Questions_10-4-2017.pdf

PDF 81 KB Posted

Attached to
NM FLAP TRAIL 77000(1), El Camino Real Trail DTFH6817B00014
Solicitation number
DTFH6817B00014
Issued by

About this file

Responses to questions

View the file

Other files

File Type Posted
Bid_summary.pdf PDF
Hydraulics.pdf PDF
NM_FLAP_77000_(1)_Bid_Set~2017-08-11_Stamped.pdf PDF
DTFH6817B00014.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions & Answers for NM FLAP TRAIL 77000(1), El Camino Real Trail

September 19, 2017

Question: Will there be an opportunity to visit the site for the subject project (at least some representative locations along the proposed trail) prior to the bid deadline?

Answer: No, there is no pre‐bid site visit planned. Interested contractors will be able to access all the areas.

September 28, 2017

Question: We are seeking clarification regarding the required compaction for the natural surface trail

(segment 3) on the El Camino Trail Project. On page 93 of the bid documents, specification 212.03 states that the trail tread is to be compacted. If compaction is required for segment 3, what are the compaction specifications?

Answer: SCRs reference 212.05 Acceptance. Linear grading will be evaluated under Subsection 106.02

Visual Inspection. Acceptance is based on visual acceptance of the work for compliance with the contract and prevailing industry standards.

File details come from the government source that posted it. Updated .