Construction Addendum Summary
This is a construction addendum issued by the Department of Technology, Management and Budget (DTMB) for the State of Michigan. The addendum modifies the existing construction contract and addresses clarifications, modifications, and supplementary requirements for the project. The document serves to update and amend the original scope of work and contract terms, providing contractors with revised specifications, additional conditions, and any necessary adjustments to the project parameters established in the base contract. The addendum applies to the referenced construction project identified as 26331 and supersedes or supplements corresponding sections of the original contract documents.
The addendum contains standard contractual provisions, technical specifications updates, and administrative requirements that bind all bidders and contractors to the revised terms upon acceptance. Any pricing adjustments, timeline modifications, or changes to deliverables resulting from this addendum are incorporated into the overall contract value and schedule. The document ensures that all parties involved in the construction project operate under consistent, current terms and understanding of project requirements, with compliance mandatory for contract performance and payment.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DTMB-0414 (Rev 6/25)
DEPARTMENT OF TECHNOLOGY, MANAGEMENT AND
BUDGET
State Facilities Administration Design & Construction Division
CONSTRUCTION BID ADDENDUM NO. 2
This form identifies an Addendum to Bidding Documents, and incorporates interpretations or clarifications, modifications, acceptance of proposed “or equal” materials, and other information into the Bidding Documents. Addenda will be numbered by the Professional and distributed through www.michigan.gov/SIGMAVSS as an attachment.
TO:
ALL BIDDERS
DATE ISSUED
11/24/2026
PROJECT NAME
Metamora Hadley Recreation Area – Minnawanna Dam Improvements
FILE NUMBER
751/26331.SAA
PROFESSIONAL
GEI Consultants, Inc
PROJECT DIRECTOR
Sheryl Ananich
BID OPENING DATE:
12/2/2026
ADDENDUM ITEMS:
Answers to questions have been posted. See attached.
Additional information has been uploaded, including the Geotechnical Data Report and some original drawings.
ACKNOWLEDGEMENT: This Addendum must be acknowledged by the Bidder in the space provided in the Bid Summary and Bid Form. Failing to acknowledge Addenda may be cause for the Bid to be rejected. Addenda will become part of the Contract Documents.
PROFESSIONAL: Mark Stoor, PE DATE: 11/24/2026
APPROVED BY:
PROJECT DIRECTOR: DATE: Click to enter date
Sheryl Ananich 11/24/26 http://www.michigan.gov/SIGMAVSS
1. The riprap on the lake side from station 1+00 to 7+00 is to be replaced/repaired(12 of 31). What is the expectation here? New stone, remove existing etc.
• The general expectation is to remove surficial material along this entire area, prepare a suitable subgrade, then place geotextile and new riprap.
There is some existing stone in place along portions of the upstream embankment. This should be removed initially, but may be re-used if it meets riprap specifications and is not mixed with organics or excessive amounts of soil.
2. Dredging is shown on plan sheet 15 of 31 at the inlet of the LLO pipe. It is also a per CY price on the change order prices. Will all dredging be paid at the change order unit? If not, what is the anticipated quantity at the LLO pipe. Is mechanical or hydraulic dredging acceptable?
• The quantity of dredging is not known at this time. All dredging will be paid at the contingent change order unit price. Hydraulic dredging is not authorized under the current EGLE permit. Dredging is to be performed via mechanical methods.
3. Do you have an anticipated amount of tree clearing that will need to be done?
• Tree clearing shall not exceed the permitted limits of disturbance indicated on Sheet EC-1.0 (sheet 9 of 31). We generally anticipate existing trees and brush within these limits will be cleared.
4. What is the LLO inlet? Is there a structure there or just the end of the pipe? Have you investigated the condition of the inlet? It appears to be 3-5' below lake bottom per plans. Is there currently flow through it or is it plugged?
• The LLO inlet consists of a 24” ID CMP. GEI did not observe the pipe during our previous inspection. Historic drawings do not show a collar or flared section at the end of the pipe. The embedment of the pipe below the current lake bottom is unknown, however, Parks Staff have reported there is flow through the pipe when opening the slide gate.
5. How do you anticipate the 24" LLO pipe being lined? From the primary spillway structure or the lake inlet? We were not allowed to look at the primary spillway so it's not clear what is possible there.
• We anticipate slip lining of the 24” CMP will likely be performed from the lake inlet.
6. The Change Order Pricing sheet has a sf item for mill and overlay. The mill alone will have a minimum charge of a couple thousand dollars. It is difficult to have true pricing for this and not very exaggerated.
• For bidding purposes, assume 30,000 SF of asphalt repair. Provide pricing based on this quantity
7. At the Prebid, ongoing clearing was mentioned. Will all necessary trees for downstream access be completed?
• No. The Contractor should anticipate clearing to establish downstream access.
8. Will UV CIPP be considered as an alternate to the slip lining with HDPE pipe?
• No.
9. For the slip lining, is the pipe SDR 21 or SDR 11?
• SDR 21
10. SDR-21 may not be available. What is the minimum ID required for the slip lining pipe upstream? What is the minimum ID required for the slip lining pipe downstream?
• Upstream ID: 18-inch. Downstream ID: 42-inch.
11. What is the diameter of the downstream outlet inside the upstream intake chamber?
• Flow enters the primary spillway chamber from the low level inlet through a 24-inch diameter hole controlled with a slide gate. All flow exiting the spillway is through a 48-inch diameter CMP.
12. Does Section 33 46 16 pertain to the slip pipe lining?
• This section pertains to subdrainage. Please refer to specification section
35 21 96 – HDPE Pipe for pipe slip lining.
13. Per Section 35 53 00-3.8: Turbidity curtain and oil boom installation is mentioned. The plans do not call out turbidity curtain or oil boom. The plans show only silt fence on the upstream embankment. Is This required?
• A turbidity curtain shall be installed downstream of the work area. The turbidity curtain location is shown on the plans, including Sheet EC-1.0
(page 9 of 31) with a detail on Sheet EC-2.0.
• The primary vessel used for any work in the impoundment shall have a sorbent boom available to be deployed in the event of a spill.
#4 says to set the new gate using divers. What is that referring to? There is no new gate shown on the plans or specs.
• Work within the spillway structure may require temporary removal of the gate. The gate is to be re-used.
14. Can you provide any historical drawings for the existing intake structure?
• Historic drawings will be uploaded.
15. How old is the existing gate? Does it operate and will it fully close?
• GEI did not receive documentation of previous gate replacements after the original construction. The gate is operational and exercised by parks staff on a regular basis. No recent inspections were performed inside the structure to confirm whether the gate fully seals.
16. Can we get a CAD file with proposed linework/surface(s)?
• Design CAD files will be available for the selected Contractor.
17. Please confirm the bidder is to assume the lake will already be at winter level 944 upon mobilization and the contractor is not responsible for drawdown or refill.
• Correct.
18. Please confirm the lake can remain at winter level 944 during the work.
• Correct.
19. Please provide all geotech information relative to the dam. Is there a geotech report available? Reference Spec 312319 section 1.4.A.
• The geotechnical data reported will be uploaded.
20. Please provide any additional water level monitoring data for M-1 & M-2 or other on site wells.
• The geotechnical data reported will be uploaded.
21. Is the contractor required to provide monitoring wells?
• The contractor may install new temporary wells to facilitate monitoring during construction dewatering. Permanent monitoring wells are not required.
22. What is the “?” line on G-3.2 profile?
• This line indicates the probable lower extent of embankment fill materials.
23. Are the impact basin safety covers to be embedded in the concrete structure?
What material, size? Is it galvanized?
• The impact basin safety covers and railings included on the bid plans are conceptual. Further detail will be provided with the construction plan set.
24. How will the CY quantity be measured for the Dredging pay item?
• Dredging quantity will be determined by comparing pre and post-excavation survey data. The contractor shall provide pre and post-construction surveys per specification section 01 71 23, including bathymetry of the lake bottom within the limits of construction.
25. Are there any limitations to means and methods associated with lining the upstream pipe?
• The contractor shall provide a detailed work plan for pipe lining for review and approval by the engineer.
26. Can you confirm location relative to the Normal Tailwater Elevation of 926 listed on the table on G-2.0? I’m comparing this to elevation 916 shown on profile C-
1.0.
• The normal tailwater elevation shown on Sheet G-2.0 is incorrect and should read approximately 916 feet NAVD88, consistent with the water surface elevations shown on Sheets G-3.2 and C-1.0.
27. Please confirm which bid item to include SESC measure in.
• Include SESC costs associated with the base scope in base bid item no.
1. Additional SESC costs required for the alternate items should be included with the alternates.
28. What bid item should upstream riprap be in?
• Base bid item No. 7.
29. Please confirm equipment operation limitations on the crest or downstream embankment of the dam. Will slope stability analysis be a requirement of the contractor?
• Our stability analysis included an equipment surcharge of 200 psf on the crest during construction conditions. Further slope stability analysis would be required for heavier equipment resulting in a greater surcharge. If proposed, the contractor should provide supporting stability analyses for the engineer’s review.
30. Do you know if the existing COMM utility near the proposed parapet wall is a live utility service?
• Yes – the contractor shall protect all existing utilities.
31. Existing topsoil thickness appears like it may be deeper than proposed filter layer thickness. Please confirm if the full thickness of topsoil is to be removed. How thick should the bidder assume? If over-excavation is required for topsoil removal, what material and in what layer, should the balance be made up?
• Yes, the full topsoil thickness shall be removed. Assume 12 inches of topsoil removal. Significant undercuts are not expected for this project.
However, if full removal of topsoil/organics results in a subgrade elevation that is lower than shown on the plans, placement of the sand filter shall begin at the approved subgrade elevation. The design top of filter elevation shall be maintained and any undercuts will result in a thicker sand filter layer.
Questions regarding EGLE permit:
32. The EGLE permit mentions 4700cy fill, 4100 + 402cy of cut. Can you define these quantities?
• The noted cut and fill volumes describe impacts within the 100-year floodplain from the planned project. These are approximate estimates based on the design excavation geometry and final proposed grades.
33. There is no water work from March 1 to June 30. The completion date is Aug
23. The window of work before March 1 is very tight and anticipating possible very little work. This leaves a very tight timeframe to complete the work. Is this the intention?
• The March 1 through June 30 in-water work restriction remains in effect.
This restriction does not prohibit all construction activities. Work outside regulated waters and wetlands may continue during this period, subject to other permit conditions. Examples may include upland embankment grading, placement of filter materials, roadway work, and other construction activities that do not disturb regulated aquatic areas.
• The project team is coordinating with DNR Fisheries regarding potential modification of the restriction. Bidders shall assume the existing permit restrictions apply unless otherwise notified.
34. Drawdown can only take place from April 1 to October 1 because of reptiles and mussels. During a drawdown, who is responsible for monitoring and relocating fish and mussels?
• Parks staff will draw down the impoundment to winter pool per standard operating procedure, prior to the start of this work. Relocation of fish and mussels is not anticipated. Drawdown below the winter pool elevation is not permitted, and the work is to proceed at winter pool. The impoundment will remain at winter pool until the work is complete and the typical spring refill will be delayed to accommodate this project.
35. Per the EGLE Permit regarding dredging, please advise on items #22(NO removal of snags, trees, stumps, logs etc) & 23(Dredging not Authorized).
• Removing these obstructions will be allowed only within the excavation area to facilitate pipe slip lining.
• Hydraulic dredging methods are not authorized under this permit.
Mechanical excavation around the LLO as necessary for slip lining is permitted.
36. EGLE permit states clearing only from Oct 1 - March 31.
• Tree removal is not permitted outside of this period.
37. Can the limits of disturbance be adjusted if needed to accommodate access if overall disturbance footprint isn’t increased?
• The Contractor shall base its bid on the limits of disturbance shown in the contract documents. Proposed modifications to these limits will be subject to review by the Engineer and any necessary regulatory approvals. No modifications are authorized by this clarification.