3P and one (1) ea. 150A/3P breakers, also provide 3-60A/3P for the additional pumps.
All breakers shall be rated at 65,000 AIC as required for this project. All Chillers Pumps disconnects shall be stainless-steel on outdoor connections. Include structural steel support base of each Chiller.
Chiller 4A, Chiller A and 5B shall be connected form only one source of power by tge existing Substation SUBN-3 AC
The new Chillers location will be located next to the existing Chiller 5 extending the existing structural support platform if structural calculations support it. See attached Riser Sketch E-AC-1AR.
Chiller 4A set point temperature shall be 38-degree Fahrenheit and chiller 5A (Air cooled) setpoint temperature shall be 41-degree Fahrenheit.
Specific Project Requirements:
Startup and Testing
1. Contractor shall perform an equipment startup in accordance with the manufacturer’s specifications.
2. Contractor shall perform testing of all operational controls and safety devices to ensure proper operation.
3. Contractor shall preform testing of the equipment’s remote capabilities.
4. Contractor shall provide VAMC personnel with documentation of all testing.
Training.
1. Contractor shall provide training to VAMC personnel in the proper Startup, Operation and Shutdown of the equipment to include manufacturers recommendations.
2. Contractor shall provide training on the maintenance requirements and performance.
Additional Contractor requirements
1. The contractor shall be responsible for all installation of Chillers (mechanical, electrical, structural and controls) located on roof next to Mechanical Room MEA-43. This includes all operational testing required by VA Directive and any other applicable codes and VA regulations.
Emergency Response
1. The contractor’s technician shall arrive on site within two (2) hours when notified by the COR of an emergency. This will apply 24 hours a day, 7 days a week including holidays.
2. Contractor shall be responsible to maintain the work area in a neat and orderly condition.
3. Contactor shall provide a dumpster for disposal of old materials and any debris generated during the work.
4. Contractor shall ensure the work area is broom clean at the end of each shift.
5. Only VAMC personnel are authorized to turn On or Off any electrical circuits or to Open or Shut any valves.
Inspection/Acceptance
1. The Contractor shall only tender for acceptance those items that conform to the requirements of this contract. The Government reserves the right to inspect or test any supplies or services that have been tendered for acceptance. The Government may require repair or replacement of nonconforming supplies or reperformance of nonconforming services at no increase in contract price. If repair/replacement or reperformance will not correct the defects or is not possible, the Government may seek an equitable price reduction or adequate consideration for acceptance of nonconforming supplies or services.
The Government must exercise its post-acceptance rights within a reasonable time after the defect was discovered or should have been discovered; and before any substantial change occurs in the condition of the item, unless the change is due to the defect in the item.
2. The DB contractor will be given written information (As Build and Existing Drawings); participate in project planning meetings, pre-bid meeting, and pre-construction meeting as required; communicate with VA personnel via telephone or email.
3. The entire work must be Tested and Certified by Mechanical Professional Engineer (PE) Chillers License Repair and meets National Fire Protection Association (NFPA), Environmental Protection Agency (EPA), American National Standards Institute (ANSI), Occupational Safety and Health Administration (OSHA), National Plumbing Code, National Electric Code, American Society of Heating, Refrigerating and Air-Conditioning Engineers (ASHRAE), National Safety Code, VA Specifications, VA Construction Standards, VA Repair Handbooks and VA Fire Protection Manual available in the Technical information Library (https://www.cfm.va.gov/TIL).
4. The detailed project shall begin with an intense on-site physical survey and collection of previous project data.
5. All installation or demolition shall be documented on the As Build Drawings and comply with all applicable requirements of, NFPA, ANSI OSHA, National Electric Code (NEC), National Safety Code (NSC), VA Specifications, VA Demolition Standards, VA Repair Handbooks, etc. and all applicable Local, State, and Federal Regulations and Standards.
Existing AS Build Drawings will be made available to the DB/Contractor; however, their accuracy shall be field verified by the DB/Contractor and all consulting firms as part of investigative services.
