Task Order for Hubzone MATOC

ED9099-09-H-0020

US Army Corps of Engineers ® New Orleans District

Calcasieu River and Pass

Foreshore Dike Construction

Approximate Mile 16.8 to Approximate Mile 20.0

Cameron and Calcasieu Parishes, Louisiana

Construction Solicitation And Specifications

July 2009

ED 09-099

B2CTPLTD

Typewritten Text

SOLICITATION: ED9099-09-H-0020

FOR: Calcasieu River and Pass, Foreshore Dike Construction, Approximate Mile 16.8 to Approximate

Mile 20.0. Cameron and Calcasieu Parishes, LA (ED-09-099)

TO OPEN:

I. NOTE THE AFFIRMATIVE ACTION PROGRAM REQUIREMENT OF THE EQUAL

OPPORTUNITY CLAUSE WHICH MAY APPLY TO THE CONTRACT RESULTING FROM THIS

SOLICITATION.

II. NOTE THE CERTIFICATION OF NONSEGREGATED FACILITIES IN THIS SOLICITATION.

Bidders, offerors and applicants are cautioned to note the "Certification of Non-segregated Facilities" in the solicitation. Failure of a bidder or offeror to agree to the certification will render his bid or offer non-responsive to the terms of solicitations involving awards of contracts exceeding $10,000 which are not exempt from the provisions of the Equal Opportunity clause.

OFFERORS MUST PROVIDE FULL, ACCURATE AND COMPLETE INFORMATION AS REQUIRED BY

THIS SOLICITATION AND ITS ATTACHMENTS. THE PENALTY FOR MAKING FALSE STATEMENTS

IN BIDS IS PRESCRIBED IN 18 U.S.C. 1001. (FAR 52.214-4 APR 1984)

DESCRIPTION AND MAGNITUDE OF WORK: The work consist of construction of a rock foreshore dike with a geotextile fabric base and bank armoring, and all associated incidental work.

CAUTION TO BIDDERS: In delivery of hand-carried proposals, offerors are cautioned to allow sufficient time for delays which may be encountered as a result of frequent trains which are subject to block all access roads to place of bid opening for various lengths of time. Such delays DO NOT permit acceptance or consideration of late proposals.

NOTE: ALL WORK UNDER THESE SPECIFICATIONS SHALL BE PERFORMED IN ACCORDANCE

WITH THE PROVISIONS OF EM 385-1-1 "CORPS OF ENGINEERS SAFETY AND HEALTH

REQUIREMENTS MANUAL", September 2008 Edition. The manual can be accessed at the following link:

http://140.194.76.129/publications/eng-manuals/em385-1-1/2008_English/entire_2008_English.pdf

ED 09-099

http://140.194.76.129/publications/eng-manuals/em385-1-1/2008_English/entire_2008_English.pdf

Calcasieu River and Pass Foreshore Construction, Approximate Mile 16.8 to Approximate Mile 20.0, Cameron and Calcasieu Parishes, LA

MTC-i ED 09-099

MAIN TABLE OF CONTENTS

Division 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

00010 Solicitation, Offer and Award

SF-1442

Bidding Schedule

00100 Instructions to Bidders

00600 Representations and Certifications

00700 Contract Clauses

Division 01 - GENERAL REQUIREMENTS

01100 General Provisions

01 33 00 Submittal Procedures

01 45 02.00 10 Quality Control System (QCS)

01 45 04.00 10 Contractor Quality Control

01 57 20.00 12 Environmental Protection

01 78 02.00 10 Closeout Submittals

Division 02 – EXISTING CONDITIONS

02 21 10.00 12 Surveys

DIVISION 31 - EARTHWORK

31 05 19.04 12 Reinforcement and Separator Geotextile

DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION

35 31 19.03 12 Stone

B2CTPLTD

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

2. TYPE OF SOLICITATION

X

SEALED BID (IFB)

NEGOTIATED (RFP)

3. DATE ISSUED

07/27/09

PAGE OF PAGES

1 2 IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

7. ISSUED BY CODE

U.S. Army Corps of Engineers New Orleans District Attn: CEMVN-CT-W (Lindsay Dawson) 7400 Leake Ave., Room 172 New Orleans, LA 70118-3651

8. ADDRESS OFFER TO

U.S. Army Corps of Engineers New Orleans District Attn: CEMVN-CT-W (Lindsay Dawson) 7400 Leake Ave., Room 172 New Orleans, LA 70118-3651

9. FOR INFORMATION

CALL:

a. NAME

Lindsay T. Dawson

b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

(504) 862-2125

SOLICITATION

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)

Calcasieu River and Pass Foreshore Dike Construction Approximate Mile 16.8 to Approximate Mile 20.0 Cameron and Calcasieu Parishes, Louisiana

THIS PROJECT IS 100% FUNDED BY RECOVERY FUNDS

11. The Contractor shall begin performance 10 calendar days and complete it within 300 calendar days after receiving

X notice to proceed. This performance period is award, X mandatory negotiable. (See .)

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12b).

