Eastside Library Gutter and Soffit Replacement.pdf

PDF 938 KB Posted

Attached to
Eastside Library Gutter and Soffit Replacement
Solicitation number
26-C01347/AP
Issued by
Hernando County, Brownsville CDP, Florida

About this file

This is an Invitation to Bid (ITB) document issued by the Board of County Commissioners of Hernando County, Florida, for the Eastside Library Gutter and Soffit Replacement project (Solicitation No. 26-C01347/AP). The County seeks a licensed Certified Roofing Contractor or Certified Building/General Contractor to furnish all labor, materials, equipment, tools, supervision, and incidentals necessary to replace existing fascia, soffit, gutter, and downspouts at the East Hernando Branch Library located at 6457 Windmere Road, Brooksville, Florida 34602. A mandatory pre-bid conference is scheduled for Wednesday, June 3, 2026, at 10:00 a.m. at the library site; failure to attend and sign in disqualifies bidders from submitting a bid. Sealed bids must be submitted electronically via the County's eProcurement Portal no later than 10:00 a.m. on Monday, June 29, 2026, with public opening of bids at the same date and time. Bidders must demonstrate previous experience with at least two similar projects completed within the past seven years and must provide resumes of the project superintendent showing a minimum of three years of experience directing comparable projects. The County estimates the project budget to fall within Threshold A (less than $100,000), though this estimate should not be the basis for bid submission amounts.

Bids must be accompanied by a bid bond, certified check, or cashier's check equal to at least five percent of the total bid amount, guaranteeing the bidder will enter into a written contract within fifteen calendar days of award and furnish a performance and payment bond equal to one hundred percent of the total bid price. The County reserves the right to award the contract to the lowest responsive and responsible bidder and may reject any or all bids. Successful bidders must provide evidence of proper Florida licensing at the time of bid submission and must obtain all required permits, including NPDES-NOI permit, building permit, and electrical permit, prior to Notice to Proceed. The Vendor/Contractor must maintain comprehensive general liability insurance with limits of at least $1,000,000 per occurrence and $2,000,000 general aggregate, along with workers' compensation and automobile liability coverage as specified. The County provides a five percent local vendor preference for bids within $10,000 of the lowest bid if the local vendor has maintained a physical business location in Hernando County for at least twelve months and complies with eligibility requirements. All bid documents, plans, specifications, and addenda are available through the County's eProcurement Portal, with questions accepted through June 8, 2026, at 5:00 p.m.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

EASTSIDE LIBRARY GUTTER AND SOFFIT REPLACEMENT

26-C01347/AP

County of Hernando

15470 Flight Path Drive

Brooksville, FL 34604

County of Hernando

Eastside Library Gutter and Soffit Replacement

I. SOLICITATION

II. INTRODUCTION

III. AWARD

IV. DEFINITIONS AND SOLICITATION INSTRUCTIONS

V. GENERAL CONDITIONS

VI. SPECIAL CONDITIONS

VII. SCOPE AND SPECIFICATIONS

VIII. PRICING PROPOSAL

IX. VENDOR QUESTIONNAIRE

Attachments:

A - Construction_Documents_required_after_Award (1)

B - Sample_Construction_Contract

C - Hernando_E_Library_Soffit_CAD_-_Update_2026-Sealed

D - Guide_Specs-_Heranando_County_East_Library_Soffit_Replace-_Sealed

E - REI Engineers Addendum undefined #26-C01347/AP Title: Eastside Library Gutter and Soffit Replacement

1. SOLICITATION

ISSUED BY:

BOARD OF COUNTY COMMISSIONERS

HERNANDO COUNTY, FLORIDA

Jerry Campbell, Chairman

Ryan Amsler, Vice Chairman

Steve Champion, Second Vice Chairman

Brian Hawkins

John Allocco

SUBMIT BID OFFER TO:

HERNANDO COUNTY

PROCUREMENT DEPARTMENT

via Hernando County's eProcurement Portal

Carla Rossiter-Smith

Chief Procurement Officer

SEALED OFFERS, FOR FURNISHING THE SERVICES, SUPPLIES OR EQUIPMENT DESCRIBED HEREIN WILL BE

RECEIVED BY THE OFFICE OF PROCUREMENT, VIA THE COUNTY'S eProcurement Portal UNTIL 10:00 a.m., LOCAL TIME ON Monday, June 29, 2026. NO BID OFFERS WILL BE ACCEPTED AFTER THE ABOVE

STIPULATED DATE AND TIME. THIS IS AN ADVERTISED SOLICITATION AND THE RESPONDING BIDDERS

WILL BE PUBLICLY READ AT 15470 FLIGHT PATH DRIVE BROOKSVILLE, FL 34604 IN THE ADMINISTRATIVE

CONFERENCE ROOM AT 10:00 a.m. ON Monday, June 29, 2026. PURSUANT TO FS 119.071 SEALED BIDS, PROPOSALS, OR REPLIES RECEIVED BY AN AGENCY PURSUANT TO A COMPETITIVE SOLICITATION ARE

EXEMPT FROM INSPECTION UNTIL SUCH TIME AS THE AGENCY PROVIDES NOTICE OF AN INTENDED

DECISION OR UNTIL THIRTY (30) DAYS AFTER OPENING THE BIDS, PROPOSALS, OR FINAL REPLIES, WHICHEVER IS EARLIER.

