This is a specification document and contract opportunity for the City of Cheyenne, Wyoming's Street and Alley Division for the procurement of bituminous asphalt materials under an annual contract. The City is soliciting sealed bids for approximately 5,000 tons of Bituminous Asphalt Hot Plant Mix (PG 64-28 grade), 6,000 gallons of Emulsified Asphalt Tack Oil (CSS-1h grade), and 350 tons of Bituminous Cold Mix for patching operations. All materials must meet stringent technical specifications including 3-5% total mix voids, 13-16% voids in mineral aggregate, minimum stability of 2,000-2,500 pounds depending on compaction method, and tensile strength retention of 75-80% depending on additives used. The successful bidder must operate a supply plant located no more than ten miles outside City limits with minimum production capacity of 120 tons per hour, capable of delivering materials within two hours of notice during operating hours of 7:00 AM to 4:30 PM, Monday through Thursday. Job mix formulas for each material type must be submitted within thirty days of award, prepared by an approved independent laboratory with a registered Wyoming engineer's signature. Questions must be submitted by April 2, 2026 at 5:00 pm, sealed bids are due electronically by April 7, 2026 at 2:00 pm with public bid opening via Zoom the same date, and City Council approval is scheduled for April 27, 2026. The contract term is one year from award with thirty-day termination provision.
All testing and quality assurance shall be conducted at the supplier's expense with results available within twenty-four hours. Award will be made to the qualified, responsible lowest responsive bidder; however, Wyoming resident bidders will receive a five percent preference provided their bid does not exceed the lowest qualified non-resident bidder's bid by more than five percent, except where federal funds are involved. Bidders must submit a bid guarantee equal to five percent of the total bid amount in the form of a bid bond or cashier's check. Liquidated damages of 0.10 percent of the per-item price per calendar day or $30.00 per item per calendar day, whichever is greater, will be assessed for non-unavoidable delivery delays. The City reserves the right to adjust quantities based on budget availability, reject any or all bids, and assess payment reductions according to Wyoming Department of Transportation pay factor tables if materials fail to comply with specifications. If the contract supplier fails to provide requested quantities, the City may acquire materials elsewhere with cost differences charged back to the supplier. No specific award value or budget range is disclosed, and no incumbent vendor information or set-aside designations for disadvantaged enterprises are indicated.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 2026_-_Bituminous_Asphalt_Hot_Mix,_Tack_Oil_and_Cold_Mix.pdf | ||
| E-17-26_SPECS.pdf | ||
| CITY_OF_CHEYENNE_BID_BOND_FORM.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
02512 - 1 of 21 March, 2022
SPECIAL PROVISIONS
These special provisions shall supplement, amend, and wherein conflict therewithin, supersede various sections of the “City of Cheyenne and Board of Public Utilities Construction Standards and Specifications , 2022” and all Amendments to date. Special Provisions may also include new sections of specifications not covered in the standard specifications and will be numbered starting from Section 04000.
CONTENTS:
SECTION 02190- AGGREGATES
SECTION 20512- PLANT MIX PAVEMENTS
SECTION 02545- BITUMINOUS MATERIALS
02512 - 2 of 21 March, 2022
SECTION 02512
PLANT MIX PAVEMENTS
PART 1 GENERAL
1.01 SUMMARY
A. This section consists of general requirements that are applicable to all types of bituminous pavements of the plant mix type irrespective of gradation of aggregate, kind, and amount of bituminous material or pavement use. Deviations from these general requirements shall be indicated in the specific requirements for each type.
B. This section consists of one (1) or more courses of bituminous mixture constructed on the prepared foundation in accordance with these specifications and the specific requirements of the type under contract, and in reasonably close conformity with the lines, grades, thickness and typical cross sections shown on the plans or established by ENGINEER.
1.02 RELATED WORK
A. Section 02190 - Aggregates.
B. Section 02514 - Crack Sealing of Asphalt Pavements.
C. Section 02515 - Asphalt Patching.
D. Section 02545 - Bituminous Materials.
E. Section 02551 - Tack Coat.
F. Section 02552 - Seal Coat.
1.03 REFERENCES
A. ASTM C150: Standard Specification for Portland Cement.
B. AASHTO M303: Lime for Asphalt Mixtures.
C. AASHTO T283: Resistance of Compacted Asphalt Mixtures to
Moisture Induced Damage.
D. Asphalt Institute MS-2: Mix Design Methods for Asphalt Concrete.
02512 - 3 of 21 March, 2022
E. ASTM D140: Standard Practice for Sampling Bituminous
Materials.
F. ASTM D979: Standard Practice for Sampling Bituminous Paving
Mixtures.
G. ASTM C1097: Standard Specification for Hydrated Lime for Use in
Asphalt Cement or Bituminous Pavements.
H. ASTM D1188: Standard Test Method for Bulk Specific Gravity and
Density of Compacted Bituminous Mixtures Using Paraffin-Coated Specimens.
I. ASTM D1559: Standard Test Method for Resistance of Plastic Flow of Bituminous Mixtures Using Marshall Apparatus.
J. ASTM D2041: Standard Test Method for Theoretical Maximum
Specific Gravity and Density of Bituminous Paving Mixtures.
