Solicitation-SF1449.pdf
PDF 1 MB Posted
- Attached to
- Enterprise Risk Management Support Services
- Solicitation number
- ED-FSA-09-R-0068
About this file
Solicitation - SF 1449
View the file
Other files
| File | Type | Posted |
|---|---|---|
| ERMSS-Blank Form Past Performance RFP ED-FSA-09-R-0068.doc | DOC document | |
| Instructions RFP ED-FSA-09-R-0068 to Offeror.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS
OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, & 30
1. REQUISITION NUMBER PAGE 1 OF
2. CONTRACT NO. 3. AWARD/EFFECTIVE
DATE
4. ORDER NUMBER 5. SOLICITATION NUMBER 6. SOLICITATION ISSUE
DATE
7. FOR SOLICITATION
INFORMATION CALL:
a. NAME b. TELEPHONE NUMBER (No collect calls)
8. OFFER DUE DATE/
LOCAL TIME
9. ISSUED BY
13b. RATING
14. METHOD OF SOLICITATION
CODE
15. DELIVER TO 16. ADMINISTERED BY CODE
18a. PAYMENT WILL BE MADE BY CODE 17a. CONTRACTOR/
OFFEROR
CODE
FACILITY
CODE
CODE
TELEPHONE NO.
17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN
OFFER
18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK
BELOW IS CHECKED
RFQ IFB RFP
SEE ADDENDUM
19.
ITEM NO.
20.
SCHEDULE OF SUPPLIES/SERVICES
21.
QUANTITY
22.
UNIT
23.
UNIT PRICE
24.
AMOUNT
(Use Reverse and/or Attach Additional Sheets as Necessary)
25. ACCOUNTING AND APPROPRIATION DATA 26. TOTAL AWARD AMOUNT (For Govt. Use Only)
28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN
DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY
ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED
29. AWARD OF CONTRACT: REF.
DATED . YOUR OFFER ON SOLICITATION
(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE
SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:
30a. SIGNATURE OF OFFEROR/CONTRACTOR
30b. NAME AND TITLE OF SIGNER (Type or print) 30c. DATE SIGNED
31a. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER)
31b. NAME OF CONTRACTING OFFICER (Type or print) 31c. DATE SIGNED
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
STANDARD FORM 1449 (REV. 3/2005)
Prescribed by GSA - FAR (48 CFR) 53.212
10. THIS ACQUISITON IS
UNRESTRICTED OR
NAICS:
SIZE STANDARD:
COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND
OFFER
13a. THIS CONTRACT IS A
RATED ORDER UNDER
DPAS (15 CFR 700)
SET ASIDE: % FOR:
SMALL BUSINESS
HUBZONE SMALL
BUSINESS
SERVICE-DISABLED VETERAN-
OWNED SMALL BUSINESS
EMERGING SMALL
BUSINESS
8(A)
11. DELIVERY FOR FOB DESTINA-
TION UNLESS BLOCK IS
MARKED
SEE SCHEDULE
12. DISCOUNT TERMS
ARE ARE NOT ATTACHED
ARE ARE NOT ATTACHED
27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1, 52.212-4. FAR 52.212-3 AND 52.212-5 ARE ATTACHED. ADDENDA
27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA
STANDARD FORM 1449 (REV. 3/2005) BACK
19.
ITEM NO.
20.
SCHEDULE OF SUPPLIES/SERVICES
21.
QUANTITY
22.
UNIT
23.
UNIT PRICE
24.
AMOUNT
32a. QUANTITY IN COLUMN 21 HAS BEEN
RECEIVED INSPECTED ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED:
41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT
32b. SIGNATURE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32c. DATE
41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER 41c. DATE
42a. RECEIVED BY (Print)
42b. RECEIVED AT (Location)
42c. DATE REC'D (YY/MM/DD) 42d. TOTAL CONTAINERS
40. PAID BY
32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE 32f. TELPHONE NUMBER OF AUTHORZED GOVERNMENT REPRESENTATIVE
32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE
33. SHIP NUMBER 34. VOUCHER NUMBER 35. AMOUNT VERIFIED
CORRECT FOR
PARTIAL FINAL
37. CHECK NUMBER
38. S/R ACCOUNT NO. 39. S/R VOUCHER NUMBER
36. PAYMENT
COMPLETE PARTIAL FINAL
Risk Management Support Services (RMSS)
SCHEDULE Continued
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
PAGE 2 OF
Enterprise Risk Management Support Services (ERMSS) (T&M) Contract
ERMSS (T&M) Contract and SOW Page 4 of 62
Section B Supplies and Services
B.1 Work Scope As ordered, the Contractor shall deliver any of the services delineated in Section D of this contract.
B.2 Pricing In pricing WPSOIs, the Contractor shall use the labor rates contained in Section B.9 of this contract.
B.3 Ordering and Contract Types The Contractor shall follow the Work Product Statement of Intent (WPSOI) procedures contained in Section C.10, using the labor rates contained in Section B.9. Orders awarded under this contract may be firm fixed price (FFP), or time and materials (T&M). Each WPSOI shall identify the pricing mechanism deemed appropriate by the Government for that WPSOI.
B.3.1 Fixed Price Type WPSOIs For Fixed Price type WPSOIs, the quantity of each item or labor category ordered shall be multiplied against the rate listed in Section B Rate Table or as negotiated for the WPSOI, and the cumulative extended total of all items ordered (to include all labor and Other Direct Costs (ODC) shall define the fixed price for the WPSOI; less any discounts. Travel and ODC, if applicable, may be estimated for each WPSOI, burdened with the markup percentages specified in this contract schedule. Financial payment of Fixed Price type WPSOIs may be negotiated based on the completion of milestones; reference Clause Performance-Based Payments in Section I. The schedule of milestone payments shall be incorporated into the WPSOI.