6. The DB/Contractor shall be required to perform all necessary site survey work such as verifying record drawings.
Investigative Work
The following investigative work shall be included within the scope of this project:
1. Provide all Engineer investigative work for application to this project including but not limited to electrical and mechanical testing, vibration studies, structural analysis and any other test or study required to complete this project. Verify existing conditions to ensure the accuracy of the Replacement/Installation.
2. Field verify VA furnished drawings to ensure DB/Contractor As Build Drawings are accurate. It is the DB/Contractor’s responsibility to determine existing conditions and to base the construction on this information.
3. Materials to be furnished to the DB/Contractor by the VA
3.1. The following shall be Furnished to the DB /Contractor upon request:
a. VA Engineering Service will provide the DB/Contractor with all available As Build and Existing Drawings. The following documents will be provided to the Contractors in a link format as part of the supporting documents (Site Plan, Miami VA Asbestos & Lead Survey; Electrical Plans, VA Construction Policy, Mechanical Drawings, One Line, and As Build Drawings).
Note: The accuracy of any paper copy or Drawings is not guaranteed and shall be used only for general information. Actual conditions must be field verified by the DB/Contractor and all consulting firms.
b. All VA standards, specifications, Space Planning Criteria, Equipment & Design Guides List and Design Submission Guidelines can be obtained by accessing the World Wide Web at the following address:
http://www.cfm.va.gov/TIL/
3.2. The following laws, regulations, policies, and procedures in effect on date of contract issuance and all subsequent changes or updates apply:
| FAR |
| Federal Acquisition Regulation |
| VAAR |
| Veterans Administration Acquisition Regulation |
| SCA DOL Website |
| Service Contract Act (SCA) Directory of Occupations (Fifth Edition) http://www.dol.gov/whd/contracts/sca.htm |
| VA Technical Information Library |
| http://www.cfm.va.gov/TIL/ |
| Federal, State, Local, Industry |
| Performance in accordance with any and all legal standards, codes, policies, permits, procedures and or otherwise governing legal doctrine. |
III. SCHEDULING, PHASING, AND WORKING HOURS:
A. All work hours MUST be coordinated with the project’s COR. All work shall be performed during WHEN hours (Weekends, Holidays, Evenings and Nights) so as not to interfere with normal hospital functions. However, some VA areas may be conducive to work being completed DURING normal business hours (7:00 am to 4:00 pm), Monday through Friday). All requests for work during normal business hours shall be requested by the Contractor at least 14 calendar days in advance. Additionally, construction shall be performed (scheduled and phased) to ensure that exterior egress/ingress areas are completely operational by normal business hours the following workday.
B. Length of Project
1. Project will have a 120-calendar day design phase. Please refer to Program Guide PG-18-15, Volume C for document requirements.
a) From Notice to Proceed, Design-Build Team A/E shall submit Schematic Design drawings to 25% within 30 calendar days. Allow 15 calendar days for VA review.
b) Design-Build Team A/E shall submit Construction Document drawings to 75%, which incorporates the VA’s comments on the 75% submission within 60 calendar days. Allow 15 calendar days for VA review.
c) Design-Build Team A/E shall submit Final Document drawings to 100% (Signed & Sealed), which incorporates the VA’s comments on the 75% submission within 30 calendar days. Allow 15 calendar days for VA review.
2. Design-Build Team A/E shall schedule a Pre-Construction Meeting with all pertinent VA personnel for final drawing approval before construction start. Submission shall be within 15 calendar days of receiving Government acceptance of 100% drawings.
3. Project will have 145 calendar days construction. Project is completed after 2 new backup Chillers for AHU-1, AHU-2 and AHU-7 are fully installed, tested, certified and up and running in accordance with VA Standards.
4. Contractor shall submit a Critical Path Method (CPM) schedule for BOTH Design phase and Construction phase with estimated dates and itemized cost of work to the Contracting Officer for review and approval before Notice to Proceed.
C. Utility Outages, including disruption of fire alarms, must be requested by the Contractor at least 15 calendar days in advance.