X YES NO

12b. CALENDAR DAYS

13. ADDITIONAL SOLICITATION REQUIREMENTS:

d. Offers providing less than 30 calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

c. All offers are subject to the (1) work reqiurements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

b. An offer guarantee X is, is not required.

a. Sealed offers in original and 0 copies to perform the work required are due at the place specified in Item 8 by 2:00 PM (hour) local time 08/17/09 (date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

NSN 7540-01-155-3212 STANDARD FORM 1442 (REV. 4-85)

Prescribed by GSA - FAR (48 CFR) 53.236-1(d)

4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.

OFFER (Must be fully completed by offeror)

15. TELEPHONE NO. (Include area code)14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)

16. REMITTANCE ADDRESS (Include only if different than Item 14.)

CODE FACILITY CODE

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within calendar days after the date offers are due. (Insert any number equal to or greater than the minimum re-quirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)

20. SIGNATURE 20c. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c) ( ) 41 U.S.C. 253(c) ( )

26. ADMINISTERED BY CODE

Layfayette Area Office U.S. Army Corps of Engineers 646 Cajundome Blvd.

Lafayette, LA 70506

27. PAYMENT WILL BE MADE BY

USAED New Orleans c/o USACE Finance Center (UFC) Attn: CEFC-AO-P 5720 Integrity Dr.

Millington, TN 38054-5005

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)

28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return copies to issuing office.) Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract.

The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

31a. NAME OF CONTRACTING OFFICER (Type or print)

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 30c. DATE

BY

STANDARD FORM 1442 (REV. 4-85) BACK

B2CTPLTD

SECTION 00010 - BIDDING SCHEDULE

Calcasieu River & Pass – Foreshore Dike Construction, Approximate Mile 16.8 to Approximate Mile 20.0, Cameron and Calcasieu Parishes, LA

Item DESCRIPTION Estimated Quantity Unit Unit Price Estimated Amount

Base Reach

0001 Mobilization and Demobilization 1 LS

0002 Armor Stone 77,500 TON

0003 Core Material 63,000 Ton

0004 Reinforcement Geotextile - Reach 1 18,000 SY

0005 Reinforcement Geotextile - Reach 2 and 3 47,500 SY

0006 Separator Geotextile 38,000 SY

0007 Flotation Channel 1 LS

Optional Reach

0008 Armor Stone (Optional Item) 33,000 TON

0009 Core Material (Optional Item) 41,000 TON

00010 Reinforcement Geotextile (Optional Item) 31,000 SY

0011 Separator Geotextile (Optional Item) 25,000 SY

0012 Flotation Channel (Optional Item) 1 LS

TOTAL $

Award will be made as a whole to one bidder.

NOTE 1: Bidders shall furnish unit prices for each item listed in the Schedule requiring a unit price. If the bidder fails to insert a unit price in the appropriate blank for required item(s), but does furnish an extended total, or an estimated amount for such item(s), the Government shall deem the unit price to be the quotient obtained by dividing the extended amount for that line item by the quantity. IF A BIDDER OMITS BOTH THE UNIT PRICE

AND THE EXTENDED TOTAL OR ESTIMATED AMOUNT FOR ANY ITEM, ITS BID

SHALL BE DECLARED NON-RESPONSIVE AND THEREFORE INELIGIBLE FOR

AWARD.

NOTE 2: Any bid may be rejected if the Contracting Officer determines in writing that it is unreasonable as to price. Unreasonableness of price includes not only total price of bid, but the price for individual line items as well. Any bid may be rejected if the prices for any line items or sub line items are materially unbalanced (See FAR 14.404-2).

ED9099-09-H-0020 00010-3 Ed 09-099

ED9099-09-H-0020 00010-4 Ed 09-099

NOTE 3: THE NOTICE TO PROCEED (NTP): The successful bidder is advised that performance and payment bonds shall be submitted in accordance with the time frame in block 12B of SF 1442. The NTP will be issued immediately after verification of acceptable performance and payment bonds. Within seven (7) days after issuance of the NTP, the Contractor shall initiate a meeting to discuss the submittal process with the Area or Resident Engineer or his authorized representative. Physical work cannot start until the Accident Prevention Program, Contractor Quality Control Plan, and other submittals which may be required, have been submitted and approved and all preliminary meetings called for under the contract, have been conducted.

NOTE 4: OPTIONAL ITEMS. The Government may require the delivery of the numbered line item(s), identified in the schedule as optional items, in the quantities and prices stated in the schedule. The Contracting Officer may exercise the options by written notice to the Contractor. Bidders shall bid on all items including optional items (see “Evaluation of Options” FAR 52.217-5). Failure to bid on all items will result in a non-responsive bid.

NOTE 5: EVALUATION OF OPTIONS (FAR 52.217-5 JUL 1990). The Government will evaluate offers for award purposes by adding the total price for all options to the total price for this basic requirement. Evaluation of options will not obligate the Government to exercise the option(s).

