ED0036972-PIP-II CDS Tunnel Warm Piping Installation SOW.pdf
PDF 2 MB Posted
- Attached to
- PIP-II CDS Tunnel Warm Piping Installation
- Solicitation number
- PIPII-366552-STE
About this file
This is a Statement of Work (SOW) for the PIP-II CDS Tunnel Warm Piping Installation project at Fermi National Accelerator Laboratory. The project involves installing a cryogenic distribution system (CDS) warm piping system within the PIP-II Linac Tunnel, which will provide room temperature helium gas to the accelerator and recover cold helium gas after pressure relief events. The scope includes installing over 230 meters of piping across three distinct process lines: Helium Low Pressure Return, Vent-to-Atmosphere Header, and High Pressure Helium Supply, with pipe sizes ranging from 0.5 to 10 inches.
The subcontractor will be responsible for fabricating and installing the piping system, including welding, cleaning, supporting, and testing, while Fermi Forward Discovery Group (FFDG) will provide materials, supports, and design documentation. The installation will be time-phased across three tunnel sections, with work occurring early in the PIP-II accelerator installation process. Critical requirements include maintaining strict cleanliness standards, performing radiographic and leak testing, following specific welding procedures, and working in a tunnel environment with cable trays and other infrastructure. The project will adhere to ASME codes and DOE worker safety regulations, with an estimated 351 total welds across process and structural piping.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PIP-II CDS Tunnel Warm Piping Installation
Statement of Work
Preparation Date: 13-Dec-2024
Date: 13-Dec-2024
Preparing Organization: APSTD-Cryogenics, PIP-II, FNAL
Document Number: ED0036972
ED0036972-PIP-II CDS Tunnel Warm Piping Installation Statement of Work
Fermi National Accelerator Laboratory 2
Document Approval
Signatures Required Date Approved
Originator: W. Soyars As in Teamcenter
Reviewer: A. Martinez As in Teamcenter
Reviewer: M. Geelhoed As in Teamcenter
Reviewer: M. Luedke As in Teamcenter
Reviewer: J. Nudell As in Teamcenter
Reviewer: C. Baffes As in Teamcenter
Reviewer: R. Dhuley As in Teamcenter
Approver: J. Leibfritz As in Teamcenter
Revision History
Revision Date of Release Description of Change
-- 12-16-2024 Initial Release
Document Reference
Reference number
Document Name Document number
1 CDS Warm Piping in Linac Tunnel F10177204 http://pip-ii-doc-4053/
Table of Contents
1 INTRODUCTION
1.1 Vent-to-Atmosphere
1.2 Helium Low Pressure Return (Helium LP Return) Header
1.3 High Pressure Helium Supply
2 ACRONYMS AND DEFINITIONS
2.1 Abbreviations
2.2 Definitions
3 DESCRIPTION OF WORK
3.1 General
3.2 Exceptions in the Assembly Drawings for PIPING installation work
3.3 Weld count estimates
4 APPLICABLE CODES AND STANDARDS
4.1 General
4.2 List of Codes and Standards
5 MATERIALS
6 GENERAL REQUIREMENTS
6.1 General
6.2 Summary of Responsibilities for Requirements
6.3 Work environment and Access Conditions
6.4 Safety Requirements
6.5 Design Pressures and Temperatures
6.6 Flexibility
6.7 Waste disposal
7 CONSTRUCTION, FABRICATION, AND ASSEMBLY REQUIREMENTS
Fermi National Accelerator Laboratory 4
7.1 Welding
7.2 Cleaning
7.3 Flanged piping joint assemblies
7.4 Drilling, coring, and anchoring
8 QUALITY CONTROL AND TESTS
8.1 Installation requirements
8.2 Acceptance Tests
8.3 Quality Control Plan
9 VALVES
9.1 Valves
9.2 Labelling
10 PIPE SUPPORTS
10.1 General
10.2 Ceiling supports and anchors
10.3 Wall mounted supports
10.4 Temporary supports
11 TIME-PHASED WORK
11.1 Start and Completion Dates
11.2 General
11.3 Section 2: Tunnel - HWR/SSR1/SSR2 Section
11.4 Section 3: Tunnel – LB650 Section
11.5 Section 4: Tunnel – HB650 Section and downstream relief lines
12 ITEMS PROVIDED BY FFDG
12.1 Design documentation
12.2 Material and parts
Fermi National Accelerator Laboratory 5
12.3 Supports
12.4 Logistics
12.5 Tunnel Field Conditions
13 SUBCONTRACTOR DOCUMENTATION
13.1 Provided to FFDG prior to starting work
13.2 Provided during installation
Fermi National Accelerator Laboratory 6
1 INTRODUCTION
The Proton Improvement Plan-II (PIP-II) is Fermi National Accelerator Laboratory’s (FNAL) plan for providing powerful, high-intensity proton beams to the laboratory's research program which includes an 800 MeV superconducting linac. In support of this program, the PIP-II project requires a new cryogenic distribution system (CDS). The Warm Piping System of CDS will provide room temperature helium gas to the PIP-II accelerator as well as recover and transport cold helium gas from the accelerator following a pressure relief event. This specification provides the basis for the piping installation contract for a portion of the CDS Warm Piping System. The scope of this specification shall be limited to the CDS Warm Piping system located in the accelerator tunnel.