K. ASTM D2726: Standard Test Method for Bulk Specific Gravity and
Density of Non-Absorptive Compacted Bituminous Mixtures.
L. ASTM D2950: Standard Test Method for Density of Bituminous
Concrete in Place by Nuclear Method.
M. ASTM D3665: Standard Practice for Random Sampling of
Construction Materials.
N. ASTM D4125: Standard Test Method for Asphalt Content of
Bituminous Mixtures by the Nuclear Method.
O. ASTM D5361: Standard Practice for Sampling Compacted
Bituminous Mixtures for Laboratory Testing.
P. ASTM D5444: Standard Test Method for Mechanical Size Analysis of Extracted Aggregate.
Q. ASTM D6307: Standard Test Method for Asphalt Content of Hot-
Mix Asphalt by Ignition Method.
02512 - 4 of 21 March, 2022
1.04 SUBMITTALS
A. Mix design shall be submitted to the ENGINEER for approval. The job-mix formula (JMF) with the allowable tolerances shall be within the master range specified. The job-mix formula for each mixture shall establish a single percentage of aggregate passing each required sieve size and a single mixing temperature. Mix designs shall be updated on an annual basis by mix verification tests performed by an independent testing laboratory. Mix verification tests shall include a laboratory batched verification point at optimal oil content and aggregate blend of the previously approved mix design. The mix verification will be approved if:
1. Do not furnish mix with virgin aggregate fractions that exceed the wide band limits or the tolerance ranges from the target JMF, in accordance with the following table:
Passing #4 and Larger Sieves + 5% Passing #8 Sieve + 4% Passing #30 Sieve + 3% Passing #200 Sieve + 2%
2. The maximum theoretical unit weight must be within two
(2) pounds per cubic foot of the previously approved mix design.
Should a change in material be made, a new job-mix formula shall be approved before the new material is used. When unsatisfactory results or other conditions make it necessary, ENGINEER may approve a new job-mix formula.
B. Mixing plant scales shall be checked as often as deemed necessary by the ENGINEER to assure their continued accuracy.
CONTRACTOR shall have on hand not less than ten (10) fifty (50) pound weights for checking of the scales.
C. Mix designs shall be submitted for review to the ENGINEER a minimum of fourteen (14) days prior to anticipated use in the work.
D. During production for CITY roadways with two hundred (200) tons or greater daily, the following shall be submitted to the CITY Construction Division on a daily basis:
1. Gradation Verification
02512 - 5 of 21 March, 2022
2. Copy of asphalt heat chart.
3. Copy of total day’s production quantities for the mix.
4. Records of tank stabs and asphaltic concrete manifests throughout production period for CITY mix.
5. Lime weights and manifests shall be provided.
6. Manifests for liquid anti-strip shall be provided.
E. During production for CITY roadways with less than two hundred
(200) tons daily, excluding patching, a gradation and asphalt binder content by tank stabs shall be submitted to the ENGINEER.
F. No payment shall be made for plant mix pavement until the above submittals are received and approved.
1.05 DEFINITIONS
A. Plant mix pavement is considered a surface course in all cases.
B. Plant mix bituminous base is considered a subsurface course.
PART 2 PRODUCTS
2.01 MATERIALS
A. BITUMINOUS MATERIALS
1. The percentage of bituminous material to be added to the job mix formula shall be designated by mix design.
2. The type and grade of bituminous material shall be PG 64-
28 unless otherwise shown on the plans or as approved by the ENGINEER.
3. The bituminous material shall meet the applicable requirements of SECTION 02545, BITUMINOUS
MATERIALS.
B. AGGREGATE MATERIALS
02512 - 6 of 21 March, 2022
1. Aggregates shall meet the applicable requirements of
SECTION 02190, AGGREGATES.
2. During crushing operations, the coarse and fine aggregates shall be stockpiled in separate piles in such manner that they can later be combined to meet the required specifications.
3. Stockpiled material shall meet the requirements of
SECTION 02190, AGGREGATES.
4. Natural filler, when required, shall be stockpiled separately.
The plans may limit or prohibit the use of crusher rejects or material from the same source as the aggregate material.
C. COMMERCIAL ADDITIVES
1. The type of commercial additive to be used will either be designated on the plans, or when no specific type is designated, any of the commercial additives conforming to either of the following requirements may be used:
a. HYDRATED LIME - Hydrated lime shall conform to the requirements of ASTM C1097, except that not less than ninety-three (93) percent of the hydrated lime shall consist of calcium and magnesium oxides.
A minimum of one and one-half (1.5) percent hydrated lime shall be used in all plant mix pavements. Hydrated lime and water shall be mixed with the aggregate prior to entering the dryer.
Payment shall be subsidiary to the pavement and not by the ton. The rate of application shall be one and one-half (1.5) percent and must achieve a minimum Tensile Strength Retained (TSR) of 75%.
b. LIQUID ANTI-STRIP AGENTS - Liquid anti-strip agents may be used provided the anti-strip agent is thermally stable and compatible with the asphalt binder. The liquid anti-strip shall be applied at the rate required to achieve a minimum TSR of 80%.
