The file's text, extracted by GovTribe without its formatting.
Sheet1
| ELINS | |
| CONTRACT: | PUMP AND MOTOR CONTINGENCY |
| CONTRACT NO: | |
| CONTRACTOR: | |
| SHIP: | USS DECATUR (DDG-73) |
| LOCATION: | NAVY REGION SOUTHWEST |
| JSN | LOCATION | LOT | UNIT PRICE | EXT PRICE |
| EM02-3404 | 4-254-0-E, NR-4 SEAWATER COOLING PUMP (PUMP ONLY) | 1 | | |
| | ELIN 0001 | | | |
| PROVIDE LABOR, SERVICES, EQUIPMENT, AND MATERIALS TO DISCONNECT AND REMOVE THE EXISTING NR-4 SEAWATER COOLING PUMP FROM THE FOUNDATION AND ASSOCIATED PIPING. AFTER OVERHAUL, INSTALL THE PUMP ONTO THE FOUNDATION AND CONNECT ASSOCIATED PIPING. RECORD, RETAIN, AND REUSE EXISTING PIPING AND PUMP FOUNDATION FASTENERS. **SEE NOTE #2** | 1 | | | | |
| JSN | LOCATION | LOT | UNIT PRICE | EXT PRICE |
| EM02-3404 | 2-254-0-E, NR-4 SEAWATER COOLING PUMP (PUMP ONLY) | 1 | | |
| | ELIN 0002 | | | |
| PROVIDE LABOR, SERVICES, EQUIPMENT, ALL PUMP PARTS AND MATERIALS TO ACCOMPLISH A OVERHAUL OF THE NR-4 SEAWATER COOLING PUMP | 1 | | | | |
| JSN | LOCATION | LOT | UNIT PRICE | EXT PRICE |
| EM02-3404 | 2-254-0-E, NR-4 SEAWATER COOLING PUMP (PUMP ONLY) | 1 | | |
| | ELIN 0003 | | | |
| PROVIDE LABOR, SERVICES, EQUIPMENT AND MATERIALS FOR THE RIGGING (ONLOAD AND OFFLOAD), CRANE SUPPORT, AND TRANSPORTATION OF THE NR-4 SEAWATER COOLING PUMP FROM THE FOUNDATION TO SHOP FOR OVERHAUL, AND BACK ONTO THE FOUNDATION AFTER REPAIR | 1 | | | | |
| JSN | LOCATION | LOT | UNIT PRICE | EXT PRICE |
| EM02-3404 | 2-254-0-E, NR-4 SEAWATER COOLING PUMP (PUMP ONLY) | 1 | | |
| | ELIN 0004 | | | |
| PROVIDE LABOR, SERVICES, EQUIPMENT AND MATERIALS FOR THE ALIGNMENT AND ADJUSTMENTS OF THE OVERHAULED NR-4 SEAWATER COOLING PUMP. PROCURE NEW DOWEL PINS AND INSTALL AFTER COMPLETION OF ALIGNMENT AND ADJUSTMENTS PROCEDURE. | 1 | | | | |
| JSN | LOCATION | LOT | UNIT PRICE | EXT PRICE |
| EM02-3404 | 2-254-0-E, NR-4 SEAWATER COOLING PUMP (PUMP ONLY) | 1 | | |
| | ELIN 0005 | | | |
| PROVIDE LABOR, SERVICES, EQUIPMENT AND MATERIALS FOR THE SHIPBOARD OPERATIONAL TESTING OF THE OVERHAULED NR-4 SEAWATER COOLING PUMP, BALANCED MAGNETIC COUPLING, AND NR-4 SEAWATER COOLING PUMP MOTOR. | 1 | | | | |
| JSN | LOCATION | LOT | UNIT PRICE | EXT PRICE |
| EM02-3404 | 2-254-0-E, NR-4 SEAWATER COOLING PUMP (PUMP ONLY) | 1 | | |
| | ELIN 0006 | | | |
| PROVIDE LABOR, SERVICES, EQUIPMENT AND MATERIALS TO DRAIN AND DISPOSE ANY LIQUID IN SUPPORT OF THE OVERHAUL OF THE NR-4 SEAWATER COOLING PUMP | 1 | | | | |
| JSN | LOCATION | LOT | UNIT PRICE | EXT PRICE |
| EM02-3404 | 2-254-0-E, NR-4 SEAWATER COOLING PUMP (PUMP ONLY) | 1 | | |
| ELIN 0007 PROVIDE LABOR, SERVICES, EQUIPMENT AND MATERIALS FOR THE PREPARATION AND PAINTING OF NEW AND DISTURBED SURFACE | 1 | | |
| JSN | LOCATION | LOT | UNIT PRICE | EXT PRICE |
| EM02-3404 | 2-254-0-E, NR-4 SEAWATER COOLING PUMP (PUMP ONLY) | 1 | | |
| ELIN 0008 PROVIDE LABOR, SERVICES, EQUIPMENT AND MATERIALS FOR THE REPAIR AND REPLACEMENT OF NEW AND DISTURBED LAGGING AND INSULATION | 1 | | |
TOTAL
| Milestone Events | |
| Purchase Order Start Date: | 21 April 2021 |
| Remove, Transport to Shop and Repair: | 21 April to 10 May 2021 |
| Install and OPTEST Pump: | 10 to 14 May 2021 |
| Purchase Order End Date: | 14 May 2021 |
| NOTES: |
| 1. Refer to Technical Manual S6226-DN-MMA-010 for detailed procedures on the overhaul, testing, adjustments, and operational testing. |
2. The Contractor shall procure and install new Pipe Gaskets and associated PUMP Unit Fasteners and Seals.
3. The Contractor shall use the existing coupling from the old Pump & Motor Unit as part of the installation and testing
Sheet2
Sheet3