Procurement Contact Information:

Alisa Pike, Procurement Manager, Special Projects and Vendor Relations

(352) 754-4020 alisap@co.hernando.fl.us https://secure.procurenow.com/portal/hernandocounty

2. INTRODUCTION

2.1. ADVERTISEMENT OF BID

INVITATION TO BID

NOTICE IS HEREBY GIVEN that the Board of County Commissioners of Hernando County, Florida, is accepting Bids for:

CONSTRUCTION CONTRACT ITB NO. SOLICITATION NO. 26-C01347/AP

FOR

Eastside Library Gutter and Soffit Replacement

Hernando County Board of County Commissioners is soliciting licensed professionals in Certified Roofing

Contractor or Certified Building or General Contractor that are active in Eastside Library Gutter and

Soffit Replacement

Offers for furnishing the above will be received and accepted up to 10:00 a.m. (local time), Monday, June 29, 2026, via Hernando County Procuremnt Department’s eProcurement Portal. Only electronic submittals through the eProcurement portal shall be accepted by the County.

The Board of County Commissioners of Hernando County, Florida reserves the right to accept or reject any or all bids and waive informalities and minor irregularities in offers received in accordance with the bid documents and the Hernando County Procurement Ordinance.

Interested firms may secure the bid documents and plans and drawings and all other pertinent information by visiting the County's eProcurement Portal. For additional project information, please visit the Hernando County Board of County Commissioners Procurement Department at www.hernandocounty.us, or by submitting a question via the Q&A Tab in the County's eProcurement

Portal.

Bid offers shall be accompanied by either a Bid Bond, Certified Check, Cashier's Check, or Official Bank

Check in the dollar amount representing not less than five percent (5%) of the total amount bid as a guarantee to enter into a contract and furnish a contract performance and payment bond in the amount of one hundred percent (100%) of the total bid price within fifteen (15) calendar days from the date of notification of the award.

Exparte Communication: Please note that to ensure the proper and fair evaluation of a submittal, the

County prohibits exparte communication (i.e., unsolicited) initiated by the Respondent to the County official or employee evaluating or considering the submittals prior to the time a decision has been made.

Communication between Respondent and the County will be initiated by the appropriate County official or employee in order to obtain information or clarification needed to develop a proper and accurate evaluation of the submittal. Exparte communication may be grounds for disqualifying the offending

Respondent from consideration or award of the solicitation or any future solicitation.

The Procurement Department will post addenda on eProcurement Portal to all questions in accordance with the Solicitation Instructions. It is the responsibility of prospective Bidders to visit the County’s portal to ensure that they are aware of all Addenda issued relative to this Solicitation.

Pursuant to Florida Statutes 119.071 (current version) sealed bids, proposals or replies received by an agency pursuant to a competitive Solicitation are exempt from inspection until such time as the agency provides notice of an intended decision or until thirty (30) days after opening the bids, proposals, or final replies whichever is earlier.

NOTICE TO BIDDERS

To ensure that your bid is responsive, you are urged to request clarification or guidance on any issues involving this Solicitation before submission of your response. Your method of contact for this solicitation is the Q&A Tab in the County's eProcurement Portal.

2.2. MANDATORY Pre-Bid Conference

MANDATORY Pre-Bid Conference will be held

Wednesday, June 3, 2026, at 10:00 a.m., at the

EAST HERNANDO BRANCH LIBRARY 6457 Windmere Road Brooksville, Florida 34602.

Representatives of Owner will be present to discuss the project. Bidders are recommended to attend and participate in the conference. THIS CONFERENCE WILL BE HELD ONLY ONCE AND FAILURE TO

ATTEND AND SIGN IN SHALL DISQUALIFY ANY BIDDER NOT ATTENDING FROM SUBMITTING A BID.

ATTENDEES MUST BE PRESENT AT THE START OF THE PRE-BID CONFERENCE. ARRIVAL AFTER THE START

OF THE PRE-BID CONFERENCE SHALL BE CAUSE FOR DISQUALIFICATION

3. AWARD

UPON AWARD, PLEASE SUBMIT INVOICES TO:

Hernando County

Library

238 Howell Avenue

Brooksville, Florida 34601

4. DEFINITIONS AND SOLICITATION INSTRUCTIONS

4.1. DEFINITION OF TERMS

DEFINITION OF TERMS Where the following terms, or their pronouns, occur herein, the intent and meaning shall be as follows:

A. ADDENDA: Written or graphic instruments issued prior to the opening of bids which clarify, correct, or change the bidding requirements or the proposed Contract Documents.

B. AGREEMENT: The written instrument which is evidence of the Agreement between Owner and

Vendor/Contractor covering the work.

C. APPLICATION FOR PAYMENT: The form acceptable to Engineer which is to be used by

Vendor/Contractor during the course of the work in requesting progress or final payments and which is to be accompanied by such supporting documentation as is required by the Contract

Documents.

D. BID: The offer or proposal of a Bidder submitted on the prescribed form setting forth the prices for the work to be performed.

E. BID BOND/GUARANTEE: The certified check or surety bond furnished by the Bidder with his bid as evidence of good faith.

F. BID DOCUMENTS: The bidding requirements and the proposed Contract Documents, including all addenda.

G. BIDDER: The term “Bidder” used herein refers to the dealer/manufacturer or business organization submitting a bid to the County in response to this Solicitation.

H. CHANGE ORDER: A document recommended by Engineer which is signed by Vendor/Contractor and Owner and Agency and authorizes an addition, deletion, or revision in the work or an adjustment in the contract price or the contract times, issued on or after the Effective Date of the Agreement.

I. CONSTRUCTION ADMINISTRATOR: Sam Burdin, shall act as the “Construction Administrator” for the work pertaining to the acceptance and approval of Applications for Payment pursuant to the provisions of the Florida Prompt Payment Act, Section 218.735, F.S .

J. CONTRACT: The Agreement executed by the Owner and Vendor/Contractor for the performance of work and the other documents (plans, specifications, notice to Bidders, proposal, surety bonds, addenda and other incorporated or referenced documents) whether attached thereto or not.