B.3.2 Time and Material (T&M) Type WPSOIs For T&M type WPSOIs, the quantity of hours ordered from each labor category shall be specified as deliverable hours billable at the ceiling rates specified in the Section B Rate Table or as negotiated, if lower rates are proposed for the WPSOI. Travel and ODC shall be estimated for each WPSOI and burdened with the ODC markup percentage specified in the Section B Rate Table. The cumulative extended total of all labor categories ordered plus travel and ODC shall define the WPSOI ceiling price that shall not be exceeded. The Government shall not reimburse the Contractor for costs incurred beyond the ceiling price, for hours not delivered, for hours delivered but in excess of the quantities ordered for a particular labor category or for travel and ODC exceeding the ordered amount. Labor dollars shall not be used to pay for ODC nor ODC dollars used to pay for labor without a WPSOI modification.
B.4 Ordering Period The ordering period for the T&M base contract is approximately eight (8) months with three (3) option periods (see B8 for beginning and end dates). Any WPSOI awarded prior to this contract expiring, completing subsequent to this expiration date, shall remain effective until completed.
However, if the WPSOI contains option(s), these will not be eligible to be exercised.
B.5 Contract T&M Values The contract value is TBD at award
ERMSS (T&M) Contract and SOW Page 5 of 62
B.6 Government Site Rates (For Fixed Price and T&M Type WPSOIs) When performing at Government sites, the Government will provide only office space, furniture, office equipment and supplies, information technology, and telecommunications (data) and landline if deemed necessary by the Contracting Officer.
B.7 Place of Performance
The place of performance for the effort required under this contract is at Federal Student Aid, 830 First St., NE, Washington, DC, unless otherwise specified in the WPSOI. Local travel expenses are not allowable under this contract. Local travel expenses include, but are not limited to:
commuter travel to and from the place of performance, parking and or mass transportation costs.
B. 8 BASE AND OPTION PERIODS
The base period of performance for the contract will be from date of award through June 7, 2010.
The contract will also include three (3) additional option periods. The base and option periods dates are as follows:
Period of Performance Beginning Date End Date
Base Period Date of award June 7, 2010
Option 1 June 8, 2010 February 20, 2011
Option 2 February 21, 2011 October 27, 2011
Option 3 October 28, 2011 June 26, 2012
B.9 RATE TABLES (CLINS AND ODC)
The Rate Tables represents all CLINS for labor rates and ODC for performance of the requirements as specified in individual WPSOIs. The hourly labor rates are for firm-fixed, and time and material type WPSOIs. The firm-fixed price labor rates and the time and material labor rates are the ceiling rates representing the maximum rates allowable for Prime and Subcontractors.
The periods cited represent contract periods. Only Government-required labor categories are included in this table. Additional labor categories may be proposed after contract award.
The Contractor shall submit the labor rate tables in Microsoft Excel as an attachment.
ERMSS (T&M) Contract and SOW Page 6 of 62
Sample Rate Tables:
Position Title Base Period
Date of Award – June 7, 2010 Labor Rate
Estimated Hours
Total Labor Rates
Project Manager 9
Senior Analyst 1312
Senior Analyst 1328
ERMSS (T&M) Contract and SOW Page 7 of 62
Option Period 1
June 8, 2010 – February 20, 2011 Labor Rate
Estimated Hours Total Labor Rates
Project Manager 8
Senior Analyst 1256
Senior Analyst 1312
ERMSS (T&M) Contract and SOW Page 8 of 62
Option Period 2
February 21, 2011 – October 27, 2011 Labor Rate
Estimated Hours Total Labor Rates
Project Manager 8
Senior Analyst 1248
Senior Analyst 1280
ERMSS (T&M) Contract and SOW Page 9 of 62
Option Period 3
October 28, 2011 – June 26, 2012 Labor Rate
Estimated Hours Total Labor Rates
Project Manager 8
Senior Analyst 1248
Senior Analyst 1232
(End of Section B)
ERMSS (T&M) Contract and SOW Page 10 of 62
Section C Contract Clauses
C.1. 52.212-4 CONTRACT TERMS AND CONDITIONS—COMMERCIAL ITEMS (MAR 2009)
(MODIFIED)
(a) Inspection/Acceptance.
The Contractor shall only tender for acceptance those items that conform to the requirements of this contract. The Government reserves the right to inspect or test any supplies or services that have been tendered for acceptance. The Government may require repair or replacement of nonconforming supplies or re-performance of nonconforming services at no increase in contract price. If repair/replacement or re-performance will not correct the defects or is not possible, the Government may seek an equitable price reduction or adequate consideration for acceptance of nonconforming supplies or services. The Government must exercise its post-acceptance rights—
(1) Within a reasonable time after the defect was discovered or should have been discovered;
and
(2) Before any substantial change occurs in the condition of the item, unless the change is due to the defect in the item.
(b) Assignment.
The Contractor or its assignee may assign its rights to receive payment due as a result of performance of this contract to a bank, trust company, or other financing institution, including any Federal lending agency in accordance with the Assignment of Claims Act (31 U.S.C. 3727).
However, when a third party makes payment (e.g., use of the Government-wide commercial purchase card), the Contractor may not assign its rights to receive payment under this contract.
(c) Disputes.
This contract is subject to the Contract Disputes Act of 1978, as amended (41 U.S.C. 601-613).
