INVITATION FOR BIDS
Solicitation No. DTFH70-09-B-00019
OR FS ERFO 2007(1)-11(1) BOOK 1
HIGHWAY 35 BETTERMENT
Solicitation, Offer & Award, Bid Schedule, Contract Clauses, Minimum Wage Schedule, Special Contract Requirements, and Plans
This solicitation cites
Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects, FP-03 U.S. Customary
ISSUING OFFICE:
U.S. DEPARTMENT OF TRANSPORTATION
FEDERAL HIGHWAY ADMINISTRATION
610 EAST FIFTH STREET
VANCOUVER, WA 98661-3801
Phone: (360) 619-7520 – FAX: (360) 619-7932 Web site: http://www.wfl.fhwa.dot.gov/contracting/ e-mail : wfl.contracts@dot.gov
Bid Opening Date:
See Page A-3, Block 13A
QUICK INDEX
Page Item --- Bid Submittal Checklist --- Authority to Sign --- Bid Bond --- Table of Contents A-1 Notice to Bidders A-3 SF 1442, Solicitation, Offer and
Award A-6a Subcontracting Plan A-7 Bid Schedule B-1 Solicitation Provisions C-1 Contract Clauses D-1 Davis-Bacon Wage Rates E-1 Special Contract Requirements
BID REMINDERS
Electronic bids will not be accepted. Submit printed copy of bid to the address listed on the enclosed SF 1442. Before submitting your bid, please review the following:
Have you rechecked your bid figures?
Have you completed the bid schedule?
Have you completed and signed the SF 1442, Solicitation, Offer & Award?
Have you acknowledged all amendments?
Have you completed the Representations &
Certifications (Page B-1)?
Is your bid guarantee enclosed in proper form and amount (see FAR Clause 52.228-1), including Power of Attorney affidavit?
Does the lower left corner of the proposal envelope state “Bid Enclosed”?
Does the lower left corner include the Solicitation Number and the project number/name? A-1 Notice to Bidders
PROJECT NAME OR FS ERFO 2007(1)-11(1)
BEGINNING AT 11+00.00 (MP 61.10)
SUSPEND WORK 66+00.00 (MP 62.14)
RESUME WORK 140+00.00 (MP 65.32)
ENDING AT 293+84.16 (MP 68.23)
NATIONAL FOREST MT HOOD
COUNTY HOOD RIVER
STATE OREGON
LENGTH 3.955 MILES
FIXED COMPLETION DATE See FAR Clause 52.211-10 (FAR Clauses begin on page C-1)
Bid Submittal Checklist
OR FS ERFO 2007(1)-11(1)
HIGHWAY 35 BETTERMENT
Before submitting your bid, please review the following:
Done?
Is this in the envelope?
Bid Envelope Did I correctly address the envelope? (See page A-3, blocks 7 & 8)
Does the lower left corner of the envelope include the Solicitation Number and the project name/number?
Pages A-3 & A-4 (SF 1442, Solicitation Offer & Award) Did I include our firm name and address in block 14?
Did I include our firm’s phone number in block 15?
Did I include our firm’s remittance address in block 16?
(Use when different than block 14)
Did I include my DUNS number?
Did I include the number & date of all amendments in block 19?
Did the appropriate official sign/date in block 20A, 20B & 20C?
Bid Schedule (see page A-7) Did I insert “Unit Bid Price” and “Amount Bid” for each bid item?
Did the appropriate official initial corrections?
Did I include the “Total” on the last page of each bid schedule?
Did I includethe firm’s name on the last page of each bid schedule?
When applicable, did I include the totals for each schedule in the summary page?
(See last page of bid schedules.)
Bid Bond (Standard Form 24) Bids received without a valid bid bond will be rejected.
Did I complete my bid bond correctly?
Did I attach the Power of Attorney to the bid bond?
Authority to Sign Did I include a completed form for each person signing the SF1442 and Bid Bond?
Representations & Certifications & other fill-ins Did I include the completed B-pages (beginning on B-1)?
Did I include the completed clause 1252.228-73 Notification of Miller Act Payment Bond Protection [DO NOT submit entire clause section. Only submit applicable page(s)].
Online Representations & Certifications Application (ORCA) http://orca.bpn.gov
Do we have up-to-date data in ORCA ?
Central Contractor Registration (CCR) http://www.ccr.gov Did I ensure our firm is currently registered in CCR?
Vets100 Reporting https://vets100.vets.dol.gov/
Did I ensure our firm has completed this annual report?
NOTE: The Contractor is fully responsible to verify that all data is correct each time a bid package is submitted. Failure to properly input and/or update your data may cause the bid to be rejected.
OR FS ERFO 2007(1)-11(1)
HIGHWAY 35 BETTERMENT
Driving Directions to our Vancouver Washington Office:
See our web page at http://www.wfl.fhwa.dot.gov/about/directions.htm
Authority to Sign
OR FS ERFO 2007(1)-11(1), HIGHWAY 35 BETTERMENT
INSTRUCTIONS: When the offeror/principal is a corporation, include this certification with your offer/bid.
Corporate Certificate
I, ____________________________________________ (name), certify that I am the
________________________________________(title), of the corporation named as the Offeror/Principal herein;
that _________________________________________(name), who signed this offer and/or bid bond on behalf of ___________________________ (company name) is
________________________________________ (title) of this corporation;
that the offer was duly signed for and on behalf of said corporation by authority and scope of its governing body, and within the scope of its corporate powers.
_____________________________________ (signature) Affix Corporate Seal
_____________________________________ (title)
INSTRUCTIONS: When the offeror/principal is a limited liability company, include this certification with your offer/bid.
Limited Liability Certificate
I, ____________________________________________ (name), certify that I am the
________________________________________(title), of the limited liability company named as the Offeror/Principal herein;
that _________________________________________(name), who signed this offer and/or bid bond on behalf of ___________________________ (company name) is
________________________________________ (title) of this company;
that the offer was duly signed for and on behalf of said company by authority and scope of its governing body, and within the scope of its powers.
_____________________________________ (signature) Affix Company Seal (as applicable)
__________ _________________________ (title)
INSTRUCTIONS: When the offeror/principal is a partnership, include this certification with your offer/bid.