K. CONTRACT PRICE: The moneys payable by Owner to Vendor/Contractor for completion of the work in accordance with the Contract Documents as stated in the Agreement.

L. CONTRACT TIMES: The number of days within which, or the dates by which, the work is to be substantially completed and ready for final payment as set forth in the Agreement. The contract times will commence on the date indicated in the Notice to Proceed.

M. CONTRACT WORK: Any and all obligations, duties and responsibilities necessary to the successful completion of the project assigned to or undertaken by the Vendor/Contractor under the Contract Documents, including the furnishing of all labor, materials, equipment, and other incidentals.

N. CONTRACTOR: The individual or entity with whom the County has entered into the Agreement.

O. COUNTY: The Board of County Commissioners, Hernando County, or its duly authorized representative.

P. ENGINEER: Under Contract to the Owner, the Engineer in the administration of this Contract and any references to the Engineer or the Professional shall be deemed to mean REI Engineers, Inc., for the plans and specifications referenced in these contract documents. Engineer may delegate or designate certain duties to be performed by other qualified professionals.

Q. FDEP: Florida Department of Environmental Protection

R. FDOT: Florida Department of Transportation.

S. FIELD ORDER: A written order issued by Engineer which requires minor changes in the work but which does not involve a change in the contract price or the contract times.

T. F.S.: Florida Statutes; all references to Florida Statutes shall mean the version in effect at the time the contract is signed.

U. ISSUING OFFICE: The office from which the bid documents are to be issued and where the bidding procedures are to be administered. Specifically - Hernando County, Procurement

Department, 15470 Flight Path Drive, Brooksville, Florida 34604.

V. MUTCD: Manual on Uniform Traffic Control Devices https://mutcd.fhwa.dot.gov

W. NATIONAL POLLUTANT DISCHARGE ELIMINATION SYSTEM: NPDES

X. NOTICE-WRITTEN: Notice shall be served upon the Vendor/Contractor either personally or by leaving the said notice at his residence or with his Agent in charge of the work, or addressed to the Vendor/Contractor at the residence or place of business given in the bid and deposited in a postpaid wrapper in any post box regularly maintained by the United States Post Office.

Y. MOT: Maintenance of Traffic.

Z. NOTICE OF AWARD: The written notice by Owner to the successful Bidder stating that upon timely compliance by the successful Bidder with the conditions precedent listed therein, Owner will sign and deliver the Agreement.

AA. NOTICE OF INTENT: NOI

BB. NOTICE TO PROCEED: A written notice given by Owner to Vendor/Contractor fixing the date on which the contract times will commence to run and on which Vendor/Contractor shall start to perform the work under the Contract Documents. A Notice to Proceed may be given at any time after the effective date of the Agreement.

CC. OCCUPATIONAL SAFETY AND HEALTH ACT: OSHA.

DD. OWNER: Hernando County Board of County Commissioners (County).

EE. OWNER DESIGNATED REPRESENTATIVE: The Owner Designated Representative will act as the

Owner’s representative, assume all duties and responsibilities, and have the rights and authority assigned to the Owner Designated Representative in the Contract Documents in connection with the completion of the work in accordance with their respective scope of work and the contract documents. Sam Burdin, shall act as the Owner Designated Representative for the work pertaining to this contract.

FF. PAYMENT AND PERFORMANCE BONDS: The approved forms of security furnished by the

Vendor/Contractor and his surety as a guaranty on the part of the Vendor/Contractor to execute the work in accordance with the terms of the contract and to pay all obligations associated with the project.

GG. PROJECT BUDGET/ESTIMATE: The project budget and/or estimate is the amount of funds the county has projected for this solicitation. The County estimates this solicitation to fall within the following dollar Threshold A: less than $100,000. Note: This is only an estimate and should not be the basis to determine the Vendor/Contractor bid submission amount.

1. Threshold A: less than $199,999.99

2. Threshold B: $200,000- $1,000,000

3. Threshold C: $1,000,000.01- $5,000,000

4. Threshold D: $5,000,000.01 - $15,000,000

5. Threshold E: $15,000,000.01 - $25,000,000

6. Threshold F: greater than or equal to $25,000,000.01

HH. PROFESSIONAL: The professional independent Architectural/Engineering firm designated to be the Engineer of Record (per Florida Administrative Code). Any references to the Engineer or the

Professional shall be deemed to mean REI Engineers, Inc., and its designee for the plans and specifications referenced in these Contract Documents.

II. PROJECT MANAGER: The duly authorized representative of the County during the construction period. The Project Manager of record for this Solicitation is: Sam Burdin.

JJ. SCOPE OF WORK: All materials, labor and equipment in order to accomplish the Project, as described in the specifications and construction plans showing the proposed improvements. The

Vendor/Contractor shall accomplish the work in a manner providing for the safety of their equipment and workers and for the safety of the general public.

KK. SHOP DRAWINGS: All drawings, diagrams, illustrations, brochures, schedules and other data which are prepared by the Vendor/Contractor, a subcontractor, a manufacturer, supplier or distributor and which illustrate the equipment, material and/or some portion of the work.

LL. SITE: Lands or areas indicated in the Contract Documents as being furnished by Owner upon which the work is to be performed, including rights-of-way and easements for access thereto, and such other lands furnished by Owner which are designated for the use of

Vendor/Contractor. The site or location for the work to be performed in this Contract will be

EAST HERNANDO BRANCH LIBRARY, 6457 Windmere Road, Brooksville, Florida 34602.

MM. SUBCONTRACTOR: Any person, firm or corporation other than employees of the

Vendor/Contractor who or which contracts with the Vendor/Contractor to furnish, or actually furnishes labor, materials and/or equipment for the performance of a part of the work on the project.