Failure of the parties to this contract to reach agreement on any request for equitable adjustment, claim, appeal or action arising under or relating to this contract shall be a dispute to be resolved in accordance with the clause at FAR 52.233-1, Disputes, which is incorporated herein by reference.
The Contractor shall proceed diligently with performance of this contract, pending final resolution of any dispute arising under the contract.
(d) Definitions.
The clause at FAR 52.202-1, Definitions, is incorporated herein by reference.
(e) Excusable delays.
The Contractor shall be liable for default unless nonperformance is caused by an occurrence beyond the reasonable control of the Contractor and without its fault or negligence such as, acts of http://uscode.house.gov/uscode-cgi/fastweb.exe?getdoc+uscview+t29t32+1665+30++%2831%29%20%20AND%20%28%2831%29%20ADJ%20USC%29%3ACITE%20%20%20%20%20%20%20%20%20 http://uscode.house.gov/uscode-cgi/fastweb.exe?getdoc+uscview+t41t42+2+13++%2841%29%20%20AND%20%28%2841%29%20ADJ%20USC%29%3ACITE%20%20%20%20%20%20%20%20%20 http://www.arnet.gov/far/current/html/52_233_240.html#wp1113304 http://www.arnet.gov/far/current/html/52_200_206.html#wp1137572
ERMSS (T&M) Contract and SOW Page 11 of 62
God or the public enemy, acts of the Government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, unusually severe weather, and delays of common carriers. The Contractor shall notify the Contracting Officer in writing as soon as it is reasonably possible after the commencement of any excusable delay, setting forth the full particulars in connection therewith, shall remedy such occurrence with all reasonable dispatch, and shall promptly give written notice to the Contracting Officer of the cessation of such occurrence.
(f) Invoice Procedures (FSA 32-1) (Aug 2007) (Tailored) The Contractor must submit a physical invoice via mail, fax or other electronic means for this contract in order to be paid for products and/or services rendered. Future invoices may be required to be submitted through Enterprise Resource Planning (ERP) software. Direct all questions regarding an invoice to the Contracting Officer.
Federal Student Aid's "designated billing office" is:
U.S. Department of Education Union Center Plaza Federal Student Aid Administration 830 First Street, NE, Suite 54B4 Washington, D.C. 20202-0001 E-mail: InvoiceAdmin@ed.gov Fax: (202) 275-3477
The Contractor shall also simultaneously submit copies of the invoice to the Contracting Officer and one to the Contracting Officer's Representative (COR). The CO and COR should receive copies via the same means as the invoice sent to the Budget Group.
At a minimum the following items must be addressed in order for the invoice to be considered "proper" for payment:
(a) Name and Address of the Contractor.
(b) Invoice Number and Invoice Date (Date invoices as close as possible to the date of mailing or transmission. The date and actual submission must occur after receipt, inspection and acceptance of the supplies or services.)
(c) The Contract number, contract line item, and if applicable, the order number must be included on the invoice and be correct.
(d) Description, quantity, unit of measure, unit price, and extended price of the item delivered must agree with the contract or order.
(e) Terms of any prompt payment discount offered.
(f) Name, title, and phone number of persons to be notified in event of defective invoice.
(g) The period of time covered by the invoice must include the first and last day of the period.
(h) Totals must be supported by subtotals and subtotals should be supported by detail, (i.e.
documentation for categories of labor, hours performed, unit prices) and deliverables provided.
(i) If required by this contract or order, receipts must be provided to support documentation of
"other direct costs" (ODC) or materials.
ERMSS (T&M) Contract and SOW Page 12 of 62
(g) Time and Material WPSOI Invoice Procedure
(a) To ensure timely processing of payment, the Contractor must submit a physical invoice via mail, fax or other electronic means for this contract in order to be paid for T&M services. The invoices shall be forwarded simultaneously to the addresses specified in Section (g) above as follows:
(1) Original to the cognizant audit office for administrative review, provisional approval and forwarding to the Finance Office listed in Section (g) above;
(2) Copy to the WPSOI CO; and
(3) Copy to the WPSOI COTR.
(b) All vouchers submitted to the Government shall delineate cost by:
(1) Contract and WPSOI Number;
(2) Funding document/order billing item or contract line item number (FFP and T&M
WPSOIs); and
(3) Any additional information required by specific payment clauses.
(c) For T&M funding documents/orders, supporting documentation shall be provided identifying the purpose and itinerary of all travel and other cost reimbursable ODC being billed during the billing period.
(d) For FFP funding documents/WPSOI, vouchers shall be submitted upon achievement of the billing milestones identified in the WPSOI if applicable. Progress payments pursuant to FAR 52.232-16 may be liquidated against the billing milestones established in each WPSOI.
(e) A completion voucher will be submitted for each funding document/order in accordance with
FAR 52.216-7.
(h) Payment
(1) Items accepted. Payment shall be made for items accepted by the Government that have been delivered to the delivery destinations set forth in this contract.
(2) Prompt payment. The Government will make payment in accordance with the Prompt Payment Act (31 U.S.C. 3903) and prompt payment regulations at 5 CFR Part 1315.
(3) Electronic Funds Transfer (EFT). If the Government makes payment by EFT, see 52.212-5(b) for the appropriate EFT clause.
(4) Discount. In connection with any discount offered for early payment, time shall be computed from the date of the invoice. For the purpose of computing the discount earned, payment shall be considered to have been made on the date which appears on the payment check or the specified payment date if an electronic funds transfer payment is made.