D. COMPOSITION OF MIXTURES
1. The bituminous plant mix shall be composed of a mixture of aggregate, natural filler or commercial additive, if required, and bituminous material. The several aggregate fractions
02512 - 7 of 21 March, 2022 shall be sized, uniformly graded, and combined in such proportions that the resultant composite blend meets the job-mix formula. The suggested job mix formula may require adjustments due to variation in aggregate, gradation, or other actual field conditions encountered.
2. Do not furnish mix with virgin aggregate fractions that exceed the wide band limits or the tolerance ranges from the target JMF, in accordance with the following table:
Passing #4 and Larger Sieves + 5% Passing #8 Sieve + 4% Passing #30 Sieve + 3% Passing #200 Sieve + 2% Bituminous Material + 0.25% Mixing Temperature + 20°F
a. The physical properties of the mix design and plant mix product during production shall meet or fall within the following mixture properties:
Voids, Total Mix 3-5% Voids in mineral aggregate 13% - 16% Stability (lbs) 2000 Minimum (50
Blows) 2500 Minimum (75
Blows) Flow, (0.01in.) 8-18 Tensile Strength Retained 75 % Minimum w/ (AASHTO T283) Lime Additive 80% Minimum w/Liquid Anti-Strip Agent
Film Thickness 8-12 Aggregate/Lime Moisture Content % Minimum 4.0% Minimum
b. Asphalt Binder Content will be determined on two hundred (200) tons or more by determining asphalt binder used as a percentage of plant mix produced.
The binder’s weight (mass) will be determined from delivery invoices and the quantity of material remaining in the storage tank at the end of a day’s production. The calculation to determine content will include all material used during the day’s production
02512 - 8 of 21 March, 2022 of plant mix, including asphalt binder and plant mix not incorporated into the project.
c. If the oil content is between + 0.25% and + 0.5%, of the approved mix design, the plant will be shut down and plant will be recalibrated before production is resumed. A letter will be sent to the project engineer explaining correction. If the oil content exceeds + 0.5% based on tank stabs on production tons of two hundred (200) tons or more, asphalt paving will be removed and replaced.
3. In general, the point of acceptance for the aggregate shall be after the material has passed through the gradation unit and prior to the addition of bituminous material. If this point of acceptance proves unsatisfactory, an alternate point of acceptance may be selected by ENGINEER.
PART 3 EXECUTION
3.01 PREPARATION
A. CONDITIONING OF EXISTING SURFACE
1. Irregular surfaces of existing pavements or bases shall be brought to uniform grade and cross section as directed.
B. PREPARATION OF BITUMINOUS MATERIAL
1. The bituminous material shall be heated to the specified temperature in a manner that will avoid local overheating and provide a continuous supply of the bituminous material to the mixer at a uniform temperature at all times and in conformance with SECTION 02545, BITUMINOUS
MATERIALS.
C. PREPARATION OF AGGREGATE
02512 - 9 of 21 March, 2022
1. The aggregates for the mixture shall be dried and heated to the required temperature. Flames used for drying and heating shall be properly adjusted to avoid damage to the aggregate or coating the aggregate with soot, oil, or other contaminants. Burner fuels may be specified by ENGINEER in the Special Provisions.
D. MIXING
1. After the required amounts of aggregate and bituminous material have been introduced into the mixer, the materials shall be mixed until a complete and uniform coating of the particles and a thorough distribution of the bituminous material throughout the aggregate is secured.
2. For hot mix bituminous pavement, the mixture shall be produced at the lowest possible temperature that will produce a workable mix within the application temperatures specified under SECTION 02545, BITUMINOUS MATERIALS. The bituminous material and aggregate shall be introduced into the mixer within the specified temperature range and shall be within 25°F of each other.
E. BITUMINOUS MIXING PLANT - GENERAL
1. Sufficient storage space shall be provided for each size of aggregate, and the different aggregate sizes shall be kept separated until they have been delivered to the cold elevator feeding the dryer.
2. Plants used for preparation of bituminous mixtures shall conform to all requirements under subsection 3.01(F) below.
In addition, dryer-drum mixers shall conform to the requirements under subsection 3.01(H) herein.
3. Mixing plants shall be of sufficient capacity and coordinated to adequately handle the proposed bituminous construction.
F. REQUIREMENTS FOR ALL PLANTS
1. Scales shall be accurate to one-half (½) percent of the maximum load that may be required. Poises shall be designed to be secured in any position to prevent inadvertent change of position. CONTRACTOR may provide an approved automatic printer system which will print the
02512 - 10 of 21 March, 2022 weights of the material delivered, provided the system is used in conjunction with an approved automatic batching and mixing control system. Such weights shall be evidenced by a weigh ticket for each load.
2. Tanks for the storage of bituminous material shall be equipped to heat and hold the material at the required temperatures. The heating shall be accomplished by steam coils, electricity, or other approved means so that no flame shall be in contact with the tank. Provision shall be made for measuring and sampling storage tanks.
3. The plant shall be provided with accurate mechanical means for uniformly feeding the aggregate into the dryer so that uniform production and uniform temperature will be obtained.
4. The plant shall include a dryer or dryers which continuously agitate the aggregate during the heating and drying process.