NN. SURETY: Any person, firm or corporation which is bound by Public Construction Bond and

Payment Bond with and for the Vendor/Contractor and which engages to be responsible for his acceptable performance of the work and for payment of all debts pertaining thereto.

OO. VENDOR/CONTRACTOR: The individual or entity with whom the County has entered into the

Agreement.

PP. WORK: The entire completed construction or the various separately identifiable parts thereof required to be furnished under the Contract Documents. Work is the result of performing services, furnishing labor and furnishing and incorporating materials and equipment into the construction, all as required by the Contract Documents.

4.2. AVAILABILITY OF BIDDING DOCUMENTS:

Interested firms may secure bid documents, plans, drawings, site locations, and other pertinent information by visiting Hernando County's eProcurement Portal. For additional information please contact the Hernando County Board of County Commissioners, Procurement Department via the

County's eProcurement Portal Q&A Tab.

4.3. PREPARATION OF BID

To ensure acceptance of your bid, please follow these instructions:

A. Interested firms are required to register via the County's eProcurement Portal . Once registered, to submit a response please click on the "DRAFT RESPONSE" button and provide an answer to all of the prompts/questions. You must respond to all required questions, and, if any, acknowledge addenda so that your response will be considered complete by the County. Bidders submitting more than one (1) bid with different pricing shall cause the Bidder to be rejected. All bids are subject to the conditions specified herein. Those, which do not comply with these conditions, may be subject to rejection.

B. Submit Bids via the Hernando County's eProcurement Portal. The responsibility for delivering the bid to the County on or before the stated time and date will be solely and strictly the responsibility of the Bidder. The County will be in no way responsible for delays caused by wi-fi connection or speed, power outage or any other occurrence.

1. Bids will be rejected unless submitted electronically via the County's eProcurement Portal along with all required bid line items. All bid forms enclosed are required to be completed and submitted using the instructions listed herein.The County will not honor any explanation or change in the bid documents unless a written addendum authorizing such change has been issued.

2. The County reserves the right to reject any and all bids and to waive any informalities related thereto.

3. All bids must be firm for a period of one hundred twenty (120) days after the time set for opening bids. Upon award, prices quoted will be in effect for the term of the contract.

4. No material, labor, or facilities will be furnished by the County unless specifically stated.

5. Blank spaces in the bid must be properly filled in and the phraseology of the bid must not be changed. Additions must not be made to items mentioned therein and any unauthorized conditions, limiting any provision, attached to a bid shall render irregular and may cause its rejection.

6. Bidders are expected to make all investigations necessary to thoroughly inform themselves regarding all drawings, specifications, delivery requirements, performance requirements, site locations and all solicitation instructions to satisfy themselves of conditions affecting submission of their bid and the terms and cost of performing the contract. No pleas of ignorance by the Bidder of conditions that exist or may hereafter exist as a result of failure or omission on the part of the Bidder to make the necessary examinations and investigations, or failure to fulfill in every detail the requirements of the contract documents, will be accepted as a basis of varying the requirements of the County or the compensation of the Bidder. Bidder agrees that submittal of a bid for the work is prima facie evidence they have conducted such examinations.

7. Communications: All technical, scope, and/or project related questions shall be submitted through the project Q&A Tab before the deadline and according to these specifications herein. Any and all other bidding communications shall only be to the County's Procurement representative using the contact information herein. Companies bidding on this project shall not communicate with any other County Staff members or they risk being disqualified.

4.4. BID OPENING

Bids received after the date and time disclosed in this Solicitation will not be accepted. Bids will be opened immediately after this date and time, and will remain binding upon the Bidder for a period of one hundred twenty (120) days thereafter. Pursuant to Florida Statutes, sec. 119.071 sealed bids, proposals, or replies received by an agency pursuant to a competitive solicitation are exempt from inspection until such time as the agency provides notice of an intended decision or until thirty (30) days after opening the bids, proposals, or final replies whichever is earlier.

4.5. SITE VISIT

Bidder may request access the site to conduct examinations, investigations, explorations, tests, and studies as Bidder deems necessary for submission of a bid by contacting the Procurement Department via the County's eProcurement Portal Q&A tab, if no mandatory site visit is scheduled. All questions after the site visit shall be submitted to the Procurement Department in writing via the County's eProcurement Portal Q&A tab . The Procurment Department will coordinate a site visit between the

Bidder and the Project Manager for this project. Bidder agrees to restore the site to its former condition upon completion of such explorations, investigations, tests, and studies. Bidder shall comply with all applicable laws and regulations relative to excavation and utility locates while accessing the site.

4.6. BIDDER’S RESPONSIBILITIES

It is the responsibility of each Bidder before submitting a bid to:

A. Read and completely understand the requirements and the specifications of the items bid.

B. Use complete sets of bid documents in preparing bids; neither Owner nor Engineer assumes any responsibility for errors or misinterpretations resulting from the use of incomplete sets of bid documents.

C. Examine and carefully study the bid documents, other related data identified in the bid documents, and any Addenda.

D. Make all investigations necessary to thoroughly inform themselves regarding all drawings, specifications, delivery requirements, performance requirements, site locations, and all solicitation instruction to satisfy themselves of conditions affecting submission of their bid and the terms and cost of performing the contract. No pleas of ignorance by the Bidder of conditions that exist or may hereafter exist as a result of failure or omission on the part of the Bidder to make the necessary examinations and investigations, or failure to fulfill in every detail the requirements of the Contract Documents, will be accepted as a basis of varying the https://secure.procurenow.com/portal/hernandocounty requirements of the County or the compensation of the Bidder. Bidder agrees that submittal of a bid for the work is prima facie evidence they have conducted such examinations.

E. Request access to the site to become familiar with general, local, and site conditions that may affect cost, progress, and performance of the work.

F. Become familiar with all Federal, State, and local laws and regulations that may affect cost, progress, or performance of the work.

