EL1016-22 SOLICITATION DOCUMENT.pdf

PDF 2 MB Posted

Attached to
FENCE PROJECT HAZELTON WV Federal contract opportunity
Solicitation number
EL1016-22
Issued by
Department of Justice Bureau of Prisons Correctional Facilities

View the file

Other files for this federal contract opportunity

Other files attached to FENCE PROJECT HAZELTON WV, newest first.
File Type Posted
EL1016-22 AMENDMENT 1.doc DOC document
wage determination Hazelton Fence.pdf PDF
NCIC FORM.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Page 1 of 60ORDER NUMBER:

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS

OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, & 30

1. REQUISITION NUMBER PAGE 1 OF

2. CONTRACT NO. 3. AWARD/EFFECTIVE

DATE

4. ORDER NUMBER 5. SOLICITATION NUMBER 6. SOLICITATION ISSUE

DATE

7. FOR SOLICITATION

INFORMATION CALL:

a. NAME b. TELEPHONE NUMBER (No collect calls)

8. OFFER DUE DATE/

LOCAL TIME

9. ISSUED BY

13b. RATING

14. METHOD OF SOLICITATION

CODE

15. DELIVER TO 16. ADMINISTERED BY CODE

18a. PAYMENT WILL BE MADE BY CODE17a. CONTRACTOR/

OFFEROR

CODE

FACILITY

CODE

CODE

TELEPHONE NO.

17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN

OFFER

18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK

BELOW IS CHECKED

RFQ IFB RFP

SEE ADDENDUM

19.

ITEM NO.

20.

SCHEDULE OF SUPPLIES/SERVICES

21.

QUANTITY

22.

UNIT

23.

UNIT PRICE

24.

AMOUNT

(Use Reverse and/or Attach Additional Sheets as Necessary)

25. ACCOUNTING AND APPROPRIATION DATA 26. TOTAL AWARD AMOUNT (For Govt. Use Only)

28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN

COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND

DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY

ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED

29. AWARD OF CONTRACT: REF. OFFER

DATED . . YOUR OFFER ON SOLICITATION

(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE

SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:

30a. SIGNATURE OF OFFEROR/CONTRACTOR

30b. NAME AND TITLE OF SIGNER (Type or print) 30c. DATE SIGNED

31a. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER)

31b. NAME OF CONTRACTING OFFICER (Type or print) 31c. DATE SIGNED

AUTHORIZED FOR LOCAL REPRODUCTION

PREVIOUS EDITION IS NOT USABLE

STANDARD FORM 1449 (REV. 2/2012)

Prescribed by GSA - FAR (48 CFR) 53.212

10. THIS ACQUISITION IS UNRESTRICTED OR

NAICS:

SIZE STANDARD:

13a. THIS CONTRACT IS A

RATED ORDER UNDER

DPAS (15 CFR 700)

SET ASIDE: % FOR:

11. DELIVERY FOR FOB DESTINA-

TION UNLESS BLOCK IS

MARKED

SEE SCHEDULE

12. DISCOUNT TERMS

ARE ARE NOT ATTACHED

ARE ARE NOT ATTACHED

27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1, 52.212-4. FAR 52.212-3 AND 52.212-5 ARE ATTACHED. ADDENDA

27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA

Coll. No.

8 (A)

EDWOSB

WOMEN-OWNED SMALL BUSINESS

(WOSB) ELIGIBLE UNDER THE WOMEN-OWNED

SMALL BUSINESS PROGRAM

SERVICE-DISABLED

VETERAN-OWNED

SMALL BUSINESS

HUBZONE SMALL

BUSINESS

SMALL BUSINESS

Page 2 of 60ORDER NUMBER:

SECTION B

SUPPLIES OR SERVICES AND PRICES/COSTS

Item No. SUPPLIES OR SERVICE Quantity U/M UNIT PRICE AMOUNT IN US$ Delivery Date

Page 3 of 60ORDER NUMBER:

Page 4 of 60ORDER NUMBER:

Page 5 of 60ORDER NUMBER:

Page 6 of 60ORDER NUMBER:

Page 7 of 60ORDER NUMBER:

Page 8 of 60ORDER NUMBER:

Page 9 of 60ORDER NUMBER:

Page 10 of 60ORDER NUMBER:

Page 11 of 60ORDER NUMBER:

Page 12 of 60ORDER NUMBER:

Page 13 of 60ORDER NUMBER:

Page 14 of 60ORDER NUMBER:

Page 15 of 60ORDER NUMBER:

Page 16 of 60ORDER NUMBER:

Page 17 of 60ORDER NUMBER:

Page 18 of 60ORDER NUMBER:

Page 19 of 60ORDER NUMBER:

Page 20 of 60ORDER NUMBER:

Page 21 of 60ORDER NUMBER:

Page 22 of 60ORDER NUMBER:

Page 23 of 60ORDER NUMBER:

Page 24 of 60ORDER NUMBER:

Page 25 of 60ORDER NUMBER:

Page 26 of 60ORDER NUMBER:

Page 27 of 60ORDER NUMBER:

Page 28 of 60ORDER NUMBER:

Page 29 of 60ORDER NUMBER:

Page 30 of 60ORDER NUMBER:

Page 31 of 60ORDER NUMBER:

Page 32 of 60ORDER NUMBER:

Page 33 of 60ORDER NUMBER:

Page 34 of 60ORDER NUMBER:

Page 35 of 60ORDER NUMBER:

Page 36 of 60ORDER NUMBER:

Page 37 of 60ORDER NUMBER:

Page 38 of 60ORDER NUMBER:

Page 39 of 60ORDER NUMBER:

Page 40 of 60ORDER NUMBER:

Page 41 of 60ORDER NUMBER:

Page 42 of 60ORDER NUMBER:

Page 43 of 60ORDER NUMBER:

Page 44 of 60ORDER NUMBER:

Page 45 of 60ORDER NUMBER:

Page 46 of 60ORDER NUMBER:

Page 47 of 60ORDER NUMBER:

Page 48 of 60ORDER NUMBER:

Page 49 of 60ORDER NUMBER:

Page 50 of 60ORDER NUMBER:

Page 51 of 60ORDER NUMBER:

Page 52 of 60ORDER NUMBER:

Page 53 of 60ORDER NUMBER:

Page 54 of 60ORDER NUMBER:

Page 55 of 60ORDER NUMBER:

Page 56 of 60ORDER NUMBER:

Page 57 of 60ORDER NUMBER:

Page 58 of 60ORDER NUMBER:

Page 59 of 60ORDER NUMBER:

Page 60 of 60ORDER NUMBER:

Page of

ORDER NUMBER:

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, & 30

1. REQUISITION NUMBER

PAGE 1 OF

2. CONTRACT NO.

3. AWARD/EFFECTIVE

DATE

4. ORDER NUMBER

5. SOLICITATION NUMBER

6. SOLICITATION ISSUE

DATE

7. FOR SOLICITATION

INFORMATION CALL:

a. NAME

b. TELEPHONE NUMBER (No collect calls)

8. OFFER DUE DATE/

LOCAL TIME

9. ISSUED BY

13b. RATING

14. METHOD OF SOLICITATION

CODE

15. DELIVER TO

16. ADMINISTERED BY

CODE

18a. PAYMENT WILL BE MADE BY

CODE

17a. CONTRACTOR/

OFFEROR

CODE

FACILITY

CODE

CODE

TELEPHONE NO.