In this specification, the vendor of the piping contract services shall be referred to as the
SUBCONTRACTOR; Fermi Forward Discovery Group, LLC shall be referred to as FFDG; and the term PIPING will refer to the Tunnel portion of CDS Warm Piping. This document outlines the
SUBCONTRACTOR’s responsibilities and obligations necessary for completing the PIPING based on the requirements as set forth herein and provides the technical description for fabrication and installation of the PIPING system for the PIP-II project.
The piping system described in this specification will reside within the PIP-II Linac Tunnel, see
Figure 1-1 for solid model view of where the piping is located. There are three distinct process lines. Helium Low Pressure Return (Helium LP Return), Vent-to-Atmosphere Header, Helium High
Pressure Supply (Helium HP Supply). See Figure 1-2 for a simple illustration of the piping’s function.
Fermi National Accelerator Laboratory 7
Figure 1-1. View of PIP-II Linac tunnel with warm piping.
Figure 1-2. Illustration of function of warm piping system
Fermi National Accelerator Laboratory 8
Figure 1-3. Representative View of Tunnel Warm piping main section, 1 of 24 locations illustrated.
Figure 1-4 View of south end of PIPING.
Fermi National Accelerator Laboratory 9
Figure 1-5 View of north end of PIPING.
1.1 Vent-to-Atmosphere
This is part of the relief pressure relief system. During worst case relieving event in linac, the
Vent-to-Atmosphere header transports cold helium gas from within the tunnel to the outside of the tunnel.
1.2 Helium Low Pressure Return (Helium LP Return) Header
During relieving events, the Helium LP Return delivers cold helium gas from within the tunnel to either be recovered by cryoplant system or relief outside via reliefs set at 6 psig. The Helium LP
Return header has additional function to deliver low pressure helium for maintaining purity of linac cryogenic systems that operate at sub-atmospheric conditions.
1.3 High Pressure Helium Supply
This header delivers room temperature high pressure helium gas (~250 psig), to the equipment in the linac tunnel. The warm helium gas is used in the linac for cryogenic system purification, and warmups and cooldowns of the linac sub-systems.
Fermi National Accelerator Laboratory 10
2 ACRONYMS AND DEFINITIONS
2.1 Abbreviations
GTAW – Gas Tungsten Arc Welding
HA – Hazard Analysis
HP – High Pressure
LP – Low Pressure
LOTO – Lockout Tagout
PQR – Procedure Qualification Record
PPE – Personal Protective Equipment
WPQ – Welder Performance Qualification
WPS – Welding Procedure Specification
Organizational acronyms
ASME – American Society of Mechanical Engineering
ASTM – American Society for Testing and Materials
AISC – American Institute of Steel Construction
BPVC – Boiler Pressure Vessel Code
DOE – Department of Energy
FFDG – Fermi Research Alliance
Fermilab System Acronyms
ES&H – Environmental, Safety & Health
PIP-II – Proton Improvement Plan II
Fermi National Accelerator Laboratory 11
2.2 Definitions
CODE
a term used to refer collectively to the various pressure safety and other safety standards by which the PIPING system shall comply
FFDG
Fermi National Accelerator Laboratory (Fermi Forward Discovery Group, LLC) may a term which indicates that a provision is neither required nor prohibited
PIPING the piping system defined here by this specification
PQR a Welding Procedure Qualification Record shall a term which indicates that a provision is a requirement should a term which indicates that a provision is recommended as good practice but is not a requirement
SUBCONTRACTOR the piping subcontractor installing the PIPING system
WPS a Welding procedure specification
WPQ a Welder Performance Qualification record
Upstream Equal to Project North. Upstream refers to the linac beam direction, counter to beam toward source
Downstream Equal to Project South. Downstream refers to the linac beam direction, with beam toward target
He helium
3 DESCRIPTION OF WORK
3.1 General
3.1.1 The SUBCONTRACTOR shall furnish all labor, tools, consumable items, and services necessary to install (handle, weld, fasten using nuts and bolts) the PIPING system in strict accordance with this specification.
3.1.2 The SUBCONTRACTOR shall provide documentation as specified in Section 0 of this specification.
Fermi National Accelerator Laboratory 12
3.1.3 The PIPING shall be built as shown on the assembly drawings F10177204 – CDS
WARM PIPING, IN LINAC TUNNEL and associated subdrawings. The assembly design was completed for installation in a site currently under construction. Some dimensions are shown as reference, and field fitting shall occur. Consequently, the
SUBCONTRACTOR shall allow adequate time to perform field verification and field fitting.
3.1.4 The main portion of the piping, which consists of over 230 m of He HP Supply header, He LP Return header, and Vent-to-Atmosphere header, is illustrated in
Figure 3-1.
Figure 3-1. Representative section of the PIPING.
3.2 Exceptions in the Assembly Drawings for PIPING installation work
3.2.1 The assembly drawings are for the full, complete piping system. However, certain parts of the piping system with instrumentation and interfaces to future components will be installed later by FFDG.
3.2.2 The figures here in section 3.2 are for illustration only. Fabrication dimensions and details shall be taken from the indicated drawings.