IV. PROJECT CLASSIFICATION:
This project has been classified per the Construction Infection Control Risk Assessment as a Type C, Low Risk, Class II and Type C Medium /High Risk Group, Class III Project.
V. SAFETY REQUIREMENTS:
All Contractor's personal are required to have completed an OSHA-approved 10-hour construction worker course prior to working on the site. The On-site general superintendent/supervisor is required to have completed an OSHA-approved 30-hour construction course prior to working on the site. Every worker must provide the Contracting Officer a copy of current certificates identifying successful completion of the training prior to executing work for the Veterans Administration. In addition, Contractor shall provide submittals for contract construction or renovation work which include the names, qualifications, and training dates for Contractor’s Competent Persons (CP), who has been designated to administer the site-specific safety program, as well as the CP for other activities as required by OSHA regulation 29 CFR 1926.32 (such as scaffolds, cranes, excavations, etc.). Contractor’s CP are required to implement and maintain effective safety programs that identify and control hazards that may cause injury or illness to VA patients, staff, visitors, and contractor employees.
The VA CP does not take the place of Contractor’s CP nor acts on their behalf. The VA CP determines if Contractor is meeting VA standards and contractual requirements for safety and OSHA compliance. When these standards and contract requirements are not being met, the VA COR and/or CP will take immediate action to prevent injury, non-compliance, and/or property damage.
The Contractor shall submit an Activity Hazard Analysis, and an Accident Prevention Plan as per FAR 52.236-13 prior to commencement of site activities. The Government shall have 21 calendar days to review the AHA and APP.
VI. GOVERNMENT FURNISHED INFORMATION:
All available record drawings will be provided upon request to the Design-Build Team A/E. They should not however, be considered “as-built”. These drawing files are provided without warranty or obligation as to the accuracy or information contained in the files. All information in the files shall be independently verified by the user. Any user shall agree to indemnify and hold the VA harmless from any and all claims, damages, losses, and expenses, including, but not limited to, attorney fees arising out of the use of the Computer Aided Design and Drafting (CADD) drawing files.
A. Records Management
1.Citation to pertinent laws, codes and regulations such as 44 U.S.C chapters 21,29,31 and 33;
Freedom of Information Act (5 U.S.C); Privacy Act (5 u.sc. 552a); 36 CFR Part 122 and Part 1228.
2. Contractor shall treat all deliverables under the contract as the property of the US Government for which the Government Agency shall have unlimited rights to use, dispose of or disclose such data contain therein as it is determined to be in the public interest.
3. Contractor shall not create or maintain any records that are not specifically tied to or authorized by the contract using Government IT equipment and/or Government records.
4. Contractor shall not retain, use, sell, or disseminate copies of any deliverable that contains information covered by the Privacy Act of 1974 or that which is generally protected by the Freedom of Information Act (FOIA).
5. Contractor shall not create or maintain any records containing any Government Agency records that are not specifically tied to or authorized by the contract.
6. The VA owns the rights to all data/records produced as part of this contract.
7. The VA owns the rights to all electronic information (electronic data, electronic information systems, electronic databases, etc.) and all supporting documentation created as part of this contract. Contractor must deliver sufficient technical documentation with all data deliverables to permit the agency to use the data.
8. Contractor shall comply with Federal and Agency records management policies, including those policies associated with the safeguarding of records covered by the Privacy Act of 1974. These policies include the preservation of all records created or received regardless of format [paper, electronic, etc.] or mode of transmission [e-mail, fax, etc.] or state of completion [draft, final, etc.].
9. No disposition of documents shall be allowed without the prior written consent of the CO. The Agency and its contractors are responsible for preventing the alienation or unauthorized destruction of records, including all forms of mutilation. Willful and unlawful destruction , damage or alienation of Federal records is subject to the fines and penalties imposed by 18 U.S.C. 2701. Records may not be removed from legal custody of the Agency or destroyed without regards to the provisions of the agency records schedules.