G. Obtain and carefully study all additional or supplementary examinations, investigations, explorations, tests, studies, and data concerning conditions (surface, subsurface, and underground facilities) at or contiguous to the site which may affect cost, progress, or performance of the work or which relate to any aspect of the means, methods, techniques, sequences, and procedures of construction to be employed by the Bidder, including applying any specific means, methods, techniques, sequences, and procedures of construction expressly required by the bid documents, and safety precautions and programs incident thereto.

H. Agree at the time of submitting its bid that no further examinations, investigations, explorations, tests, studies, or data are necessary for the determination of its bid for performance of the work at the price(s) bid and within the times and in accordance with the other terms and conditions of the bid documents.

I. Become aware of the general nature of the work to be performed by Owner and others at the site that relates to the work as indicated in the bid documents.

J. Correlate the information known to Bidder, information and observations obtained from visits to the site, reports and drawings identified in the bid documents, and all additional examinations, investigations, explorations, tests, studies, and data with the bid documents.

K. Promptly give Engineer written notice of all conflicts, errors, ambiguities, or discrepancies that

Bidder discovers in the bid documents and confirm that the written resolution thereof by

Engineer is acceptable to Bidder.

L. Determine that the bid documents are generally sufficient to indicate and convey understanding of all terms and conditions for the performance of the work.

M. Bidder accepts all of the terms and conditions of the Instructions to Bidders, including without limitation those dealing with the disposition of bid security. This bid will remain subject to acceptance for one hundred twenty (120) days after the bid opening, or for such longer period of time that Bidder may agree to in writing upon request of Owner.

N. Bidder has enclosed a Certified check, Cashier’s Check or Bid Bond in the amount of not less than the five percent (5%) of the Total Base Bid Amount payable to the Hernando County Board of County Commissioners as a guarantee for the purpose set out in the Instructions to Bidders.

4.7. QUESTIONS REGARDING SPECIFICATIONS OR BIDDING PROCESS:

To ensure fair consideration for all Bidders, the County prohibits communication to or with any department, division or employee during the bid process, except as provided below:

A. All questions relative to interpretation of the specifications or the bid process shall be addressed in writing via Hernando County's County's eProcurement Portal Q&A Tab, prior to the date set for submittal and opening of the bids.

B. Any interpretation or clarification made to prospective Bidders will be expressed in the form of an addendum which, if issued, will be posted on the County's eProcurement Portal Q&A tab:.

Oral answers will not be authoritative.

C. It will be the responsibility of the Bidder to visit https://secure.procurenow.com/portal/hernandocounty to insure they are aware of all addenda issued for this solicitation.

D. Questions will only be accepted through the period specified Monday, June 8, 2026 until 5 P.M.

E. All addenda must be acknowledged via the County's eProcurement Poral. Failure of any Bidder to acknowledge any addenda may be found non-responsive and subject to rejection.

4.8. COMMUNICATION

There shall be no communication between the Vendor/Contractor, their employees or subcontractors and County employees and elected officials (hereafter referred to as “County Representative”), except through the Procurement Department. Any attempt to communicate with any County Representative outside the Procurement Department will be considered a violation of the Procurement Policy and may result in the rejection of your bid.

4.9. WITHDRAWAL OF BIDS:

Bids may be withdrawn prior to the Monday, June 29, 2026 , 10:00 am via the County's eProcurement

Portal. Negligence on the part of the Bidder in preparing the bid confers no right for the withdrawal of the Bid after it has been opened. No Bidder may withdraw their bid after the scheduled opening time for receipt of bids. Faxed or electronically mailed withdrawals will not be recognized.

4.10. BID PROTESTS

Any Bidder who protests the Bid Specifications or Award or Intent to Award, must file with the County a notice of protest and formal written protest in compliance with the Hernando County Procurement

Manual, Section 22, which can be found at procurement-manual_v-july-2025.pdf. Failure to timely file such documents will constitute a waiver of proceedings. Failure to file a protest within the time prescribed by, or failure to post the bond or other security in strict accordance with, the Hernando

County Procurement Manual, Section 22, shall constitute a waiver of protest proceedings.

https://secure.procurenow.com/portal/hernandocounty https://secure.procurenow.com/portal/hernandocounty https://secure.procurenow.com/portal/hernandocounty https://secure.procurenow.com/portal/hernandocounty https://www.hernandocounty.us/media/vwnjxtgp/procurement-manual_v-july-2025.pdf

4.11. QUALIFICATION OF BIDDERS

A. The Vendor/Contractor shall have previous experience in the type of construction work specified herein, and experience in the installation of the materials to be provided for the project specified herein.

B. The Vendor/Contractor and/or subcontractors shall be an appropriately licensed Contractor in the State of Florida at the time of the bid and must have successfully completed a minimum of two (2) projects of similar size and complexity in the past seven (7) years. These requirements are in addition to the requirements in Section entitled, "Reference Documents" below.

C. The Vendor/Contractor’s Project Superintendent must have a minimum of three (3) years’ experience as Project Superintendent and must have directed at least two (2) previous projects of similar size and complexity. These requirements are in addition to the requirements in

Section entitled, "Reference Documents."

D. Bidders shall submit evidence of this experience on the forms provided in the bid documents, along with the accompanying information requested below:

1. Overview of construction experience, including a list of projects successfully completed and indicating Owner, location, contract value and completion date.

2. Documentation of two (2) projects, similar in scope and complexity to this project, which have been successfully completed by the Bidder within the past seven (7) years.

3. Identification of firms comprising the Vendor/Contractor’s team on the Construction

Contractor Qualification Submittal Package attached to Vendor Questionnaire.