NOTE 6: RAPID VENDOR PAYMENT: Web based instructions for the submission of invoices; http://www.mvn.usace.army.mil/ebs/rapid_vendor_payment.asp http://www.mvn.usace.army.mil/ebs/rapid_vendor_payment.asp

Section Table of Contents

SECTION 00700 - CONTRACT CLAUSES

1. COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK 1

2. LIQUIDATED DAMAGES 1

3. CONTRACT DRAWINGS AND SPECIFICATIONS 1

4. PHYSICAL DATA 3

5. LAYOUT OF WORK 3

6. QUANTITY SURVEYS 4

7. OBSTRUCTION OF NAVIGABLE WATERWAYS 5

8. PAYMENT FOR MOBILIZATION AND DEMOBILIZATION 5

9. EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE 6

10. PERFORMANCE OF WORK BY CONTRACTOR 7

11. VARIATION IN ESTIMATED QUANTITIES 7

12. SCHEDULES FOR CONSTRUCTION CONTRACTS 7

13. WHISTLEBLOWER PROTECTIONS UNDER THE AMERICAN 8

14. AMERICAN RECOVERY AND REINVESTMENT ACT—REPORTING REQUIREMENTS 9

15. NOTICE OF REQUIRED USE OF AMERICAN IRON, STEEL, AND OTHER

MANUFACTURED GOODS—BUY AMERICAN ACT—CONSTRUCTION MATERIALS 12

16. AUDIT AND RECORDS—NEGOTIATION. ALTERNATE I 16

ED9099-09-H-0020 00700-a ED 09-099

SECTION 00700 - CONTRACT CLAUSES

1. COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (FAR

52.211-10 - 1984 APR)

The Contractor shall be required to

(a) Commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed,

(b) Prosecute the work diligently, and

(c) Complete the entire work ready for use not later than 300 calendar days after the date of receipt by him of notice to proceed. The time stated for completion shall include final cleanup of the premises.

(End of Clause)

NOTE 1: The 300 calendar days specified in subparagraph (c) is for the Base Reach. If the work for the Optional Reach is executed, then an additional 85 calendar days are added to this contract for that additional work.

NOTE 2: The term “work” includes tasks such as submission of submittals, performance of preliminary and/or Before Construction surveys, or mobilization of rock, flotation access; and does not have to be placement of stone.

NOTE 3: The Contractor is hereby informed that time allowed for completion of work has been established as the shortest reasonable duration and that it shall make any and all provisions necessary (multiple crews, overtime, concurrent operations, etc.) to accomplish the work within the available time period.

2. LIQUIDATED DAMAGES - CONSTRUCTION (FAR 52.211-12 – SEPT 2000)

(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $2,110.00/day for each calendar day of delay until the work is completed or accepted.

(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.

3. CONTRACT DRAWINGS AND SPECIFICATIONS (DFARS 252.236-7001 –

AUG 2000)

ED9099-09-H-0020 00700-1 ED 09-099

(a) The Government will provide to the Contractor, without charge, one set of contract drawings and specifications, except publications incorporated into the technical provisions by reference, in electronic or paper media as chosen by the Contracting Officer.

(b) The Contractor shall --

(1) Check all drawings furnished immediately upon receipt;

(2) Compare all drawings and verify the figures before laying out the work;

(3) Promptly notify the Contracting Officer of any discrepancies;

(4) Be responsible for any errors that might have been avoided by complying with this paragraph (b); and

(5) Reproduce and print contract drawings and specifications as needed.

(c) In general --

(1) Large-scale drawings shall govern small-scale drawings; and

(2) The Contractor shall follow figures marked on drawings in preference to scale measurements.

(d) Omissions from the drawings or specifications or the mis-description of details of work that are manifestly necessary to carry out the intent of the drawings and specifications, or that are customarily performed, shall not relieve the Contractor from performing such omitted or mis-described details of the work. The Contractor shall perform such details as if fully and correctly set forth and described in the drawings and specifications.

(e) The work shall conform to the specifications and the contract drawings identified on the following index of drawings:

Title File Drawing No.

Calcasieu River and Pass, Foreshore H-16-47032 1 thru 5 of 5 Construction, Approximate Mile 16.8 to Approximate Mile 20.0, Cameron and Calcasieu Parishes, LA

ED9099-09-H-0020 00700-2 ED 09-099

4. PHYSICAL DATA (FAR 52.236-4 - 1984 APR)

Data and information furnished or referred to below is for the Contractor's information.

The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.

(a) The indications of physical conditions on the drawings and in the specifications are the result of site investigations by surveys and borings.

(b) Weather Conditions. Data on weather conditions may be obtained from the National Weather Services.

(c) Transportation Facilities. The work site may be reached with Floating Plant via the Gulf of Mexico, or the GIWW to the Calcasieu River.

(d) Condition of Channel. Depths and channel widths within the Calcasieu River main channel are adequate for movement of floating plant. Since the required worksite is inshore of the main channel, flotation channel excavation will be required to access the immediate worksite.

(e) Channel Traffic. Traffic in the channel consists of tugs, heavy barge tows, ocean going vessels, LNG and LPG tankers, and small boats.

(f) Obstruction of Channel. The Government will not undertake to keep the channel free from vessels or other obstructions, except to the extent of such regulations, if any, as may be prescribed by the Secretary of the Army, in accordance with the provisions of Section 7 of the River and Harbor Act approved 8 August 1917. The Contractor shall conduct the work in such manner as to obstruct navigation as little as possible, and in case the Contractor's plant so obstructs the channel as to make difficult or endanger the passage of vessels, said plant shall be promptly moved on the approach of any vessel to such an extent as may be necessary to afford a practicable passage. Upon completion of the work, the Contractor shall promptly remove its plant, including ranges, buoys, piles and other markers placed by him/her under the contract in navigable water or on shore.