VII. RESOURCES:
All designs shall comply with applicable sections of VA standards and publications, and all references therein. Ensure that construction documents comply with the latest edition of these VA construction and design standards.
VA standards can be found on the World Wide Web at http://www.cfm.va.gov/TIL/. VA publications and standards shall include but shall not be limited to the following:
1. Office of Construction & Facilities Management Site Map:
http://www.cfm.va.gov/sitemap.asp
2. The Technical Information Library (TIL): http://www.cfm.va.gov/TIL/
a) Master Construction Specifications Index (PG-18-1)
b) Design and Construction Procedures (PG-18-3)
c) VA Standard Details and CAD Standards (PG-18-4)
d) Equipment Guide List (PG-18-5)
e) Equipment Inspection Manual (Program Guide 7610.2)
f) Equipment Reference Manual (PG-18-6)
g) Space Planning Criteria (PG-18-9)
h) Design Manuals (by discipline) (PG-18-10)
i) Design Guides (graphical, by function) (PG-18-12)
j) Barrier Free Design Guide (PG-18-13)
k) Room Finishes, Door and Hardware Schedules (PG-18-14)
l) Minimum Requirements for A/E Submissions (PG-18-15)
m) Environmental Planning Guidance (PG-18-17)
n) HVAC Design Manual for Hospitals Amendment B
o) Lighting Study
p) Design Alerts
q) Quality Alerts
r) VA Signage Design Guide
s) Fire Protection Design Manual – Latest Edition
t) Cost Estimating
u) Physical Security Design Manuals for VA Facilities – Mission Critical Facilities (VA Handbook 0730)
v) Information Security Handbook VA 6500
w) Energy Reduction Manual (First Draft)
3. TIL - Master Construction Specifications:
http://www.cfm.va.gov/til/spec.asp
4. Department of Veterans Affair Utilities Design Manual.
B. Office of Construction & Facilities Management: http://www.cfm.va.gov/index.asp
1. VA Office of Facilities Management citations of the AIA design standards found on the world wide web at http://cfm.va.gov.TIL/
2. VA Office of Health and Safety (OHS): http://www1.va.gov/vasafety/
3. Construction Infection Control Risk Assessment Memorandum
C. Other design and construction standards and publications that shall be applied to this work includes, but are not limited to:
1. American Society of Heating, Refrigerating and Air-Conditioning Engineers Manual (ASHRAE)
2. National Fire Protection Association (NFPA) Codes & Standards - www.nfpa.org
3. OSHA Rules and Regulations/
4. International Building Code (ICC) latest edition.
5. Life Safety Code (NFPA 101) latest edition
6. The Joint Commission (TJC) Accreditation manual (latest edition)
7. Sustainable Design Requirements (01 81 11)
8. Construction Waste Management (01 74 19)
D. Applicable sections of the VA Master Construction Specifications shall be prepared by the Architect/Engineer, including all the necessary adaptations.
E. Particular attention is called to CD4, Symbol Identification of Contract Drawings.
F. Equipment symbols shall be in accordance with PG-18-6, Equipment Reference Manual (previously List of Equipment Symbols, H-08-6).
G. Standard Drawing Details, in accordance with PG-18-4, shall be utilized to the greatest extent practicable.
H. Cost estimates shall be developed in strict conformance with VA’s Manual for Preparation of Cost Estimates & Related Documents for VA Facilities (March 8, 2011). http://www.cfm.va.gov/til/dManual/dmCost.pdf
I. Guidelines for Design and Construction of Health Care Facilities, Latest Edition, published by The Facilities Guidelines Institute (FGI). http://www.fgiguidelines.org/
J. Physical Security Standard, compliance with Medical Center Policy 138-3 and VHA Handbook 0730/2 dated May 27, 2010 “Space Key Control”.
K. Plumbing System Design & Water Treatment/Design to prevent Legionnaires. VA Plumbing Design Manual and VHA Directive 2008-010, PREVENTION OF LEGIONEELA DISEASE, and VHA Directive 2009-009, DOMESTIC HOT WATER TEMPERATURE LIMITS FOR LEGIONELLA PREVENTION AND SCALD CONTROL.