17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN

OFFER

18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK

BELOW IS CHECKED

RFQ

IFB

RFP

SEE ADDENDUM

19.

ITEM NO.

20.

SCHEDULE OF SUPPLIES/SERVICES

21.

QUANTITY

22.

UNIT

23.

UNIT PRICE

24.

AMOUNT

(Use Reverse and/or Attach Additional Sheets as Necessary)

25. ACCOUNTING AND APPROPRIATION DATA

26. TOTAL AWARD AMOUNT (For Govt. Use Only)

28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN

COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND

DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY

ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED

29. AWARD OF CONTRACT: REF. OFFER

DATED . . YOUR OFFER ON SOLICITATION

(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE

SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:

30a. SIGNATURE OF OFFEROR/CONTRACTOR 30b. NAME AND TITLE OF SIGNER (Type or print) 30c. DATE SIGNED 31a. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER) 31b. NAME OF CONTRACTING OFFICER (Type or print) 31c. DATE SIGNED

AUTHORIZED FOR LOCAL REPRODUCTION

PREVIOUS EDITION IS NOT USABLE

STANDARD FORM 1449 (REV. 2/2012)

Prescribed by GSA - FAR (48 CFR) 53.212

10. THIS ACQUISITION IS

UNRESTRICTED OR

NAICS:

SIZE STANDARD:

13a. THIS CONTRACT IS A

RATED ORDER UNDER

DPAS (15 CFR 700)

SET ASIDE:

% FOR:

11. DELIVERY FOR FOB DESTINA-

TION UNLESS BLOCK IS

MARKED

SEE SCHEDULE

12. DISCOUNT TERMS

ARE

ARE NOT ATTACHED

ARE

ARE NOT ATTACHED

27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1, 52.212-4. FAR 52.212-3 AND 52.212-5 ARE ATTACHED. ADDENDA 27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA \\iaimain\apps1\Pam_Ward\Logos\Pointer.jpg Right Arrow Pointing to Call the Contact Point for this Solicitation/Contract/Order 8 (A)

EDWOSB

SMALL BUSINESS

WOMEN-OWNED SMALL BUSINESS

(WOSB) ELIGIBLE UNDER THE WOMEN-OWNED

SMALL BUSINESS PROGRAM

SMALL BUSINESS

SERVICE-DISABLED

VETERAN-OWNED

SMALL BUSINESS

HUBZONE SMALL

BUSINESS

SMALL BUSINESS

SMALL BUSINESS

Page of Printing C:\FORMFLOW\FORMS\SF\S1449_3.FRP BarbMWilliams

SECTION B

SUPPLIES OR SERVICES AND PRICES/COSTS

Item No. SUPPLIES OR SERVICE Quantity U/M UNIT PRICE AMOUNT IN US$ Delivery Date

LV_TITLE: Request for Quotation
CurrentSheet:
SheetCount:
20. SCHEDULE OF SUPPLIES/ SERVICES: 1600000108
20. SCHEDULE OF SUPPLIES/ SERVICES: 1600000108
20. SCHEDULE OF SUPPLIES/ SERVICES: 1600000108
1. REQUISITION NUMBER:
PAGE 1 OF:
2. CONTRACT NUMBER:
4. ORDER NUMBER:
5. SOLICITATION NUMBER: EL1016-22
31b. NAME OF CONTRACTING OFFICER (Type or print): Tiffani Balestrini
31b. NAME OF CONTRACTING OFFICER (Type or print): Tiffani Balestrini
7. FOR SOLICITATION INFORMATION CALL: b. TELEPHONE NUMBER (No collect calls): 570-547-1990
7. FOR SOLICITATION INFORMATION CALL: b. TELEPHONE NUMBER (No collect calls): 570-547-1990
15. DELIVER TO CODE: HAF1
15. DELIVER TO CODE: HAF1
% For : 100
12. DISCOUNT TERMS:
13b. RATING:
15. DELIVER TO:
17a. CONTRACTOR/ OFFEROR CODE: 391014499
17a. CONTRACTOR/ OFFEROR CODE: 391014499
17a. CONTRACTOR/ OFFEROR CODE: 391014499
17a. CONTRACTOR/ OFFEROR: UNDETERMINED SOURCE

NA BLANK

WASHINGTON DC 20534

17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN OFFER:
18a. PAYMENT WILL BE MADE BY:
19. ITEM NUMBER. Line 1 of 8.:
20. SCHEDULE OF SUPPLIES/ SERVICES: See Section B
21. QUANTITY:
22. UNIT:
23. UNIT PRICE:
19. ITEM NUMBER. Line 2 of 8.:
20. SCHEDULE OF SUPPLIES/ SERVICES:
21. QUANTITY:
22. UNIT:
23. UNIT PRICE:
19. ITEM NUMBER. Line 3 of 8.:
21. QUANTITY:
22. UNIT:
23. UNIT PRICE:
19. ITEM NUMBER. Line 4 of 8.:
20. SCHEDULE OF SUPPLIES/ SERVICES: EL1016-22
20. SCHEDULE OF SUPPLIES/ SERVICES: EL1016-22
21. QUANTITY:
22. UNIT:
23. UNIT PRICE:
19. ITEM NUMBER. Line 5 of 8.:
20. SCHEDULE OF SUPPLIES/ SERVICES:
21. QUANTITY:
22. UNIT:
23. UNIT PRICE:
19. ITEM NUMBER. Line 6 of 8.:
21. QUANTITY:
22. UNIT:
23. UNIT PRICE:
19. ITEM NUMBER. Line 7 of 8.:
20. SCHEDULE OF SUPPLIES/ SERVICES:
20. SCHEDULE OF SUPPLIES/ SERVICES:
21. QUANTITY:
22. UNIT:
23. UNIT PRICE:
19. ITEM NUMBER. Line 8 of 8.:
20. SCHEDULE OF SUPPLIES/ SERVICES:
21. QUANTITY:
22. UNIT:
23. UNIT PRICE:
25. ACCOUNTING AND APPROPRIATION DATA:
28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY

ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED. INITIALS :

29. AWARD OF CONTRACT: REFERENCE OFFER:
DATE. YOUR OFFER ON SOLICITATION

(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE

SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS.:

30b. NAME OF SIGNER (Type or print):
30b. TITLE OF SIGNER (Type or print):
10. THIS ACQUISITION IS UNRESTRICTED: 0
10. THIS ACQUISITION IS SET ASIDE:: 1
11. DELIVERY FOR FOB DESTINATION UNLESS BLOCK IS MARKED SEE SCHEDULE: X
13a. THIS CONTRACT IS A RATED ORDER UNDER DPAS (15 CFR 700): 0
14. METHOD OF SOLICITATION RFQ: 1
10. THIS ACQUISITION IS NAICS:: 238190
14. METHOD OF SOLICITATION IFB:
14. METHOD OF SOLICITATION RFP: 0
18a. PAYMENT WILL BE MADE BY CODE:
17a. CONTRACTOR/ OFFEROR TELEPHONE NUMBER:
27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA: 0
29. AWARD OF CONTRACT :
27a. ARE ATTACHED: 0
29. AWARD OF CONTRACT DATE Enter 2 digit month, 2 digit day and 4 digit year.:
30c. DATE SIGNED. Enter 2 digit month, 2 digit day and 4 digit year.:
6. SOLICITATION ISSUE DATE. Enter 2 digit month, 2 digit day and 4 digit year.: 2022-01-28
8. OFFER DUE DATE Enter 2 digit month, 2 digit day and 4 digit year.: 2022-02-21
8. OFFER LOCAL TIME: 2:00 PM
9. ISSUED BY: HAZELTON ELECTRONICS

1640 SKY VIEW DRIVE

BRUCETON MILLS WV 26525

18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK IS CHECKED SEE ADDENDUM:
26. TOTAL AWARD AMOUNT (FOR GOVT. USE ONLY): 0.00
26. TOTAL AWARD AMOUNT (FOR GOVT. USE ONLY): 0.00
17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN

OFFER :

