attchmt_3_SOW.docx
DOCX document 20 KB Posted
- Solicitation number
- DTMA94Q1600018
About this file
statement of work
View the file
Other files
| File | Type | Posted |
|---|---|---|
| amendment_1_SOW_1-12-16_Revision.docx | DOCX document | |
| dtma94q16000018_0001revd_.pdf | ||
| ATTCH_4_terms_and_condition.docx | DOCX document | |
| attchmt_6_sample_quote_for_parts.pdf | ||
| wage_determination.pdf | ||
| dtma94q1600018_TSGB_MSW.pdf | ||
| attchmt_5_drwg.pdf | ||
| ATTCH_2_quote_sheet_MSW.xlsx | XLSX spreadsheet | |
| ATTCH_1_clauses.docx | DOCX document | |
| attchmt_7_history_svc_report.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SR No 5189810 MAIN SALTWATER PUMP RENEWAL
1.0 ABSTRACT
This Item describes the renewal of three Main Saltwater Pumps
2.0 REFERENCES
Technical manuals and drawings available on vessel Suggested piping arrangements for suction and discharge piping Suggested pump support used on Aux Saltwater pumps renewal
3.0 ITEM LOCATION / DESCRIPTION
3.1 Item Location: Engine Room, Port side, 12 ft flat, frame 120.
3.2 Item Description: Provide and install three model Paco 80951 VLS or equivalent pumps.
4.0 GOVERNMENT FURNISHED / EQUIPMENT / MATERIAL / SERVICES:
4.1 None.
5.0 STATEMENT OF WORK - GENERAL
5.1 Provide all labor, materials, and services to perform the following. All dimensions are estimated.
5.2 Contractor is responsible for ship checking and verifying dimensions prior to bid submission and notice to proceed.
5.3 Installation shall meet all Regulatory Body requirements.
5.4 Contractor shall acquire three new saltwater pumps matching materials, dimensions and the operational characteristics of:
| 5.4.1 Manufacturer: | Paco | |
| Model: | 80951 VLS | |
| Motor: | 40 HP, 440V, Marine Duty, TEFC | |
| Construction: | Nickel Aluminum Bronze | |
| Design: | Vertical | |
| Performance: | 2000 GPM @ 56.2ft Disc. Hd. |
5.4.2 Recommended Pump Vendor:
R.F. MacDonald Co.
642 Martin Ave, Suite B Rohnert Park, CA 94928 510-774-6229 POC: John Thyken
5.4.3 Pump selection other than that listed above may only be approved by COTR or Chief Engineer.
5.5 REMOVAL OF OLD MSW PUMPS
5.5.1 With assistance of ship’s crew #1, #2 and #3 MSW Pumps shall be electrically and physically tagged out. During work all suction and discharge piping shall be blanked prior to installing new pumps.
5.5.2 Existing pumps shall be removed from system, preserved, palletized and delivered to the MARAD warehouse in Alameda, CA.
5.6 SUCTION AND DISCHARGE VALVE REPAIR AND RENEWAL
5.6.1 The three (3) 10 inch Discharge Stop Check Valves shall be rebuilt with new seats and discs or renewed.
5.6.1.1 Current valves are Bronze 150 angle stop checks manufactured by Pima.
5.7 NEW PUMP INSTALLATION
5.7.1 The intent is for the new pump installation to “target” the new pump discharge flanges to the existing 10 inch discharge elbows. Refer to sketch for suggested piping arrangement.
5.7.2 Contractor shall rig new pumps to site of installation.
5.7.3 New pumps shall be supported by plate “Saddles” bolted to pump suction and discharge flanges and bolted to existing 6” x 6” angle iron support structure which crosses fore and aft at pump flanges. Saddles should be fashioned to match those fabricated for the #1 and #2 Auxiliary Seawater Pump installations. Refer to ASW Installation Drawings 1040-S11-13-1 and 140-S11-13-2. NOTE: Dimensions from these drawings will have to be scaled up to reflect larger Main Seawater Pumps flange sizes.
5.7.4 Pump suction piping shall require the fashioning of new 12” to 8” spool piece transitions. These transitions shall be constructed of 70 - 30 copper nickel. Existing flanges may be reused to fashion transitions. Refer to sketch for suggested piping arrangement.
5.8 ELECTRICAL
5.8.1 Motors shall be oriented such that the distance between electrical service and motor junction boxes are minimized.
5.8.2 Electrical Connections shall be to existing pump services.
5.8.3 After flooding pump casings, motors shall be “bumped” in presence of COTR or Chief Engineer to prove proper rotation.
5.9 COATINGS
5.9.1 All affected coatings shall be restored to original paint system requirements and shall match Ship’s current color schemes.
5.10 COMMISSIONING
5.10.1 Pump manufactures representative shall be present for commissioning.
5.10.2 After clearing all tags, Ship’s Force shall test each pump.
5.10.3 Pumps and piping shall be inspected for leaks.
5.10.4 Contractor shall secure the services of a reputable Vibration Analysis provider to perform a base line vibration survey of each pump.
5.11 NOTES
None
5.12 DELIVERABLES
5.12.1 Four complete Motor and Pump Manufactures Technical Manual.
5.12.2 Two copies of Vibration Analysis Report.
6.0 SUPPLEMENTARY
6.1 SUPPLEMENTARY LABOR = 118HRS X $____/HR This CLIN’s use is subject to terms of ATTCHMT 1 Clauses , MCL-H2 Supplemental Work
6.2 SUPPLEMENTARY MATERIAL = Not To Exceed $10,000 This CLIN’s use is subject to terms of ATTCHMT 1 Clauses , MCL-H2 Supplemental Work