(g) Estimates of quantities involved in certain items of work for which bids are being solicited on a lump sum or job basis have been made for the use of the Government. Copies of these quantity estimates may be viewed/obtained by contacting the District Engineer, Attn: Contracting Officer, CEMVN-CT, P.O. Box 60267, New Orleans, Louisiana 70160-0267. It is expressly understood that the accuracy of these estimates is in no way warranted and that the furnishing of this information to a bidder will not relieve him of his responsibility to estimate the quantities involved.

5. LAYOUT OF WORK (FAR 52.236-17 - APR 1984)

ED9099-09-H-0020 00700-3 ED 09-099

The Contractor shall lay out its work from Government established base lines and bench marks indicated on the drawings, and shall be responsible for all measurements in connection with the layout. The Contractor shall furnish, at its own expense, all stakes, templates, platforms, equipment, tools, materials, and labor required to lay out any part of the work. The Contractor shall be responsible for executing the work to the lines and grades that may be established or indicated by the Contracting Officer. The Contractor shall also be responsible for maintaining and preserving all stakes and other marks established by the Contracting Officer until authorized to remove them. If such marks are destroyed by the Contractor or through its negligence before their removal is authorized, the Contracting Officer may replace them and deduct the expense of replacement from any amounts due or to become due to the Contractor.

NOTE: In lieu of the "baselines and benchmarks" mentioned in the paragraph entitled "LAYOUT OF WORK", the Contractor shall layout and monitors his work from the gages, channel centerline, and dike centerline reference points shown on the drawings.

6. QUANTITY SURVEYS (FAR 52.236-16 ALTERNATE 1 - 1984 APR

(a) Quantity surveys shall be conducted, and the data derived from these surveys shall be used in computing the quantities of work performed and the actual construction completed and in place.

(b) The Contractor shall conduct the original and final surveys and surveys for any periods for which progress payments are requested. All these surveys shall be conducted under the direction of a representative of the Contracting Officer, unless the Contracting Officer waives this requirement in a specific instance.

The Government shall make such computations as are necessary to determine the quantities of work performed or finally in place. The Contractor shall make the computations based on the surveys for any periods for which progress payments are requested.

(c) Promptly upon completing a survey, the Contractor shall furnish the originals of all field notes and all other records relating to the survey or to the layout of the work to the Contracting Officer, who shall use them as necessary to determine the amount of progress payments. The Contractor shall retain copies of all such material furnished to the Contracting Officer.

NOTE: In subparagraph 6.(c), the word “Promptly” is defined as “within three (3) calendar days.

ED9099-09-H-0020 00700-4 ED 09-099

7. OBSTRUCTION OF NAVIGABLE WATERWAYS (DFARS 252.236-7002 - DEC

91)

(a) The Contractor shall:

(1) Promptly recover and remove any material, plant, machinery, or appliance that the Contractor loses, dumps, throws overboard, sinks, or misplaces, and which, in the opinion of the Contracting Officer, may be dangerous to or obstruct navigation;

(2) Give immediate notice, with description and locations of any such obstructions, to the Contracting Officer; and

(3) When required by the Contracting Officer, mark or buoy such obstructions until the same are removed.

(b) The Contracting Officer may:

(1) Remove the obstructions by contract or otherwise should the Contractor refuse, neglect, or delay compliance with paragraph (a) of this clause; and

(2) Deduct the cost of removal from any monies due or to become due to the Contractor; or

(3) Recover the cost of removal under the Contractor's bond.

(c) The Contractor's liability for the removal of a vessel wrecked or sunk without fault or negligence is limited to that provided in Sections 15, 19 and 20 of the River and Harbor Act of March 3, 1899 (33 U.S.C.410 et.seq.).

8. PAYMENT FOR MOBILIZATION AND DEMOBILIZATION (DFARS 252.236-

7004 - 1991 DEC)

(a) The Government will pay all costs for the mobilization and demobilization of all of the Contractor's plant and equipment at the contract lump sum price for this item.

(1) Sixty percent (60%) of the lump sum price upon completion of the Contractor's mobilization at the work site.

(2) The remaining forty percent (40%) upon completion of demobilization.

ED9099-09-H-0020 00700-5 ED 09-099

(b) The Contracting Officer may require the Contractor to furnish cost data to justify this portion of the bid if the Contracting Officer believes that the percentages in paragraphs (a)(1) and (a)(2) of this clause do not bear a reasonable relation to the cost of the work in this contract.

(1) Failure to justify such price to the satisfaction of the Contracting Officer will result in payment, as determined by the Contracting Officer, of-

(i) Actual mobilization costs at completion of mobilization;

(ii) Actual demobilization costs at completion of demobilization; and

(iii) The remainder of this item in the final payment under this contract.

(2) The Contracting Officer's determination of the actual costs in paragraph (b)(1) of this clause is not subject to appeal.

9. EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE (EFARS

52.231-5000 - MAR 95)

(a) This clause does not apply to terminations. See EFARS 52.249-5000, Basis For Settlement of Proposals, and FAR Part 49.