(5) Overpayments. If the Contractor becomes aware of a duplicate contract financing or invoice payment or that the Government has otherwise overpaid on a contract financing or invoice payment, the Contractor shall—
(i) Remit the overpayment amount to the payment office cited in the contract along with a description of the overpayment including the—
(A) Circumstances of the overpayment (e.g., duplicate payment, erroneous payment, liquidation errors, date(s) of overpayment);
(B) Affected contract number and delivery order number, if applicable;
(C) Affected contract line item or sub-line item, if applicable; and
(D) Contractor point of contact.
http://uscode.house.gov/uscode-cgi/fastweb.exe?getdoc+uscview+t29t32+1665+30++%2831%29%20%20AND%20%28%2831%29%20ADJ%20USC%29%3ACITE%20%20%20%20%20%20%20%20%20 http://www.arnet.gov/far/current/html/52_212_213.html#wp1179527
ERMSS (T&M) Contract and SOW Page 13 of 62
(ii) Provide a copy of the remittance and supporting documentation to the Contracting Officer.
(6) Interest.
(i) All amounts that become payable by the Contractor to the Government under this contract shall bear simple interest from the date due until paid unless paid within 30 days of becoming due. The interest rate shall be the interest rate established by the Secretary of the Treasury as provided in Section 611 of the Contract Disputes Act of 1978 (Public Law 95-563), which is applicable to the period in which the amount becomes due, as provided in (i) (6) (v) of this clause, and then at the rate applicable for each six-month period as fixed by the Secretary until the amount is paid.
(ii) The Government may issue a demand for payment to the Contractor upon finding a debt is due under the contract.
(iii) Final decisions. The Contracting Officer will issue a final decision as required by
33.211 if—
(A) The Contracting Officer and the Contractor are unable to reach agreement on the existence or amount of a debt within 30 days;
(B) The Contractor fails to liquidate a debt previously demanded by the Contracting Officer within the timeline specified in the demand for payment unless the amounts were not repaid because the Contractor has requested an installment payment agreement; or
(C) The Contractor requests a deferment of collection on a debt previously demanded by the Contracting Officer (see 32.607-2).
(iv) If a demand for payment was previously issued for the debt, the demand for payment included in the final decision shall identify the same due date as the original demand for payment.
(v) Amounts shall be due at the earliest of the following dates:
(A) The date fixed under this contract.
(B) The date of the first written demand for payment, including any demand for payment resulting from a default termination.
(vi) The interest charge shall be computed for the actual number of calendar days involved beginning on the due date and ending on—
(A) The date on which the designated office receives payment from the Contractor;
(B) The date of issuance of a Government check to the Contractor from which an amount otherwise payable has been withheld as a credit against the contract debt; or
(C) The date on which an amount withheld and applied to the contract debt would otherwise have become payable to the Contractor.
(vii) The interest charge made under this clause may be reduced under the procedures prescribed in 32.608-2 of the Federal Acquisition Regulation in effect on the date of this contract.
http://www.arnet.gov/far/current/html/Subpart 33_2.html#wp1079912 http://www.arnet.gov/far/current/html/Subpart 32_6.html#wp1031290 http://www.arnet.gov/far/current/html/Subpart 32_6.html#wp1031326
ERMSS (T&M) Contract and SOW Page 14 of 62
(i) Risk of loss.
Unless the contract specifically provides otherwise, risk of loss or damage to the supplies provided under this contract shall remain with the Contractor until, and shall pass to the Government upon:
(1) Delivery of the supplies to a carrier, if transportation is f.o.b. origin; or
(2) Delivery of the supplies to the Government at the destination specified in the contract, if transportation is f.o.b. destination.
(j) Taxes.
The contract price includes all applicable Federal, State, and local taxes and duties.
(k) Termination for the Government’s convenience.
The Government reserves the right to terminate this contract, or any part hereof, for its sole convenience. In the event of such termination, the Contractor shall immediately stop all work hereunder and shall immediately cause any and all of its suppliers and subcontractors to cease work. Subject to the terms of this contract, the Contractor shall be paid a percentage of the contract price reflecting the percentage of the work performed prior to the notice of termination, plus reasonable charges the Contractor can demonstrate to the satisfaction of the Government using its standard record keeping system, have resulted from the termination. The Contractor shall not be required to comply with the cost accounting standards or contract cost principles for this purpose. This paragraph does not give the Government any right to audit the Contractor’s records.
The Contractor shall not be paid for any work performed or costs incurred which reasonably could have been avoided.
(l) Termination for cause.
The Government may terminate this contract, or any part hereof, for cause in the event of any default by the Contractor, or if the Contractor fails to comply with any contract terms and conditions, or fails to provide the Government, upon request, with adequate assurances of future performance. In the event of termination for cause, the Government shall not be liable to the Contractor for any amount for supplies or services not accepted, and the Contractor shall be liable to the Government for any and all rights and remedies provided by law. If it is determined that the Government improperly terminated this contract for default, such termination shall be deemed a termination for convenience.
(m) Title.
Unless specified elsewhere in this contract, title to items furnished under this contract shall pass to the Government upon acceptance, regardless of when or where the Government takes physical possession.
ERMSS (T&M) Contract and SOW Page 15 of 62
(n) Warranty.
The Contractor warrants and implies that the items delivered hereunder are merchantable and fit for use for the particular purpose described in this contract.
(o) Limitation of liability.
Except as otherwise provided by an express warranty, the Contractor will not be liable to the Government for consequential damages resulting from any defect or deficiencies in accepted items.
(p) Other compliances.
The Contractor shall comply with all applicable Federal, State and local laws, executive orders, rules and regulations applicable to its performance under this contract.
(q) Compliance with laws unique to Government contracts.