VIII. DESIGN and DOCUMENT REQUIREMENTS:
A. Design Requirements - Compliance with codes and standards.
1. Project design shall be in compliance with applicable standards and codes described in VA Program Guides and design materials included or referenced in the solicitation materials. See “Resources” above.
2. See “Approved Construction documents”, below, for required inclusion of design review comments.
3. In the design of new building and alteration work under this contract, the Design-Build Team A/E shall consider all requirements (other than procedural requirements) of:
a) Zoning laws:
b) Environmental and erosion control regulations; and
c) Laws relating to landscaping, open space, minimum distance of a building from the property line, maximum height of a building, historic preservation, and esthetic qualities of a building. Also, similar laws, of the State and local political division, which would apply to the building if it, were not to be constructed or altered by the U.S. Government. The Design-Build Team A/E shall consult with appropriate officials of the Federal, state, and political subdivision, and submit plans under the rules prescribed by those reviewing authorities. The Design-Build Team A/E and VA shall give due consideration to the recommendations of the referenced building officials. VA will also permit inspection by the officials described above during the construction period in accordance with the customary schedule of inspections in the locality of the building construction.
Such officials shall provide VA with a copy of the schedule before construction begins or give reasonable notice of their intention to inspect before conducting an inspection.
4. The Design-Build Team A/E shall provide prompt, written notification to the Contracting Officer concerning conflicts with, or recommended deviations from codes, laws, regulations, standards, and opinions of review officials as described above. No work altering OR increasing the scope of this contract shall be undertaken prior to receipt of written approval from the Contracting Officer.
5. No action may be brought against the VA and no fine or penalty may be imposed for failure to carry out any of the previously described recommendations of Federal, state, or local officials. VA and its contractors, including A/E, shall not be required to pay any amount for any action taken by a state or political division of a state in carrying out functions described in this article, including reviewing plans, carrying out on-site inspections, issuing permits, and making recommendations.
6. The Design-Build Team A/E shall advise the Contracting Officer of any variances with the applicable Department of Labor, Occupational Safety and Health Standards, for occupancy requirements.
B. Design Review Meetings:
1. A review meeting to resolve design issues will be held for each design review package submitted. The meeting will include discussion of VA comments on functional relationships and technical peer review comments (by others).
2. Participants will include VA Staff and Design-Build Team A/E members as appropriate for the specific package to be reviewed and others. The Design-Build Team A/E members will each allow for (1) full day for each package design review meeting. Design-Build Team A/E management shall be present at each review meeting.
3. The DB team shall allow a minimum of fifteen (15) calendar days for each review cycle. A cycle includes:
| a. | The VA’s receipt of the design review submission package. |
| b. | The review meeting. |
| c. | DB teams’ receipt of comments from the VA, either electronically, by fax, or by hard copy delivery. |
4. Coordination of the review meeting schedules will be the responsibility of the VA Project Manager/COR (for the VA) and the Design-Build Team A/E Project Manager (for the Design-Build Team A/E). See Quality Assurance/Quality Control.
C. Design Review Submissions:
1. The Design-Build Team A/E shall prepare and submit complete construction documents for review and approval by the VA in accordance with standard professional practice and prevailing codes.
2. The documents may be divided into multiple review submission packages. The VA will review as many as six (6) package submissions (examples: demolition, civil, architectural, structural, mechanical, Electrical, plumbing etc.) to facilitate the start of construction.
3. All submission packages will be reviewed at Schematic Design (25%), Design Development (75%), Construction Documents (75%) and Final Documents (100%) completion stages. The (100%) review submission packages will incorporate the final review comments from the (75%) review. If any package is not complete for the required stage a post review may be required, the cost of which will be borne by the DB Team. The (100%) set of drawings will be the final set of drawings that will be used for construction and stamped by engineer and architect of record.