(b) Allowable cost for construction and marine plant and equipment in sound workable condition, owned or controlled and furnished by a Contractor or Subcontractor at any tier shall be based on actual cost data for each piece of equipment or groups of similar serial and series for which the Government can determine both ownership and operating costs from the Contractor's accounting records. When both ownership and operating costs cannot be determined for any piece of equipment or groups of similar serial or series equipment from the Contractor's accounting records, costs for that equipment shall be based upon the applicable provisions of EP 1110-1-8, "Construction Equipment Ownership and Operating Expense Schedule," Region III. Working conditions shall be considered to be average for determining equipment rates using the schedule unless specified otherwise by the Contracting Officer. For equipment not included in the schedule, rates for comparable pieces of equipment may be used or a rate may be developed using the formula provided in the schedule. For forward pricing, the schedule in effect at the time of negotiations shall apply. For retroactive pricing, the schedule in effect at the time the work was performed shall apply.

(c) Equipment rental costs are allowable, subject to the provisions of FAR 31.105(d) (ii) and FAR 31.205-36. Rates for equipment rented from an organization under common control, lease-purchase arrangements, and sale-leaseback arrangements will be determined using the schedule, except that

ED9099-09-H-0020 00700-6 ED 09-099

actual rates will be used for equipment leased from an organization under common control that has an established practice of leasing the same or similar equipment to unaffiliated lessees.

(d) When actual equipment costs are proposed and the total amount of the pricing action exceeds the small purchase threshold, the Contracting Officer shall request the Contractor to submit either certified cost or pricing data, or partial/limited data, as appropriate. The data shall be submitted on Standard Form 1411, Contract Pricing Proposal Cover Sheet.

NOTE1: Costs for repairs or overhauling are not allowed.

NOTE 2: A copy of the "EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE" CD can be obtained from the Government Printing Office (GPO) by calling (202) 512-1800 or through the Internet site

WWW.GPOACCESS.GOV/INDEX.HTML.

10. PERFORMANCE OF WORK BY CONTRACTOR (FAR 52.236-1 - 1984 APR)

The Contractor shall perform on the site, and with its own organization, work equivalent to at least twenty percent (20%) of the total amount of the work to be performed under the contract. This percentage may be reduced by a supplemental agreement to this contract, if, during performing the work, the Contractor requests a reduction and the Contracting Officer determines that the reduction would be to the advantage of the Government.

11. VARIATION IN ESTIMATED QUANTITIES (FAR 52.211-18- APR 1984)

If the quantity of a unit-priced item in this contract is an estimated quantity and the actual quantity of the unit-priced item varies more than 15 percent above or below the estimated quantity, an equitable adjustment in the contract price shall be made upon demand of either party. The equitable adjustment shall be based upon any increase or decrease in costs due solely to the variation above 115 percent or below 85 percent of the estimated quantity. If the quantity variation is such as to cause an increase in the time necessary for completion, the Contractor may request, in writing, an extension of time, to be received by the Contracting Officer within 10 days from the beginning of the delay, or within such further period as may be granted by the Contracting Officer before the date of final settlement of the contract. Upon the receipt of a written request for an extension, the Contracting Officer shall ascertain the facts and make an adjustment for extending the completion date as, in the judgment of the Contracting Officer, is justified.

12. SCHEDULES FOR CONSTRUCTION CONTRACTS (FAR 52.236-14 - 1984

APR).

ED9099-09-H-0020 00700-7 ED 09-099

http://www.gpoaccess.gov/index.html

(a) The Contractor shall, within five days after the work commences on the contract or another period of time determined by the Contracting Officer, prepare and submit to the Contracting Officer for approval three copies of a practicable schedule showing the order in which the Contractor proposes to perform the work, and the dates on which the Contractor contemplates starting and completing the several salient features of the work (including acquiring materials, plant, and equipment). The schedule shall be in the form of a progress chart of suitable scale to indicate appropriately the percentage of work scheduled for completion by any given date during the period. If the Contractor fails to submit a schedule within the time prescribed, the Contracting Officer may withhold approval of progress payments until the Contractor submits the required schedule.

(b) The Contractor shall enter the actual progress on the chart as directed by the Contracting Officer, and upon doing so shall immediately deliver three copies of the annotated schedule to the Contracting Officer. If, in the opinion of the Contracting Officer, the Contractor falls behind the approved schedule, the Contractor shall take steps necessary to improve its progress, including those that may be required by the Contracting Officer, without additional cost to the Government. In this circumstance, the Contracting Officer may require the Contractor to increase the number of shifts, overtime operations, days of work, and/or the amount of construction plant, and to submit for approval any supplementary schedule or schedules in chart form as the Contracting Officer deems necessary to demonstrate how the approved rate of progress will be regained.

(c) Failure of the Contractor to comply with the requirements of the Contracting Officer under this clause shall be grounds for a determination by the Contracting Officer that the Contractor is not prosecuting the work with sufficient diligence to ensure completion within the time specified in the contract. Upon making this determination, the Contracting Officer may terminate the Contractor’s right to proceed with the work, or any separable part of it, in accordance with the default terms of this contract.