Fermi National Accelerator Laboratory 13
3.2.3 LP connect branches excluded from this PIPING installation is illustrated in Figure
3-2. This boundary will be marked on F10142875_BOUNDARY REFERENCE.pdf and
F10177365_BOUNDARY REFERENCE.pdf. A 2-inch pipe cap shall be welded at this boundary.
Figure 3-2. Excluded portion, LP branch connection for relief and guard, 1 of 25 locations.
3.2.4 HP supply branch excluded from this PIPING installation is illustrated in Figure 3-3.
This boundary will be marked on F10202904_BOUNDARY REFERENCE.pdf and
F10223548_BOUNDARY REFERENCE.pdf. A plastic pipe cover shall be placed on the ½” pipe opening.
Fermi National Accelerator Laboratory 14
Figure 3-3. Excluded portion, Helium HP supply branch, 1 of 25 locations.
3.2.5 HP Supply branch at the turnaround excluded from this PIPING installation is illustrated in Figure 3-4. This boundary will be marked on F10145098_BOUNDARY
REFERENCE.pdf. A 1/2 inch blank off flange cap shall be installed at this boundary.
Figure 3-4 Excluded portion, Helium HP supply at turnaround, 1 location.
Fermi National Accelerator Laboratory 15
3.2.6 For the 10-inch piping at far southern end of PIPING, subassemblies provided by
FFDG and excluded portion is illustrated in Figure 3-5. This boundary will be marked on F10228356_BOUNDARY REFERENCE.pdf and F10174816_BOUNDARY
REFERENCE.pdf.
Figure 3-5. Excluded portion, He LP Return 10” piping at southern end.
3.3 Weld count estimates.
3.3.1 An estimated number of welds by size and type for process piping are shown in
Table 3-1. Next, estimated welds by size and type for structural elements are shown in Table 3-2. These tables are intended only as an aid for estimation. The actual number of welds may vary during actual field installation. Drawings shall be reviewed for more detailed information.
Table 3-1 Sizes and Estimated Quantities of Welds: Process piping
Weld type Size Qty.
Pipe to pipe buttweld 10" 11
Pipe to pipe buttweld 8" 168
Pipe to pipe buttweld 4" 125
Pipe to pipe buttweld 2" 41
Pipe to pipe buttweld 1” 6
Fermi National Accelerator Laboratory 16
Pipe to pipe buttweld 0.5” 182
Weldolet weld to pipe 2” 26
Weldolet weld to pipe 1” 2
Weldolet weld to pipe 0.5” 26
Table 3-2 Sizes and Estimated Quantities of Welds: Structural
Weld type Size Qty. Location
Linear fillet weld 3/16 fillet weld x 2” long 296 Unistrut to Ceiling plates at roller locations
Linear fillet weld 3/16 fillet weld x 14” long 48 Future Relief support pipe
Linear fillet weld 1/8 fillet weld x 3” long 96 Future Relief support unistrut
Linear fillet weld ¼” fillet skip weld, 1.75” – 3.5” x 12” long 96 Side plates to Ceiling plates and pipe at anchor location
Linear fillet weld 1/8” fillet skip weld, 1.75” – 3.5” x 12” long 96 Pipe reinforcement at anchors
4 APPLICABLE CODES AND STANDARDS
4.1 General
4.1.1 In the event of conflict between drawings and the written specification, the written specification shall be the governing document.
4.1.2 In the event of incompleteness, error or contradictions in FFDG-supplied documents or drawings, the SUBCONTRACTOR shall notify FFDG in writing at the earliest convenience to obtain directives.
4.1.3 If the SUBCONTRACTOR deems it necessary to observe additional governing codes and regulations, FFDG shall be notified of this in writing. FFDG shall notify the
SUBCONTRACTOR in writing of the outcome of this request.
4.1.4 The PIPING and its subcomponents shall be designed to comply with all applicable requirements of the CODE, documents and standards listed in this specification.
4.2 List of Codes and Standards
Health and safety applicable regulations
• 10 CFR 851 - DOE Worker Safety and Health Program
Fermi National Accelerator Laboratory 17
• Illinois rules of the road apply at Fermilab Site
The following list of codes in their latest edition, drawings and standards shall be applied to the fabrication, assembly and testing of the PIPING system and its components:
• ASME B31.3 Process Piping
• ASME B31.9 Building Services Piping
• AISC Manual of Steel Construction
• ASTM A380 Cleaning and De-scaling Stainless Steel Parts
5 MATERIALS
5.1.1 FFDG shall provide all PIPING materials and hardware, for example: pipe, fittings, supports, expansion joints, flange bolting, flange gaskets, hardware for supports, etc.
5.1.2 All piping and PIPING components will be stainless steel (Type 304/L) or (Type
316/L).
5.1.3 The tunnel ceiling will have embedded structural carbon steel plates. These are used to provide support and anchoring of the 8” Vent-to-Atmosphere Header and the 8” (including a section of 10”) Helium LP Return Header. PIPING supports will be welded to this structure by the SUBCONTRACTOR as shown in F10177204.
5.1.3.1 At roller locations, carbon steel unistruts will be welded to the ceiling plate.
5.1.3.2 At anchor points, stainless steel plates will be welded to the ceiling plate.
5.1.4 All materials used in pressure containing piping components will conform to the required CODE material requirements for the appropriate fluid service category and operating temperature range.