Authority to Bind Partnership
This certifies that the names and signatures of all partners are listed below, and that the person signing the proposal has the authority to actually bind the partnership pursuant to its partnership agreement. Each of the partners individually has full authority to enter into and execute contractual instruments on behalf of said partnership, except as follows:
(State “None” or describe limitations, if any)
This authority shall remain in full force and effect until such time as the revocation of authority by any cause whatsoever has been furnished in writing to and acknowledge by the Contracting Officer.
(Include names and signatures of all partners)
INSTRUCTIONS: When the offeror/principal is a joint venture, include this certification with your offer/bid.
Authority to Bind Joint Venture
This certifies that the person signing the proposal has the authority to actually bind the joint venture pursuant to its joint venture agreement, and that each of the named persons listed below individually has full authority to enter into and execute contractual instruments on behalf of said joint venture, except as follows:
(State “None” or describe limitations, if any)
This authority shall remain in full force and effect until such time as the revocation of authority by any cause whatsoever has been furnished in writing to and acknowledge by the Contracting Officer.
(Include names and signatures of all applicable individuals)
INSTRUCTIONS: When the offeror/principal is a sole proprietorship, the signature on the offer/bid and on the bonds must be as follows:
Sole Proprietorship Requirement
An Offeror/Principal that is a sole proprietorship must submit an offer/bid and a bond signed by the sole proprietor, or by one duly authorized to sign for the sole proprietor.
If the signature is by someone other than the sole proprietor, a copy of the power of attorney authorizing the individual to sign must be provided with the offer/bid.
20%�12�� ���������
2%/,*$7,21�
:H�� WKH�3ULQFLSDO� DQG�6XUHW\�LHV�� DUH� ILUPO\�ERXQG�WR�WKH�8QLWHG�6WDWHV�RI�$PHULFD��KHUHLQDIWHU�FDOOHG�WKH�*RYHUQPHQW��LQ�WKH�DERYH�SHQDO�VXP���)RU SD\PHQW� RI� WKH� SHQDO� VXP�� ZH� ELQG� RXUVHOYHV�� RXU� KHLUV�� H[HFXWRUV�� DGPLQLVWUDWRUV�� DQG� VXFFHVVRUV�� MRLQWO\� DQG� VHYHUDOO\�� � +RZHYHU�� ZKHUH� WKH 6XUHWLHV�DUH�FRUSRUDWLRQV�DFWLQJ�DV�FR�VXUHWLHV��ZH��WKH�6XUHWLHV��ELQG�RXUVHOYHV�LQ�VXFK�VXP��MRLQWO\�DQG�VHYHUDOO\��DV�ZHOO�DV��VHYHUDOO\��RQO\�IRU�WKH SXUSRVH�RI�DOORZLQJ�D� MRLQW�DFWLRQ�RU�DFWLRQV�DJDLQVW�DQ\�RU�DOO� RI�XV�� �)RU�DOO�RWKHU�SXUSRVHV��HDFK�6XUHW\�ELQGV�LWVHOI��MRLQWO\�DQG�VHYHUDOO\�ZLWK�WKH 3ULQFLSDO��IRU�WKH�SD\PHQW�RI�WKH�VXP�VKRZQ�RSSRVLWH�WKH�QDPH�RI�WKH�6XUHW\�� �,I�QR�OLPLW�RI�OLDELOLW\�LV�LQGLFDWHG��WKH�OLPLW�RI�OLDELOLW\�LV�WKH�IXOO�DPRXQW
RI�WKH�SHQDO�VXP�
&21',7,216�
7KH�3ULQFLSDO�KDV�VXEPLWWHG�WKH�ELG�LGHQWLILHG�DERYH�
7+(5()25(�
7KH�DERYH�REOLJDWLRQ�LV�YRLG�LI�WKH�3ULQFLSDO����D��XSRQ�DFFHSWDQFH�E\�WKH�*RYHUQPHQW�RI�WKH�ELG�LGHQWLILHG�DERYH��ZLWKLQ�WKH�SHULRG�VSHFLILHG�WKHUHLQ�IRU DFFHSWDQFH� �VL[W\������GD\V�LI�QR�SHULRG�LV�VSHFLILHG���H[HFXWHV�WKH�IXUWKHU�FRQWUDFWXDO�GRFXPHQWV�DQG�JLYHV�WKH�ERQG�V��UHTXLUHG�E\�WKH�WHUPV�RI�WKH ELG�DV�DFFHSWHG�ZLWKLQ�WKH�WLPH�VSHFLILHG��WHQ������GD\V�LI�QR�SHULRG�LV�VSHFLILHG��DIWHU�UHFHLSW�RI�WKH�IRUPV�E\�WKH�SULQFLSDO��RU��E��LQ�WKH�HYHQW�RI�IDLOXUH WR� H[HFXWH� VXFK� IXUWKHU� FRQWUDFWXDO� GRFXPHQWV�DQG�JLYH�VXFK�ERQGV��SD\V� WKH�*RYHUQPHQW� IRU�DQ\�FRVW�RI�SURFXULQJ� WKH�ZRUN�ZKLFK�H[FHHGV� WKH
DPRXQW�RI�WKH�ELG�
(DFK� 6XUHW\�H[HFXWLQJ� WKLV� LQVWUXPHQW�DJUHHV� WKDW� LWV�REOLJDWLRQ� LV�QRW� LPSDLUHG�E\�DQ\�H[WHQVLRQ�V��RI� WKH� WLPH� IRU� DFFHSWDQFH�RI� WKH�ELG� WKDW� WKH 3ULQFLSDO�PD\�JUDQW�WR�WKH�*RYHUQPHQW���1RWLFH�WR�WKH�VXUHW\�LHV��RI�H[WHQVLRQ�V��DUH�ZDLYHG���+RZHYHU��ZDLYHU�RI�WKH�QRWLFH�DSSOLHV�RQO\�WR�H[WHQVLRQV DJJUHJDWLQJ�QRW�PRUH�WKDQ�VL[W\������FDOHQGDU�GD\V�LQ�DGGLWLRQ�WR�WKH�SHULRG�RULJLQDOO\�DOORZHG�IRU�DFFHSWDQFH�RI�WKH�ELG�
:,71(66�
7KH�3ULQFLSDO�DQG�6XUHW\�LHV��H[HFXWHG�WKLV�ELG�ERQG�DQG�DIIL[HG�WKHLU�VHDOV�RQ�WKH�DERYH�GDWH�
67$1'$5'�)250�����5(9��������
3UHVFULEHG�E\�*6$���)$5�����&)5���������D�
$87+25,=('�)25�/2&$/�5(352'8&7,21
3UHYLRXV�HGLWLRQ�LV�XVDEOH
35,1&,3$/
6,*1$785(�6�
1$0(�6�� 7,7/(�6�
�7\SHG�
6,*1$785(�6�
1$0(�6��
�7\SHG�
&RUSRUDWH
6HDO
�6HDO� �6HDO� �6HDO�
,1',9,'8$/�685(7<�,(6�
�6HDO� �6HDO�
3.�� ��
%,'�%21'
�6HH�LQVWUXFWLRQ�RQ�UHYHUVH�
'$7(�%21'� (;(&87('��0XVW�QRW�EH�ODWHU� WKDQ�ELG
RSHQLQJ�GDWH�
7<3(�2)�25*$1,=$7,21� ��;��RQH�
,1',9,'8$/
-2,17� 9(1785(
3$571(56+,3
&25325$7,21
67$7(�2)� ,1&25325$7,21
35,1&,3$/��/HJDO�QDPH�DQG�EXVLQHVV�DGGUHVV�
685(7<�,(6���1DPH�DQG�EXVLQHVV�DGGUHVV�
PENAL SUM OF BOND
3(5&(17 2)�%,' 35,&(
$02817� 127� 72�(;&(('
0,//,21�6� 7+286$1'�6� +81'5('�6� &(176
%,'�,'(17,),&$7,21
%,'�'$7(
)25��&RQVWUXFWLRQ�
6XSSOLHV��RU�6HUYLFHV�
,19,7$7,21� 12�
&25325$7(�685(7<�,(6�
1$0(� $''5(66
6,*1$785(�6�
1$0(�6�� 7,7/(�6�
�7\SHG�
&RUSRUDWH
6HDO
67$7(�2)� ,1&� /,$%,/,7<�/,0,7� ���
3XEOLF�UHSRUWLQJ�EXUGHQ�IRU�WKLV�FROOHFWLRQ�RI�LQIRUPDWLRQ�LV�HVWLPDWHG�WR�DYHUDJH����PLQXWHV�SHU�UHVSRQVH��LQFOXGLQJ�WKH�WLPH�IRU�UHYLHZLQJ�LQVWUXFWLRQV��VHDUFKLQJ�H[LVWLQJ�GDWD VRXUFHV��JDWKHULQJ�DQG�PDLQWDLQLQJ�WKH�GDWD�QHHGHG��DQG�FRPSOHWLQJ�DQG�UHYLHZLQJ�WKH�FROOHFWLRQ�RI�LQIRUPDWLRQ�� �6HQG�FRPPHQWV�UHJDUGLQJ�WKLV�EXUGHQ�HVWLPDWH�RU�DQ\�RWKHU DVSHFW�RI�WKLV�FROOHFWLRQ�RI�LQIRUPDWLRQ��LQFOXGLQJ�VXJJHVWLRQV�IRU�UHGXFLQJ�WKLV�EXUGHQ��WR�WKH�)$5�6HFUHWDULDW��095���)HGHUDO�$FTXLVLWLRQ�3ROLF\�'LYLVLRQ��*6$��:DVKLQJWRQ��'& helen.radcliff Typewritten Text helen.radcliff Typewritten Text
DTFH70-09-B-00019
helen.radcliff Typewritten Text
OR FS ERFO 2007(1)-11(1)
INSTRUCTIONS
1. This form is authorized for use when a bid guaranty is required. Any deviation from this form will require the written approval of the Administrator of General Services.
2. Insert the full legal name and business address of the Principal in the space designated "Principal" on the face of the form. An authorized person shall sign the bond. Any person signing in a representative capacity (e.g., an attorney-in-fact) must furnish evidence of authority if that representative is not a member of the firm, partnership, or joint venture, or an officer of the corporation involved.
3. The bond may express penal sum as a percentage of the bid price. In these cases, the bond may state a maximum dollar limitation (e.g., 67$1'$5'�)250�����5(9���������%$&.
1$0(� $''5(66
6,*1$785(�6�
1$0(�6�� 7,7/(�6�
�7\SHG�
67$7(�2)� ,1&� /,$%,/,7<�/,0,7� ���
&RUSRUDWH
6HDO
1$0(� $''5(66
6,*1$785(�6�
1$0(�6�� 7,7/(�6�
�7\SHG�
67$7(�2)� ,1&� /,$%,/,7<�/,0,7� ���
&RUSRUDWH
6HDO
1$0(� $''5(66
6,*1$785(�6�
1$0(�6�� 7,7/(�6�
�7\SHG�
67$7(�2)� ,1&� /,$%,/,7<�/,0,7� ���
&RUSRUDWH
6HDO
1$0(� $''5(66
6,*1$785(�6�
1$0(�6�� 7,7/(�6�
�7\SHG�
67$7(�2)� ,1&� /,$%,/,7<�/,0,7� ���
&RUSRUDWH
6HDO
1$0(� $''5(66
6,*1$785(�6�
1$0(�6�� 7,7/(�6�
�7\SHG�
67$7(�2)� ,1&� /,$%,/,7<�/,0,7� ���
&RUSRUDWH
6HDO
1$0(� $''5(66
6,*1$785(�6�
1$0(�6�� 7,7/(�6�
�7\SHG�
67$7(�2)� ,1&� /,$%,/,7<�/,0,7� ���
&RUSRUDWH
6HDO
(e.g., 20% of the bid price but the amount not to exceed dollars).
4. (a) Corporations executing the bond as sureties must appear on the Department of the Treasury's list of approved sureties and must act within the limitation listed therein. where more than one corporate surety is involved, their names and addresses shall appear in the spaces (Surety A, Surety B, etc.) headed "CORPORATE SURETY(IES)." In the space designed "SURETY(IES)" on the face of the form, insert only the letter identification of the sureties.
(b) Where individual sureties are involved, a completed Affidavit of Individual surety (Standard Form 28), for each individual surety, shall accompany the bond. The Government may require the surety to furnish additional substantiating information concerning its financial capability.
5. Corporations executing the bond shall affix their corporate seals. Individuals shall execute the bond opposite the word "Corporate Seal";
and shall affix an adhesive seal if executed in Maine, New Hampshire, or any other jurisdiction requiring adhesive seals.