4. Each review submission package shall include 3 hard copy sets (2 Full Size & 1 Half Size) and 1 PDF sets on CD-ROM. The package will include an index of drawings (by sheet number and title) and specifications (by section number and title) submitted. The packages will be distributed to the VA Project’s COR, the VA Contracting Officer (CO) and others as determined to be appropriate by the VA.
5. Upon Contractor review of the TIL Specifications and Design Guidelines associated with the Project Scope of Work, the Design-Build Team A/E shall be responsible to prepare and submit for Government review and acceptance a full set of specifications (2 hard copies, 2 electronic), specific to the project, from the Master Specifications located in the TIL.
The Specifications shall be contractor modified to include VA Guidelines and Code requirements consistent with NFPA, IBC, FBC, FGI Guidelines for Design and Construction of Health Care Facilities, 2010 edition.
6. In addition to the Project Specific Specifications, the Contractor shall submit a binder of product cut sheets, MSDSs, and all required Contract submittals.
7. Contractor shall be responsible to submit as-build CAD drawings at the end of the project reflecting the new floor layout changes to the VA Engineering office as part of the close out documents.
D. Electronic Media:
1. Design review submission drawings and final Construction Document submission drawings will be executed in electronic format AutoCAD version 2018 or backwards compatible format. Revit 2019 or backwards compatible format drawings of data infrastructure must also be provided.
2. The drawings included will be available to the Design-Build Team A/E team in electronic format in AutoCAD version 2018 or PDF format for use in preparing the construction drawings if possible.
Since data stored on electronic media can deteriorate undetected or be modified without the Architect/Engineer’s knowledge, the CAD drawing files are provided without warranty or obligation on the part of the Architect/Engineer as to accuracy or information contained in the files. The user shall independently verify all information in the files. Any user shall agree to indemnify and hold the Architect Engineer harmless from any and all claims, damages, losses, and expenses including, but not limited to, attorney’s fee arising out of the use of the CAD drawing files.
3. Design review submission specifications, final Construction Document submission specifications and other 8 1/2 by 11 formatted material will be executed in electronic format Microsoft Word.
4. The specifications included shall be available to the Design-Build Team A/E in electronic format in Microsoft Word, for use in preparing the construction specifications.
Since data stored on electronic media can deteriorate undetected or be modified without the Architect/Engineer’s knowledge, the CAD version 2013 drawing files are provided without warranty or obligation on the part of the Architect/Engineer as to accuracy or information contained in the files. The design builder shall independently verify all information in the files and shall agree to indemnify and hold the Architect Engineer harmless from any and all claims, damages, losses, and expenses including, but not limited to, attorney’s fee arising out of the use of the electronic files.
5. The construction record drawings shall be completed in at least AutoCAD version 2018 and backward compatible format. Designer/contractor will submit an AUTOCAD copy (as build drawings) after the completion of the project and before closeout to the VA for engineering records and update tracking purposes.
6. Construction shop drawings are not required to be completed in AutoCAD.
E. Professional Licensing:
1. The Design-Build Team A/E who prepares the construction documents shall be a professional architect or engineer licensed in the State of Florida.
2. The professional seal indicating such license by the state shall appear on the final construction documents.
The architect whose seal is shown will be known as the Architect of Record. The Design-Build Team A/E shall certify compliance with the VA RFP and all applicable codes.
F. Approved Construction Documents:
1. The final construction document submission package will be submitted by the Design-Build Team A/E for approval by the VA after completion of the 75% review cycle for the final package to be submitted by the Design-Build Team A/E. The VA will have 15 calendar days to take approval action.
2. The final construction documents submission package will include a full set of construction documents including all disciplines/packages.
3. The final construction documents submission package will incorporate all VA supplied comments from the earlier 25%, 75% and 100% submission package reviews and will comply with the VA requirements.
4. If the final construction documents submission package is not complete a post submittal may be required, the cost of which will be borne by the Design-Build Team A/E.
5. The approved final construction documents include such details that the project can be constructed and will be used for construction of the project.