13. WHISTLEBLOWER PROTECTIONS UNDER THE AMERICAN RECOVERY

AND REINVESTMENT ACT OF 2009 (MAR 2009 - 52.203-15)

(a) The Contractor shall post notice of employees rights and remedies for whistleblower protections provided under section 1553 of the American Recovery and Reinvestment Act of 2009 (Pub. L. 111-5).

(b) The Contractor shall include the substance of this clause including this paragraph (b) in all subcontracts.

(End of clause)

ED9099-09-H-0020 00700-8 ED 09-099

14. AMERICAN RECOVERY AND REINVESTMENT ACT—REPORTING

REQUIREMENTS ( 52.204-11 Mar 2009)

(a) Definitions. As used in this clause— “Contract”, as defined in FAR 2.101, means a mutually binding legal relationship obligating the seller to furnish the supplies or services (including construction) and the buyer to pay for them. It includes all types of commitments that obligate the Government to an expenditure of appropriated funds and that, except as otherwise authorized, are in writing. In addition to bilateral instruments, contracts include (but are not limited to) awards and notices of awards; job orders or task letters issued under basic ordering agreements; letter contracts; orders, such as purchase orders, under which the contract becomes effective by written acceptance or performance; and bilateral contract modifications. Contracts do not include grants and cooperative agreements covered by 31 U.S.C. 6301, et seq. For discussion of various types of contracts, see FAR Part 16.

“First-tier subcontract” means a subcontract awarded directly by a Federal Government prime contractor whose contract is funded by the Recovery Act.

“Jobs created” means an estimate of those new positions created and filled, or previously existing unfilled positions that are filled, as a result of funding by the American Recovery and Reinvestment Act of 2009 (Recovery Act). This definition covers only prime contractor positions established in the United States and outlying areas (see definition in FAR 2.101). The number shall be expressed as “full-time equivalent” (FTE), calculated cumulatively as all hours worked divided by the total number of hours in a full-time schedule, as defined by the contractor. For instance, two full-time employees and one part-time employee working half days would be reported as

2.5 FTE in each calendar quarter.

“Jobs retained” means an estimate of those previously existing filled positions that are retained as a result of funding by the American Recovery and Reinvestment Act of 2009 (Recovery Act). This definition covers only prime contractor positions established in the United States and outlying areas (see definition in FAR 2.101). The number shall be expressed as “full-time equivalent” (FTE), calculated cumulatively as all hours worked divided by the total number of hours in a full-time schedule, as defined by the contractor. For instance, two full-time employees and one part-time employee working half days would be reported as 2.5 FTE in each calendar quarter.

“Total compensation” means the cash and noncash dollar value earned by the executive during the contractor’s past fiscal year of the following (for more information see 17 CFR 229.402(c)(2)):

(1) Salary and bonus.

ED9099-09-H-0020 00700-9 ED 09-099

http://www.arnet.gov/far/current/html/Subpart 2_1.html#wp1145508 http://uscode.house.gov/lawrevisioncounsel.shtml http://www.arnet.gov/far/current/html/FARTOCP16.html#wp226194 http://www.arnet.gov/far/current/html/Subpart 2_1.html#wp1145508

(2) Awards of stock, stock options, and stock appreciation rights. Use the dollar amount recognized for financial statement reporting purposes with respect to the fiscal year in accordance with the Statement of Financial Accounting Standards No. 123 (Revised 2004) (FAS 123R), Shared Based Payments.

(3) Earnings for services under non-equity incentive plans. Does not include group life, health, hospitalization or medical reimbursement plans that do not discriminate in favor of executives, and are available generally to all salaried employees.

(4) Change in pension value. This is the change in present value of defined benefit and actuarial pension plans.

(5) Above-market earnings on deferred compensation which is not tax-qualified.

(6) Other compensation. For example, severance, termination payments, value of life insurance paid on behalf of the employee, perquisites or property if the value for the executive exceeds $10,000.

(b) This contract requires the contractor to provide products and/or services that are funded under the American Recovery and Reinvestment Act of 2009 (Recovery Act).

Section 1512(c) of the Recovery Act requires each contractor to report on its use of Recovery Act funds under this contract. These reports will be made available to the public.

(c) Reports from contractors for all work funded, in whole or in part, by the Recovery Act, and for which an invoice is submitted prior to June 30, 2009, are due no later than July 10, 2009. Thereafter, reports shall be submitted no later than the 10th day after the end of each calendar quarter.

(d) The Contractor shall report the following information, using the online reporting tool available at www.FederalReporting.gov.

(1) The Government contract and order number, as applicable.

(2) The amount of Recovery Act funds invoiced by the contractor for the reporting period. A cumulative amount from all the reports submitted for this action will be maintained by the government’s on-line reporting tool.

(3) A list of all significant services performed or supplies delivered, including construction, for which the contractor invoiced in this calendar quarter.

(4) Program or project title, if any.

(5) A description of the overall purpose and expected outcomes or results of the contract, including significant deliverables and, if appropriate, associated units of measure.

(6) An assessment of the contractor’s progress towards the completion of the overall purpose and expected outcomes or results of the contract (i.e., not started, less than 50 percent completed, completed 50 percent or more, or fully completed). This covers the contract (or portion thereof) funded by the Recovery Act.