6. Type the name and title of each person signing this bond in the space provided.
7. In its application to negotiated contracts, the terms "bid" and "bidder" shall include "proposal" and "offeror."
Table of Contents Project: OR FS ERFO 2007(1) – 11(1), Highway 35 Betterment
03USC01/01/04
TABLE OF CONTENTS
DESCRIPTION PAGE
Notice to Bidders ...................................................................................................................A-1
Solicitation, Offer, and Award (SF 1442)..............................................................................A-3
Bid Schedule ..........................................................................................................................A-7
Solicitation Provisions ...........................................................................................................B-1
Contract Clauses ....................................................................................................................C-1
Minimum Wage Schedule......................................................................................................D-1
SCRs Table of Contents
SPECIAL CONTRACT REQUIREMENTS (SCR’s)
The following Special Contract Requirements amend and supplement the Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects, FP-03 U.S. Customary Units.
Division 100...................................................................................................................E-1 Division 150...................................................................................................................E-36
Division 200...................................................................................................................F-1 Division 250...................................................................................................................F-14 Division 300...................................................................................................................F-16 Division 400...................................................................................................................F-20 Division 500...................................................................................................................F-32 Division 550...................................................................................................................F-32 Division 600...................................................................................................................F-59
Division 700...................................................................................................................G-1
Reserved.................................................................................................................................H-1
Erosion and Sedimentation Control Plan Narrative............................................................... I-1
USDA Forest Service – Fire and Suppression Plan and Forms............................................. J-1
Electrofishing Guidelines.......................................................................................................K-1
A-1
Notice to Bidders Project: OR FS ERFO 2007(1) – 11(1), Highway 35 Betterment
NOTICE TO BIDDERS
I. Project Location.
The project work is located approximately 7 miles east of Government Camp, OR in Hood River County.
Signs have not been erected to identify the project limits. No Government personnel will be available for show-me tours.
II. Pre-bid Information.
TECHNICAL QUESTIONS REGARDING PROPOSED WORK FOR THIS
PROJECT WILL BE ACCEPTED UNTIL CLOSE-OF-BUSINESS ON MAY 6, 2010.
Questions can be submitted and answers viewed by going to project information at:
http://www.wfl.fhwa.dot.gov/contracting/construction/advertised.htm Every attempt to respond to questions will be made. However, response to questions received after the above posted date is not guaranteed.
This solicitation includes electronic plan sheets. Plan sheets can be found at http://www.wfl.fhwa.dot.gov/contracting/construction/plans/highway-35/ and viewed by individual sections, downloaded by individual sections, or the entire plan set downloaded in a zip file. A paper copy of the plan sheets is available by submitting the form included in this solicitation. A CD of the physical data is available by submitting the form included in this solicitation.
REPS & CERTS. Submit or update Representations and Certifications online at http://orca.bpn.gov before bid submittal. For more details go to FAR Provision 52.204-8 Annual Representations and Certifications (see page B-2). If you have previously registered on-line and the NAICS code for this solicitation is different than the code listed in your online file, please note the amended changes on the lines provided in FAR 52.204-8.
Requests for technical information (Plan and Division 100 – 700 Specification questions only) about this project will only be accepted in writing (see Block 9 on page A-5).
This solicitation contains a Price Evaluation Factor. In accordance with 13 CFR subsection 126.613, we will apply a factor of 10% to an apparent low bid submitted by a large business when we also receive a bid from a HUBZone small business; the 10% factor does not apply to an apparent low bid submitted by a small business.
If the contract is awarded after applying the price preference for HUBZone small business concerns under FAR clause 52.219-4; at least 50 percent of the cost of the contract performance incurred for personnel must be spent on the prime Contractor’s employees or the employees of other qualified HUBZone small business concerns. See Subsection 108.02A.
http://www.wfl.fhwa.dot.gov/contracting/construction/plans/highway-35/ http://orca.bpn.gov/ http://www.wfl.fha.dot.gov/edi/current.htm
A-2
Notice to Bidders Project: OR FS ERFO 2007(1) – 11(1), Highway 35 Betterment
Particular attention should be paid to Standard Form l442, Solicitation, Offer and Award, to assure that Blocks 14, 15, 16, 19, 20A, and 20C are completed correctly. Sign Block 20B according to the instructions in Subsection 102.02. You must submit a completed ‘Authority to Sign’ document. You must also complete the representations and certifications contained in the Contract Provisions beginning on page B-1. Failure to furnish or complete any of the above may result in your bid being considered nonresponsive and being rejected.
Facsimile bids are not authorized for this solicitation. Bids may be modified or withdrawn by facsimile, if such notice is received by the time specified for receipt of bids. The Government will not be responsible for any failure attributable to the transmission or receipt of facsimile data.
See FAR Provision 52.214-5, Submission of Bids. FAX 360.619.7932.
Notice of CCR Registration. You must register in the Central Contract Registration (CCR) prior to award of this contact. Failure to register prior to contract award will require award to be offered to the next successful registered Offeror. See FAR Subpart 4.1103(c). Register online at http://www.ccr.gov.
III. Post Award Information.
Insurance requirements are set forth in Subsection 107.05.
Contractor Performance Evaluations. FHWA is now posting evaluations in the National Institutes of Health’s Contractor Performance System (CPS) for completed projects. Register at https://cps.nih.gov/infopage.asp (Click on “CPS Info” tab, then click on “Contractor Information” button) to view and comment on evaluations. System registration is only required once. Review the evaluation and submit comments within 30 days of notification. Reviewing the evaluation and submitting comments is limited to one entry. If unable to register, call
360.619.7520 for assistance or a copy of the evaluation. You can also access the Contractor User Manual from this web link.
IV. Specifications and Permits.
This solicitation and subsequent contract are governed by the Federal Acquisition Regulation (FAR), agency supplemental regulations, and the Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects, FP-03 U.S. Customary Units. Obtain paper copies of the FP-03 by calling 360.619.7520, e-mailing at plans_spec@fhwa.dot.gov, or writing Federal Highway Administration, 610 East Fifth Street, Vancouver, WA 98661. An electronic version may be found at http://www.wfl.fhwa.dot.gov/resources/design/specs/.
Geotechnical, hydraulic, bridge, and design data applicable to this project is listed in FAR Clause 52.236-4, Physical Data.
The Government offers to make available to the Contractor a laboratory trailer with test equipment. See Subsection 154.04A, Laboratory Trailer and Testing Equipment.
An adjustment for the price of fuel and asphalt binder has been included in this contract. See Subsection 109.06A.