The Contractor agrees to comply with 31 U.S.C. 1352 relating to limitations on the use of appropriated funds to influence certain Federal contracts; 18 U.S.C. 431 relating to officials not to benefit; 40 U.S.C. 3701, et seq., Contract Work Hours and Safety Standards Act; 41 U.S.C. 51-58, Anti-Kickback Act of 1986; 41 U.S.C. 265 and 10 U.S.C. 2409 relating to whistleblower protections; Section 1553 of the American Recovery and Reinvestment Act of 2009 relating to whistleblower protections for contracts funded under that Act; 49 U.S.C. 40118, Fly American;
and 41 U.S.C. 423 relating to procurement integrity.
(r) Order of precedence.
Any inconsistencies in this solicitation or contract shall be resolved by giving precedence in the following order:
(1) The schedule of supplies/services.
(2) The Assignments, Disputes, Payments, Invoice, Other Compliances, and Compliance with Laws Unique to Government Contracts paragraphs of this clause.
(3) The clause at 52.212-5.
(4) Addenda to this solicitation or contract, including any license agreements for computer software.
(5) Solicitation provisions if this is a solicitation.
(6) Other paragraphs of this clause.
(7) The Standard Form 1449.
(8) Other documents, exhibits, and attachments.
(9) The specification.
(s) Central Contractor Registration (CCR).
(1) Unless exempted by an addendum to this contract, the Contractor is responsible during performance and through final payment of any contract for the accuracy and completeness of http://uscode.house.gov/uscode-cgi/fastweb.exe?getdoc+uscview+t29t32+1665+30++%2831%29%20%20AND%20%28%2831%29%20ADJ%20USC%29%3ACITE%20%20%20%20%20%20%20%20%20 http://uscode.house.gov/uscode-cgi/fastweb.exe?getdoc+uscview+t17t20+160+141++%2818%29%20%25 http://uscode.house.gov/uscode-cgi/fastweb.exe?getdoc+uscview+t37t40+1574+51++%2840%29%20%20AND%20%28%2840%29%20ADJ%20USC%29%3ACITE%20%20%20%20%20%20%20%20%20 http://uscode.house.gov/uscode-cgi/fastweb.exe?getdoc+uscview+t41t42+2+13++%2841%29%20%20AND%20%28%2841%29%20ADJ%20USC%29%3ACITE%20%20%20%20%20%20%20%20%20 http://uscode.house.gov/uscode-cgi/fastweb.exe?getdoc+uscview+t41t42+2+13++%2841%29%20%20AND%20%28%2841%29%20ADJ%20USC%29%3ACITE%20%20%20%20%20%20%20%20%20 http://uscode.house.gov/uscode-cgi/fastweb.exe?getdoc+uscview+t09t12+37+408++%2810%29%20%252 http://uscode.house.gov/uscode-cgi/fastweb.exe?getdoc+uscview+t49t50+2+224++%2849%29%20%20AND%20%28%2849%29%20ADJ%20USC%29%3ACITE%20%20%20%20%20%20%20%20%20 http://uscode.house.gov/uscode-cgi/fastweb.exe?getdoc+uscview+t41t42+2+13++%2841%29%20%20AND%20%28%2841%29%20ADJ%20USC%29%3ACITE%20%20%20%20%20%20%20%20%20 http://www.arnet.gov/far/current/html/FormsStandard68.html#wp1186059
ERMSS (T&M) Contract and SOW Page 16 of 62 the data within the CCR database, and for any liability resulting from the Government’s reliance on inaccurate or incomplete data. To remain registered in the CCR database after the initial registration, the Contractor is required to review and update on an annual basis from the date of initial registration or subsequent updates its information in the CCR database to ensure it is current, accurate and complete. Updating information in the CCR does not alter the terms and conditions of this contract and is not a substitute for a properly executed contractual document.
(2)(i) If a Contractor has legally changed its business name, “doing business as” name, or division name (whichever is shown on the contract), or has transferred the assets used in performing the contract, but has not completed the necessary requirements regarding novation and change-of-name agreements in FAR Subpart 42.12, the Contractor shall provide the responsible Contracting Officer a minimum of one business day’s written notification of its intention to (A) change the name in the CCR database; (B) comply with the requirements of Subpart 42.12; and (C) agree in writing to the timeline and procedures specified by the responsible Contracting Officer. The Contractor must provide with the notification sufficient documentation to support the legally changed name.
(ii) If the Contractor fails to comply with the requirements of paragraph (t)(2)(i) of this clause, or fails to perform the agreement at paragraph (t)(2)(i)(C) of this clause, and, in the absence of a properly executed novation or change-of-name agreement, the CCR information that shows the Contractor to be other than the Contractor indicated in the contract will be considered to be incorrect information within the meaning of the “Suspension of Payment” paragraph of the electronic funds transfer (EFT) clause of this contract.
(3) The Contractor shall not change the name or address for EFT payments or manual payments, as appropriate, in the CCR record to reflect an assignee for the purpose of assignment of claims (see Subpart 32.8, Assignment of Claims). Assignees shall be separately registered in the CCR database. Information provided to the Contractor’s CCR record that indicates payments, including those made by EFT, to an ultimate recipient other than that Contractor will be considered to be incorrect information within the meaning of the “Suspension of payment” paragraph of the EFT clause of this contract.
(4) Offerors and Contractors may obtain information on registration and annual confirmation requirements via the internet at http://www.ccr.gov or by calling 1-888-227-2423 or 269-961- 5757.
(t) Inspection/Acceptance Alternate I (Oct 2008).
When a time-and-materials or labor-hour contract is contemplated, substitute the following paragraphs (a), (e), (i) and (l) for those in the basic clause.