31A. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER) :
10. THIS ACQUISITION IS SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESS: 0
10. THIS ACQUISITION IS HUBZONE SMALL BUSINESS: 0
27a. ARE ATTACHED:
6. SOLICITATION ISSUE DATE. Enter 2 digit month, 2 digit day and 4 digit year.: 2022-01-28
10. THIS ACQUISITION IS SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESS: 0
10. THIS ACQUISITION IS HUBZONE SMALL BUSINESS: 1
10. THIS ACQUISITION IS HUBZONE SMALL BUSINESS: 0
10. THIS ACQUISITION IS HUBZONE SMALL BUSINESS: 0
23. UNIT PRICE:
23. UNIT PRICE:
23. UNIT PRICE:
23. UNIT PRICE:
23. UNIT PRICE:
23. UNIT PRICE:
23. UNIT PRICE:
23. UNIT PRICE:
27a. ARE ATTACHED: 0
10. THIS ACQUISITION IS NAICS:: 16.5 M Ann Rece
LV_TERMS_OF_DELIV: Terms:
INCO1:
INCO2:
LV_TARGET_VALUE_CHAR:
TDLINE: OMB Clearance Number 1103-0018
TDLINE: GENERAL INTENTION: It is the intent of this solicitation to result in a
TDLINE: Firm Fixed Price, Construction Type Contract for a project at the UNICOR
TDLINE: Federal Prison Industries located at FCI Hazelton WV as outlined in the
TDLINE: attached Statement of Work. The solicitation is 100% set aside for
TDLINE: Small Business with competition limited to Small Business firms located
TDLINE: within the geographical area with a bona fide place of business in the
TDLINE: State of West Virginia. The North American Industrial Classification
TDLINE: System (NAICS) Code applicable to this project is 238190 Other
TDLINE: Foundation, Structure, and Building Exterior Contractors. The Small
TDLINE: Business Size Standard is $16.5 million.
TDLINE: Contract Line Item: Offerors shall enter unit price and amount for
TDLINE: contract line item.
TDLINE: QUESTIONS WILL ONLY be accepted in writing and WILL NOT BE ACCEPTED
TDLINE: AFTER Friday, February 11, 2022 at 12:00 Noon EST. Responses to
TDLINE: questions and site visit sign in sheet will be posted via www.fbo.gov
TDLINE: NO PHONE CALLS PLEASE.
TDLINE: Proposal due date is Monday, February 21, 2022 at 2:00 PM EST. Late
TDLINE: offers will not be accepted.
TDLINE: QUESTIONS PERTAINING TO THIS SOLICITATION WILL ONLY BE ADDRESSED IN
TDLINE: WRITING VIA EMAIL TO:tiffani.balestrini@USDOJ.GOV
TDLINE: THE NAICS CODE FOR THIS PROJECT IS: 238190 Other Foundation, Structure,
TDLINE: and Building Exterior Contractors. The Small Business Size Standard
TDLINE: is $16.5 million
TDLINE: SITE VISIT IS MANDATORY.
TDLINE: Mandatory Site visit has been scheduled for Thursday, February 10, 2022
TDLINE: at 9:00 AM EST. Participants will meet at the front entrance of the
TDLINE: Federal Correctional Institution, Hazelton WV, 1640 Sky View Drive,
TDLINE: Bruceton Mills, WV 26525. The Contractor shall inspect the site where
TDLINE: services are to be performed. This site review shall satisfy the
TDLINE: Contractor's need to identify all general and local conditions that may
TDLINE: affect the cost of the contract. Failure to inspect the site will not
TDLINE: constitute grounds for claims after contract award. UP to two (2)
TDLINE: people per company may attend.
TDLINE: Mandatory attendance is required for award. All representatives of your
TDLINE: company who intend on attending the site visit must submit a NCIC
TDLINE: clearance form to tiffani.balestrini@usdoj.gov no later than 12:00 noon
TDLINE: EST Tuesday February 8, 2022. The NCIC form will be posted as an
TDLINE: attachment to this RFQ. All participants must have a valid photo id to
TDLINE: gain entry. No weapons should be brought onto Government property.
TDLINE: No cell phones will be allowed into the secure perimeter of the
TDLINE: institution.
TDLINE: PROJECT MUST BE COMPLETED WITHIN sixty (60) days after AWARD. However,
TDLINE: project completion date is an evaluation factor. (Please see Section
TDLINE: M)
TDLINE: THE FOLLOWING INFORMATION IS REQUIRED TO BE COMPLETED BY THE OFFEROR:
TDLINE: VENDOR'S DUN & BRADSTREET NUMBER:_______________________________
TDLINE: VENDOR'S POINT OF CONTACT: _____________________________________
TDLINE: VENDOR'S TELEPHONE & FAX NUMBER: ______________________________
TDLINE: VENDOR'S EMAIL ADDRESS: ________________________________________
TDLINE: VENDOR'S BUSINESS SIZE (i.e. SMALL,LARGE,ETC.): ________________
TDLINE: By submission of an offer, the offeror acknowledges the requirement that
TDLINE: a prospective awardee shall be registered in the SAM database (System
TDLINE: Award Management) prior to award, during performance and through final
TDLINE: payment of any contract resulting from this solicitation.
TDLINE: _______________________________________________ Signature
TDLINE: All offerors must complete the following information prior to submission
TDLINE: of offer to be considered for award, in addition to the requirements of
TDLINE: Section L:
TDLINE: 1.,,SAM REGISTRATION WWW.SAM.GOV
TDLINE: 2.,,Section B-Provide pricing to include supplies and labor in
TDLINE: accordance with the Davis Bacon Act
TDLINE: 3.,,Section L - Business Management Questionnaire
TDLINE: All offerors must complete the Business Management questionnaire with
TDLINE: three references from the past three (3) years that are same or similar
TDLINE: in scope to this requirement. This includes size of requirement.
TDLINE: 4.,,DUNS NUMBER_________________
TDLINE: 5.,,TIN Number __________________
TDLINE: 6. Bid Bond if proposal price is over $100,000
TDLINE: 7. Performance and payment bod if proposal price is over $100,000
TDLINE: 8. Signed proposal (SF-1449) (including signed SF-30 amendments that
TDLINE: were issued)
TDLINE: After award the following will be required:
TDLINE: 1. Required completed packets for background clearance for workers
TDLINE: 2. Insurance documents as required by solicitation.
TDLINE: 3. Certified payroll with invoice to document compliance with Wage Rate
TDLINE: Determination
TDLINE: 4. any other requested documents.
TDLINE: Section C: Statement of Work
TDLINE: STATEMENT OF WORK
TDLINE: FENCE AND GATE INSTALLATION
TDLINE: FCC HAZELTON, WV
TDLINE: A.,,SUMMARY OF WORK & PLACE OF PERFORMANCE
TDLINE: The Federal Prison Industries (UNICOR), Federal Correctional Complex
TDLINE: (FCC), located at 1640 Sky View Drive, Bruceton Mills, West Virginia
TDLINE: intends to make a single award to a responsible entity that will provide
TDLINE: labor, materials, and equipment necessary to install 2 separate Chain
TDLINE: Link fences and one tractor trailer gate, gate must be prepared for a
TDLINE: Folger Adams locking mechanism. The dimension of the first chain Link
TDLINE: fence is approximately 32ft long and 20ft tall and will be a
TDLINE: non-enclosed barrier wall. The second chain link fence is approximately
TDLINE: 54ft long and 21ft wide with a height of 16ft with a gate that has
TDLINE: double swinging doors, one of which shall be prepped for a Folger Adams
TDLINE: locking mechanism to be installed by FCC Hazelton Lock Shop.
TDLINE: B.,,SCHEDULE
TDLINE: a.,,Anticipated time work is to be completed between the hours of 7:00
TDLINE: AM - 3:00 PM, Eastern Standard Time (EST) Monday - Friday, excluding
TDLINE: weekends and federal holidays. Times are subject to change based on
TDLINE: institutional security needs, alternative hours may be required during
TDLINE: evening hour after 4:00 PM EST.
TDLINE: b.,,Any work required to be completed at any other time than noted above
TDLINE: must be scheduled five (5) working days prior to the start of the work
TDLINE: and approved by the Contracting Officer.
TDLINE: c.,,No work will be conducted on weekends, or federal holidays unless
TDLINE: submitted in writing to the Contracting Officer five (5) working days
TDLINE: prior to the start of the work and approval is granted.
TDLINE: C. CONTRACTOR RESPONSIBILITIES
TDLINE: a.,,Contractor shall be responsible for the procurement and delivery of
TDLINE: all equipment.
TDLINE: b.,,Contractor will be certified/authorized by the manufacturer to
TDLINE: perform installations/repairs.
TDLINE: c.,,Contractor shall take all necessary precautions to ensure against
TDLINE: any/all damage to the existing property. Any damaged items or property