For cold-type bituminous mix, equipment for mechanical cooling of the dried aggregate to the temperature prescribed for cold mixtures shall be provided and shall be capable of supplying prepared material for the mixer to operate at full capacity.
5. The plant shall include storage bins of sufficient capacity to supply the mixer when it is operating at full capacity. Bins shall be arranged to assure separate and adequate storage of appropriate fractions of the mineral aggregates. Separate dry storage shall be provided for commercial additives when used, and the plant shall be equipped to feed such material into the mixer. Each bin shall be provided with overflow pipes of such size and at such location as to prevent backing up of material into other compartments or bins.
6. The plant shall be equipped with suitable sampling devices or facilities to insure representative samples. If ENGINEER is unable to obtain samples which represent the material being accepted for incorporation into the project, CONTRACTOR shall make necessary adjustments or revisions to the plant before any further mixing is done.
7. Satisfactory means, either by weighing, metering or tank stabs, shall be provided to obtain the proper amount of bituminous material in the mix. The accuracy of bituminous content measured either by weighing, metering or tank stabs, 02512 - 11 of 21 March, 2022 may be checked by computing the daily yield of total material being processed.
8. Thermometric Equipment:
a. An armored thermometer of adequate range in temperature reading shall be fixed in the bituminous feed line at a suitable location near the charging valve at the mixer unit.
b. The plant shall also be equipped with an approved temperature recording device so placed at the discharge chute of the dryer as to register automatically or indicate the temperature of the heated aggregates or plant mix. The printed temperature recordings shall be furnished to ENGINEER after each day’s run.
9. The bituminous mixture shall be weighed on approved scales. Such scales shall be inspected as often as ENGINEER deems necessary to assure their accuracy.
G. REQUIREMENTS FOR DRYER-DRUM MIXER
1. The plant shall be equipped to control aggregate gradation as described for cold feed control. The total cold aggregate feed shall be weighed continuously by an approved belt scale. When tested for accuracy, the weighing system shall register within + 0.5%.
2. An automatic digital record of the dry aggregate and the asphalt shall be displayed, recorded and totaled in appropriate units of weight and time. A positive interlock shall be provided between the dry weight of the aggregate and the bituminous material. The flow of the bituminous material shall be adjusted to compensate for the changes in the dry weight of the aggregate.
3. The dryer-drum mixer shall be capable of drying and heating the aggregate to the moisture and temperature requirements.
A uniform mixture of aggregates and bituminous material shall be produced. The plant shall have a temperature recording device at the discharge chute of the dryer.
H. REQUIREMENTS FOR ADDING HYDRATED LIME
02512 - 12 of 21 March, 2022
1. Provide a mechanical mixing device that creates a uniform and homogeneous mixture with all aggregate particles coated with hydrated lime as approved by the ENGINEER.
2. Equip the mixing plant with facilities to weigh check samples and to calibrate gate openings and metering devices.
Equip with weighing or metering devices (such as a vane feeder with a calibrated revolution counter) to determine the rate of hydrated lime introduced into the aggregate while the plant is in full operation. Do not use belt scales.
3. Use a spray bar or other approved method to wet the aggregate uniformly. Equip the plant with devices that meter the water and hydrated lime into the mixer. Interlock and synchronize the metering devices and feeders to maintain a constant rate of hydrated lime and water to the aggregate.
4. To control the daily quantity of hydrated lime added to the aggregate and to facilitate calibration of the metering devices, place the bulk storage container from which hydrated lime is metered on scales or equip with load cells to enable the accurate measurement of the remaining weight [mass] in the container at the end of each day. Do not use strain gages.
5. Use a pug mill with a mixing chamber to mix the hydrated lime and water with the aggregate. Keep the materials in the chamber until obtaining a uniform and homogeneous mixture of lime, water, and aggregate. Do not use devices that allow the materials to drop directly through the mixture paddles.
6. Locate the pug mill to allow inspection of the mixture during mixing and after discharge from the mixer. Make the belt from the pug mill to the dryer accessible for sampling.
Provide a template of the belt for taking a sample to determine moisture content. Moisture shall be 4% minimum or as determined by ENGINEER.
7. Mix the hydrated lime and water with the aggregate before they enter the dryer.
3.02 APPLICATION
A. The temperature of the mixture prior to lay down shall not be more than 25°F less than the mixing temperature.
02512 - 13 of 21 March, 2022
B. Plant mix wearing course shall be placed between the dates of April
15th and November 15th unless otherwise specified by ENGINEER.
C. Bituminous plant mix shall not be placed on any wet pavement surface; when the atmospheric temperatures are less than those specified in the following table; or, when weather conditions otherwise prevent the proper handling or finishing of the bituminous mixtures:
Minimum Ambient Temperature and Rising (°F)
COMPACTED
THICKNESS SURFACE COURSE SUBSURFACE COURSE
Less than 1" 60 55
1" - 2" 40 40 > 2" 40 35
D. Spot leveling or the bottom lift of a leveling course may be placed at 50°F if additional courses are placed on the same contract.
E. HAULING EQUIPMENT
1. Trucks used for hauling bituminous mixtures shall have tight, clean, metal beds which have been thinly coated with a minimum amount of paraffin oil or other approved material to prevent the mixture from adhering to the beds. This material shall not be used in amounts which will contaminate the mixture.