(a) Inspection/Acceptance. (1) The Government has the right to inspect and test all materials furnished and services performed under this contract, to the extent practicable at all places and times, including the period of performance, and in any event before acceptance. The http://www.arnet.gov/far/current/html/Subpart 42_12.html#wp1084217 http://www.arnet.gov/far/current/html/Subpart 42_12.html#wp1084217 http://www.arnet.gov/far/current/html/Subpart 32_8.html#wp1029202 http://www.ccr.gov/
ERMSS (T&M) Contract and SOW Page 17 of 62
Government may also inspect the plant or plants of the Contractor or any subcontractor engaged in contract performance. The Government will perform inspections and tests in a manner that will not unduly delay the work.
(2) If the Government performs inspection or tests on the premises of the Contractor or a subcontractor, the Contractor shall furnish and shall require subcontractors to furnish all reasonable facilities and assistance for the safe and convenient performance of these duties.
(3) Unless otherwise specified in the contract, the Government will accept or reject services and materials at the place of delivery as promptly as practicable after delivery, and they will be presumed accepted 60 days after the date of delivery, unless accepted earlier.
(4) At any time during contract performance, but not later than 6 months (or such other time as may be specified in the contract) after acceptance of the services or materials last delivered under this contract, the Government may require the Contractor to replace or correct services or materials that at time of delivery failed to meet contract requirements.
Except as otherwise specified in paragraph (a)(6) of this clause, the cost of replacement or correction shall be determined under paragraph (i) of this clause, but the “hourly rate” for labor hours incurred in the replacement or correction shall be reduced to exclude that portion of the rate attributable to profit. Unless otherwise specified below, the portion of the “hourly rate” attributable to profit shall be 10 percent. The Contractor shall not tender for acceptance materials and services required to be replaced or corrected without disclosing the former requirement for replacement or correction, and, when required, shall disclose the corrective action taken. [Insert portion of labor rate attributable to profit.] (5)(i) If the Contractor fails to proceed with reasonable promptness to perform required replacement or correction, and if the replacement or correction can be performed within the ceiling price (or the ceiling price as increased by the Government), the Government may—
(A) By contract or otherwise, perform the replacement or correction, charge to the Contractor any increased cost, or deduct such increased cost from any amounts paid or due under this contract; or
(B) Terminate this contract for cause.
(ii) Failure to agree to the amount of increased cost to be charged to the Contractor shall be a dispute under the Disputes clause of the contract.
(6) Notwithstanding paragraphs (a)(4) and (5) above, the Government may at any time require the Contractor to remedy by correction or replacement, without cost to the Government, any failure by the Contractor to comply with the requirements of this contract, if the failure is due to—
(i) Fraud, lack of good faith, or willful misconduct on the part of the Contractor's managerial personnel; or
(ii) The conduct of one or more of the Contractor’s employees selected or retained by the Contractor after any of the Contractor’s managerial personnel has reasonable grounds to believe that the employee is habitually careless or unqualified.
ERMSS (T&M) Contract and SOW Page 18 of 62
(7) This clause applies in the same manner and to the same extent to correct or replacement materials or services as to materials and services originally delivered under this contract.
(8) The Contractor has no obligation or liability under this contract to correct or replace materials and services that at time of delivery do not meet contract requirements, except as provided in this clause or as may be otherwise specified in the contract.
(9) Unless otherwise specified in the contract, the Contractor's obligation to correct or replace Government-furnished property shall be governed by the clause pertaining to Government property.
(e) Definitions. (1) The clause at FAR 52.202-1, Definitions, is incorporated herein by reference. As used in this clause—
(i) Direct materials means those materials that enter directly into the end product, or that are used or consumed directly in connection with the furnishing of the end product or service.
(ii) Hourly rate means the rate(s) prescribed in the contract for payment for labor that meets the labor category qualifications of a labor category specified in the contract that are—
(A) Performed by the contractor;
(B) Performed by the subcontractors; or
(C) Transferred between divisions, subsidiaries, or affiliates of the contractor under a common control.
(iii) Materials means—
(A) Direct materials, including supplies transferred between divisions, subsidiaries, or affiliates of the contractor under a common control;
(B) Subcontracts for supplies and incidental services for which there is not a labor category specified in the contract;
(C) Other direct costs (e.g., incidental services for which there is not a labor category specified in the contract, travel, computer usage charges, etc.);
(D) The following subcontracts for services which are specifically excluded from the hourly rate: [Insert any subcontracts for services to be excluded from the hourly rates prescribed in the schedule.]; and
(E) Indirect costs specifically provided for in this clause.
(iv) Subcontract means any contract, as defined in FAR Subpart 2.1, entered into with a subcontractor to furnish supplies or services for performance of the prime contract or a subcontract including transfers between divisions, subsidiaries, or affiliates of a contractor or subcontractor. It includes, but is not limited to, purchase orders, and changes and modifications to purchase orders.
(i) Payments. (1) Services accepted. Payment shall be made for services accepted by the Government that have been delivered to the delivery destination(s) set forth in this contract.
The Government will pay the Contractor as follows upon the submission of commercial invoices approved by the Contracting Officer:
http://www.arnet.gov/far/current/html/52_200_206.html#wp1137572 http://www.arnet.gov/far/current/html/Subpart 2_1.html#wp1145507
ERMSS (T&M) Contract and SOW Page 19 of 62
(i) Hourly rate.
(A) The amounts shall be computed by multiplying the appropriate hourly rates prescribed in the contract by the number of direct labor hours performed. Fractional parts of an hour shall be payable on a prorated basis.