5.1.5 All fittings, flanges, and blanks will conform to CODE requirements for the appropriate service category.
5.1.6 All piping will be provided in general lengths of 20 feet.
5.1.7 All piping, fittings and hardware will be staged at the job site for SUBCONTRACTOR use.
Fermi National Accelerator Laboratory 18
5.1.8 From the time that the materials are released to the SUBCONTRACTOR until the final acceptance of the work is performed, all costs for the replacement of materials lost or damaged become the responsibility of the SUBCONTRACTOR.
5.1.9 Any excess material supplied by FFDG remains the property of FFDG and shall be returned upon completion of the work.
6 GENERAL REQUIREMENTS
6.1 General
6.1.1 The SUBCONTRACTOR shall supply all equipment, special tooling, consumables, and perform all work and services necessary to fabricate, assemble, a fully functional PIPING system suitable for long-term operation in accordance with this specification.
6.1.2 The SUBCONTRACTOR shall perform all drilling/coring of holes for piping penetrations of the Vent-to-Atmosphere and Helium LP Return headers at the north end of the tunnel. This allows PIPING weldment F10225877 (behind the wall in Figure 6-2) to be installed for interfacing the PIPING to the future surface piping.
Layout drawing F10232815 shows the location of required cored holes leading out of tunnel. This is show in model in Figure 6-2 and schematically in Figure 6-2. The wall is 24 inch thick concrete. See 7.4 for further requirements for Drilling and
Coring.
Fermi National Accelerator Laboratory 19
Figure 6-1 Model showing core drilling locations at north end of tunnel.
Figure 6-2 Illustration of core drilled holes needed for piping penetrations at north end of tunnel. Layout fully defined in F10232815.
Fermi National Accelerator Laboratory 20
6.1.3 At the south end of the tunnel, the PIPING connects to pipe runs that will be in place at the east wall. See Figure 6-3. No core drilling is required here as the interfacing piping will already be in place at the time of PIPING system installation.
Figure 6-3 Image of PIPING connection, south end of tunnel.
6.1.4 FFDG shall be available to perform in-process and/or radiographic weld inspections/examinations for CODE compliance.
6.1.4.1 FFDG shall be responsible for coordinating independent radiographic inspections and the cost for these services.
6.1.5 FFDG shall perform all pressure testing in coordination with the SUBCONTRACTOR per FFDG requirements.
6.1.6 The SUBCONTRACTOR shall repair any welds that fail inspections or qualification tests.
Fermi National Accelerator Laboratory 21
6.1.7 The SUBCONTRACTOR may fabricate subassemblies at their home shop with FFDG written approval. It is the responsibility of the SUBCONTRACTOR to verify all field dimensions. When fabricating at their home shop, recognize that assembly design was completed for installation in a site currently under construction. Some dimensions are shown as reference, and field fitting shall occur. The
SUBCONTRACTOR shall allow FFDG representatives to visit the SUBCONTRACTOR home shop to inspect any work at their site. The SUBCONTRACTOR shall sign out all piping materials taken off the Fermilab site.
6.2 Summary of Responsibilities for Requirements.
6.2.1 See Table 6-1 Task Responsibilities Summary.
Table 6-1 Task Responsibilities Summary.
TASK OR ITEMS SUBCONTRACTOR FFDG
Purchasing of all materials for the PIPING system. X
Purchasing of all consumables including weld gas. X
Purchasing subassemblies comprising expansion joints (flex hoses at branch connection, axial bellows along main run) X
Purchasing of all support and anchor hardware. X
Assembling and installing supports X
Fabricating and installing PIPING as shown in drawings F10177204 and sub-drawings.
X
Coordinating independent radiography weld inspections for CODE compliance as required and the cost for such services.
X
Performing any in-process weld inspections for CODE compliance. X
Performing pressure testing. X
Repairing any welds that fail inspection or pressure tests. X
Drilling/coring holes in the tunnel walls as detailed in F10232815 for piping penetrations.
X
Fermi National Accelerator Laboratory 22
Providing of man-lifts, scaffolding, other equipment to perform work at elevated heights, and lifts, cranes, and other equipment to deliver piping materials to elevated heights.
X
Providing mobile fall protection systems for persons working at elevation, if required.
X
Completing all required FFDG safety training. X
Fabricating instrumentation subassemblies and their installation.
(Not in scope of this specification, see 3.2) X
6.3 Work environment and Access Conditions
6.3.1 The PIPING installation work will be in an underground tunnel.
6.3.2 The PIPING installation work will be at elevated levels above the tunnel floor. The tunnel ceiling is 13.5 ft above the floor.
6.3.3 The PIPING installation area will be time-phased for access. The full tunnel length will be divided into three different sections for access. See Section 11 TIME
PHASED WORK for details.
6.3.4 At the time of PIPING installation at a given section, the tunnel will be mostly empty except for cable tray and utility infrastructure. The SUBCONTRACTOR will have priority access to all areas of the tunnel during installation. Other work may be going on nearby, but the PIPING installation work will take priority.