4. Resumes of the Vendor/Contractor’s Project Superintendent documenting the experience required for these individuals.

E. Failure to submit this information may be basis for rejection of the bid.

4.12. QUALIFICATION OF SUBCONTRACTORS, MATERIAL VENDOR, SUPPLIERS,

AND OTHERS:

A. The Vendor/Contractor will, within ten (10) days after execution of the Agreement, submit to the County through the Owner Designated Representative for acceptance a list of the names of subcontractors and such other persons and organizations proposed for those portions of the work as to which the identity of the subcontractors and other persons and organizations must be submitted as specified in the Contract Documents. The Owner Designated Representative will notify the Vendor/Contractor in writing if the Owner Designated Representative, after due investigation, has reasonable objection to any subcontractor, person or organization on such list. The failure of the Owner Designated Representative to make objections to any subcontractor, person or organization on the list shall constitute an acceptance of such subcontractor, person or organization. Acceptance of any such subcontractor, person or organization shall not constitute a waiver of any right of the County to reject defective work, material or equipment, or work material or equipment not in conformance with the requirements of the Contract Documents.

B. If the apparent successful Bidder declines to make any such substitution, County may award the

Contract to the next lowest responsive, responsible Bidder that proposes to use acceptable subcontractors, suppliers, individuals, or entities. Declining to make requested substitutions will not constitute grounds for forfeiture of the bid security of any Bidder. Any subcontractor, supplier, individual, or entity so listed and against which the County and Owner Designated

Representative makes no written objection prior to the giving of the Notice of Award will be deemed acceptable to the County and Owner Designated Representative subject to revocation of such acceptance after the effective date of the Agreement.

C. Vendor/Contractor shall not be required to employ any subcontractor, supplier, individual, or entity against whom Vendor/Contractor has reasonable objection.

D. The Vendor/Contractor agrees that he is as fully responsible to the County for the acts and omissions of his subcontractors and of persons either directly or indirectly employed by them, as he is for the acts and omissions of persons directly employed by him. Nothing contained in the Contract Documents shall create any contractual relation between any subcontractor and the County.

4.13. EXAMINATION OF BIDDING DOCUMENTS, OTHER RELATED DATA, AND SITE:

A. Subsurface and Physical Conditions:

1. The Technical Specifications will identify:

a. Any reports of explorations and tests of subsurface conditions at or contiguous to the site that Engineer has used in preparing the bid documents.

b. Any drawings of physical conditions in or relating to existing surface and subsurface structures at or contiguous to the site (except underground facilities) that Engineer has used in preparing the bid documents.

2. Copies of any reports and drawings referenced in the solicitation documents will be made available by Owner to any Bidder via the County's eProcurement Portal. Bidder is responsible for any interpretation or conclusion Bidder draws from any technical data or any other data, interpretations, opinions, or information contained in such reports or shown or indicated in such drawings.

B. Underground Facilities:

1. Information and data shown or indicated in the bid documents with respect to existing underground facilities at or contiguous to the site is based upon information and data furnished to Owner and Engineer by owners of such underground facilities, including Owner, or others.

C. Hazardous Environmental Condition:

1. The Technical Specifications identify any reports and drawings relating to a hazardous environmental condition identified at the site that Engineer has used in preparing the bid documents.

4.14. BID GUARANTEE/BID BOND:

A. Each bid must be accompanied by a Certified Check, Cashier’s Check, Official Bank Check or Bid

Bond payable to the Owner for an amount equal to at least five percent (5%) of the amount of bid, as guarantee that the Bidder will within fifteen (15) consecutive calendar days after award, enter into a written contract with the County for the performance of the work as awarded.

B. Any submitted Bid Bond must be submitted to the County.

C. Any submitted checks shall be drawn on a solvent bank or trust company to the order the

Hernando County Board of County Commissioners and shall have all necessary documentary revenue stamps attached, if required by law.

D. Surety of Bid Bonds shall be a duly authorized surety company authorized to do business in the

State of Florida; all such bonds being issued or countersigned by a local producing agent who is a resident of the State of Florida and satisfactory evidence of the authority of the person or persons executing such bond being submitted with the bond. Personal checks are not acceptable to Hernando County.

E. The County will, within ten (10) days after the Notice of Intent to Award, return the deposit of all Bidders except those posted by the three (3) lowest acceptable Bidders, whose deposit will be returned upon the final award and execution of the Contract between the successful Bidder and County, and after a satisfactory Performance Bond and Payment Bond have been executed.

F. Attorneys-in-fact who sign bonds or other surety instruments must attach with each bond or surety instrument a certified and effectively dated copy of their power of attorney.

G. If the successful Bidder fails to execute and deliver the Contract Documents and furnish the required contract security within fifteen (15) days after the Notice of Award, Owner may withdraw the Notice of Award and the Bid Bond of that Bidder will be forfeited. The Bid Bond of other Bidders whom Owner believes to have a reasonable chance of receiving the award may be retained by Owner until the earlier of seven (7) days after the effective date of the Agreement or sixty-one (61) days after the bid opening, whereupon Bid Bonds furnished by such Bidders will be returned.

H. Bid Bonds of other Bidders whom Owner believes do not have a reasonable chance of receiving the award will be returned within thirty (30) days after the Bid opening.

I. Bidders desiring their original Bid Bonds returned shall enclose a self-addressed stamped envelope with their bids marked “Bid Bond” in the lower left corner.

4.15. PERFORMANCE AND PAYMENT BOND:

A. Performance and Payment Bond issued in a sum equal to one hundred percent (100%) of the total awarded contract amount by a surety company considered satisfactory by the County and otherwise authorized to transact business in the State of Florida will be required from the successful Bidder for purposes of insuring the faithful performance of the obligations imposed by the resulting contract and for purposes of protecting the County from lawsuits for non-payment of debts as might be incurred during the successful Bidder's performance under such contract. When applicable, the performance and payment bond form will be included in the contract documents and said form must be properly executed by the surety company and successful Bidder within fifteen (15) calendar days after notification by the County of the

County's intent to award the contract.