Water will be necessary for dust abatement, processing material and other construction related activities. Water sources within the project limits have naturally high levels of sediment. A Limited Water Use License will be required for water withdrawal in support of this project. This license may be obtained from the Oregon Department of Water Resources. Water withdrawn from a live stream must meet the requirements of Subsection 107.10(f) of this contract.
http://www.ccr.gov/ https://cps.nih.gov/infopage.asp http://www.wfl.fhwa.dot.gov/resources/design/specs/
1. Solicitation No. 2. Type of Solicitation 3. Date Issued PageSOLICITATION, OFFER, AND AWARD DTFH70-09-B-00019 x Sealed Bid (IFB) 4/1/2010 A-3
(Construction, Alteration, or Repair) Negotiated (RFP)
IMPORTANT–The“offer” section on the reverse must be fully completed by offeror.
4. Contract No. - 5. Requisition/Purchase Request No. 6. Project No.
N/A OR FS ERFO 2007(1)-11(1)
HIGHWAY 35 BETTERMENT
7. Issued By Code: N/A 8. Address Offer to Code: N/A U.S. Department of Transportation Attn: Contracts Section Federal Highway Administration 610 East Fifth Street .
Vancouver WA 98661-3801
A. Name B. Telephone No. (Include area code) (No Collect Calls)
See page A-5. 360.619.75209. For Information Call:
SOLICITATION
NOTE: In sealed bid solicitation “offer” and “offeror” mean “bid” and “bidder”
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS:
This solicitation is designated OR FS ERFO 2007(1)-11(1), HIGHWAY 35 BETTERMENT, MT. HOOD NATIONAL FOREST, HOOD RIVER COUNTY, OREGON
IN STRICT ACCORDANCE WITH:
Bid Schedule Federal Acquisition Regulations (FAR) and Transportation Acquisition Regulations (TAR) General Wage Decision Special Contract Requirements Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects, FP-03 US Customary
11. The Contractor shall begin performance within 10 calendar days and complete it within __*___ calendar days after receiving the award, x notice to proceed. This performance period is x mandatory negotiable. ( See *see page A-5 .)
12A. The Contractor must furnish any required performance and payment bonds? 12B. Calendar Days
(If “YES”, indicate within how many calendar days after award in item 12B.)
x Yes No 10
13. Additional Solicitation Requirements:
A. Sealed offers in original and 0 copies to perform the work required are due at the place specified in Item 8 by 2:00 PM local time
May 14, 2010. If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror’s name and address, the solicitation number, and the date and time offers are due.
B. An offer guarantee x is Is not required.
C. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than 60 calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
NSN 7540-01-155-3212 1442-101 Standard Form 1442 (REV. 4-85) Prescribed by GSA FAR (48 CFR) 53.236-1 (e)
A-4 OFFER (Must be fully completed by offeror)
15. Telephone No. (Include are code)14. Name and Address of Offeror (Include ZIP Code)
DUNS number:
16. Remittance Address (Include on it different than Item 14)
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this is accepted by the Government in writing within 60 calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in Item 13D.
Failure to insert any number means the offeror accepts the minimum in Item 13D.)
AMOUNTS
See Bid Schedule
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGEMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendment to the solicitation - give number and date of each)
AMENDMENT
No.
DATE
20A NAME,TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or Print) 20B. SIGNATURE 20c. OFFER DATE
AWARD (to be completed by Government)
21. ITEM(S) ACCEPTED
All items on Bid Schedule.
22. Amount 23. Accounting and Appropriation Data
25. Other Than full and open competition pursuant to24. Submit Invoices to Address shown in (4 copies unless otherwise specified)
Item See
Page A-5 10 U.S.C. 2304(c) (_____) 41 U.S.C 253 (c) (_____)
26. Administered by Payment will be made by
Federal Highway Administration Western Federal Lands Highway Division 610 East Fifth Street Vancouver WA 98661-3801
Finance Section Western Federal Lands Highway Division 610 East Fifth Street Vancouver WA 98661-3801
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
X28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return copies to issuing office) Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and(c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation, is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30A. Name and Title of Contractor or Person authorized to sign (Type or Print)
31A. Name of Contracting Officer (Type or Print)
Julee McTaggart 30b. Signature 30C. Date 31B. United States of America
By
31C. Award Date
STANDARD FORM 1442 BACK (REV. 4-85)
A-5
Continuation SF 1442
OR FS ERFO 2007(1)-11(1), HIGHWAY 35 BETTERMENT
Block 9 FOR GENERAL INFORMATION, call 360.619.7520 from the hours of 8:00 a.m. to 4:00 p.m. local time or e-mail us at wfl.contracts@dot.gov. You can also submit questions online from our Western Federal Lands webpage as described below.
FOR TECHNICAL INFORMATION (plan and specification questions only), requests for technical information about this project will only be accepted in writing.
Submit questions via fax (360.619.7932) or e-mail at plans_spec@dot.gov (plans_spec@dot.gov).You can also submit questions online from our Western Federal Lands webpage as described below.
SUBMIT QUESTIONS ONLINE. You can submit your questions from our Western Federal Lands website http://www.wfl.fhwa.dot.gov/contracting/construction/advertised.htm.
In “Advertised Projects”, scroll to the project.
Click on “Technical Information Question” or “General Information Question”, as applicable.
Previously asked and answered questions will be available for viewing on the website.
FOR DAVIS-BACON WAGE RATE INFORMATION call the Department of Labor at 415.848.6616.
FOR PHYSICAL DATA, See FAR Contract Clause 52.236-4, Physical Data, (clauses begin on page C-1) for a listing of available data. To obtain copies of Physical Data, submit a written request to the Contracts Section, FAX 360.619-7932 or e-mail us at wfl.contracts@dot.gov. Requests should be made early to assure timely arrival.
FOR BID RESULTS, call 360.619.7773. Bid tabulations will be available on our website approximately 3 work days after the bid opening. Our website is located at:
http://www.wfl.fhwa.dot.gov/contracting/construction/tabs/.
Block 11 COMPLETION DATE: Work shall be completed on or before the date specified in FAR Clause 52.211-10, Commencement, Prosecution, and Completion of Work, subject to such extensions as may be authorized by the terms of the contract and the specifications made a part thereof. Contract Clauses begin on pages C-1.
Block 12A PERFORMANCE & PAYMENT BONDS: See FAR Clause, 52.228-15, Performance and Payment Bonds - Construction (clauses begin on page C-1) and Subsection 102.06 of the Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects, FP-03 U.S. Customary Units.