TDLINE: shall be returned to original condition by the Contractor via repaired
TDLINE: and/or replacement at no additional cost to the Government.
TDLINE: d.,,The contractor will ensure all manufacturers recommendations are
TDLINE: implemented for this project.
TDLINE: e.,,Contractor shall provide a designated Project Manager (PM) for
TDLINE: administration of this project while installation is in progress.
TDLINE: f.,,Contractor will be permitted to wear jeans in the institution,
TDLINE: however, green or khaki-color clothing will not be allowed. The clothes
TDLINE: will be proper and suitable for the services that are being provided.
TDLINE: g.,,Lunches will be consumed at the work site. Contractor shall ensure
TDLINE: they have everything they need for their lunch when they check-in first
TDLINE: thing in the morning.
TDLINE: h.,,Federal smoking policy on Federal property states that smoking is
TDLINE: only allowed in designated areas. This policy will be strictly enforced.
TDLINE: i.,,The contractor will be responsible for notifying the Contracting if
TDLINE: for any reason there will be an interruption of service.
TDLINE: j.,,The contractor is responsible for removal of all debris prior to
TDLINE: final invoice submission.
TDLINE: k.,,The contractor is responsible for adhering to all safety
TDLINE: regulations.
TDLINE: D. GOVERNMENT RESPONSIBILITIES
TDLINE: a.,,FCC Hazelton shall ensure all energy sources needing to be secured
TDLINE: to prevent personal injury and/or property damage will be locked-out and
TDLINE: tagged-out with the appropriate safety hardware. All system isolations
TDLINE: and Lockout/Tag out measures to be implemented, and/or removed, will
TDLINE: require written verification by the Contractor, the Facility Manager,
TDLINE: and the Safety Manager prior to doing so.
TDLINE: b.,,FCC Hazelton shall ensure a representative is present to allow
TDLINE: access to all areas requested by the Contractor as needed.
TDLINE: E. SECURITY
TDLINE: 1. DELIVERY OF MATERIALS
TDLINE: a.,,All materials/equipment required for work on this project is
TDLINE: required to be processed by the Contractor and coordinated with the
TDLINE: Contracting Officer Representative (COR) for temporary storage.
TDLINE: b.,,No additional construction related deliveries are permitted to be
TDLINE: shipped to the contractor at FCC Hazelton.
TDLINE: c.,,Under no circumstances will the Federal Bureau of Prisons or its
TDLINE: staff be responsible for the acceptance of any Contractor or company
TDLINE: deliveries.
TDLINE: d.,,The Contractor shall be responsible to provide for loading and
TDLINE: unloading contractor material and equipment. FBOP employees will not be
TDLINE: used.
TDLINE: e.,,The Contractor shall not use the institution’s warehouse rear dock
TDLINE: ramp for the loading, unloading, or storage of any materials or
TDLINE: equipment. The contractor will not impede/block the rear dock ramp at
TDLINE: any time during or after the work shift.
TDLINE: 2. STORAGE OF MATERIALS AND EQUIPMENT
TDLINE: a.,,No construction material / tools shall be stored on site. At the
TDLINE: start of each work day all tools will be inventoried out on a daily tool
TDLINE: inventory sheet and at the end of the work day all tools will be
TDLINE: inventoried back in to ensure accurate accountability of all tools at
TDLINE: the end of each work day.
TDLINE: b.,,The Federal Bureau of Prisons (FBOP) will not provide a secure
TDLINE: lay-down area for storage of equipment and material from the Contractor.
TDLINE: The FBOP does not take any responsibility for the security of such
TDLINE: equipment and materials.
TDLINE: 3. SECURITY CLEARANCE/CONTRACTOR BADGES
TDLINE: a.,,All contractors/sub-contractors (no exceptions) working on the
TDLINE: grounds of FCC Hazelton will be required to conform with requirements
TDLINE: set forth in the Homeland Security Presidential Directive (HSPD-12). All
TDLINE: applicable HSPD-12 paperwork must be filled out in its entirety. Once
TDLINE: the contract has been awarded, all necessary HSPD-12 paperwork will be
TDLINE: sent to the awarded contractor.
TDLINE: b.,,The prime contractor will be responsible to provide the necessary
TDLINE: information for security clearance on the HSPD-12 paperwork for
TDLINE: employees and sub-contractors. A Point of Contact will be designated
TDLINE: after contract award. HSPD-12 documentation will not be accepted from a
TDLINE: sub-contractor.
TDLINE: c.,,In the event a contractor’s employee does not pass the security
TDLINE: clearance, it shall be the contractor’s responsibility to submit another
TDLINE: employee for security clearance.
TDLINE: d.,,All security clearances shall be submitted to a designated person
TDLINE: (Facilities Assistant), a minimum of ten working days after receiving
TDLINE: the packets. Security clearances will be in effect for the term of up to
TDLINE: one year, prior to the expiration period ending September 30 of each
TDLINE: calendar year.
TDLINE: e.,,All contractors and sub-contractor employees will provide a check
TDLINE: list of all employees on site-each day to the COR, verifying the number
TDLINE: of workers on site each day and that all workers are pre-approved to be
TDLINE: on the site.
TDLINE: F.,,UTILITIES
TDLINE: The FBOP will provide electricity service, restroom services and water.
TDLINE: G.,,INSTITUTION SECURITY
TDLINE: Contractor personnel shall wear clothes that are suitable for the work
TDLINE: they are performing. The inmate population wears khaki and olive green
TDLINE: clothes. For this reason, no Bureau of Prisons employees or contract
TDLINE: personnel can wear these colors. No sleeveless shirts (tank tops) or
TDLINE: camouflage clothing is allowed.
TDLINE: The Contractor will be required to be escorted at all times while
TDLINE: entering and working within the institution. Items will be restricted to
TDLINE: the equipment/tools required to complete the contract action only.
TDLINE: Electronic devices or weapons of any kind shall not be permitted within
TDLINE: the institution at any time. The Contractor shall be constantly aware
TDLINE: of security and maintain a professional relationship with the inmates at
TDLINE: all times if they come in contact with the inmate population.
TDLINE: H.,,GENERAL PROJECT REQUIREMENTS
TDLINE: The contractor will provide all labor and equipment for the install of
TDLINE: two separate Chain Link fences and one tractor trailer gate, gate must
TDLINE: be prepared for a Folger Adams locking mechanism. The contractor shall
TDLINE: supply the following, 1 - 16’ wide x 14’ tall loading dock gate with
TDLINE: panic hardware, and enough of the following supplies for the above
TDLINE: mentioned fences, galvanized, 9 gauge chain link fabric, 1 5/8”
TDLINE: galvanized top rail, 1 5/8” galvanized middle rail, 6 5/8” galvanized
TDLINE: post, 4” galvanized posts, bottom tension wire, and any misc. materials
TDLINE: needed to complete the fences.
TDLINE: I.,,FIELD QUALITY CONTROL
TDLINE: At the time of project completion, the contractor shall ensure that the
TDLINE: gate is operational and complete a walk through with UNICOR and
TDLINE: Facilities Department and address any areas of concern or needs the
TDLINE: institution may have before the project will be considered complete and
TDLINE: satisfactory.
TDLINE: Section D: Packaging and Marking
TDLINE: SECTION D - PACKAGING AND MARKING
TDLINE: PRESERVATION, PACKING AND MARKING
TDLINE: Preservation, packaging, and packing for all items delivered hereunder
TDLINE: shall be in accordance with commercial practice, and shall be paid by
TDLINE: the contractor. All packaging, postage fees and payment related to
TDLINE: submitting information, forms and reports, etc. to the Government (i.e.
TDLINE: Contracting Officer, Contracting Officer's Representative) shall be paid
TDLINE: by the Contractor.
TDLINE: MARKING
TDLINE: All information submitted to the Contracting Officer or the Contracting
TDLINE: Officer's Representative shall clearly indicate the contract number and