F. SPREADING AND FINISHING
1. The mixture shall be laid upon an approved surface, spread, and struck off to the grade and elevation established.
Bituminous pavers shall be used to distribute the mixture either over the entire width or over such partial width as may be practicable.
2. When the total compacted thickness of the mat is to be in excess of three (3) inches, it shall be placed in two (2) or more lifts. The compacted thickness of any one (1) lift in multiple-lift construction shall not exceed three (3) inches.
3. Except on tapers, narrow median areas, shoulders, and other
02512 - 14 of 21 March, 2022 such areas of irregular shape, limited length or restrictive width, or such other areas as directed, the paver screed shall be controlled by the automatic screed control described under subsection 3.02(G) herein.
4. CONTRACTOR shall furnish, place, and maintain such materials, devices, and equipment as may be required to provide specified independent line and grade control references and other controls which may be required for proper execution of the work.
5. Line and grade control for use with automatic paver control systems shall be an independent control reference consisting of:
a. A tightly stretched wire or string line offset and paralleling true line for pavement edge and established grade for pavement surface; or
b. A floating beam of not less than twenty (20) feet in length attached to the paver and riding on previously placed base or pavement material. The beam shall be equipped with a floating string or other device that will actuate the automatic screed control in reference to the base on which it is riding. Unless otherwise permitted by ENGINEER, the first ribbon of the first course of pavement material shall be controlled by the independent control wire. Subsequent ribbons may be controlled by the beam reference system; or
c. Non-contact electronic sensors may be used.
6. The longitudinal joint in one (1) layer shall offset that in the layer immediately below, by at least six (6) inches. The longitudinal joints in the top lift need to coincide with the centerline and/or planned lane lines of the roadway unless otherwise shown in the plans or approved by the engineer.
7. On areas where irregularities or unavoidable obstacles make the use of mechanical spreading and finishing equipment impracticable, the mixture shall be spread, raked and luted by hand tools. For such areas the mixture shall be dumped, spread, and screeded to give the required compacted thickness.
8. Asphalt shall extend over lip of gutter on inflow curb and
02512 - 15 of 21 March, 2022 gutter ¼” to ½”, on outflow curb and gutter asphalt shall be flush with lip of gutter. At all ADA ramps asphalt shall be flush with lip of gutter to facilitate wheelchair and other supportive devices movements.
G. BITUMINOUS PAVERS
1. Bituminous pavers shall be self-contained, power-propelled units, provided with an activated screed or strikeoff assembly, heated, and capable of spreading and finishing courses of bituminous plant mix material in lane widths applicable to the specified typical section and thickness shown on the plans. Pavers used for shoulders and similar construction shall be capable of spreading and finishing courses of bituminous plant mix material in widths shown on the plans.
2. The paver shall be equipped with a receiving hopper having sufficient capacity for a uniform spreading operation. The hopper shall be equipped with a distribution system to place the mixture uniformly in front of the screed.
3. The screed or strikeoff assembly shall effectively produce a finished surface of the required evenness and texture without tearing, shoving, or gouging the mixture.
4. Pavers shall be equipped with a paver control system which will automatically control the laying of the mixture to specified transverse slope and established longitudinal grade. The paver control system shall be automatically actuated from an independent line and grade control reference and through a system of mechanical sensors and sensor directed devices which shall maintain the paver screed at the proper transverse slope and at proper height to establish the top surface of the finally compacted mixture at specified slope and grade. In case of failure of the control system, the paver shall be operated by mechanical control only until the material under production at the time of breakdown is laid.
5. The paver shall be capable of being operated, when laying mixtures, at forward speeds consistent with satisfactory laying of the mixture.
H. ROLLERS
02512 - 16 of 21 March, 2022
1. All rollers shall be in good condition, capable of reversing without backlash, and shall be operated at speeds slow enough to avoid displacement of the bituminous mixture.
The number and weight of rollers shall be sufficient to compact the mixture to the required density while it is still in a workable condition. The use of equipment which results in excessive crushing of the aggregate will not be permitted.
2. The pneumatic-tired roller shall be self propelled with a total weight, including ballast, not greater than thirty (30) tons.
The roller shall be constructed so contact pressure may be varied between forty (40) psi and ninety (90) psi. Each roller shall be equipped with not less than seven (7) wheels with tires of equal size and ply and having a smooth tread design.
The wheels shall be staggered on the front and rear axles to provide complete coverage, have a system for uniformly moistening each wheel without an excess of water, and have close-fitting scrapers for each wheel. The tire pressures shall not vary by more than five (5) psi between individual tires from the designated pressure.
I. COMPACTION
1. Immediately after the bituminous mixture has been spread and struck off and the surface irregularities adjusted, it shall be thoroughly and uniformly compacted by rolling. Rolling shall be continued while the mixture is in a workable condition until all roller marks are eliminated and, unless otherwise designated on the plans, until a minimum of the required density (see table below), as established by test results as determined by an approved laboratory, has been obtained. Samples shall be taken in accordance with ASTM D5361, or density shall be determined by the use of properly calibrated nuclear density gauge.
