WA NPS MORA 14(8), Nisqually to Paradise, Phase II Utilities, Mount Rainier National Park, Pierce County, Washington

The work consists of trenching, conduit placement, vault installation, minor drainage, installing power line in conduit and other small items of work.

Project length: 6.52 Miles

Tentative Fixed Completion Date: Summer 2015 (Once solicitation is issued, see FAR Clause 52.211-10 for exact date.)

Estimated Price Range: $2 million to $3 million

Location: 12 Miles East of Ashford, Washington

DESCRIPTION OF WORK in US CUSTOMARY UNITS

FP-03

O ne

S ch ed ul e Sc h N am e

A

DIVISION 150 – Project Requirements 152 Construction Survey & Staking (yes/no) No 153 Contractor Quality Control and Assurance

(yes/no) No 154 Contractor Sampling & Testing (yes/no) No 155 Schedules for Construction Contracts (construction schedules) (yes/no) Yes

DIVISION 200 – Earthwork 203 Removal of Structures & Obstructions (

Utility Cabinet 1 ea

DIVISION 600 – Incidental Construction 635 Temporary Traffic Control – Flagger 1200 hr 635 Temporary Traffic Control

Temporary traffic control Traffic and safety supervisor

LPSM

60 day

636 Signal, Lighting, & Electrical Systems Electrical Connection to existing vault

Concrete vault 2” PVC conduit

Wire electrical conductors Utility Trench

7 ea 44 ea

206,400 lnft 103,200 lnft 34,400 lnft