6.3.5 Cable trays will be installed prior to PIPING installation. The main North-South cable tray runs will not interfere with the PIPING work. However, there will be 29
East-West cable tray cross-overs that are expected to interfere with PIPING installation. See Figure 6-4. These cable trays are also shown in Figure 12-1. The
SUBCONTRACTOR shall remove these trays for PIPING installation. The
SUBCONTRACTOR shall re-install these trays at conclusion of the work.
Fermi National Accelerator Laboratory 23
Figure 6-4 Cable tray cross-overs for removal and installation
6.4 Safety Requirements
6.4.1 SUBCONTRACTOR employees will be required to complete Fermilab General
Contractor Training. The SUBCONTRACTOR shall allocate one half day to complete the training.
6.4.2 The SUBCONTRACTOR shall provide proof of Fall Protection training and implement fall protection protocols as required.
6.4.3 The SUBCONTRACTOR shall submit a signed and dated Hazard Analysis (HA) for all scope including work at heights above 6 feet, which are required to meet the following criteria:
Fermi National Accelerator Laboratory 24
6.4.3.1 If applicable, the SUBCONTRACTOR shall prioritize use of 100% fall protection systems that requires minimal user input (e.g., Self-Retracting Lifeline System
(SRL) connected to an attachment point approved by the form manufacturer) over dual lanyard systems. If dual lanyards are deemed the best equipment for the task, documentation of that analysis shall be reviewed and approved by
FFDG ES&H personnel.
6.4.3.2 Explicitly identified and documented acceptable tie-off points necessary for each element of work.
6.4.3.3 Fall protection rescue plans that have been crafted and are incorporated into the HA.
6.4.3.4 Daily inspection of Personal Protective Equipment and mechanical equipment.
6.4.3.5 Ensure the knowledgeable supervisor communicates the HA, both verbally and in writing, to all workers in a consistent manner. This is especially important for workers new to the PIP-II site.
6.4.3.6 Workplans and HAs will require a 3-day DOE review and approval before work may commence. FFDG subject matter expert (SME) reviews of the HA will also be required. The SUBCONTRACTOR shall allocate sufficient time for HA preparation and review.
6.4.4 For any work using SUBCONTRACTOR supplied equipment such as a scissor lift, articulating lift, etc., the SUBCONTRACTOR shall supply proof of training.
6.4.5 If required, FFDG shall provide a certified crane operator for use of building overhead cranes. The SUBCONTRACTOR shall not be authorized to operate the building overhead cranes.
6.4.6 For any work with a crane supplied by the SUBCONTRACTOR, the
SUBCONTRACTOR shall submit operator training records and lifting documentation to FFDG for approval.
Fermi National Accelerator Laboratory 25
6.4.7 The SUBCONTRACTOR shall have proper PPE as outlined in the approved hazard analysis. Specifically, the use of safety helmets/hard hats will be required in situations that include but not limited to crawling under equipment, climbing ladders, exposed work with safety line, etc. The use of safety helmets shall be covered as PPE in the Hazard Analysis.
6.5 Design Pressures and Temperatures
6.5.1 The PIPING system design consists of design temperatures and pressures as presented in Error! Reference source not found..
Table 6-2 Process Piping Design Pressure and Temperature.
Circuit Circuit Description Design Pressure Minimum Design
Temperature
Helium HP Supply and its branches
Helium High Pressure Supply header and branches
23 barg 245 K
Helium LP Return
Helium Low Pressure Return header and branches
1 barg 20 K
Vent to Atm.
Header
Relief header 1 barg 20 K
6.6 Flexibility
6.6.1 The FFDG design in drawings F10177204 and sub-drawings allow for thermal contraction due to ambient and process temperature changes. Support, guide, and anchor positions are also shown on these drawings.
6.6.2 FFDG will provide supports, guides, and anchor hardware that supports and compensates for this motion.
6.7 Waste disposal
6.7.1 The SUBCONTRACTOR shall separate and dispose of waste separately:
Fermi National Accelerator Laboratory 26
6.7.1.1 A general waste container will be made available by FFDG.
6.7.1.2 Disposal of discarded metal parts will be performed in a separate bulk container/pallet and will be managed by FFDG.
6.7.1.3 Hazardous substances shall be managed in a separate disposal area and managed by FFDG.
6.7.1.4 Upon demobilization, the SUBCONTRACTOR shall perform a site cleanup.
7 CONSTRUCTION, FABRICATION, AND ASSEMBLY REQUIREMENTS
7.1 Welding
7.1.1 All weld joint preparation and welding techniques shall be performed in accordance as required by Section VIII-Division 1 and IX of the ASME BPVC and/or
Chapter V of the ASME B31.3 code.
Table 7-1 ASME Piping Code Categories.
Circuit Piping Type Applicable ASME code Weld preparation and techniques
Helium HP Supply Compressor helium discharge B31.3 Normal Fluid Service B31.3 Chapter V
Helium LP Return Compressor helium suction B31.3 Normal Fluid Service B31.3 Chapter V
Vent to Atm. Header Vent-to-Atmosphere Relief header
B31.9 Building Services B31.9 Chapter V
7.1.2 The SUBCONTRACTOR shall conduct the tests required to provide a Procedure
Qualification Record (PQR) for each Welding Procedure Specification (WPS) as required by Section VIII-Division 1 and Section IX of the ASME BPVC and/or
Chapter V of the ASME B31.3 code.