ED9099-09-H-0020 00700-10 ED 09-099

(7) A narrative description of the employment impact of work funded by the Recovery Act. This narrative should be cumulative for each calendar quarter and only address the impact on the contractor’s workforce. At a minimum, the contractor shall provide—

(i) A brief description of the types of jobs created and jobs retained in the United States and outlying areas (see definition in FAR 2.101). This description may rely on job titles, broader labor categories, or the contractor’s existing practice for describing jobs as long as the terms used are widely understood and describe the general nature of the work; and

(ii) An estimate of the number of jobs created and jobs retained by the prime contractor, in the United States and outlying areas. A job cannot be reported as both created and retained.

(8) Names and total compensation of each of the five most highly compensated officers of the Contractor for the calendar year in which the contract is awarded if—

(i) In the Contractor’s preceding fiscal year, the Contractor received—

(A) 80 percent or more of its annual gross revenues from Federal contracts

(and subcontracts), loans, grants (and subgrants) and cooperative agreements; and

(B) $25,000,000 or more in annual gross revenues from Federal contracts (and subcontracts), loans, grants (and subgrants) and cooperative agreements; and

(ii) The public does not have access to information about the compensation of the senior executives through periodic reports filed under section 13(a) or 15(d) of the Securities Exchange Act of 1934 (15 U.S.C. 78m(a), 78o(d)) or section 6104 of the Internal Revenue Code of 1986.

(9) For subcontracts valued at less than $25,000 or any subcontracts awarded to an individual, or subcontracts awarded to a subcontractor that in the previous tax year had gross income under $300,000, the Contractor shall only report the aggregate number of such first tier subcontracts awarded in the quarter and their aggregate total dollar amount.

(10) For any first-tier subcontract funded in whole or in part under the Recovery Act, that is over $25,000 and not subject to reporting under paragraph 9, the contractor shall require the subcontractor to provide the information described in (i), (ix), (x), and

(xi) below to the contractor for the purposes of the quarterly report. The contractor shall advise the subcontractor that the information will be made available to the public as required by section 1512 of the Recovery Act. The contractor shall provide detailed information on these first-tier subcontracts as follows:

(i) Unique identifier (DUNS Number) for the subcontractor receiving the award and for the subcontractor’s parent company, if the subcontractor has a parent company.

(ii) Name of the subcontractor.

(iii) Amount of the subcontract award.

ED9099-09-H-0020 00700-11 ED 09-099

http://uscode.house.gov/lawrevisioncounsel.shtml

(iv) Date of the subcontract award.

(v) The applicable North American Industry Classification System (NAICS) code.

(vi) Funding agency.

(vii) A description of the products or services (including construction) being provided under the subcontract, including the overall purpose and expected outcomes or results of the subcontract.

(viii) Subcontract number (the contract number assigned by the prime contractor).

(ix) Subcontractor’s physical address including street address, city, state, and country. Also include the nine-digit zip code and congressional district if applicable.

(x) Subcontract primary performance location including street address, city, state, and country. Also include the nine-digit zip code and congressional district if applicable.

(xi) Names and total compensation of each of the subcontractor’s five most highly compensated officers, for the calendar year in which the subcontract is awarded if—

(A) In the subcontractor’s preceding fiscal year, the subcontractor received—

(1) 80 percent or more of its annual gross revenues in Federal contracts

(and subcontracts), loans, grants (and subgrants), and cooperative agreements; and

(2) $25,000,000 or more in annual gross revenues from Federal contracts

(and subcontracts), loans, grants (and subgrants), and cooperative agreements; and

(B) The public does not have access to information about the compensation of the senior executives through periodic reports filed under section 13(a) or 15(d) of the Securities Exchange Act of 1934 (15 U.S.C. 78m(a), 78o(d)) or section 6104 of the Internal Revenue Code of 1986.

(End of clause)

15. REQUIRED USE OF AMERICAN IRON, STEEL, AND OTHER

MANUFACTURED GOODS—BUY AMERICAN ACT—CONSTRUCTION MATERIALS

UNDER TRADE AGREEMENTS (52.225-23 Mar 2009)

(a) Definitions. As used in this clause— “Construction material” means an article, material, or supply brought to the construction site by the Contractor or subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction

ED9099-09-H-0020 00700-12 ED 09-099

site. Materials purchased directly by the Government are supplies, not construction material.

“Domestic construction material” means—

(1) An unmanufactured construction material mined or produced in the United

States; or

(2) A construction material manufactured in the United States.

“Foreign construction material” means a construction material other than a domestic construction material.

“Free trade agreement (FTA) country construction material” means a construction material that—

(1) Is wholly the growth, product, or manufacture of an FTA country; or

(2) In the case of a construction material that consists in whole or in part of materials from another country, has been substantially transformed in an FTA country into a new and different construction material distinct from the materials from which it was transformed.

“Least developed country construction material” means a construction material that—

(1) Is wholly the growth, product, or manufacture of a least developed country; or

(2) In the case of a construction material that consists in whole or in part of materials from another country, has been substantially transformed in a least developed country into a new and different construction material distinct from the materials from which it was transformed.

“Manufactured construction material” means any construction material that is not unmanufactured construction material.

