Elgin MHC Dental Equipment B 7938 Q and A.docx
DOCX document 12 KB Posted
- Attached to
- DHS SP Elgin Dental Equipment
- Solicitation number
- 20-444DHS-MENTH-B-7938
- Issued by
- Kane County, Illinois
About this file
This document is a question and answer (Q&A) related to the Elgin MHC Dental Equipment Bid Buy B 7938 contract opportunity. The requested services include providing new dental equipment to be connected to the existing plumbing system at the facility. The facility is open from 8 a.m. to 4 p.m. to allow for removal and installation of the equipment, and vendor staff will be escorted by facility engineering or security staff. Training on the use of the new equipment is also required.
The existing water system is not treated, and the facility prefers a system connected to the plumbing rather than a bottled water system. No other details about pricing, set asides, incumbents, funding, or contract terms are provided in this Q&A document.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Request for Quote Dental Eqmt.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Elgin MHC Dental Equipment Bid Buy B 7938 Questions and Answers
| Q1. | Do you want a bottled water system or do you want the system connected | to existing plumbing? |
| A1. | We currently are connected to the plumbing system and prefer the new | equipment be connected to the plumbing system. |
| Q2. | Is the water treated? | |
| A2. | No it is not. | |
| Q3. | Do you require training on the use of the new chair and equipment? | |
| A3. | Yes | |
| Q4. | Hours the facility is open to allow removal and installation of the | equipment? |
| A4. | Hours would be from 8 a.m. to 4 p.m. Vendor’s staff would be escorted by | either facility engineering staff or security staff. |