Block 13B BID BOND AMOUNT: See FAR Clause 52.228-1, Bid Guarantee (clauses begin on page C-1).
ADDITIONAL INFORMATION: See Subsections 102.03 and 102.04 of Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects, FP-03 U.S. Customary Units.
A-6
Continuation SF 1442
OR FS ERFO 2007(1)-11(1), HIGHWAY 35 BETTERMENT
Block 24 SUBMITTING INVOICES: See Subsection 109.08 of the Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects FP-03 U.S. Customary Units.
ESTIMATED PRICES. The price range of the project work is over $20,000,000.
SMALL BUSINESS COMPETITIVENESS DEMONSTRATION PROGRAM. This solicitation is NOT a Small Business Set-Aside. However, award is made pursuant to the Small Business Competitiveness Demonstration Program.
SUBCONTRACTING PLAN. This invitation for bids requires a low bidder who is a LARGE business to submit an acceptable subcontracting plan prior to contract award. Do not submit this form with your bid. A large business is one whose average gross annual receipts over the past 3 years equal $33.5 million or more. For your information the subcontracting plan form is included beginning on page A-6a.
This requirement does not apply to SMALL businesses.
Subcontracting Plan–A-6a
Subcontracting Plan
OR FS ERFO 2007(1)-11(1) HIGHWAY 35 BETTERMENT
Subcontracting Plan For Information Only. Do not submit with your bid.
Contractor: _____________________________________________________________
Address: _____________________________________________________________
This plan is submitted in accordance with Federal Acquisition Regulations Contract Clause 52.219-9, Small Business Subcontracting Plan (Apr 2008), and will be applicable to any contract awarded as result of this solicitation.
Use the following table to indicate:
1. Goals (column 4) - Express in terms of percentages of total planned subcontracting dollars (box “2(i)”).
2. Planned subcontracting dollars (column 2).
Business Type
Planned
Subcontracting (Dollars)
How to calculate Goal shown in
Column 4
Goal
(Percent)
(i) Total planned for Subcontracting.
Include businesses of all sizes (large, small, vet owned, etc.).
2(i) n/a 100%
(ii) Small business concerns (including ANCs & Indian tribes)
2(ii) Amount in 2(ii) divided by
Amount in 2(i)
(iii) Veteran-owned small business concerns
2(iii) Amount in 2(iii) divided by
Amount in 2(i)
(iv) Service-disabled veteran-owned small business concerns
2(iv) Amount in 2(iv) divided by
Amount in 2(i)
(v) HUBZone small business concerns.
2(v) Amount in 2(v) divided by
Amount in 2(i)
(vi) Small disadvantaged business concerns (including ANCs & Indian tribes)
2(vi) Amount in 2(vi) divided by
Amount in 2(i)
(vii) Women-owned small business concerns
2(vii) Amount in 2(vii) divided by
Amount in 2(i)
Subcontracting Plan–A-6b
OR FS ERFO 2007(1)-11(1) HIGHWAY 35 BETTERMENT
3(i). Supplies and services (work) to be subcontracted to small business concerns:
3(ii). Supplies and services (work) to be subcontracted to veteran-owned small business concerns:
3(iii). Supplies and services (work) to be subcontracted to service-disabled veteran-owned small business concerns:
3(iv). Supplies and services (work) to be subcontracted to HUBZone small business concerns
3(v). Supplies and services (work) to be subcontracted to small disadvantaged business concerns
(including ANCs & Indian tribes):
3(vi). Supplies and services (work) to be subcontracted to women-owned small business concerns:
Subcontracting Plan–A-6c
OR FS ERFO 2007(1)-11(1) HIGHWAY 35 BETTERMENT
4. The following method was used to develop the subcontracting goals:
5. The following method(s) was/were used to identify potential sources [e.g., existing company source lists, the Central Contractor Registration database (CCR)), veterans service organizations, the National Minority Purchasing Council Vender Information Service, the Research & Information Division of the Minority Business Development Agency in the Department of Commerce, or small, HUBZone, small disadvantaged and women-owned small business trade associations]. A firm may rely on the information contained in CCR as an accurate representation of a concern’s size and ownership characteristics for the purposes of maintaining a small, veteran-owned small, service-disabled veteran-owned small, HUBZone small, small disadvantaged, and women-owned small business source list. Use of CCR as its source list does not relieve a firm of its responsibilities (e.g., outreach, assistance, counseling, or publicizing subcontracting opportunities) in this clause.
6. Indirect or overhead costs (__)have (__)have not been included in the goals specified above. If costs have been included, describe the method used to determine the proportionate share of costs to be incurred with each type of business.
7. The following individual will administer this subcontracting program:
Name: ___________________________________________
Describe the individual's duties relating to the accomplishment of this subcontracting program:
8. Describe the efforts the Contractor will make to assure that small business, veteran-owned small business, service-disabled veteran-owned small business, HUBZone small business, small disadvantaged business, and women-owned small business concerns have an equitable opportunity to compete for subcontracts.
Subcontracting Plan–A-6d
OR FS ERFO 2007(1)-11(1) HIGHWAY 35 BETTERMENT
9. The Contractor agrees that FAR Contract Clause 52.219-8, Utilization of Small Business Concerns, will be included in all subcontracts that offer further subcontracting opportunities, and that the Contractor will require all subcontractors (except small business concerns) who receive subcontracts in excess of $550,000 ($1,000,000 if construction) to adopt a subcontracting plan that complies with the requirements of FAR Contract Clause 52.219-9, Small Business Subcontracting Plan.
10. The Contractor agrees to: (i) Cooperate in any studies or surveys as may be required; (ii) Submit periodic reports so that the Government can determine the extent of compliance with the subcontracting plan; (iii) Submit the Individual Subcontract Report (ISR) and/or the Summary Subcontract Report (SSR), using the Electronic Subcontracting Reporting System (eSRS) at http://www.esrs.gov; (iv) Ensure that its subcontractors with subcontracting plans agree to submit the ISR and/or the SSR using eSRS; (v) Provide its prime contract number, its DUNS number, and the e-mail address of the Government or Contractor official responsible for acknowledging or rejecting the reports, to all first-tier subcontractors with subcontracting plans so they can enter this information into the eSRS when submitting their reports; and (vi) Require that each subcontractor with a subcontracting plan provide the prime contract number, its own DUNS number, and the e-mail address of the Government or Contractor official responsible for acknowledging or rejecting the reports, to its subcontractors with subcontracting plans.