TABLE OF MINIMUM DENSITY REQUIREMENTS
New construction inside city right-of-way.
92% of theoretical maximum density as established by
ASTM D2041.
Construction outside the city right-of-way (patching, parking lots).
94% of maximum density as established by ASTM D1559.
Patching inside city right-of-way.
94% of maximum density as established by ASTM D1559.
02512 - 17 of 21 March, 2022
Overlays. Density requirement shall be achieved when a determined number of passes of a steel wheel roller establishes the compaction of the mix no longer increases as determined by use of a nuclear density gauge.
2. The number, weight, and type of rollers furnished shall be sufficient to obtain the required compaction without undue displacement, cracking, or shoving.
3. When the pavement is placed by machines in echelon or abutted against a previously placed lane, the longitudinal joint shall be rolled first, followed by the regular rolling procedure. On superelevated curves, the rolling shall begin at the low side and progress to the high side by overlapping of longitudinal trips parallel to the centerline.
4. Any displacement occurring as a result of the reversing of the direction of a roller, or from other causes, shall be corrected at once by the use of rakes and addition of fresh mixture when required. Care should be exercised in rolling not to displace the line and grade of the edges of the bituminous mixture.
5. To prevent adhesion of the mixture to the rollers, the wheels shall be kept properly moistened with water or water mixed with very small quantities of detergent or other approved material. Excess liquid shall not be permitted.
6. Along forms, curbs, headers, walls, and other places not accessible to the rollers, the mixture shall be thoroughly compacted with hot hand tampers, smoothing irons, or mechanical tampers. On depressed areas, a trench roller may be used, or cleated compression strips may be used under the roller to transmit compression to the depressed area.
7. Any mixture that becomes loose and broken, mixed with dirt, or is in any way defective shall be removed and replaced with fresh hot mixture, which shall be compacted to conform with the surrounding area. Any area showing an excess or deficiency of bituminous material shall be removed and replaced.
02512 - 18 of 21 March, 2022
J. JOINTS
1. Placing of the bituminous paving shall be as continuous as possible. Rollers shall not pass over the unprotected end of a freshly laid mixture unless authorized by ENGINEER.
Transverse joints shall be formed by cutting back on the previous run to expose the full depth of the course. When directed by ENGINEER, a brush of bituminous material shall be used on contact surfaces of transverse joints just before additional mixture is placed against the previously rolled material.
3.03 PROTECTION
A. During any delays or suspensions of work, as outlined in the
Contract Documents, CONTRACTOR shall be responsible for maintaining the quality of all leveling courses until the placement of additional courses. Maintenance of leveling courses because of delays or suspension of work shall be done at CONTRACTOR’s expense unless otherwise specified in the Contract Documents.
3.04 QUALITY CONTROL
A. The surface shall be tested by ENGINEER using an approved a ten
(10) foot straightedge provided by the CONTRACTOR at selected locations. The variation of the surface from the testing edge of the straightedge between any two (2) contacts with the surface shall at no point exceed one-quarter (¼) inch. All humps or depressions exceeding the specified tolerance shall be corrected by removing defective work and replacing it with new material, or as directed.
B. CONTRACTOR shall perform gradation verification testing every five hundred (500) tons of material produced. Particle size analysis sample to be taken at the hot mix plant from the cold feed belt.
C. Minimum compaction of the mat shall be in accordance with the table indicated in Section 3.02.I.1 as established by ASTM D2041 or ASTM D6926 and D2726. Density shall be determined by coring in accordance with ASTM D5361 and compaction verified by ASTM D1188 or ASTM D2726. The rate of testing shall be every five hundred (500) tons or every three hundred (300) linear feet of street. The use of a nuclear density gauge, per ASTM D2950, is acceptable for quality control and acceptance. To use for quality control and acceptance, a nuclear density gauge must be correlated by coring and must be based on a minimum of seven (7) cores.
Samples for determining maximum density shall be taken in
02512 - 19 of 21 March, 2022 accordance with ASTM D979. Testing will be paid by for the
CONTRACTOR.
D. Testing for moisture after pug mill shall be once per day when producing for CITY roads.
PART 4 METHOD OF MEASUREMENT AND BASIS OF PAYMENT
4.01 METHOD OF MEASUREMENT
A. Plant mix bituminous pavement shall be measured by the ton.
B. Weigh tickets shall be issued for each load either by an automatic printer system as described under subsection 3.01(F) herein, or by a weighman. In the case of a nonautomatic plant, an inspector may be assigned to check the scales and metering devices during the batching process.
C. No deduction shall be made for the weight of bituminous material in the mixture.
D. When specified in the contract as pay items, the quantity of bituminous materials and commercial additive shall be the number of tons of each used in the accepted work.
4.02 BASIS OF PAYMENT
A. All work performed and measured as prescribed above shall be paid for as provided in the respective sections for each type specified.
B. Work prescribed in subsection 3.01(A) herein shall be paid for at the contract unit prices for the material used. Payment shall be made under:
Pay Item Pay Unit
Plant Mix Bituminous Base Ton or Sq. Yd.
Plant Mix Bituminous Pavement Ton or Sq. Yd.
Plant Mix Wearing Course Ton or Sq. Yd.
Leveling Course Ton
END OF SECTION
02512 - 20 of 21 March, 2022
SECTION 02545
BITMINOUS MATERIALS
2.05 PERFORMANCE GRADED ASPHALT BINDER
A. 1. Provide PGAB in accordance with the high- and low- grade temperatures specified.
B. BINDER PROPERTIES
1. Provide binder in accordance with AASHTO M 320, excluding pressure aging vessel residue tests for dynamic shear, physical hardening, and direct tension. When the difference between specified high- and low-grade temperatures is at least 90, provide binder that also in accordance with AASHTO T 301 with at least 60 percent elongation recovery. Test at 77° F [25°C] using RTFO residue and server specimen immediately after elongation. Base asphalt may be modified with no greater than 0.50 percent phosphoric acid. Ensure the total phosphorus content does not exceed 3800 ppm.
2. Do not provide or use PGAB with fibers or discrete particles larger than 0.010 in [250 um] or with carcinogenic modifiers.
3. Base asphalt may be modified with no greater than 0.50 percent phosphoric acid. Ensure the total phosphorus content does not exceed 3800 ppm.
SPECIFICATIONS FOR ANNUAL CONTRACT FOR
PLANT MIX PAVEMENTS, TACK COAT, AND COLD MIX ASPHALT PAVEMENT
CONTRACT PERIOD
The Contract will cover a period of one year, from the time of the award, unless terminated earlier by the City upon thirty (30) days written notice to the supplier.
PLANT MIX PAVEMENT
Plant mix pavement material shall conform to SECTION 02512 with Special Provisions, herein attached, of the CITY OF CHEYENNE AND BOARD OF PUBLIC UTILITIES CONSTRUCTION
SPECIFICATIONS AND STANDARD DRAWINGS, 2022 EDITION WITH ALL AMENDMENTS.
The physical properties of the mix design and plant mix product during production shall meet or fall within the following mixture properties:
Voids, Total Mix 3% - 5% Voids in mineral aggregate 13% - 16% Stability (lbs) 2000 Minimum (50 Blows)
2500 Minimum (75) Blows Flow, (0.01in.) 8-18 Tensile Strength Retained 75% Minimum w/ lime additive (AASHTO T283) 80% Minimum w/ liquid anti-strip agent Film Thickness 8-12 Microns Aggregate/Lime Moisture Content % Minimum 4.0
AGGREGATE FOR PLANT MIX PAVEMENT
Aggregate for Plant Mix Pavement shall conform to SECTION 02190 with Special Provisions, herein attached, of the CITY OF CHEYENNE AND BOARD OF PUBLIC UTILITIES
CONSTRUCTION SPECIFICATIONS AND STANDARD DRAWINGS, 2022 EDITION WITH ALL
AMENDMENTS.
Aggregate shall be Type II pavement aggregate, Grading 1/2" MAX
Sieve Designations % By Weight Passing 3/4" 100 1/2" 90-100 3/8" 55-90 #4 35-70 #8 20-55 #30 5-30 #200 2-7
After the Job Mix Formula is established and approved, do not furnish mix with virgin aggregate fractions that exceed the wide band limits or the tolerance ranges from the target JMF, in accordance with the following table:
Passing #4 and larger sieves ± 5% Passing #8 Sieve ± 4% Passing #30 Sieve ± 3% Passing #200 Sieve ± 2% Bituminous Material ± 0.25% Mixing Temperature ± 20° F
TACK MATERIAL
Tack material shall conform to SECTION 02551 of the CITY OF CHEYENNE AND BOARD OF
PUBLIC UTILITIES CONSTRUCTION SPECIFICATIONS AND STANDARD DRAWINGS, 2022
EDITION WITH ALL AMENDMENTS.
The tack material supplied shall be emulsified asphalt compatible with the hot mix material supplied (CSS-1h)
BITUMINOUS MATERIAL FOR COLD MIX PATCHING
Bituminous material for cold mix patching shall conform to SECTION 02545 of the CITY OF
CHEYENNE AND BOARD OF PUBLIC UTILITIES CONSTRUCTION SPECIFICATIONS AND
STANDARD DRAWINGS, 2022 EDITION WITH ALL AMENDMENTS.
Asphalt Cement SC800, (6%) SC250 may be used when SC800 is not available.
Minimum content shall be 6.0% ± 0.25
Hydrated Lime 1.5% (by dry weight)
AGGREGATES FOR COLD MIX PATCHING MATERIAL
Aggregate for cold mix patching material shall conform to SECTION 02190 with Special Provisions, herein attached, of the CITY OF CHEYENNE AND BOARD OF PUBLIC UTILITIES
CONSTRUCTION SPECIFICATIONS AND STANDARD DRAWINGS, 2022 EDITION WITH ALL
AMENDMENTS.
Aggregate Gradation shall be as follows:
Sieve Designation % By Weight Passing 3/4" 100 1/2" 100 3/8" 75-90 #4 50-70 #8 25-55 #30 15-40 #200 2-11
No more than 15% of the pit run #4 shall be incorporated into the total mix.
JOB MIX FORMULA
1. A Job Mix Formula is required for each type of material provided under this contract. The Job Mix Formulas shall be prepared by an approved independent laboratory using standard testing methods, signed by an Engineer registered to practice in the State of Wyoming.
2. The Job Mix Formulas shall be submitted for approval no later than 30 days after award of the Contract by the governing body of the City of Cheyenne, to both the Street and Alley Division Office and the City Engineer's Office.
3. If requested by the City, material will be provided prior to City approval of the Job Mix Formula. However, once the City approves the formula, all material shall conform to the approved Job Mix Formula.
4. The Job Mix Formula shall specify mixing and compaction temperatures.
5. The supplier shall make all arrangements for the Job Mix Formula and bear all cost involved.
6. If a change in the sources of material is made, a new Job Mix Formula will be required.
PLANT OPERATION
The plant operation shall conform to the requirements stated in SECTION 02512 of the CITY OF
CHEYENNE AND BOARD OF PUBLIC UTILITIES CONSTRUCTION SPECIFICATIONS AND
STANDARD DRAWINGS, 2022 EDITION WITH ALL AMENDMENTS.
The supply plant shall be capable of supplying City trucks a minimum of one hundred-twenty
(120) tons per hour starting as early as 7:00AM, on any normal working day with twenty-four (24) hours advance notice by the City.
NOTICE TO SUPPLIERS
When the City requires more than fifty (50) tons of material in a day, the City will notify the supplier twenty-four (24) hours in advance of the time material is required. Quantities are estimated and are not guaranteed. The City anticipates the purchase of approximately four thousand two hundred fifty (4,250) tons of hot mix material, four thousand (4,000) gallons of tack material and two hundred (200) tons of cold mix patching material. The city reserves the option to purchase the materials elsewhere if doing so would result in cost savings to the City.
ACCEPTANCE OF ASPHALT MATERIAL
Asphalt material supplied for this project that does not meet the contract requirements or expected performance for the designated type and grade may at the direction of the Public Works Director or designee be:
1. Reject the material and the contactor will be required to replace all the material affected by the non-specification material at no additional cost to the City;
2. Accept after evaluation in accordance with the applicable technical section and left in place with no payment made for the asphalt material; or
3. Accepted at a reduced unit price.
PICK UP OF MATERIAL
The City of Cheyenne will pick up material at the plant. Plant shall not be located more than ten
(10) miles outside the City limits.
Beginning the first day of the contract period, the material supplier shall be able to furnish material to any City unit within two (2) hours, 7:00AM to 4:30 PM, Monday thru Thursday, excluding holidays. If for any reason the City truck cannot be loaded within thirty (30) minutes after arrival at the plant and the supplier's representative at the plant has been given proper notification of material needed, the City reserves the right to invoke alternatives as specified under "PROVIDING MATERIALS REQUIRED" contained within the agreement.
PROVIDING MATERIALS REQUIRED
If the contract supplier fails to provide the requested amount of material, the City reserves the right to acquire said material from another supplier. The difference between the amount actually paid to the other supplier and the amount that would have been paid to the contract supplier will be deducted from the next payment to the contract supplier if the amount paid to the other supplier is greater than the contract price. This adjustment will not apply if the failure to provide material occurs after November 14, 2026 or if the City requests twenty-five (25) percent more material than it had previously notified the supplier it would need.
TESTING
Testing will be conducted at the supplier's expense on the material provided to the City. Testing is for the Job Mix Formula verification and will include oil content by extraction and particle size analysis on extracted aggregate. The supplier will furnish the City tests results of material supplied at intervals not to exceed fifteen hundred (1,500) tons. Test results will be available within twenty-four (24) hours of sampling. The City will sample at the City's expense as deemed necessary for proper control. If the testing indicates that the materials are not within compliance of all specifications, the City reserves the right to assess payment reductions in accordance with the Wyoming Department of Transportation Pay Factors Table and Pay Adjustment Calculations.
Any reductions would cover materials purchased that day or until a test with passing results is obtained, either by the contractor or the City.
PAYMENT
Payment requests are to be made monthly to the Street and Alley Division Office for the material supplied up to and including the last working day of the month. Due to the City's fiscal year-end procedures, the payment requested for material supplied in June must be submitted the first working day after the last day in June that materials were furnished.
NO PREEMPTIVE RIGHTS
Contract supplier shall not grant preemptive delivery rights to other consumer to the detriment of the City of Cheyenne. The contract supplier may allow a single non-City truck to move in line ahead of any City truck, provided the mix formula is not revised to accept it.
| Asphalt Hot Mix Specs Corrected Oil changes 2024docx |
| J. ASTM D2041: Standard Test Method for Theoretical Maximum Specific Gravity and Density of Bituminous Paving Mixtures. |
| K. ASTM D2726: Standard Test Method for Bulk Specific Gravity and Density of Non-Absorptive Compacted Bituminous Mixtures. |
| L. ASTM D2950: Standard Test Method for Density of Bituminous Concrete in Place by Nuclear Method. |
| M. ASTM D3665: Standard Practice for Random Sampling of Construction Materials. |
| N. ASTM D4125: Standard Test Method for Asphalt Content of Bituminous Mixtures by the Nuclear Method. |
| O. ASTM D5361: Standard Practice for Sampling Compacted Bituminous Mixtures for Laboratory Testing. |