(B) The rates shall be paid for all labor performed on the contract that meets the labor qualifications specified in the contract. Labor hours incurred to perform tasks for which labor qualifications were specified in the contract will not be paid to the extent the work is performed by individuals that do not meet the qualifications specified in the contract, unless specifically authorized by the Contracting Officer.
(C) Invoices may be submitted once each month (or at more frequent intervals, if approved by the Contracting Officer) to the Contracting Officer or the authorized representative.
(D) When requested by the Contracting Officer or the authorized representative, the Contractor shall substantiate invoices (including any subcontractor hours reimbursed at the hourly rate in the schedule) by evidence of actual payment, individual daily job timecards, records that verify the employees meet the qualifications for the labor categories specified in the contract, or other substantiation specified in the contract.
(E) Unless the Schedule prescribes otherwise, the hourly rates in the Schedule shall not be varied by virtue of the Contractor having performed work on an overtime basis.
(1) If no overtime rates are provided in the Schedule and the Contracting Officer approves overtime work in advance, overtime rates shall be negotiated.
(2) Failure to agree upon these overtime rates shall be treated as a dispute under the Disputes clause of this contract.
(3) If the Schedule provides rates for overtime, the premium portion of those rates will be reimbursable only to the extent the overtime is approved by the Contracting Officer.
(ii) Materials.
(A) If the Contractor furnishes materials that meet the definition of a commercial item at FAR 2.101, the price to be paid for such materials shall be the contractor's established catalog or market price, adjusted to reflect the—
(1) Quantities being acquired; and
(2) Any modifications necessary because of contract requirements.
(B) Except as provided for in paragraph (i)(1)(ii)(A) and (D)(2) of this clause, the Government will reimburse the Contractor the actual cost of materials (less any rebates, refunds, or discounts received by the contractor that are identifiable to the contract) provided the Contractor—
(1) Has made payments for materials in accordance with the terms and conditions of the agreement or invoice; or http://www.arnet.gov/far/current/html/Subpart 2_1.html#wp1145508
ERMSS (T&M) Contract and SOW Page 20 of 62
(2) Makes these payments within 30 days of the submission of the Contractor’s payment request to the Government and such payment is in accordance with the terms and conditions of the agreement or invoice.
(C) To the extent able, the Contractor shall—
(1) Obtain materials at the most advantageous prices available with due regard to securing prompt delivery of satisfactory materials; and
(2) Give credit to the Government for cash and trade discounts, rebates, scrap, commissions, and other amounts that are identifiable to the contract.
(D) Other Costs. Unless listed below, other direct and indirect costs will not be reimbursed.
(1) Other Direct Costs. The Government will reimburse the Contractor on the basis of actual cost for the following, provided such costs comply with the requirements in paragraph (i) (1) (ii) (B) of this clause: [“Each order must list separately the elements of other direct charge(s) for that order.”]
(2) Indirect Costs (Material Handling, Subcontract Administration, etc.). The Government will reimburse the Contractor for indirect costs on a pro-rata basis over the period of contract performance at the following fixed price: [“$0”unless agreed otherwise in individual orders.]
(2) Total cost. It is estimated that the total cost to the Government for the performance of this contract shall not exceed the ceiling price set forth in the Schedule and the Contractor agrees to use its best efforts to perform the work specified in the Schedule and all obligations under this contract within such ceiling price. If at any time the Contractor has reason to believe that the hourly rate payments and material costs that will accrue in performing this contract in the next succeeding 30 days, if added to all other payments and costs previously accrued, will exceed 85 percent of the ceiling price in the Schedule, the Contractor shall notify the Contracting Officer giving a revised estimate of the total price to the Government for performing this contract with supporting reasons and documentation. If at any time during the performance of this contract, the Contractor has reason to believe that the total price to the Government for performing this contract will be substantially greater or less than the then stated ceiling price, the Contractor shall so notify the Contracting Officer, giving a revised estimate of the total price for performing this contract, with supporting reasons and documentation. If at any time during performance of this contract, the Government has reason to believe that the work to be required in performing this contract will be substantially greater or less than the stated ceiling price, the Contracting Officer will so advise the Contractor, giving the then revised estimate of the total amount of effort to be required under the contract.
(3) Ceiling price. The Government will not be obligated to pay the Contractor any amount in excess of the ceiling price specified in orders issued under this contract, and the Contractor shall not be obligated to continue performance if to do so would exceed the ceiling price set forth in individual orders, unless and until the Contracting Officer notifies the Contractor in writing that the ceiling price has been increased and specifies in the
ERMSS (T&M) Contract and SOW Page 21 of 62 notice a revised ceiling that shall constitute the ceiling price for performance of the individual order awarded under this contract. When and to the extent that the ceiling price set forth in the individual order has been increased, any hours expended and material costs incurred by the Contractor in excess of the ceiling price before the increase shall be allowable to the same extent as if the hours expended and material costs had been incurred after the increase in the ceiling price.
(4) Access to records. At any time before final payment under this contract, the Contracting Officer (or authorized representative) will have access to the following (access shall be limited to the listing below unless otherwise agreed to by the Contractor and the Contracting Officer):
(i) Records that verify that the employees whose time has been included in any invoice meet the qualifications for the labor categories specified in the contract;
(ii) For labor hours (including any subcontractor hours reimbursed at the hourly rate in the schedule), when timecards are required as substantiation for payment—
(A) The original timecards (paper-based or electronic);
(B) The Contractor’s timekeeping procedures;
(C) Contractor records that show the distribution of labor between jobs or contracts; and
(D) Employees whose time has been included in any invoice for the purpose of verifying that these employees have worked the hours shown on the invoices.