11. The Contractor agrees to maintain records to demonstrate procedures adopted to comply with the requirements and goals of this plan. These records shall describe the Contractor's efforts to locate small business, veteran-owned small business, service-disabled veteran-owned small business, HUBZone small business, small disadvantaged business, and women-owned small business concerns and award subcontracts to these concerns. At a minimum, the records shall include the following:
(i) Source lists (e.g. CCR), guides, and other data used to identify small business, veteran-owned small business, service-disabled veteran-owned small business, HUBZone small business, small disadvantaged business, and women-owned small business concerns.
(ii) Organizations contacted in an attempt to locate sources that are small business, veteran-owned small business, service-disabled veteran-owned small business, HUBZone small business, small disadvantaged business, and women-owned small business concerns.
(iii) Records on each subcontract award of more than $100,000. These records shall indicate:
(A)Whether small business concerns were solicited and, if not, why not.
(B) Whether veteran-owned small business concerns were contacted and, if not, why not.
(C) Whether service-disabled veteran-owned small business concerns were contacted and, if not, why not.
(D) Whether HUBZone small business concerns were contacted and, if not, why not.
(E) Whether small disadvantaged business concerns (including ANCs & Indian tribes) were contacted and, if not, why not.
(F) Whether women-owned small business concerns were contacted and, if not, why not.
(G) If applicable, the reason award was not made to a small business.
Subcontracting Plan–A-6e
OR FS ERFO 2007(1)-11(1) HIGHWAY 35 BETTERMENT
(iv) Records of outreach efforts to contact trade associations, business development organizations, and conferences/trade fairs in an attempt to locate small, HUBZone small, small disadvantaged and women-owned small business concerns. Records of efforts to contact veterans service organizations.
(v). Records of internal guidance/encouragement provided to buyers through workshops, seminars, training, etc., and monitoring performance to evaluate compliance with the program’s requirements.
(vi).On a contract-by-contract basis, records to support award data submitted by the offeror to the Government, including the name, address, and business size of each subcontractor.
The Contractor agrees to:
1. Assist small business, veteran-owned small business, service-disabled veteran-owned small business, HUBZone small business, small disadvantaged business, and women-owned small business concerns by arranging solicitations, time for the preparation of bids, quantities, specifications, and delivery schedules so as to facilitate the participation by such concerns. Where the Contractor's lists of potential small business, veteran-owned small business, service-disabled veteran-owned small business, HUBZone small business, small disadvantaged business, and women-owned small business subcontractors are excessively long, reasonable effort shall be made to give all such small business concerns an opportunity to compete over a period of time.
2. Provide adequate and timely consideration of the potentialities of small business, veteran-owned small business, service-disabled veteran-owned small business, HUBZone small business, small disadvantaged business, and women-owned small business concerns in all "make-or-buy" decisions.
3. Counsel and discuss subcontracting opportunities with representatives of small business, veteran-owned small business, service-disabled veteran-owned small business, HUBZone small business, small disadvantaged business, and women-owned small business concerns.
4. Confirm that a subcontractor representing itself as a HUBZone small business concern is identified as a certified HUBZone small business concern by accessing the Central Contrator Registration (CCR) database or by contacting SBA.
5. Provide notice to subcontractors concerning penalties and remedies for misrepresentations of business status as small business, veteran-owned small business, service-disabled veteran-owned small business, HUBZone small business, small disadvantaged business, and women-owned small business for the purpose of obtaining a subcontract that is to be included as part or all of a goal contained in this subcontracting plan.
The Contractor acknowledges that a failure of the Contractor or subcontractor to comply in good faith with clause 52.219-8, Utilization of Small Business Concerns, or this approved subcontracting plan shall be considered a material breach of the contract.
Subcontracting Plan–A-6f
OR FS ERFO 2007(1)-11(1) HIGHWAY 35 BETTERMENT
Contractor:
Submitted By: ______________________________________________________ Name and Title of Signer (Type or Print)
_______________________________________ Date: __________________ Signature of Person Authorized to Sign
Federal Highway Administration:
Accepted by: _______________________________________ Date: __________________ Julee McTaggart, Contracting Officer
Project: OR FS ERFO 2007(1)-11(1)
Bidder please note: Before preparing the bid, carefully read the Solicitation Provisions.
Insert a unit bid price, in figures, for each pay item for which a quantity appears in the bid schedule. Multiply the unit price by the quantity for each pay item and show the amount bid.
Should any mathematical check made by the Government show a mistake in the amount bid, the Amount Bid for the item will be based on the Unit Bid Price.
When "LPSM" (Lump Sum) appears as a unit bid price, insert an amount for each lump sum pay item.
When a sum based on a fixed rate appears for any pay item in the amount bid column, include the Government inserted amount bid for the item in the total bid amount.
Total the amounts bid for all pay items and insert the total bid amount.
The quantities for the following items of work are Contract Quantities (see FP-03 Subsection 109.02):
20801-0000, 20803-0000, 55201-0200, 55302-3200, 55302-3200, 55302-3200, 55401-1000, 55401-2000, 55601-1100, 56401-1000, 56501-0600, 56501-0900, 57801-0000, 57802-0000, 61301-0000, 61302-0000
A- 7
Bid Schedule
Pay Item No.
Estimated Quantity Unit Bid Price Amount Bid
15101-0000 MOBILIZATION
ALL Lump Sum $___________________
15201-0000 CONSTRUCTION SURVEY AND STAKING
ALL Lump Sum $___________________
15214-1000 SURVEY AND STAKING, BRIDGE
ALL Lump Sum $___________________
15301-0000 CONTRACTOR QUALITY CONTROL
ALL Lump Sum $___________________
15401-0000 CONTRACTOR TESTING
ALL Lump Sum $___________________
15501-0000 CONSTRUCTION SCHEDULE
ALL Lump Sum $___________________
Project: OR FS ERFO 2007(1)-11(1)
Bid Schedule A
Pay Item No.