“Recovery Act designated country” means any of the following countries:

(1) A World Trade Organization Government Procurement Agreement (WTO GPA) country (Aruba, Austria, Belgium, Bulgaria, Canada, Cyprus, Czech Republic, Denmark, Estonia, Finland, France, Germany, Greece, Hong Kong, Hungary, Iceland, Ireland, Israel, Italy, Japan, Korea (Republic of), Latvia, Liechtenstein, Lithuania, Luxembourg, Malta, Netherlands, Norway, Poland, Portugal, Romania, Singapore, Slovak Republic, Slovenia, Spain, Sweden, Switzerland, or United Kingdom);

(2) A Free Trade Agreement country (FTA)(Australia, Bahrain, Canada, Chile, Costa Rica, Dominican Republic, El Salvador, Guatemala, Honduras, Israel, Mexico, Morocco, Nicaragua, Oman, Peru, or Singapore); or

(3) A least developed country (Afghanistan, Angola, Bangladesh, Benin, Bhutan, Burkina Faso, Burundi, Cambodia, Central African Republic, Chad, Comoros, Democratic Republic of Congo, Djibouti, East Timor, Equatorial Guinea, Eritrea, Ethiopia, Gambia, Guinea, Guinea-Bissau, Haiti, Kiribati, Laos, Lesotho, Liberia, Madagascar, Malawi, Maldives, Mali, Mauritania, Mozambique, Nepal, Niger, Rwanda, ED9099-09-H-0020 00700-13 ED 09-099

Samoa, Sao Tome and Principe, Senegal, Sierra Leone, Solomon Islands, Somalia, Tanzania, Togo, Tuvalu, Uganda, Vanuatu, Yemen, or Zambia).

“Recovery Act designated country construction material” means a construction material that is a WTO GPA country construction material, an FTA country construction material, or a least developed country construction material.

“Steel” means an alloy that includes at least 50 percent iron, between .02 and 2 percent carbon, and may include other elements.

“United States” means the 50 States, the District of Columbia, and outlying areas.

“Unmanufactured construction material” means raw material brought to the construction site for incorporation into the building or work that has not been—

(1) Processed into a specific form and shape; or

(2) Combined with other raw material to create a material that has different properties than the properties of the individual raw materials.

“WTO GPA country construction material” means a construction material that—

(1) Is wholly the growth, product, or manufacture of a WTO GPA country; or

(2) In the case of a construction material that consists in whole or in part of materials from another country, has been substantially transformed in a WTO GPA country into a new and different construction material distinct from the materials from which it was transformed.

(b) Construction materials.

(1) The restrictions of section 1605 of the American Recovery and Reinvestment

Act of 2009 (Pub. L. 111-5) (Recovery Act) and the Buy American Act (41 U.S.C. 10a– 10d) do not apply to Recovery Act designated country construction material. Consistent with U.S. obligations under international agreements, this clause implements—

(i) Section 1605 of the Recovery Act by requiring, unless an exception applies, that all iron, steel, and other manufactured goods used as construction material in the project are produced in the United States; and

(ii) The Buy American Act by providing a preference for unmanufactured domestic construction material.

(2) The Contractor shall use only domestic or Recovery Act designated country construction material in performing this contract, except as provided in paragraphs (b)(3) and (b)(4) of this clause.

(3) The requirement in paragraph (b)(2) of this clause does not apply to the construction materials or components listed by the Government as follows:

[Contracting Officer to list applicable excepted materials or indicate “none”.]

(4) The Contracting Officer may add other construction material to the list in paragraph (b)(3) of this clause if the Government determines that—

(i) The cost of domestic construction material would be unreasonable.

ED9099-09-H-0020 00700-14 ED 09-099

(A) The cost of domestic iron, steel, or other manufactured goods used as construction material is unreasonable when the cumulative cost of such material will increase the overall cost of the contract by more than 25 percent;

(B) The cost of unmanufactured construction material is unreasonable when the cost of such material exceeds the cost of foreign material by more than 6 percent;

(ii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality; or

(iii) The application of the restriction of section 1605 of the Recovery Act or the Buy American Act to a particular construction material would be inconsistent with the public interest.

(c) Request for determination of inapplicability of section 1605 of the Recovery Act or the Buy American Act.

(1)(i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(4) of this clause shall include adequate information for Government evaluation of the request, including—

(A) A description of the foreign and domestic construction materials;

(B) Unit of measure;

(C) Quantity;

(D) Cost;

(E) Time of delivery or availability;

(F) Location of the construction project;

(G) Name and address of the proposed supplier; and

(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(4) of this clause.

(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed cost comparison table in the format in paragraph (d) of this clause.

(iii) The cost of construction material shall include all delivery costs to the construction site and any applicable duty.

(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.

(2) If the Government determines after contract award that an exception to section 1605 of the Recovery Act or the Buy American Act applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify

ED9099-09-H-0020 00700-15 ED 09-099

the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable cost of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(4)(i) of this clause.

(3) Unless the Government determines that an exception to the section 1605 of the Recovery Act or the Buy American Act applies, use of foreign construction material other than that covered by trade agreements is noncompliant with the applicable Act.

(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:

Construction Material Description Unit of Measure Quantity Cost (Dollars)*

Item 1:

Foreign construction material

Domes…