About this file
Report 3_Geotech
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Bid_Opening_Results_Schedule_A B_-_FW-JOHE_10(1) _100(1).pdf | ||
| Amendment_0001_-_FW-JOHE_10(1) _100(1).pdf | ||
| Report_2_Pavement.pdf | ||
| Report_1_NEPA.pdf | ||
| ADV_Bidder's_Qualifications_Form.doc | DOC document | |
| FP14_Eng.pdf | ||
| VETS-4212_-_Form.pdf | ||
| Plans_-_FW-JOHE_10(1) _100(1).pdf | ||
| IFB_Solicitation_-_FW-JOHE_10(1) _100(1).pdf | ||
| Synopsis__-_FW-JOHE_10(1) _100(1).doc | DOC document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TO MESSAGE/COMMENT FROM/DATE
Appendix No. 1
Project Location Map
SHEET
NO. PROJECT
STATEREG
JOHE 10(1), 100(1)
TOTAL
SHEETS
1PA
FIGURE 1
Project Location Map
U.S. DEPARTMENT OF TRANSPORTATION
FEDERAL LANDS HIGHWAY DIVISION
EASTERN FEDERAL LANDS HIGHWAY DIVISION
STERLING, VIRGINIA
Appendix No. 2
Borings Location Map
Appendix No. 3
Boring Logs
Appendix No. 4
Field Infiltration Tests Data
Boring B-1
Soaking Data
Date
Depth to water surface
(ft)
Drop
(ft) Drop (in)
Infiltration Rate
(in/hr)
5/13/15 12:35 PM 3.10 -- --
5/14/15 7:20 AM 4.79 Dry 20.28 >1.08
Note: No water in bottom of pipe at second reading.
Infiltration Testing Data
Time
Depth to water surface
(ft)
Drop
(ft) Drop (in)
Infiltration Rate
(in/hr) Remarks
5/14/15 7:22 AM 3.06 - - - Start Test 5/14/15 8:16 AM 3.23 0.17 2.04 2.04* Reading 5/14/15 9:17 AM 3.40 0.17 2.04 2.04* Reading 5/14/15 9:17 AM 3.07 - - - Add water 5/14/15 10:17 AM 3.24 0.17 2.04 2.04* Reading 5/14/15 11:16 AM 3.42 0.18 2.16 2.16* Reading
Notes:
All measurements are from top of the casing (TOC).
Measurements were taken with a water meter with an accuracy of 0.01 ft.
Bottom of the PVC pipe is at a depth of 2± ft below existing ground surface.
No coarse sand or fine gravel was placed on the bottom of the hole.
* This rate is unrealistically high and should not be considered in design computations. It is possible that the bottom of the PVC pipe has “rested” on a piece of gravel that existed in the fill materials.
Recommended field infiltration rate: 0.12 inch/hr, to be consistent with the other infiltration rates measured.
Boring B-2
Date
Depth to water surface
(ft)
Drop
(ft) Drop (in)
Infiltration Rate
(in/hr)
5/13/15 9:45 AM 2.50 -- --
5/14/15 7:07 AM 2.90 0.40 4.80 0.22
Infiltration Testing Data
Time
Depth to water surface
(ft)
Drop
(ft) Drop (in)
Infiltration Rate
(in/hr) Remarks
5/14/15 7:12 AM 2.48 - - - Start Test 5/14/15 8:07 AM 2.48 0.00 0.00 0.00 Reading 5/14/15 9:07 AM 2.49 0.01 0.12 0.12 Reading 5/14/15 10:06 AM 2.51 0.02 0.24 0.24 Reading 5/14/15 11:08 AM 2.51 <0.01 <0.01 <0.01 Reading
Notes:
All measurements are from top of the casing (TOC).
Measurements were taken with a water meter with an accuracy of 0.01 ft.
Bottom of the PVC pipe is at a depth of 2± ft below existing ground surface.
No coarse sand or fine gravel was placed on the bottom of the hole.