Estimated Quantity Unit Bid Price Amount Bid
A- 8
15703-2000 SOIL EROSION CONTROL, TEMPORARY TURF ESTABLISHMENT
(BONDED FIBER MATRIX)
42.0
ACRE $_______________ $___________________
15705-0300 SOIL EROSION CONTROL, SLOPE DRAINS (WATER QUALITY,
BIO-RETENTION SWALE)
LNFT $_______________ $___________________
15705-1300 SOIL EROSION CONTROL, TEMPORARY DIVERSION CHANNEL
LNFT $_______________ $___________________
15705-1500 SOIL EROSION CONTROL, SEDIMENT WATTLE
3,000
LNFT $_______________ $___________________
15705-1700 SOIL EROSION CONTROL, FILTER BERM (COMPOST BERM)
17,000
LNFT $_______________ $___________________
15706-0200 SOIL EROSION CONTROL, CHECK DAM
EACH $_______________ $___________________
15708-1000 SOIL EROSION CONTROL, SUPERVISOR
DAY $_______________ $___________________
15801-0000 WATERING FOR DUST CONTROL
5,000
MGAL $_______________ $___________________
20101-0000 CLEARING AND GRUBBING
38.0
ACRE $_______________ $___________________
20301-0700 REMOVAL OF DELINEATOR
EACH $_______________ $___________________
20301-1400 REMOVAL OF INLET
EACH $_______________ $___________________
Project: OR FS ERFO 2007(1)-11(1)
Estimated Quantity Unit Bid Price Amount Bid
A- 9
20301-1900 REMOVAL OF PIPE CULVERT
EACH $_______________ $___________________
20301-2300 REMOVAL OF SIGN/MARKER
EACH $_______________ $___________________
20301-2400 REMOVAL OF SIGN
EACH $_______________ $___________________
20302-1200 REMOVAL OF GUARDRAIL
6,776
LNFT $_______________ $___________________
20304-2000 REMOVAL OF BRIDGE
ALL Lump Sum $___________________
20401-0000 ROADWAY EXCAVATION
198,000
CUYD $_______________ $___________________
20402-0000 SUBEXCAVATION
6,000
CUYD $_______________ $___________________
20403-0000 UNCLASSIFIED BORROW
358,000
CUYD $_______________ $___________________
20425-1000 DITCH, EXCAVATION (FILTRATION TRENCH)
15,200
LNFT $_______________ $___________________
20426-1000 DITCH, EXCAVATION
3,900
CUYD $_______________ $___________________
20801-0000 STRUCTURE EXCAVATION
6,422
CUYD $_______________ $___________________
20803-0000 STRUCTURAL BACKFILL
2,996
CUYD $_______________ $___________________
Project: OR FS ERFO 2007(1)-11(1)
Estimated Quantity Unit Bid Price Amount Bid
A- 10
21101-1000 ROADWAY OBLITERATION, METHOD 1
11,700
SQYD $_______________ $___________________
25101-1000 PLACED RIPRAP, CLASS 1
2,000
CUYD $_______________ $___________________
25101-3000 PLACED RIPRAP, CLASS 3
3,900
CUYD $_______________ $___________________
25101-4000 PLACED RIPRAP, CLASS 4
32,000
CUYD $_______________ $___________________
25101-5000 PLACED RIPRAP, CLASS 5
8,000
CUYD $_______________ $___________________
25105-4000 KEYED RIPRAP, CLASS 4
3,220
CUYD $_______________ $___________________
25125-0000 BOULDER
EACH $_______________ $___________________
30101-2000 AGGREGATE BASE GRADING D
37,500
TON $_______________ $___________________
30801-1000 ROADWAY AGGREGATE, METHOD 1
12,800
CUYD $_______________ $___________________
31102-0000 STOCKPILED AGGREGATE (SANDING ROCK)
80,000
CUYD $_______________ $___________________
40101-0600 SUPERPAVE PAVEMENT, 1/2-INCH NOMINAL MAXIMUM SIZE
AGGREGATE, 0.3 TO <3 MILLION ESAL , TYPE III ROUGHNESS
28,000
TON $_______________ $___________________
40105-3000 ANTISTRIP ADDITIVE, TYPE 3
TON $_______________ $___________________
Project: OR FS ERFO 2007(1)-11(1)
Estimated Quantity Unit Bid Price Amount Bid
A- 11
40401-0000 MINOR HOT ASPHALT CONCRETE
14,300
TON $_______________ $___________________
41101-1000 PRIME COAT, GRADE CMS-2
TON $_______________ $___________________
41105-0000 BLOTTER
1,100
TON $_______________ $___________________
41201-1000 TACK COAT GRADE CSS-1, CSS-1H, SS-1, OR SS-1H
TON $_______________ $___________________
55201-0200 STRUCTURAL CONCRETE, CLASS A (AE)
1,147
CUYD $_______________ $___________________
55302-3200 PRECAST, PRESTRESSED CONCRETE GIRDERS , 51"
LNFT $_______________ $___________________
55302-3200 PRECAST, PRESTRESSED CONCRETE GIRDERS , 63"
2,289
LNFT $_______________ $___________________
55302-3200 PRECAST, PRESTRESSED CONCRETE GIRDERS , 75"
1,944
LNFT $_______________ $___________________
55401-1000 REINFORCING STEEL
173,372
LB $_______________ $___________________
55401-2000 REINFORCING STEEL, EPOXY COATED
318,500
LB $_______________ $___________________
55601-1100 BRIDGE RAILING, STEEL, TWO RAIL
1,463
LNFT $_______________ $___________________
56401-1000 BEARING DEVICE, ELASTOMERIC
EACH $_______________ $___________________
Project: OR FS ERFO 2007(1)-11(1)
Estimated Quantity Unit Bid Price Amount Bid
A- 12
56501-0600 DRILLED SHAFTS, 48-INCH DIAMETER
1,085
LNFT $_______________ $___________________
56501-0900 DRILLED SHAFTS, 72-INCH DIAMETER
LNFT $_______________ $___________________
57801-0000 HIGH PERFORMANCE CONCRETE (DECK)
CUYD $_______________ $___________________
57802-0000 HIGH PERFORMANCE CONCRETE (APPROACH SLAB)
SQYD $_______________ $___________________
60102-0000 CONCRETE (PRECAST WING WALL)
SQYD $_______________ $___________________
60201-0300 8-INCH PIPE CULVERT
LNFT $_______________ $___________________
60201-0600 18-INCH PIPE CULVERT
LNFT $_______________ $___________________
60201-0800 24-INCH PIPE CULVERT
LNFT $_______________ $___________________
60201-1000 36-INCH PIPE CULVERT
1,400
LNFT $_______________ $___________________
60201-1200 48-INCH PIPE CULVERT
LNFT $_______________ $___________________
60201-1400 60-INCH PIPE CULVERT
LNFT $_______________…
This is the start of the file's text. The full file is on GovTribe.