7.1.3 The SUBCONTRACTOR shall conduct the tests required to qualify each welder to a
Welder Performance Qualification (WPQ) as required by Section VIII-Division 1 and
IX of the ASME BPVC and/or Chapter V of the ASME B31.3 code.
Fermi National Accelerator Laboratory 27
7.1.4 The SUBCONTRACTOR shall maintain records in accordance with paragraph UW-
48 Section VIII-Division 1 of the ASME BPVC for all welders and welding operators working on the PIPING system.
7.1.5 All stainless-steel welding performed on piping shall utilize the Gas Tungsten Arc
Weld (GTAW) process using weld quality argon gas for the inert shield. Carbon steel welding shall utilize any process selected by the SUBCONRACTOR that meets
Code requirements.
7.1.6 All stainless-steel welds shall be internally purged with weld quality argon gas during the time of welding and post welding treatment. Oxygen levels shall be less than 1% as read by a TOPAC oxygen meter or equivalent.
7.1.7 Stainless-steel welds that show evidence of a lack of purge will not be accepted and shall be repaired by the SUBCONTRACTOR.
7.1.8 All welding shall be performed in such a manner that the weld surface is smooth and free of irregularities. No visible metal chips or foreign material shall be detectable within any component of the PIPING system. All external surfaces in the weld area shall be cleaned of heat tint, slag, and other deposits. No mechanical process shall be used to achieve a smooth appearance.
7.1.9 No production welding shall be performed on the PIPING system until all WPS, PQR, and WPQ documents have been qualified in accordance with ASME BPVC
Section VIII-Division 1 paragraphs UW-28 and UW-29 and Section IX of the ASME
BPVC and submitted to and approved by FFDG.
7.1.10 The SUBCONTRACTOR shall supply weld maps which identify each weld and name of welder performing the weld. This applies to piping covered by B31.3.
7.1.11 At the conclusion of each workday, the SUBCONTRACTOR shall attach removable caps on all open piping ends to maintain cleanliness. FFDG shall provide the removable caps.
7.1.12 Acceptance tests
Fermi National Accelerator Laboratory 28
• Random radiographic examination according to the CODE for 5% of all butt welds shall be coordinated by FFDG using an independent subcontractor.
It is the SUBCONTRACTOR’S responsibility to repair any welds that fail a radiographic exam.
• If a weld fails radiography, it is the SUBCONTRACTOR’S responsibility for costs incurred for any subsequent radiographic examinations required by the CODE. This includes radiographic examination of additional welds due to the progressive sampling clause of the CODE. All radiographic examinations shall be coordinated by FFDG.
• In-Process Inspection according to the CODE may be substituted for radiographic examination at the discretion of FFDG. The SUCONTRACTOR shall allow access to FFDG to perform In-Process Inspection as required.
7.2 Cleaning
7.2.1 FFDG shall provide initially clean piping material and components. It is the responsibility of the SUBCONTRACTOR to maintain this cleanliness throughout the fabrication process, as described below:
• Cleaning agents shall be suitable for the materials of construction and shall be neutralized if necessary.
• Each assembly shall be cleaned to provide an inner surface of all pipes and tubes free of grease, flux, moisture, dirt, and other foreign materials by vapor degreasing or suitable wash. Surfaces shall be visibly inspected and wiped down with a white cloth. To be considered free of contamination, no discoloration shall appear on the white cloth.
• After cleaning, each section shall be blown dry with clean dry air until no visual moisture remains.
7.2.2 All pipe sections, fittings and valves shall remain clean internally at every stage of installation by the SUBCONTRACTOR. No visible metal chips or foreign material shall be allowed to remain inside any component of the piping system including, but not limited to, scale, spatter, flux, and grease. At the end of each shift, open pipe ends shall be kept sealed with a cap, tape, or equivalent material.
Fermi National Accelerator Laboratory 29
7.2.3 Weld spatter shall be removed by wire brushing using only stainless-steel brushes.
7.2.4 The SUBCONTRACTOR shall ensure all piping, fittings, and component interiors stay clean and dry while awaiting installation.
7.3 Flanged piping joint assemblies
7.3.1 The SUBCONTRACTOR shall treat all flanged assembly sealing faces carefully and is responsible for any scratches or damage that cause leaks.
7.3.2 Special flanges such as CF flanges and double o-ring machined flanges may be expected at certain interfaces. At the work start milestone, the SUBCONTRACTOR shall receive instructions on how to prepare and fasten the specific connections.
7.3.3 Copper-based anti-seize LOCTITE LB 8065 shall be used in the interface between stainless steel bolts and nuts and shall be provided by the FFDG.
7.4 Drilling, coring, and anchoring
7.4.1 The SUBCONTRACTOR shall perform any concrete drilling and coring operations with the precautions specified in FESHM 4195 Special Toxic Hazards – Silica including but not limited to worker respiratory protection and dust management via wet slurry or HEPA vacuums.
8 QUALITY CONTROL AND TESTS
8.1 Installation requirements
8.1.1 During installation, FFDG will perform spot checks to verify the PIPING complies with 7.2 cleanliness requirements. The SUBCONTRACTOR shall correct any cleanliness non-conformities before finalizing the affected piping circuit.