G. Construction Drawing Preparation - Mandatory material and equipment schedules and details may be indicated either on the drawings or in the specifications, at the option of the Design-Build Team A/E. The construction drawings shall include a coordinated set of the following. (Reference Program Guide, PG-18-15, Volume C)
1. Structural drawings: including foundation plans, framing plans, schedules, and details, including general notes and all calculations.
2. Architectural drawings: including floor plans, building elevations, building sections, wall sections, reflected ceiling plans, stair details, toilet and bath details, door schedules and details, window schedules and details, room finish schedules, auto transport and other details.
3. Fire protection drawings: including floor and roof plans, riser diagrams, equipment schedules, and details, including general notes calculations and all related calculations.
4. Plumbing drawings: including floor and roof plans, riser diagrams equipment schedules, plumbing fixture schedules, and details, including general notes, and all related calculations.
5. HVAC drawings: including floor and roof plans, one-line flow diagrams, equipment schedules, and details, including general notes and all related calculations. Also provide sections for mechanical equipment rooms and sequence of operation for all HVAC equipment.
6 Electrical drawings: including site demolition plans, site, floor and roof plans (power, lighting, and other systems), one-line diagrams, panel schedules, equipment schedules, light fixture schedules calculations and details
7 Asbestos abatement: drawings including site demolition plans and floor plans indicating asbestos abatement method.
H. Construction Specifications - Project specifications shall include specifications for all products, materials, equipment, methods, and systems shown on the construction drawings in accordance with standard professional practice and the VA requirements. The specification submitted for review shall include:
1. The name of the manufacturer, the product name, model number, or other identification as appropriate to clearly identify the product that will be used in the construction of the project.
2. Other data as appropriate to clearly identify the product that will be used in the construction of the project i.e. shop drawings, product data, and samples as required by the VA documents; and
3. The required stamp of the licensed architect or engineer of record will be considered as certification of compliance with the project’s requirements.
I. Design Requirements – Compliance with codes and standards.
Project design shall be in compliance with applicable standards and codes described in VA Program Guides and design materials included or referenced in the solicitation materials.
4. The Design-Build Team A/E shall provide prompt, written notification to the Contracting Officer concerning conflicts with, or recommended deviations from codes, laws, regulations, standards, and opinions of review officials as described above. No work altering the scope of this contract shall be undertaken prior to receipt of written approval from the Contracting
5. No action may be brought against the Design-Build Team A/E or VA and no fine or penalty may be imposed for failure to carry out any of the previously described recommendations of Federal, state, or local officials. The VA and its contractors, shall not be required to pay any amount for any action taken by a state or political division of a state in carrying out functions described in this article, including reviewing plans, carrying out on-site inspections, issuing permits, and making recommendations.
6. The Design-Build Team A/E shall advise the Contracting Officer of any variances with the applicable Department of Labor, Occupational Safety and Health Standards, for occupancy requirements.
IX. QUALITY ASSURANCE (QA)/QUALITY CONTROL(QC):
A. To reduce design errors and omissions, the Design-Build Team A/E shall develop and execute a QA/QC plan that demonstrates the project plans and specifications have gone through a rigorous, thorough review and coordination effort.
B. Within 2 weeks of receipt of Notice to Proceed, the Design-Build Team A/E shall submit a detailed QA/QC plan describing each QA/QC task that will be taken during the development of the various design submission packages and the name of the Design-Build Team A/E member responsible for QA/QC.
1. Upon its completion each task shall be initialed and dated by the responsible Design-Build Team A/E member.
2. A 100% completed QA/QC plan shall be submitted with the final construction document submission package.
X. CONSTRUCTION PERIOD SERVICES:
A. Pre-Construction Meeting
The DB A/E, as part of the Design-Build Team A/E, shall participate in the pre-construction meeting with the VA and DB Contractor. The DB A/E shall be prepared to respond to the VA concerns, and shall provide overview of the design.
B. Site Visits & Inspections
1. During Construction Period Services, the DB A/E shall visit the job site as appropriate to the stage of construction to determine in general if the work is being performed in a manner indicating that the work, when completed, will be in accordance with the working drawings.