TDLINE: task order number, if applicable, for which the information is being
TDLINE: submitted.
TDLINE: Section E: Inspection and Acceptance
TDLINE: CONTRACTING OFFICER'S REPRESENTATIVE (COR)
TDLINE: The COR is responsible, as applicable, for: receiving all deliverables,
TDLINE: inspecting and accepting the supplies or services provided hereunder in
TDLINE: accordance with the terms and conditions of this contract; providing
TDLINE: direction to the contractor which clarifies the contract effort, fills
TDLINE: in details or otherwise serves to accomplish the contractual Scope of
TDLINE: Work; evaluating performance; and certifying all invoices/vouchers for
TDLINE: acceptance of the supplies or services furnished for payments. Also, see
TDLINE: Section H.3 of the solicitation.
TDLINE: 52.236-5 Material and Workmanship (APR 1984)
TDLINE: 52.246-12 Inspection of Construction. (Aug 1996)
TDLINE: Section F: Delivery & Performance
TDLINE: Federal Correction Institution, Hazelton
TDLINE: UNICOR
TDLINE: 1640 Sky View Drive
TDLINE: Bruceton Mills, WV 26525
TDLINE: FAR 52.211-10, COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK
TDLINE: For each building, the Contractor shall be required to (a) commence work
TDLINE: under the awarded contract within 30 calendar days of receipt of task
TDLINE: order, and (b) prosecute the work diligently. The time stated for
TDLINE: completion shall include final cleanup of the premises.
TDLINE: (End of clause)
TDLINE: CONTRACT PERIOD OF PERFORMANCE
TDLINE: The period of performance of this contract shall be sixty (60) calendar
TDLINE: days, and commence from the contract award date and continue thru final
TDLINE: completion.
TDLINE: Section G Contract Administration Data:
TDLINE: FEDERAL GOVERNMENT HOLIDAYS
TDLINE: The following is a list of Federal Holidays observed by the Government:
TDLINE: New Year's Day (JAN 1),,
TDLINE: Labor Day (1st Monday in September)
TDLINE: Martin Luther King's Birthday (3rd Monday in January)
TDLINE: Columbus Day (2nd Monday in OCT)
TDLINE: Washington's Birthday (3rd Monday in February)
TDLINE: Veteran's Day (November 11th)
TDLINE: Thanksgiving (4th Thursday in November)
TDLINE: Memorial Day (last Monday in May)
TDLINE: Independence Day (JUL 4)
TDLINE: Christmas (DEC 25)
TDLINE: ADMINISTRATIVE INFORMATION
TDLINE: A. ROLE OF GOVERNMENT PERSONNEL AND RESPONSIBILITY FOR
TDLINE: CONTRACT AWARD AND ADMINISTRATION
TDLINE: 1. Administration of this contract shall be performed by:
TDLINE: Tiffani Balestrini, Supervisory Contract Specialist
TDLINE: Telephone: 570-547-1990 x4669
TDLINE: E-mail: tiffani.balestrini@usdoj.gov
TDLINE: Address:
TDLINE: UNICOR, Federal Prison Industries
TDLINE: Attn: Tiffani Balestrini, Supervisory Contract Specialist
TDLINE: Route 15, 2 Miles N. of Allenwood
TDLINE: Allenwood, PA 17810
TDLINE: Written communications shall make reference to the contract number and
TDLINE: shall be sent via Email to tiffani.balestrini@usdoj.gov
TDLINE: Administrative Contracting Officer is Tiffani Balestrini at
TDLINE: tiffani.balestrini@usdoj.gov
TDLINE: The Contracting Officer (CO) has the overall and primary responsibility
TDLINE: for the administration of this Contract. The CO alone, without
TDLINE: delegation, is authorized to take actions on behalf of the Government
TDLINE: to: modify or deviate from the contract terms, conditions,
TDLINE: requirements, specifications, details and/or delivery schedules; make
TDLINE: final decisions involving deductions from contract payments or other
TDLINE: consideration due to the Government, for nonperformance or
TDLINE: unsatisfactory performance, whether or not in dispute; terminate the
TDLINE: contract for convenience or default; issue final decisions regarding
TDLINE: contract questions or matters under dispute. The CO may delegate
TDLINE: certain other responsibilities to an authorized representative.
TDLINE: JAR 2852.201-70, CONTRACTING OFFICER'S REPRESENTATIVE
TDLINE: a),, The following are hereby designated to act as Contracting Officer's
TDLINE: Representative (COR) under this contract:
TDLINE: The COR will be designated at a later date.
TDLINE: (b) The COR is responsible, as directed by the CO, for: 1. receiving
TDLINE: all deliverables, inspecting and accepting the supplies or services
TDLINE: provided hereunder in accordance with the terms and conditions of this
TDLINE: contract; 2. providing direction to the contractor which clarifies the
TDLINE: contract effort; 3. fills in details or otherwise serves to accomplish
TDLINE: the contractual Scope of Work; 4. evaluating performance; and
TDLINE: certifying all invoices/vouchers for acceptance of the supplies or
TDLINE: services furnished for payments.
TDLINE: (c) The COR does not have the authority to alter the contractor's
TDLINE: obligations under the contract, and/or modify any of the expressed
TDLINE: terms, conditions, specifications, or cost of the agreement. If as a
TDLINE: result of technical discussions, it is desirable to alter/change
TDLINE: contractual obligations or the Scope of Work, the Contracting Officer
TDLINE: shall issue such changes in writing and signed.
TDLINE: CONTRACTOR'S PROJECT SITE MANAGER –
TDLINE: The Contractor shall provide a full time Project Site Manager for all
TDLINE: construction and/or installation activities associated with each
TDLINE: facility. The Project Site Manager shall be present in the work area
TDLINE: whenever work is being performed.
TDLINE: Contractor's Project Site Manager shall provide signed and dated resume
TDLINE: to include a copy of certifications for credentialed professionals.
TDLINE: In the event of replacement of Project Site Manager, the Contractor is
TDLINE: required to replace the individuals listed below with individuals of
TDLINE: comparable qualifications.
TDLINE: CONTRACTOR'S PROJECT SUPERINTENDENT
TDLINE: The Contractor shall appoint a Project Superintendent who will be the
TDLINE: Contractor's authorized representative for technical and administrative
TDLINE: performance of all services required hereunder. The supervisor shall
TDLINE: provide the single point of contact through which all Contractor and
TDLINE: Government communications, work, and technical direction shall flow.
TDLINE: The supervisor shall receive and execute, on behalf of the Contractor,
TDLINE: such technical direction as the COR may issue within the terms and
TDLINE: conditions of the Contract. All administrative support of the
TDLINE: Contractor's technical personnel required to fulfill the tasks assigned
TDLINE: under this Contract shall be the responsibility of the Contractor.
TDLINE: Contractor's Project Superintendent shall provide signed and dated
TDLINE: resume to include a copy of certifications for credentialed
TDLINE: professionals, proximity to job-site and all current projects assigned
TDLINE: to them.
TDLINE: In the event of replacement of Project Superintendent, the Contractor is
TDLINE: required to replace the individuals listed below with individuals of
TDLINE: comparable qualifications.
TDLINE: REQUIREMENTS FOR CORRECTION OF SUB-STANDARD PERFORMANCE
TDLINE: When any member of the Contract Administration Team (CO & COR) becomes
TDLINE: aware of substandard performance in any area of the Contract, the
TDLINE: Contractor will be given verbal and/or written notification, depending
TDLINE: on the circumstances of the issue. The Contractor shall resolve the
TDLINE: performance issues consistent with the requirements specified in the SOW
TDLINE: and/or task order. For other types of deficiencies where the corrective
TDLINE: actions are not specifically stated, the Contractor shall submit a Plan
TDLINE: of Action to correct the performance issue within ten (10) working days.
TDLINE: If it is not corrected to the satisfaction of the Contract
TDLINE: Administration Team member, the Contract Administration Team member
TDLINE: shall annotate the performance files and include the observations in the
TDLINE: Contractor Performance Report as appropriate.
TDLINE: 52.236-7 Permits and Responsibilities (NOV 1991)
