ID NPS PP CRMO 2016(6)
Pavement Preservation Craters of the Moon
# General Technical Question Answer Date 1 x Is there a period of time (minimum or maximum) from the time the milling operation is complete that the chip seal coat is required to be performed and placed on the roadway surface?
no 10/24/16
2 x
The contract special provisions do not specify a milling machine that would be classified as a “micro mill” specification. Teeth spacing on the milling mandrel that would produce the smoothest surface possible. A milling machine that has a standard milling mandrel will leave a rough cut that the chip sealed surface could conform to the same surface the milling leaves as a result of a rough cut.
smoother mill
10/24/16
Check General or Technical
3 x
The milling machine will not be able to mill next to the asphalt curbing on the project, it will be approximately 1 foot of asphalt that will not be able to be cut by the milling machine. Is it the intent of the contract to mill the width of the existing asphalt right next to the asphalt curb?
mill as close as possible with traditional milling methods
10/24/16
4 x
Can the bid schedule and subcontracting plan be emailed to WFL the same day of bid letting as long as the SF 1442, Solicitation documents and bid bond originals are sent to WFL prior to the close of offers?
No. Offers, withdrawals, or modifications by email will not be accepted. The soliciation does not call for a subcontracting plan.