OR FS ERFO 2007(1) -11(1) Highway 35 Betterment, Mt. Hood National Forest, Hood River County, Oregon
The work consists of grading, drainage, base, paving, structures, and other smaller items of work.
Project length: 4.906 miles
Fixed Completion Date: Tentatively October 1, 2012
Estimated Price: Over $20 million
Location: 28 miles south of Hood River, Oregon
�Clark-Newton Section–This section begins at MP 68.6 and continues approximately
2.9 miles to the Teacup Recreational Area. Work consists of grading, drainage, base, paving, riprap, and structures. There is one single-span bridge across Clark Creek and seven large concrete box culverts for drainages crossing Hwy 35. The project will raise the grade of the road approximately four feet throughout most of the project length. No work will be done on the bridge crossing the dry Newton Creek channel at MP 68.0. The Clark Creek Sno-Park will be decommissioned and wetland restoration of the area will be part of the project.
�White River Section–This section is also located on Highway 35 beginning approximately one-quarter of a mile before Forest Service Road 48 (MP 62.4) and continuing across the White River (MP 62.0) approximately 1 mile (MP 61.2), which is approximately one-half mile beyond the entrance to the Boy Scout Camp. Work consists of grading, drainage, base, paving, riprap, and structures. There is a three-span bridge across White River, a two-span bridge across Green Apple Creek (MP 62.1) and large culverts at North Mineral Creek (MP 61.8) and South Mineral Creek (MP 61.6). The project will raise the grade of the road approximately 15-feet above the current White River bridge. Debris material from previous White River events, above and below the bridge, will be used to construct embankments on both sections. Aggregate for base, paving, and rip-rap will come from the Tamarack Quarry, located near Trillium Lake, approximately 8 miles from the project site.
Highway 35 is an important freight route for the State of Oregon and the Northwest. Through traffic must be maintained at all times. Cumulative construction-caused delays to public traffic must be limited to no more than 30 minutes. Cumulative delay is the total delay caused by construction related operations along the entire project length. Temporary lane widths must accommodate large highway vehicles. During winter closures all recreational facilities must have full access. In addition, construction equipment and materials must be removed from the roadside, Sno-Parks, and parking lots.
DESCRIPTION OF WORK in US CUSTOMARY UNITS
DIVISION 150 –Project Requirements 152 Construction Survey & Staking X YES NO 153 Contractor Quality Control and Assurance X YES NO 154 Contractor Sampling & Testing X YES NO 155 Schedules for Construction Contracts (construction schedules) X YES NO 157 Soil Erosion Control Devices (erosion control devices) Yes
DIVISION 200 –Earthwork 201 Clearing & Grubbing Yes 203 Removal of Structures & Obstructions (structures, demolition) Yes 204 Excavation
Embankment 50,755cuyd 304707cuyd
207 Earthwork Geotextiles (geotextiles) Yes 208 Structure Excavation Yes 211 Roadway Obliteration Yes
DIVISION 250 - Slope Reinforcement and Retaining Walls 251 Riprap 40,627 cuyd
DIVISION 300 –Aggregate Courses 301 Untreated Aggregate Courses (crushed aggregate) 39,166 ton
DIVISION 400 –Asphalt Pavements & Surface Treatments 401 Superpave Hot Asphalt Concrete Pavement 28,307 ton
DIVISION 550 –Bridge Construction
White River Bridge - 287.5-foot long, 43’-2” wide, 3-span with 5’-3”-deep concrete precast, pre-stressed I-girders, cast-in-place concrete deck and drilled shaft foundations.
Green Apple Creek Bridge - 244-foot long, 48’-2” wide, 2-span with 6’-3”-deep concrete precast, pre-stressed I-girders, cast-in-place concrete deck and drilled shaft foundations.
Clark Creek Bridge - 92-foot long, 43’-2” wide, single span with 4’-3”deep concrete precast, pre-stressed I-girders, cast-in-place concrete deck and drilled shaft foundations.
DIVISION 600 –Incidental Construction 602 Culverts & Drains (indicate one or both)
Box culverts Box culverts Box culverts
2’=170lnft 3’=165lnft 12’=165lnft 20’=255lnft 10 x 8 = 425lnft 10 x 10 = 140lnft 30 x 8 = 410lnft
617 Guardrail 8,803lnft 622 Rental Equipment X YES NO 633 Permanent Traffic Control Devices (traffic control devices) Yes 634 Permanent Pavement Markings (traffic pavement markings) Yes 635 Temporary Traffic Control
(traffic control –flaggers & pilot cars) Yes Flagger: Hours: 18,000 Pilot Car: Hours: 9,000