8.2 Acceptance Tests
8.2.1 Random radiographic examination according to the CODE shall be coordinated by
FFDG using an independent subcontractor. It is the SUBCONTRACTOR’s responsibility to repair any welds that fail a radiographic exam.
Fermi National Accelerator Laboratory 30
8.2.2 All piping pressure tests shall be done by FFDG. Tests will be conducted in accordance with Fermilab ES&H requirements.
8.2.3 The PIPING system shall be pneumatically tested with nitrogen gas at the following pressures, see Table 8-1.
Table 8-1. Process Piping Pressure Tests.
Circuit Description Design Pressure
[bara]
Test Pressure
[bara] Test Type
Helium HP Supply 24 26.4 Pneumatic pressure test
Helium LP Return 2 2.1 Leak test
Vent to Atm. Header 2 NA NA
* Soap bubble solution test at low pressure # Soap bubble solution test at design pressure
8.2.4 All joints shall show no indication of any gas leak when tested with a soap bubble solution (LEAK-TEC or equivalent).
8.2.5 The SUBCONTRACTOR shall be responsible for repairing any leaks or failed radiographically examined welds.
8.3 Quality Control Plan
8.3.1 The SUBCONTRACTOR shall develop a Quality Control (QC) Plan for review by FFDG prior to the start of installation. The quality control plan shall include:
Fermi National Accelerator Laboratory 31
8.3.1.1 Description of equipment and testing/inspection methods planned to ensure requirements outlined in this SOW are met.
8.3.1.2 Description of documentation planned to communicate contract conformance to FFDG.
8.3.1.3 Description of nonconformance management process to be used.
8.3.1.4 Applicable training/qualifications required.
8.3.1.5 Description of receiving inspections and how cleanliness will be maintained for
FFDG provided components.
8.3.2 The Quality Control Plan information should be presented at the Kickoff Meeting at the start of the contract. The information shall be presented prior to the start of installation work.
9 VALVES
9.1 Valves
9.1.1 Manual valves are defined in the Parts List for drawings listed below. Valves shall be provided by FFDG and installed by the SUBCONTRACTOR. Subassemblies using manual valves are:
9.1.1.1 He HP Supply, south end: F10228356.
9.1.1.2 He HP Supply, branches: F10175088, F1016667 and F10224104.
9.1.2 The SUBCONTRACTOR shall take appropriate precautions when welding near valves to prevent overheating of valve seals. The SUBCONTRACTOR shall follow the manufacturer instructions to protect the valve internal parts from welding damage.
9.2 Labelling
9.2.1 FFDG is responsible for final labelling of valves.
Fermi National Accelerator Laboratory 32
10 PIPE SUPPORTS
10.1 General
10.1.1 FFDG shall supply pipe support materials, i.e., clevises and lengths of threaded rod, Unistrut pieces, roller hangers, etc.
10.1.2 The SUBCONTRACTOR shall install all the pipe supports and make welded or bolted connections to tunnel building interfaces as detailed in 10.1.3.
10.1.3 Specific support and anchoring details are shown on drawings F10177204.
Anchoring locations are shown on drawing F10177232 and sub-drawings.
10.1.4 Pipe welds shall be located to avoid interfering with the operation of any sliding or rolling points.
10.2 Ceiling supports and anchors.
10.2.1 Embedded plates in the tunnel ceiling are used for supporting the 8 inch LP Return and Vent piping at key locations where these lines will interface with other linac cryogenic systems. These either provide fixed support or roller support for the piping. Schematically, fixed (F) and roller (F) support locations are shown in Figure
10-1. There are 12 fixed ceiling plate locations and 16 roller ceiling plate locations.
Figure 10-1 Schematic of 8 inch pipe support style (Fixed or Roller) from embedded ceiling plates
10.2.2 The welding for supports at the embedded plates involves welding stainless steel pieces (Unistrut and vertical side plates) to carbon steel (embedded ceiling plate).
Some of the installed, embedded plates is shown in Figure 10-2. The plates are 48 inches x 42 inches.
Fermi National Accelerator Laboratory 33
Figure 10-2 Embedded plate in ceiling of linac tunnel.
10.2.1 An illustration of the PIPING with the structural welds at the embedded ceiling plates is shown in Figure 10-3.
Figure 10-3. A view of locations with structural welds to the ceiling plates
Fermi National Accelerator Laboratory 34
10.3 Wall mounted supports
10.3.1 The 2” HP supply will be supported from Unistrut braces mounted into wall-embedded Unistrut channels.
Figure 10-4 Supports for 2" HP Helium line
10.4 Temporary supports
10.4.1 Temporary supports, such as pipe stands, shall be provided for the HP branch lines at 26 locations. The pipe stands will be provided by FFDG.