TDLINE: Section H Special Contract Requirements:
TDLINE: CONTRACT AWARD
TDLINE: The Government intends to award a Firm Fixed-Price Construction type
TDLINE: contract as a result of this solicitation. Award will be made to the
TDLINE: offeror, pursuant to an affirmative determination of responsibility,
TDLINE: whose offer conforms to the terms of the solicitation, and is determined
TDLINE: to be in the best interest of the Government, based upon evaluation of
TDLINE: the factors included in this solicitation.
TDLINE: WAGE DETERMINATION APPLICABLE TO THIS CONTRACT
TDLINE: The rates referred to in the Davis-Bacon Act for Bricklayers, Laborers,
TDLINE: Carpenters, Electricians, etc., are included in the General Wage
TDLINE: Determination issued by U.S. Department of Labor Employment Standards
TDLINE: Administration Wage and Hour Division, General Decision Number
TDLINE: WV20220074, dated 01/07/2022.
TDLINE: Payment will be made to individuals used in the performance of this
TDLINE: contract, the rates of wages contained therein. The complete wage rate
TDLINE: decision is incorporated as a part of this solicitation.
TDLINE: SUBMISSION AND PAYMENT OF INVOICES
TDLINE: Reference Standard Contract Clause entitled "Prompt Payment For
TDLINE: Construction Contracts (FAR 52.232-27) of this solicitation. All
TDLINE: invoices shall include the complete contract number and line item(s)
TDLINE: billed. To avoid delay in payment, invoices shall be submitted in an
TDLINE: original and one copy (if prepared by a copying process, one copy shall
TDLINE: be marked "Original").
TDLINE: Pay Applications and Certified Payrolls shall be submitted to: UNICOR,
TDLINE: Federal Prison Industries, ATTN: Tiffani Balestrini, Contracting
TDLINE: Officer, tiffan.balestrini@usdoj.gov.
TDLINE: Delay in contractor payment due to invoice submission to any address
TDLINE: other than the email address listed above shall be the fault of the
TDLINE: contractor, and payment will be processed only upon receipt at the
TDLINE: physical or email address noted above, and after approval by UNICOR's
TDLINE: customer (DAU) and the project COR.
TDLINE: ALL INVOICES SHALL REFERENCE THE order NUMBER.
TDLINE: All invoices must match the contract dollar amount and payments will
TDLINE: only be processed upon approval by UNICOR's customer and project COR.
TDLINE: PREFERED METHOD: Submission of "Invoices by E-mail":
TDLINE: LIABILITY COVERAGE / INSURANCE
TDLINE: 52.228-5 Insurance-Work on a Government Installation
TDLINE: Insurance-Work on a Government Installation (Jan 1997)
TDLINE: (a) The Contractor shall, at its own expense, provide and maintain
TDLINE: during the entire performance of this contract, at least the kinds and
TDLINE: minimum amounts of insurance required in the Schedule or elsewhere in
TDLINE: the contract.
TDLINE: (b) Before commencing work under this contract, the Contractor shall
TDLINE: notify the Contracting Officer in writing that the required insurance
TDLINE: has been obtained. The policies evidencing required insurance shall
TDLINE: contain an endorsement to the effect that any cancellation or any
TDLINE: material change adversely affecting the Government's interest shall not
TDLINE: be effective-
TDLINE: (1) For such period as the laws of the State in which this contract is
TDLINE: to be performed prescribe; or
TDLINE: (2) Until 30 days after the insurer or the Contractor gives written
TDLINE: notice to the Contracting Officer, whichever period is longer.
TDLINE: (c) The Contractor shall insert the substance of this clause, including
TDLINE: this paragraph (c), in subcontracts under this contract that require
TDLINE: work on a Government installation and shall require subcontractors to
TDLINE: provide and maintain the insurance required in the Schedule or elsewhere
TDLINE: in the contract. The Contractor shall maintain a copy of all
TDLINE: subcontractors' proofs of required insurance, and shall make copies
TDLINE: available to the Contracting Officer upon request.
TDLINE: (End of clause)
TDLINE: (a) (In accordance with Standard FAR Contract Clause 52.228-5 entitled
TDLINE: "Insurance - Work on a Government Installation (JAN 1997) the Contractor
TDLINE: shall procure and maintain, during the entire period of his performance
TDLINE: under this contract, the following minimum insurance:
TDLINE: (1) General Liability Insurance
TDLINE: Bodily injury liability insurance, in the minimum limit of $500,000 per
TDLINE: occurrence is required on the comprehensive form policy.
TDLINE: (2) Automobile Liability Insurance
TDLINE: This insurance is required on the comprehensive form policy and shall
TDLINE: provide bodily injury liability and property damage liability covering
TDLINE: the operation of all automobiles sued in connection with the performance
TDLINE: of the contract. At least, the minimum limits of $200,000 per person
TDLINE: and $500,000 per occurrence for bodily injury and $20,000 per occurrence
TDLINE: for property damage shall be required.
TDLINE: (3) Workmen's Compensation and Employer's Liability Insurance
TDLINE: Employer's liability coverage is required in the minimum amount of $100
TDLINE: ,000 or as required by the state where the project is performed.
TDLINE: (b) Prior to the commencement of work hereunder, the Contractor shall
TDLINE: furnish to the Contracting Officer a certificate or written statement of
TDLINE: the above required insurance. The policies evidencing required
TDLINE: insurance shall contain an endorsement to the effect that cancellation
TDLINE: of any material change in the policies adversely affecting the interests
TDLINE: of the Government in such insurance shall not be effective for such
TDLINE: period as may be prescribed by the laws of the state in which this
TDLINE: contract is to be performed and in no event less than thirty (30) days
TDLINE: after written notice thereof to the Contracting Officer.
TDLINE: (c) The Contractor agrees to insert in all subcontracts the required
TDLINE: insurance information provided above, including this paragraph (c).
TDLINE: GOVERNMENT PROPERTY
TDLINE: The Contractor shall be responsible for all government property in its
TDLINE: custody if applicable. Any incidents of damage or loss shall be
TDLINE: reported to the COR in writing within one (1) working day.
TDLINE: CONTRACTOR'S RESPONSIBILITY
TDLINE: It is the responsibility of the Contractor to follow any Special
TDLINE: Security Requirements of the facility where the work is performed in the
TDLINE: performance of the contract and to consider the effects of those
TDLINE: security requirements in the pricing of the proposal.
TDLINE: Personnel access and identity verification: -
TDLINE: Access to the installation of FCI Hazelton will require NCIC Background
TDLINE: clearance for all staff gaining entrance to the institution. They will
TDLINE: be screened daily for entrance into the institution. No cell phones
TDLINE: will be permitted into the secure perimeter of the institution and photo
TDLINE: ID will be required daily. The Contractor, in the event of heightened
TDLINE: National Security Levels, may be subject to additional control measures.
TDLINE: All construction vehicles and Contractor's private vehicles will be
TDLINE: parked in an orderly manner at all times and will not block normal
TDLINE: traffic in the area.
TDLINE: The Contractor is required to furnish all services, materials, labor,
TDLINE: tools, and equipment necessary to fulfill the work as set out in the
TDLINE: Statement of Work.
TDLINE: The Contractor is to notify the Project COR and/or Contracting Officer
TDLINE: when problems arise, and offer possible solutions. The Contractor must
TDLINE: promptly report to the Project COR and/or Contracting Officer any
TDLINE: ambiguities, discrepancies and/or apparent wage violations when
TDLINE: discovered in the performance of this Statement of Work.
TDLINE: When required to support the work being performed under this Statement
TDLINE: of Work, the contract may be modified to include providing reimbursable