B. If, within fifteen (15) calendar days after notification by the County of the County's intent to award a contract, the successful Bidder refuses or otherwise neglects to execute the required written contract or fails to furnish the required performance and payment bond, the amount of the Bidder's bid security (check or Bid Bond) shall be forfeited and the same shall be retained by the County. No plea of mistake in the Bid or misunderstanding of the conditions of forfeiture shall be available to the Bidder for the recovery of his bid security or as a defense to any action based upon the neglect or refusal to execute a written contract.

C. The surety company must provide an Increase Rider to the Performance and Payment Bond or execute the Consent of Surety and Increase of Penalty form provided by the County if the contract is increased by change order.

4.16. FOREIGN COUNTRIES OF CONCERN:

Pursuant to 287.138 F.S., effective July 1, 2023, the County may not enter into contracts which grants the Vendor/Contractor access to personal identifiable information if: a) the Contractor is owned by the government of a Foreign Country of Concern (as defined by the statute): (b) the government of a

Foreign Country of Concern has a controlling interest in the entity; or (c) the Contractor is organized under the law of or has its principal place of business in a Foreign Country of Concern.

Bidders/Proposers must provide a response to the section titled VENDOR QUESTIONNAIRE, Foreign

Countries of Concern included in this solicitation.

Beginning July 1, 2025, a governmental entity is prohibited from extending or renewing a contract with an entity meeting the requirements of (a), (b) or (c) above, if the contract would give such entity access to an individual’s personal identifying information.

5. GENERAL CONDITIONS

5.1. CONTRACT DOCUMENTS

The following constitute the Contract Documents (Title, Subtitles, Headings, Running Headlines, Table of

Contents, and Indexes are used merely for convenience purposes):

Solicitation

Introduction

Definitions and Solicitation Instructions

General Conditions

Special Conditions

Scope and Specifications

Attachments

Exhibit A--Construction_Documents_required_after_Award

Exhibit B--Sample_Construction_Contract

Exhibit C -- Hernando_E_Library_Soffit_CAD_-_Update_2026-Sealed

Exhibit D -- Guide_Specs-_Heranando_County_Wast_Library_Soffit_Replace-_Sealed

Exhibit E -- Engineers Addendum

A. All addenda issued by the County prior to the receipt of bids and all supplementary drawings issued after award of the Contract become part of the Contract Document.

B. Amending and Supplementing Contract Documents:

1. The Contract Documents may be amended to provide for additions, deletions, and revisions in the work or to modify the terms and conditions thereof by Change Order.

2. The requirements of the Contract Documents may be supplemented, and minor variations and deviations in the work may be authorized, by one (1) or more of the following ways:

a. A field order;

b. Engineer’s approval of a shop drawing or sample; or

c. Engineer’s written interpretation or clarification per the provisions described in the

Contract Documents.

3. In resolving such conflicts, errors and discrepancies, the documents shall be given preference in the following order: Agreement, Specifications, Drawings, Solicitation

Instructions. Within the specifications the order of preference shall be as follows: Addenda, General Conditions, Technical Specifications. Figure dimensions on drawings shall govern over scale dimensions, and the detailed drawings shall govern over general drawings. Any work that may reasonably be inferred from the specifications or drawings as being required to produce the intended result shall be supplied whether or not it is specifically called for.

Work materials or equipment described in words which so applied have a well-known technical or trade meaning shall be deemed to refer to such recognized standards. In case of conflict the more stringent requirements shall take precedence and govern.

4. The Vendor/Contractor shall take no advantage of any error or omission in the plans or of any discrepancy between the plans and specifications, and the Engineer shall make such interpretation as may be deemed necessary for the fulfillment of the intent of the plans and specifications as construed by him and his decision shall be final.

C. All provisions required by law to be inserted in this Contract, whether actually inserted or not.

D. Exhibits to this Agreement (as follows):

1. Vendor/Contractor’s Pricing Proposal (Bid).

2. Documentation submitted by Vendor/Contractor after the Notice of Award:

a. Insurance Certificate.

b. Payment and Performance Bond.

3. The following which may be delivered or issued on or after the effective date of the

Agreement and are not attached hereto:

a. Notice to Proceed.

b. Change Order(s).

E. The documents listed in this paragraph are attached to the Agreement (except as expressly noted otherwise).

F. There are no Contract Documents other than those listed in this paragraph.

G. The Contract Documents may only be amended, modified, or supplemented as provided in the

Contract Documents.

5.2. BID PRICE/SUBMITTAL REQUIREMENTS:

A. The prices bid shall remain firm during the period of the Contract. The prices bid shall be inclusive of all labor, equipment, and materials as specified within this Solicitation. The price bid constitutes the total compensation payable to the Vendor/Contractor for performing the work.

B. Unless otherwise stated, the prices bid shall include all costs of packing, transporting, delivery, and services to the designated point within Hernando County.

C. The Bidder hereby certifies that this bid is made without prior understanding, agreement, or connection with any corporation, firm, or person submitting a bid for the same materials, supplies, services, or equipment and is in all respects fair and without collusion or fraud.

Further, the Bidder hereby agrees to abide by all terms and conditions of this bid and certifies that the person executing the Bid Form is authorized to sign this bid for the Bidder.

D. Bidders shall submit a lump sum bid based on unit price line item components as indicated on the Bid Form, and include a separate price for each alternate described in the bid documents and provided for in the Bid Form. The sum of each unit price line item will be the Total Base Bid.

The price for each alternate will be the amount added to or deducted from the Total Base Bid if the County selects the alternate.

