Bid_Results_-_FW-LIS_10(1).pdf
PDF 36 KB Posted
- Attached to
- Lake Isom National Wildlife Refuge
- Solicitation number
- DTFH71-16-B-00010
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment_0001_-_FW-LIS_10(1).pdf | ||
| VETS-100A-Form.pdf | ||
| Plans_-_FW-LIS_10(1).pdf | ||
| FP03_Errata.pdf | ||
| Report_3_Geotech.pdf | ||
| Report_1_NEPA.pdf | ||
| ADV_Bidder's_Qualifications_Form.doc | DOC document | |
| IFB_Solicitation_-_FW-LIS_10(10.pdf | ||
| FP03_Eng_.pdf | ||
| Report_2_Pavement.pdf | ||
| ROW_Temp_Const_Easement.pdf | ||
| Synopsis_-_FW-LIS_10(1).doc | DOC document |
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Federal Highway Administration
Eastern Federal Lands Highway Division
Bid Opening for
Lake Isom National Wildlife Refuge
PROJECTS: FW-LIS 10(1)
SOLICITATION NO. DTFH71-16-B-00010
December 10, 2015 at 2:00 p.m.
Sterling, VA
FEDERAL HIGHWAY ADMINISTRATION
EASTERN FEDERAL LANDS HIGHWAY DIVISION
BID OPENING for SOLICITATION NO. DTFH71-16-B-00010 Project: FW-LIS 10(1) December 10, 2015, 2:00 p.m. local time
BIDDER’S BID TOTALS DAYS TOTAL PRICE
Aspen Construction Company SCHEDULE A
$1,995,143.95
SCHEDULE A
$2,502,643.95
Claunch Construction Company
SCHEDULE A
$1,891,142.75
$2,398,642.75
Graham County Land Company, LLC
SCHEDULE A
$1,599,028.73
$2,106,528.73
Randy Kinder Excavating, Inc. SCHEDULE A
$1,673,955.00
$2,181,455.00
Pavkov Contracting SCHEDULE A
$4,253.553.00
SCHEDULE A
SCHEDULE A
$4,864,233.00
The total calendar days bid to complete all contract work must be greater than or equal to ( > ) 95 and less than or equal to ( < ) 145.
Fuel Tank Maintenance SCHEDULE A
$1,707,195.17
$2,127,195.17
Harold Coffey Construction SCHEDULE A
$1,766,863.47
$2,274,363.47
Kovilic Construction SCHEDULE A
$2,651,595.00
$3,159,095.00
Still Contractors SCHEDULE A
$1,462,879.50
$1,785,379.50
VuCon, LLC. SCHEDULE A
$1,607,488.00
SCHEDULE A
SCHEDULE A
$2,023,988.00
Engineer’s Estimate SCHEDULE A
$2,370,000.00
SCHEDULE A
SCHEDULE A
$2,877,500.00
| Slide Number 1 |
| FEDERAL HIGHWAY ADMINISTRATION�EASTERN FEDERAL LANDS HIGHWAY DIVISION�BID OPENING for SOLICITATION NO. DTFH71-16-B-00010 Project: FW-LIS 10(1)�December 10, 2015, 2:00 p.m. local time � |
| FEDERAL HIGHWAY ADMINISTRATION�EASTERN FEDERAL LANDS HIGHWAY DIVISION�BID OPENING for SOLICITATION NO. DTFH71-16-B-00010 Project: FW-LIS 10(1)�December 10, 2015, 2:00 p.m. local time � |
| FEDERAL HIGHWAY ADMINISTRATION�EASTERN FEDERAL LANDS HIGHWAY DIVISION�BID OPENING for SOLICITATION NO. DTFH71-16-B-00010 Project: FW-LIS 10(1)�December 10, 2015, 2:00 p.m. local time � |
File details come from the government source that posted it. Updated .