(iii) For material and subcontract costs that are reimbursed on the basis of actual cost—
(A) Any invoices or subcontract agreements substantiating material costs; and
(B) Any documents supporting payment of those invoices.
(5) Overpayments/Underpayments. Each payment previously made shall be subject to reduction to the extent of amounts, on preceding invoices, that are found by the Contracting Officer not to have been properly payable and shall also be subject to reduction for overpayments or to increase for underpayments. The Contractor shall promptly pay any such reduction within 30 days unless the parties agree otherwise. The Government within 30 days will pay any such increases, unless the parties agree otherwise.
The Contractor’s payment will be made by check. If the Contractor becomes aware of a duplicate invoice payment or that the Government has otherwise overpaid on an invoice payment, the Contractor shall—
(i) Remit the overpayment amount to the payment office cited in the contract along with a description of the overpayment including the—
(A) Circumstances of the overpayment (e.g., duplicate payment, erroneous payment, liquidation errors, date(s) of overpayment);
(B) Affected contract number and delivery order number, if applicable;
(C) Affected contract line item or sub line item, if applicable; and
(D) Contractor point of contact.
(ii) Provide a copy of the remittance and supporting documentation to the Contracting Officer.
ERMSS (T&M) Contract and SOW Page 22 of 62
(6)(i) All amounts that become payable by the Contractor to the Government under this contract shall bear simple interest from the date due until paid unless paid within 30 days of becoming due. The interest rate shall be the interest rate established by the Secretary of the Treasury, as provided in section 611 of the Contract Disputes Act of 1978 (Public Law 95-563), which is applicable to the period in which the amount becomes due, and then at the rate applicable for each six month period as established by the Secretary until the amount is paid.
(ii) The Government may issue a demand for payment to the Contractor upon finding a debt is due under the contract.
(iii) Final Decisions. The Contracting Officer will issue a final decision as required by
33.211 if—
(A) The Contracting Officer and the Contractor are unable to reach agreement on the existence or amount of a debt in a timely manner;
(B) The Contractor fails to liquidate a debt previously demanded by the Contracting Officer within the timeline specified in the demand for payment unless the amounts were not repaid because the Contractor has requested an installment payment agreement; or
(C) The Contractor requests a deferment of collection on a debt previously demanded by the Contracting Officer (see FAR 32.607-2).
(iv) If a demand for payment was previously issued for the debt, the demand for payment included in the final decision shall identify the same due date as the original demand for payment.
(v) Amounts shall be due at the earliest of the following dates:
(A) The date fixed under this contract.
(B) The date of the first written demand for payment, including any demand for payment resulting from a default termination.
(vi) The interest charge shall be computed for the actual number of calendar days involved beginning on the due date and ending on—
(A) The date on which the designated office receives payment from the Contractor;
(B) The date of issuance of a Government check to the Contractor from which an amount otherwise payable has been withheld as a credit against the contract debt; or
(C) The date on which an amount withheld and applied to the contract debt would otherwise have become payable to the Contractor.
(vii) The interest charge made under this clause may be reduced under the procedures prescribed in 32.608-2 of the Federal Acquisition Regulation in effect on the date of this contract.
(viii) Upon receipt and approval of the invoice designated by the Contractor as the “completion invoice” and supporting documentation, and upon compliance by the Contractor with all terms of this contract, any outstanding balances will be paid within 30 days unless the parties agree otherwise. The completion invoice, and supporting documentation, shall be submitted by the Contractor as promptly as practicable http://www.arnet.gov/far/current/html/Subpart 33_2.html#wp1079912 http://www.arnet.gov/far/current/html/Subpart 32_6.html#wp1031290 http://www.arnet.gov/far/current/html/Subpart 32_6.html#wp1031326
ERMSS (T&M) Contract and SOW Page 23 of 62 following completion of the work under this contract, but in no event later than 1 year (or such longer period as the Contracting Officer may approve in writing) from the date of completion.
(7) Release of claims. The Contractor, and each assignee under an assignment entered into under this contract and in effect at the time of final payment under this contract, shall execute and deliver, at the time of and as a condition precedent to final payment under this contract, a release discharging the Government, its officers, agents, and employees of and from all liabilities, obligations, and claims arising out of or under this contract, subject only to the following exceptions.
(i) Specified claims in stated amounts, or in estimated amounts if the amounts are not susceptible to exact statement by the Contractor.
(ii) Claims, together with reasonable incidental expenses, based upon the liabilities of the Contractor to third parties arising out of performing this contract, that are not known to the Contractor on the date of the execution of the release, and of which the Contractor gives notice in writing to the Contracting Officer not more than 6 years after the date of the release or the date of any notice to the Contractor that the Government is prepared to make final payment, whichever is earlier.
(iii) Claims for reimbursement of costs (other than expenses of the Contractor by reason of its indemnification of the Government against patent liability), including reasonable incidental expenses, incurred by the Contractor under the terms of this contract relating to patents.
(8) Prompt payment. The Government will make payment in accordance with the Prompt Payment Act (31 U.S.C. 3903) and prompt payment regulations at 5 CFR part 1315.
(9) Electronic Funds Transfer (EFT). If the Government makes payment by EFT, see 52.212-5(b) for the appropriate EFT clause.
(10) Discount. In connection with any discount offered for early payment, time shall be computed from the date of the invoice. For the purpose of computing the discount earned, payment shall be considered to have been made on the date that appears on the payment check or the specified payment date if an electronic funds transfer payment is made.
(l) Termination for the Government’s Convenience. The Government reserves the right to terminate this contract, or any part…
This is the start of the file's text. The full file is on GovTribe.