E. Discrepancies between the multiplication of units of work and unit prices will be resolved in favor of the unit prices. Discrepancies between the indicated sum of any column of figures and the correct sum thereof will be resolved in favor of the correct sum. Discrepancies between words and figures will be resolved in favor of the words.

F. Bidder must submit all Required Forms and Certifications. Failure to submit these forms may render the bid non-responsive.

5.3. HOURS

All work is to be performed during regular working hours, 8:00 a.m. to 6:00 p.m; Monday through

Friday, except County holidays. The County may, on certain occasions, approve work outside of these times. Such exception(s) must be approved in writing by the County at least one (1) day in advance.

5.4. REJECTION OF BID:

The County reserves the right to reject any and all bids. Bids which are incomplete, unbalanced, conditional, obscure or which contain additions not required, or irregularities of any kind, or which do not comply with every aspect of this Solicitation, may be rejected at the option of the County. A Bidder shall not be qualified to bid when an investigation by the Chief Procurement Officer reveals that the

Bidder is delinquent on a previously awarded contact or in litigation with Hernando County regarding a previously awarded contract.

5.5. MINOR INFORMALITIES AND IRREGULARITIES:

Hernando County has the right to waive minor defects or variations of a bid from the exact requirements of the specifications that do not affect price, quality, quantity, delivery, or performance time of the services being procured. If insufficient information is submitted by a Bidder with the bid for

Hernando County to properly evaluate the bid, Hernando County has the right to require such additional information as it may deem necessary after the time set for receipt of bids, provided that the information requested does not change the price, quality, quantity, delivery or performance time of the services being procured. The Board of County Commissioners reserves the right to reject any or all bids in whole or in part; to award by any item, group(s) of items or in the aggregate whichever is most advantageous to the County.

5.6. NON-EXCLUSIVE CONTRACT:

Award of a contract resulting from this bid imposes no obligation on the County to utilize the

Vendor/Contractor for all work of this type, which may develop during the contract period. This is not an exclusive contract. The County specifically reserves the right to contract with another company for similar work if it deems such action to be in the County’s best interest.

5.7. NON-PERFORMANCE:

A. Time is of the essence in this Contract and failure to deliver the services specified within the time period required shall be considered a default.

B. In case of default, the County may procure the services from other sources and hold the

Vendor/Contractor responsible for all costs occasioned thereby and may immediately cancel the

Contract.

5.8. ASSIGNMENT

The successful Bidder is required to perform this Contract and may not assign, transfer, convey, sublet or otherwise dispose of any award or any or all of its rights, title, or interest therein, or the resulting

Agreement in whole or in part without prior written authorization given at the sole discretion of

Hernando County.

5.9. PUBLIC ENTITY CRIMES:

Any person submitting a bid or proposal in response to this invitation certifies that they are aware of, and in compliance with, all requirements under Section 287.133, Florida Statutes, on Public Entity

Crimes. Bidders must provide a response to the section titled VENDOR QUESTIONNAIRE, Sworn

Statement to Public Entity Crimes included in these bid documents.

5.10. LICENSES AND PERMITS:

A. Prior to furnishing the requested product(s) or service(s), it shall be the responsibility of the awarded Vendor/Contractor to obtain, at no additional cost to Hernando County, any and all licenses and permits required to complete this contractual service, unless otherwise stated in the Contract Documents. These licenses and permits shall be readily available for review by the

Chief Procurement Officer or his/her designee. Failure to have and/or furnish the required licenses or permits may be cause for rejection.

B. The Vendor/Contractor is hereby notified that a list of fees for construction related County certified licenses and County issued permits can be located at:

https://www.hernandocounty.us/departments/departments-a-e/building-division/contractors.

C. The following permits are necessary for prosecution of the work. It is the Vendor/Contractor's responsibility to determine whether additional permits are required. Vendor/Contractor and/or subcontractors shall obtain and pay for required permits. Notice to Proceed will not be issued until the permits are provided to the Project Manager.

1. NPDES-NOI Permit - The NPDES-FDEP legislation and permit information can be found on this site: https://floridadep.gov/water/stormwater

2. Building Permit, Electrical Permit.

D. Vendor/Contractor and/or subcontractors shall be responsible for complying with all State of

Florida and Hernando County license requirements prior to bidding on County projects and shall submit proof of licenses with the Bid. All licenses shall be in the Bidder’s name or the key subcontractor’s name, as listed in Questionnaire. Failure to submit proof of the required licenses shall deem the Bidder non-responsive. The following is a non-exhaustive list of the licenses necessary for prosecution of the work. It is the Vendor/Contractor's responsibility to determine if additional licenses are necessary.

1. Certified Roofing Contractor or Certified Building or General Contractor

E. Vendor/Contractors and/or subcontractors who are not properly licensed and/or do not furnish proof thereof with their bid, may be deemed non-responsive and may be rejected.

F. Owner shall assist Vendor/Contractor, when necessary, in obtaining such permits and licenses.

Vendor/Contractor shall pay all governmental charges and inspection fees necessary for the prosecution of the work which are applicable at the time of opening of bids. Owner shall pay all charges of utility owners for connections for providing permanent service to the work.

5.11. LAWS, REGULATIONS, PERMITS AND TAXES:

A. All applicable Federal and State laws, municipal and county ordinances, and the rules and regulations of all authorities having jurisdiction over any part of the project shall apply to the

Contract throughout, and they will be deemed to be included in the Contract the same as through herein written https://www.hernandocounty.us/building-development/building/ https://floridadep.gov/water/stormwater

B. Vendor/Contractor shall comply with County's jobsite procedures and regulations and with all applicable local, State and Federal laws, rules and regulations and shall obtain all permits required for…

This is the start of the file's text. The full file is on GovTribe.