Amendment_0001_-_NP-UPDE_10(1).pdf

PDF 419 KB Posted

Attached to
Upper Delaware Scenic and Recreational River
Solicitation number
DTFH71-16-B-00022
Issued by

About this file

The Bid Opening date of March 29 2016 at 2 00 p.m. EST will remain the same.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

DTFH7116B00022

x x

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT

THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

Sterling VA 20166-6511

EFLHD-CO

21400 Ridgetop Circle Construction Office Eastern Federal Lands Highway Div.

Federal Highway Administration

Sterling VA 20166-6511

EFLHD-AC

21400 Ridgetop Circle Acquisitions Office Eastern Federal Lands Highway Div.

Federal Highway Administration

SEE BLOCK 1403/21/20160001

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

02/26/2016

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not, is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Project: NP-UPDE 10(1)

The purpose of this Amendment is to:

1) Revise the Special Contract Requirements (J Pages) to include the missing title for

Section 633.

2) Revise the Plans to include the missing Temporary Traffic Control, Shoulder Closure

Layout standard detail.

3) Provide a summary of responses to questions/clarifications asked by potential bidders.

The Bid Opening date of March 29, 2016, at 2:00 p.m. EST will remain the same.

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

NSN 7540-01-152-8070

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

Amendment No. 0001

Info Page 1 of 1

U.S. DEPARTMENT OF TRANSPORTATION

FEDERAL HIGHWAY ADMINISTRATION

EASTERN FEDERAL LANDS HIGHWAY DIVISION

Project NP-UPDE 10(1)

Upper Delaware Scenic and Recreational River Solicitation: DTFH71-16-B-00022

The purpose of this Amendment is to:

1) Revise the Special Contract Requirements (J Pages) to include the missing title for Section 633.

2) Revise the Plans to include the missing Temporary Traffic Control, Shoulder Closure

Layout standard detail.

3) Provide a summary of responses to questions/clarifications asked by potential bidders.

The Bid Opening date of March 29, 2016, at 2:00 p.m. will remain the same.

Special Contract Requirement (J Pages) changes

1. Add the following after Subsection 625.09 of the Special Contract Requirements, page J-13:

Section 633. — PERMANENT TRAFFIC CONTROL

Plan Sheet changes

1. Add Plan Sheet S16, which was mistakenly omitted from the advertisement plan set and contains temporary traffic control requirements for shoulder closures.

Questions-Clarifications Page 1 of 1

Questions / Clarifications

Bidders can send written questions or inquiries for clarification to: eflhd.contracts@dot.gov.

Questions can be submitted at any time, but questions submitted within 7 days of the bid opening may not be answered in time for the bidder to properly incorporate the responses into their bids.

The following questions and issues were submitted via email. The Government response or clarification is provided. Due to the repetitive nature of several questions and issues, the wording of the questions may have been revised and some questions have not been included.

The Government’s direct response to the sender may also have been updated below for better clarity.

1. We need clarification concerning the quantities that are stated in the drawings. Sheet D04 shows 4,014 square feet of asphalt pavement reconstruction with 7-inch thickness. Using a base line density of 145 pounds per cubic foot, this work would require 169.8 tons. The Bid Schedule for Government Option 1 (B-2) has a quantity of 21 tons for Asphalt Concrete Pavement Type-1.

Are we supposed to provide the Government with costs for quantities as stated in the Bid Schedules?

Response: Please note that quantities shown on the Plans and Bid Schedule(s) (the B Pages section of the Solicitation Booklet) are estimated and all items are bid and paid for on a unit price basis. Bidders are instructed to complete their bids with the bid quantities as shown in the Bid Schedule(s). The Contractor will be paid for the amount of work ordered by the CO, completed and accepted according to the specifications. If there is an error in the estimated (Bid Schedule) quantity, the overrun/underrun will be accounted for during construction. Please also note all quantities of work must be ordered by the CO; if the Contractor performs work not ordered, the Government will not pay for it. See the last paragraph of Subsection 109.05 of the Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects (FP).

Regarding the Asphalt Concrete Pavement Type 1 quantity, the asphalt reconstruction area shown on sheet D04 is part of pavement rehabilitation work which is under Schedule C. The 21 tons included in Schedule B is to be used for backfill work related to drainage improvements.

2. Section 637 “Facilities and Services” details requirements for residential housing. However, this bid item is missing from the bid schedules; only the field office bid item was included. Is residential housing part of the contract? If residential housing is a bid item, where do we show its cost on the bid schedules?

Response: Providing residential housing is not a requirement of the contract. Subsection

637.03 of the Special Contract Requirements (J Pages) replaces Tables 637-1 and 637-2 of the FP with tables that only provide field office requirements. It is the Contractor’s decision which type of facility will be provided for the field office whether it is an office in a building, trailer, or other facility as long as it meets the requirements in the FP and the Special Contract Requirements.

File details come from the government source that posted it. Updated .