11 TIME-PHASED WORK
11.1 Start and Completion Dates
The piping work is separated into three sections based on the availability of the components, interfacing systems, and physical facility envelope. The SUBCONTRACTOR may combine and coordinate work in multiple sections or may work in a single section as conditions permit. The sections do not necessarily need to be installed in numerical order. The s descriptions and start constraints for each section of the machine is given in
Fermi National Accelerator Laboratory 35
11.1.1 Table 11-1:
Fermi National Accelerator Laboratory 36
Table 11-1. Tunnel Warm Piping Sections Time phased work description
Section Start Constraint Comments
1: Tunnel Warm
Piping-
HWR/SSR1/SSR2
Section
Conventional Facility
Tunnel Handoff (to column line L18) +1 month
Interfaces for 10 cryomodules
2: Tunnel Warm
Piping – LB650
Section
Conventional Facility
Tunnel Handoff (to column line L26) +1 month
Interfaces for 9 cryomodules
3: Tunnel Warm
Piping – HB650
Section and downstream relief lines
Conventional Facility
Tunnel Handoff (to end of
Linac Tunnel) +1 month
Interfaces for 6 cryomodules + turnaround can, downstream relief runs
Figure 11-1 Warm Piping Sections
Fermi National Accelerator Laboratory 37
Figure 11-2 Work Areas for Warm Piping Sections
11.2 General
11.2.1 The main components of the tunnel warm piping system consist of the following:
• Warm piping 8 inch headers o Vent-to-Atmosphere o Low Pressure Return o Helium low pressure guard and relief collector, branch connections.
• Helium high pressure supply o 2 inch header o GHe supply, branch connections.
• Piping supports.
11.2.2 All parts are expected to be available at the start of the contract.
Fermi National Accelerator Laboratory 38
11.3 Section 2: Tunnel - HWR/SSR1/SSR2 Section
11.3.1 In F10177232 for LP He Return and Vent Piping, this is Section A-D.
11.3.2 In F10177347 for HP He Supply, this is section A-F.
11.3.3 See Figure 11-2 for the areas available for installation in Phase 2.
11.4 Section 3: Tunnel – LB650 Section
11.4.1 In F10177232 for LP He Return and Vent Piping, this is Section D-G.
11.4.2 In F10177347 for HP He Supply, this is section G-L.
11.4.3 See Figure 11-2 for the areas available for installation in Phase 3.
11.5 Section 4: Tunnel – HB650 Section and downstream relief lines
11.5.1 In F10177232 for LP He Return and Vent Piping, this is Section G-N.
11.5.2 In F10177347 for HP He Supply, this is section M-V.
11.5.3 See Figure 11-2 for the areas available for installation in Phase 3.
Fermi National Accelerator Laboratory 39
12 ITEMS PROVIDED BY FFDG
12.1 Design documentation
• Piping assembly drawing pdf for F10177204, supporting sub-drawings.
• 3D model in STEP format upon request
12.2 Material and parts
• Stainless steel pipe for helium lines in 20 ft. sections in appropriate sizes
• Flanges, fittings, fasteners, gaskets, valves, expansion joint assemblies, etc.
• Hand valves
• Solenoid valves (excluded from this installation specification)
• Pressure indicators and transducers (excluded from this installation specification)
• Flexhoses
• Axial bellows
12.3 Supports
Supports supplied by FFDG, installed by SUBCONTRACTOR
• Clevises and threaded rods
• Roller supports and threaded rods
• Unistrut in standard lengths (to be cut by the SUBCONTRACTOR as needed)
• Miscellaneous support hardware including stainless-steel plates, nuts, bolts, and washers.
• Plates for anchor locations.
• Temporary Pipe stands for HP He branches at conclusion of project (see Error! R eference source not found.)
Supporting elements installed by FFDG
• Carbon steel plates embedded in the tunnel ceiling at predetermined locations
• Unistrut channels embedded in the tunnel ceiling at predetermined locations
• Unistrut channels embedded in the tunnel ceiling at predetermined locations
• Unistrut channels embedded in the east wall at predetermined locations
Fermi National Accelerator Laboratory 40
12.4 Logistics
FFDG will provide access to the following equipment and areas:
• Exterior material lay-down area (as requested by SUBCONTRACTOR)
• Loading dock at High Bay Building
• Work area adjacent to Warm Piping installation footprint
• AC power (utility 120VAC, welding 480VAC 3ph) in interior (Section 2, 3, 4) work areas.
AC power is NOT provided in exterior areas of Section 1.
12.5 Tunnel Field Conditions
While the work of this subcontract is ongoing, the SUBCONTRACTOR will have priority but NON-
EXCLUSIVE access to the work areas. The SUBCONTRACTOR shall:
• Preserve safe aisleways for the transport of personnel and materials through the work area
• Implement appropriate protective equipment (e.g. weld screens) to protect personnel transiting through the work area or in adjacent areas
• Notify Fermilab Task Manager in advance of any need for more stringent access restrictions (e.g. exclusion of personnel from the work area during critical equipment lifts)
• Make reasonable accommodations for other nearby work
This work will occur early in the installation of the PIP-II accelerator, and before the majority of other technical equipment installation. Cable trays, water and air piping, and AC electrical distribution systems will be installed, as shown in representative Figure 12-1.
Fermi National Accelerator Laboratory 41
Figure 12-1. Representative Tunnel condition at start of Warm Piping installation work
13 SUBCONTRACTOR DOCUMENTATION
13.1 Provided to FFDG prior to starting work
13.1.1 This is defined in document 010010_General Requirements.
13.2 Provided during installation
13.2.1 For consumable items such as weld rods, electrodes, and fasteners, certificates of compliance shall be supplied.
13.2.2 Weld maps as required in section 7.1.10.