Recommended field infiltration rate: 0.12 inch/hr, Boring B-3
Date
Depth to water surface
(ft)
Drop
(ft) Drop (in)
Infiltration Rate
(in/hr)
5/13/15 11:07 AM 2.80 -- --
5/14/15 7:15 AM 2.99 0.19 2.28 0.11
Infiltration Testing Data
Time
Depth to water surface
(ft)
Drop
(ft) Drop (in)
Infiltration Rate
(in/hr) Remarks
5/14/15 7:16 AM 2.72 - - - Start Test 5/14/15 8:14 AM 2.73 0.01 0.12 0.12 Reading 5/14/15 9:14 AM 2.74 0.01 0.12 0.12 Reading 5/14/15 10:07 AM 2.76 0.02 0.24 0.24 Reading 5/14/15 11:09 AM 2.78 0.02 0.24 0.24 Reading
Notes:
All measurements are from top of the casing (TOC).
Measurements were taken with a water meter with an accuracy of 0.01 ft.
Bottom of the PVC pipe is at a depth of 2± ft below existing ground surface.
Recommended field infiltration rate: 0.12 inch/hr
Boring B-4
Date
Depth to water surface
(ft)
Drop
(ft) Drop (in)
Infiltration Rate
(in/hr)
5/13/15 1:25 PM 2.60 -- --
5/14/15 7:23 AM 2.64 0.04 0.48 0.03
Infiltration Testing Data
Time
Depth to water surface
(ft)
Drop
(ft) Drop (in)
Infiltration Rate
(in/hr) Remarks
5/14/15 7:23 AM 2.64 - - - Start Test 5/14/15 8:20 AM 2.64 0.00 0.00 0.00 Reading 5/14/15 9:20 AM 2.64 0.00 0.00 0.00 Reading 5/14/15 10:19 AM 2.65 0.01 0.12 0.12 Reading 5/14/15 11:21 AM 2.65 <0.01 <0.01 <0.01 Reading
Notes:
All measurements are from top of the casing (TOC).
Measurements were taken with a water meter with an accuracy of 0.01 ft.
Bottom of the PVC pipe is at a depth of 2± ft below existing ground surface.
Boring B-5
Date
Depth to water surface
(ft)
Drop
(ft) Drop (in)
Infiltration Rate
(in/hr)
5/13/15 2:00 PM 3.00 -- --
5/14/15 7:25 AM 3.02 0.02 0.24 0.01
Infiltration Testing Data
Time
Depth to water surface
(ft)
Drop
(ft) Drop (in)
Infiltration Rate
(in/hr) Remarks
5/14/15 7:25 AM 3.02 - - - Start Test 5/14/15 8:22 AM 3.02 0.00 0.00 0.00 Reading 5/14/15 9:21 AM 3.04 0.02 0.24 0.24 Reading 5/14/15 10:20 AM 3.05 0.01 0.12 0.12 Reading 5/14/15 11:23 AM 3.06 0.01 0.12 0.12 Reading
Notes:
All measurements are from top of the casing (TOC).
Measurements were taken with a water meter with an accuracy of 0.01 ft.
Bottom of the PVC pipe is at a depth of 2± ft below existing ground surface.
Boring B-6
Date
Depth to water surface
(ft)
Drop
(ft) Drop (in)
Infiltration Rate
(in/hr)
5/13/15 2:40 PM 2.80 -- --
5/14/15 7:28 AM 3.06 0.26 3.12 0.19
Infiltration Testing Data
Time
Depth to water surface
(ft)
Drop
(ft) Drop (in)
Infiltration Rate
(in/hr) Remarks
5/14/15 7:30 AM 2.78 - - - Start Test 5/14/15 8:23 AM 2.80 0.02 0.24 0.24 Reading 5/14/15 9:23 AM 2.83 0.03 0.36 0.36 Reading 5/14/15 10:21 AM 2.85 0.02 0.24 0.24 Reading 5/14/15 11:25 AM 2.88 0.03 0.36 0.36 Reading
Notes:
All measurements are from top of the casing (TOC).
Measurements were taken with a water meter with an accuracy of 0.01 ft.
Bottom of the PVC pipe is at a depth of 2± ft below existing ground surface.
Recommended field infiltration rate: 0.24 inch/hr
Appendix No. 5
Selected Photographs
Photo No. 1 Boring B-2, Sample J-4, 8’ to 10’, note the fill material
Photo No. 2 Boring B-2, Sample J-4, 8’ to 10’, note the soils discoloration
Photo No. 3 Boring B-2, auger cuttings, note the soils discoloration
Photo No. 4 Boring B-2, Sample J-6, 13’ to 15’, note the clay material
Photo No. 5 Boring B-4, Sample J-4, 4’ to 6’, not the soil discoloration
Photo No. 6 Boring B-4, Sample J-2, 2’ to 4’, note the construction debris