TDLINE: services as authorized in advance by the Contracting Officer.
TDLINE: The Contractor must be aware of standards, codes, requirements and
TDLINE: guidelines governing the construction of Government buildings.
TDLINE: The Contractor shall comply with all local, state, and federal building
TDLINE: codes and life safety codes.
TDLINE: The Contractor shall be responsible for all office supplies, included
TDLINE: but limited to, pencils, pens, calculators, binders, paper, printers,
TDLINE: fax machines, markers, whiteboards, hole punches, staples, etc. The
TDLINE: office supplies are not provided as part of this Statement of Work.
TDLINE: It shall be the sole responsibility of the Contractor to obtain all
TDLINE: information required to successfully carry out each contract task, other
TDLINE: than the information provided by the project COR.
TDLINE: PROJECT MAGNITUDE
TDLINE: BONDS
TDLINE: BID BOND
TDLINE: For offers in excess of $100,000, contractor shall submit with his offer
TDLINE: a Bid Bond (Standard Form 24) with good and sufficient surety or
TDLINE: sureties acceptable to the Government, or other security as provided in
TDLINE: paragraph entitled Bid Guarantee in the form of twenty percent (20%) of
TDLINE: the offer price, whichever is less. The bid bond penalty may be
TDLINE: expressed in terms of percentages of the offer price or may be expressed
TDLINE: in dollars and cents.
TDLINE: PERFORMANCE AND PAYMENT BONDS
TDLINE: If required, the bidder to whom award is made must furnish performance
TDLINE: (Standard Form 25), and payment (Standard Form 25A) bonds within 10
TDLINE: calendar days of award. The bonds will be good and sufficient surety or
TDLINE: sureties acceptable to the Government.
TDLINE: (a) PERFORMANCE BOND
TDLINE: When the contract price is in excess of $100,000, the penal sum of the
TDLINE: performance bond shall be equal to one hundred percent (100%) of the
TDLINE: contract price. The performance bond shall specifically provide coverage
TDLINE: for taxes imposed by the United States which are collected, deducted, or
TDLINE: withheld from wages paid by the contractor in carrying out the contract
TDLINE: with respect to which such bond is furnished.
TDLINE: (b) PAYMENT BOND
TDLINE: (1) Payment bonds are required for contracts in excess of $100,000.
TDLINE: (2) The penal amount of payment bonds shall equal one hundred percent of
TDLINE: the contract price.
TDLINE: PART II
TDLINE: Section I Clauses:
TDLINE: 52.203-12 Limitation on Payments to Influence Certain Federal
TDLINE: Transactions (JUN 2020)
TDLINE: 52.204-10 Reporting Executive Compensation and First Tier Subcontract
TDLINE: Awards (JUN 2020)
TDLINE: 52.204-12 Unique Entity Identifier Maintenance (Oct 2016.
TDLINE: 52.204-13 System for Award Management Maintenance (Oct 2018
TDLINE: 52.204-14 Service Contract Reporting Requirements (Oct 2016
TDLINE: 52.204-21 Basic Safeguarding of Covered Contractor Information Systems
TDLINE: (Jun 2016)
TDLINE: 52.207-3 Right of First Refusal of Employment (MAY 2006)
TDLINE: 52.209-6 Protecting the Government’s Interest When Subcontracting with
TDLINE: Contractors Debarred, Suspended, or Proposed for Debarment (JUN 2020)
TDLINE: 52.209-10 Prohibition on Contracting with Inverted Domestic Corporations
TDLINE: (NOV 2015)
TDLINE: 52.211-10 Commencement, Prosecution, and Completion of Work.(Apr 1984)
TDLINE: Alternate I (Apr1984)
TDLINE: 52.211-12 Liquidated Damages—Construction. (Sept 2000)
TDLINE: 52.211-13 Time Extensions (SEPT 2000)
TDLINE: 52.215-8 Order of Precedence—Uniform Contract Format. (Oct 1997)
TDLINE: 52.215-17 Waiver of Facilities Capital Cost of Money. (Oct 1997)
TDLINE: 52.219-6 Notice of Total Small Business Set-Aside. (NOV 2020)
TDLINE: 52.219-28 Post-Award Small Business Program Representation. (NOV 2020)
TDLINE: 52.222-3 Convict Labor. (June 2003)
TDLINE: 52.222-6 Construction Wage Rate Requirements (MAY 2014) (By Reference)
TDLINE: ) in solicitations and contracts in excess of $2,000 for construction
TDLINE: within the United States
TDLINE: 52.222-7 Withholding of Funds. (MAY 2014)
TDLINE: 52.222-8 Payrolls and Basic Records. (AUG 2018)
TDLINE: 52.222-9 Apprentices and Trainees. (July 2005)
TDLINE: 52.222-10 Compliance with Copeland Act Requirements. (Feb 1988)
TDLINE: 52.222-11 Subcontracts (Labor Standards). (MAY 2014)
TDLINE: 52.222-12 Contract Termination—Debarment. (MAY 2014
TDLINE: 52.222-13 Compliance with Davis-Bacon and Related Act Regulations.
TDLINE: (MAY 2014)
TDLINE: 52.222-14 Disputes Concerning Labor Standards. (Feb 1988)
TDLINE: 52.222-15 Certification of Eligibility. (MAY 2014)
TDLINE: 52.222-20 Contracts for Materials, Supplies, Articles, and Equipment
TDLINE: Exceeding $15,000 (JUN 2020)
TDLINE: 52.222-21 Prohibition of Segregated Facilities. (APR 2015
TDLINE: 52.222-26 Equal Opportunity. (SEP 2016)
TDLINE: Alternate I (Feb 1999). As prescribed in 22.810(e), add the following as
TDLINE: a preamble to the clause:
TDLINE: Notice: The following terms of this clause are waived for this contract:
TDLINE: __________ [Contracting Officer shall list terms].
TDLINE: 52.222-27 Affirmative Action Compliance Requirements for Construction.
TDLINE: (APR 2015)
TDLINE: 52.222-34 Project Labor Agreement (May 2010)
TDLINE: 52.222-36 Equal Opportunity for Workers with Disabilities (JUN 2020)
TDLINE: 52.222-50 Combating Trafficking in Persons (OCT 2020)
TDLINE: Alternate I (Mar 2015).
TDLINE: (i)(A) The United States Government's policy prohibiting trafficking in
TDLINE: persons described in paragraph (b) of this clause; and
TDLINE: (B) The following directive(s) or notice(s) applicable to employees
TDLINE: performing work at the contract place(s) of performance as indicated
TDLINE: below:
TDLINE: Document Title ,,Document may be obtained from:,,,,Applies to
TDLINE: performance in/at:
TDLINE: _____________,,_____________,,,,,,,,_______________
TDLINE: ______________,,_____________,,,,,,,,_______________
TDLINE: 52.222-55 Minimum Wage Under Executive Order 13658 (NOV 2020
TDLINE: 52.223-2 Affirmative Procurement of Biobased Products Under Service and
TDLINE: Construction Contracts.(Sept 2013)
TDLINE: 52.223-3 Hazardous Material Identification and Material Safety Data.
TDLINE: (FEB 2021)
TDLINE: Alternate I (July 1995)
TDLINE: .
TDLINE: 52.223-5 Pollution Prevention and Right-to-Know Information. (May 2011
TDLINE: 52.223-6 Drug-Free Workplace. (May 2001) (
TDLINE: 52.223-9 Estimate of Percentage of Recovered Material Content for
TDLINE: EPA-Designated Items. (May 2008)
TDLINE: As prescribed in 23.406(d), insert the following clause:
TDLINE: Estimate of Percentage of Recovered Material Content for EPA-Designated
TDLINE: Items (May 2008)
TDLINE: (a) Definitions. As used in this clause—
TDLINE: “Postconsumer material” means a material or finished product that has
TDLINE: served its intended use and has been discarded for disposal or recovery,
TDLINE: having completed its life as a consumer item. Postconsumer material is a
TDLINE: part of the broader category of “recovered material.”
TDLINE: “Recovered material” means waste materials and by-products recovered or
TDLINE: diverted from solid waste, but the term does not include those materials
TDLINE: and by-products generated from, and commonly reused within, an original
TDLINE: manufacturing process.
TDLINE: (b) The Contractor, on completion of this contract, shall—
TDLINE: (1) Estimate the percentage of the total recovered material content for
TDLINE: EPA-designated item(s) delivered and/or used in contract performance,
TDLINE: including, if applicable, the percentage of post-consumer material
TDLINE: content; and
TDLINE: (2) Submit this estimate to _____________________ [Contracting Officer
TDLINE: complete in accordance with agency procedures].
TDLINE: (End of clause)
TDLINE: Alternate I (May 2008). As prescribed in 23.406(d), redesignate
TDLINE: paragraph (b) of the basic clause as paragraph (c) and add the following
TDLINE: paragraph (b) to the basic clause:

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .