DTMB-0414 (Construction Addendum).pdf

PDF 7 MB Posted

Attached to
472/24055. DPL; Gus Harrison CF - Replace Smoke Purge System
Solicitation number
RFQ 171 260000000466 2
Issued by
Kent County, Michigan

About this file

This is a Construction Bid Addendum No. 1 issued by the Michigan Department of Technology, Management and Budget, State Facilities Administration Design & Construction Division for the Gus Harrison Correctional Facility Smoke Purge System Repair/Replace project (File Number 472/24055.DPL). The addendum, issued on September 25, 2026, provides clarifications and modifications to the bidding documents for this construction project. Key clarifications include specifications regarding ceiling modifications in the Support Services building, which features 12x12 surface-mounted tiles glued to existing cement board/plaster backing that contractors must modify as needed and restore to match existing conditions upon completion. Additionally, the addendum restricts storage of salvaged equipment and new construction materials inside the Support Services Building, requiring contractors to bring materials in and remove them as needed during work execution. For Housing Units 4 and 5, contractors must route new conduit for exhaust fans similar to existing installations, with existing conduit routed through the existing bulkhead. The bid opening date is scheduled for October 14, 2026, and the professional managing the project is Matrix Consulting Engineers, with David Lenz serving as Project Director.

Bidders must acknowledge this addendum in the Bid Summary and Bid Form, as failure to do so may result in bid rejection. The addendum was approved by Project Director David Lenz on September 25, 2026, and will become part of the contract documents. A pre-bid meeting attendance sign-in sheet was distributed with this addendum through www.michigan.gov/SIGMAVSS. The addendum contains no specific pricing information, funding amounts, or other financial terms, as it serves solely to clarify and modify the existing bidding documents for the project.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DTMB-0414 (Rev 6/25)

DEPARTMENT OF TECHNOLOGY, MANAGEMENT AND

BUDGET

State Facilities Administration Design & Construction Division

CONSTRUCTION BID ADDENDUM NO. 1

This form identifies an Addendum to Bidding Documents, and incorporates interpretations or clarifications, modifications, acceptance of proposed “or equal” materials, and other information into the Bidding Documents. Addenda will be numbered by the Professional and distributed through www.michigan.gov/SIGMAVSS as an attachment.

TO:

ALL BIDDERS

DATE ISSUED

9/25/2026

PROJECT NAME

Gus Harrison Correctional Facility – Smoke Purge System Repair/ Replace

FILE NUMBER

472/24055.DPL

PROFESSIONAL

Matrix Consulting Engineers

PROJECT DIRECTOR

David Lenz

BID OPENING DATE:

10/14/2026

ADDENDUM ITEMS:

1. Attached is the pre-bid meeting attendance sign-in sheet.

2. Clarification: The ceiling in the Support Services building is constructed of 12x12 surface mounted tiles glued to existing cement board/plaster backing. Contractor to modify ceilings as required to work as indicated on the construction documents. Contractor repair ceilings as required to match existing once all work is completed as indicated on the construction documents.

3. Clarification: Salvaged equipment and new construction materials cannot be stored inside the Support Services Building. Materials must be brought into the building/removed as needed to complete the work.

4. Clarification: In Housing Unit 4 and Housing Unit 5, contractor to route new conduit for new exhaust fans similar to the existing exhaust fans. Existing conduit is routed through the existing bulkhead.

ACKNOWLEDGEMENT: This Addendum must be acknowledged by the Bidder in the space provided in the Bid Summary and Bid Form. Failing to acknowledge Addenda may be cause for the Bid to be rejected. Addenda will become part of the Contract Documents.

PROFESSIONAL: Troy Thelen, Matrix DATE: 9/25/2026

APPROVED BY:

PROJECT DIRECTOR: David Lenz

DATE: 9/25/2026

File details come from the government source that posted it. Updated .