2. During the construction period the DB A/E shall make weekly visits to the project site when requested by the Contracting Officers Representative (COR). The Contracting Officers Representative (COR) may also request visits for special purposes. Only registered architects and engineers thoroughly familiar with the project may make these site visits. The Contracting Officers Representative (COR) has the prerogative to determine the professional discipline(s) required for any visit. The DB A/E shall observe the construction, advise the COR of any deviations or deficiencies or solutions to issues discussed.
A site inspection report which includes the purpose of the inspection, items reviewed, deficiencies observed, recommendations and additional actions required, shall be furnished to the Contracting Officers Representative (COR) within three workdays following the site visit date.
C. Disputes, Interpretations and Clarifications
Upon written request from the VA, the DB Contractor shall furnish to the VA, with reasonable promptness, in writing or in the form of drawings, interpretations of the Contract Documents prepared by the DB A/E, if, in the opinion of the VA, such interpretations are necessary for the proper execution or progress of the Work.
D. Other submittals
The DB team shall submit test results, certificates, manufacturer’s instructions, manufacturer’s field reports, etc. as required by the VA RFP specifications, to the VA Project Manager/COR.
E. Project record drawings
The Design-Build Team A/E shall maintain a set of construction documents (field as-built drawings) to record actual construction changes during the construction process as required by the RFP specifications. The project record drawings will be available for review by the VA Resident Engineer at all times.
F. Shop drawings and submittals
The DB A/E shall check government furnished and/or the contractor's shop drawings, detail drawings, schedules, descriptive literature and samples, testing labor-laboratory reports, field test data and review the color, texture and suitability of materials for conformity with the RFP Documents and construction documents. The DB A/E shall recommend approval, disapproval, or other suitable disposition to the VA. The VA will have final approval authority. The DB A/E shall evaluate the submittals with reference to any companion submittals that constitute a system. When necessary, the DB A/E shall request the Contractor to submit related components of a system before acting on a single component.
Should this procedure be inappropriate, the DB A/E shall review all prior submittals for related components of the system before acting on a single component. The DB A/E may be required to hold joint reviews with the VA technical staff and /or the Contractor on complicated system submittals. The DB A/E shall notify the VA COR in writing of any and all deviations from the requirements of the construction documents that he has found in the submittals.
G. Inspections and Testing
1. DB A/E shall be present during one (1) Pre-Final inspection and one (1) Final inspection of Work and shall generate Punch List and forward the list to the VA with explanations of found deficiencies and/or omissions in work, and recommended correctives.
2. DB A/E shall review and approve or take other appropriate action on test reports and Punch List items to be completed or corrected. DB A/E shall approve or disapprove test reports and forward findings to the VA for final disposition. DB Team shall forward approved inspection and testing document or lists to the VA for final disposition.
1. Review of Documents and Work Acceptance
On closeout of Construction Period Services, the Design-Build Team A/E shall certify that the Contract Documents requirements and intent have been satisfied, workmanship is Professional and at an acceptable level, submittals and other DB supplied Documents as required in Contract Documents are in order and stamped approved. However, the Government’s final acceptance of the Work is at the discretion of the COR and shall be authorized in writing by the VA Contracting Officer only.
1. Project Close-Out
The Design-Build Team A/E shall comply with the requirements in the “General Conditions”, Section 01001, and “General Requirements”, Section 01010, for submission of final RFP as built drawings, manuals, and other documents as noted. Required as built drawings and specifications will be submitted in the same format required for the construction documents.
1. AS-BUILT
The Design-Build Team A/E shall prepare and submit AS-BUILT drawings as developed from the Construction activities re-lined as-built. Drawings shall be submitted in AutoCAD 2018 (or earlier) format and shall reflect the actual as-built conditions. Stamp drawings in large red bold letters “AS-BUILT” in the lower right hand corner of all drawings. Drawings shall be submitted on full size consistent with previous requirements herein.