Text version
Tabulation of Bids Report Date: 11/13/14
1 out of 11Source Selection Information - See FAR 2.101 & 3.104
Project No: CA FTNP YOSE PRES 1(14)
Project Name: Yosemite NP Tunnel Preservation
Schedule: A
Schedule Type: Base
Solcitation No: DTFH68-14-B-00018
Division: Central Federal Lands
State: CA County: Mariposa
Federal Land: Yosemite National Park Opened at: Lakewood
Opened by: Joe Wilson
Date: 11/13/14
I certify that this Bid Tabulation accurately reflects the offers received for this solicitation.
Signed: _______________________________
Title: _______________________________
Date: _______________________________
Contract Awarded to: ____________________ Award Date: ____________________
Contractor Comment Bid Amount Responsive
Maloney Construction, Inc. $2,180,214.60 7445 Redwood Blvd. Suite A Novato, CA 94945
K.W. Emerson, Inc. $2,255,586.20 P.O. Box 549 San Andreas, CA 95249
Kovillic Construction Co., Inc. $2,957,550.00 3721 N. Carnation Street Franklin Park, IL 60131
Engineer's Estimate $1,845,865.00
2 out of 11Source Selection Information - See FAR 2.101 & 3.104
Project No: CA FTNP YOSE PRES 1(14)
Project Name: Yosemite NP Tunnel Preservation
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A1000 15101-0000 MOBILIZATION
Maloney Construction, Inc. Lump Sum $55,345.63 K.W. Emerson, Inc. Lump Sum $241,856.00 Kovillic Construction Co., Inc. Lump Sum $400,000.00 Engineer's Estimate ALL LPSM Lump Sum $155,000.00
A1005 15215-3000 SURVEY AND STAKING, DRAINAGE STRUCTURE
Maloney Construction, Inc. $2,856.40 $17,138.40 K.W. Emerson, Inc. $1,571.00 $9,426.00 Kovillic Construction Co., Inc. $2,000.00 $12,000.00 Engineer's Estimate 6 EACH $1,550.00 $9,300.00
A1010 15301-0000 CONTRACTOR QUALITY CONTROL
Maloney Construction, Inc. Lump Sum $105,227.55 K.W. Emerson, Inc. Lump Sum $56,496.00 Kovillic Construction Co., Inc. Lump Sum $150,000.00 Engineer's Estimate ALL LPSM Lump Sum $72,500.00
A1015 15401-0000 CONTRACTOR TESTING
Maloney Construction, Inc. Lump Sum $71,969.64 K.W. Emerson, Inc. Lump Sum $36,300.00 Kovillic Construction Co., Inc. Lump Sum $50,000.00 Engineer's Estimate ALL LPSM Lump Sum $32,000.00
A1020 15501-0000 CONSTRUCTION SCHEDULE
Maloney Construction, Inc. Lump Sum $23,845.22 K.W. Emerson, Inc. Lump Sum $5,855.00 Kovillic Construction Co., Inc. Lump Sum $20,000.00 Engineer's Estimate ALL LPSM Lump Sum $10,000.00
A1025 15706-1000 SOIL EROSION CONTROL, INLET PROTECTION
Maloney Construction, Inc. $3,046.70 $9,140.10 K.W. Emerson, Inc. $995.00 $2,985.00 Kovillic Construction Co., Inc. $500.00 $1,500.00 Engineer's Estimate 3 EACH $750.00 $2,250.00
3 out of 11Source Selection Information - See FAR 2.101 & 3.104
Project No: CA FTNP YOSE PRES 1(14)
Project Name: Yosemite NP Tunnel Preservation
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A1030 20301-2700 REMOVAL OF STRUCTURE
Maloney Construction, Inc. $7,088.19 $28,352.76 K.W. Emerson, Inc. $2,749.00 $10,996.00 Kovillic Construction Co., Inc. $20,000.00 $80,000.00 Engineer's Estimate 4 EACH $5,000.00 $20,000.00
A1035 20302-2100 REMOVAL OF PIPE CULVERT
Maloney Construction, Inc. $67.95 $5,300.10 K.W. Emerson, Inc. $27.63 $2,155.14 Kovillic Construction Co., Inc. $100.00 $7,800.00 Engineer's Estimate 78 LNFT $100.00 $7,800.00
A1040 20304-1000 REMOVAL OF STRUCTURES AND OBSTRUCTIONS
Maloney Construction, Inc. Lump Sum $112,555.32 K.W. Emerson, Inc. Lump Sum $89,767.00 Kovillic Construction Co., Inc. Lump Sum $125,000.00 Engineer's Estimate ALL LPSM Lump Sum $74,000.00
A1045 30302-1000 DITCH RECONDITIONING
Maloney Construction, Inc. $25.53 $919.08 K.W. Emerson, Inc. $20.00 $720.00 Kovillic Construction Co., Inc. $100.00 $3,600.00 Engineer's Estimate 36 LNFT $80.00 $2,880.00
A1050 30802-2000 ROADWAY AGGREGATE, METHOD 2
Maloney Construction, Inc. $265.26 $20,690.28 K.W. Emerson, Inc. $113.53 $8,855.34 Kovillic Construction Co., Inc. $50.00 $3,900.00 Engineer's Estimate 78 TON $190.00 $14,820.00
A1055 40401-0000 MINOR HOT ASPHALT CONCRETE
Maloney Construction, Inc. $436.72 $25,329.76 K.W. Emerson, Inc. $286.34 $16,607.72 Kovillic Construction Co., Inc. $500.00 $29,000.00 Engineer's Estimate 58 TON $600.00 $34,800.00
4 out of 11Source Selection Information - See FAR 2.101 & 3.104
Project No: CA FTNP YOSE PRES 1(14)
Project Name: Yosemite NP Tunnel Preservation
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A1060 50101-1500 REINFORCED RIGID PAVEMENT, 10-INCH DEPTH, TYPE C SMOOTHNESS/ROUGHNESS
Maloney Construction, Inc. $638.76 $84,316.32 K.W. Emerson, Inc. $699.78 $92,370.96 Kovillic Construction Co., Inc. $350.00 $46,200.00 Engineer's Estimate 132 SQYD $600.00 $79,200.00
A1065 50201-0000 RIGID PAVEMENT PATCH
Maloney Construction, Inc. $76.71 $67,504.80 K.W. Emerson, Inc. $83.28 $73,286.40 Kovillic Construction Co., Inc. $50.00 $44,000.00 Engineer's Estimate 880 SQFT $56.00 $49,280.00
A1070 50202-0000 SEALING JOINTS AND CRACKS
Maloney Construction, Inc. $7.68 $89,856.00 K.W. Emerson, Inc. $11.00 $128,700.00 Kovillic Construction Co., Inc. $15.00 $175,500.00 Engineer's Estimate 11,700 LNFT $5.70 $66,690.00
A1075 55205-0000 REPAIR CONCRETE
Maloney Construction, Inc. $5,581.41 $251,163.45 K.W. Emerson, Inc. $3,951.87 $177,834.15 Kovillic Construction Co., Inc. $5,000.00 $225,000.00 Engineer's Estimate 45 SQYD $4,000.00 $180,000.00
A1080 55212-0000 CLEAN CONCRETE SURFACE
Maloney Construction, Inc. $0.79 $71,890.00 K.W. Emerson, Inc. $1.30 $118,300.00 Kovillic Construction Co., Inc. $4.00 $364,000.00 Engineer's Estimate 91,000 SQFT $2.00 $182,000.00
A1085 55216-0000 CONCRETE COLOR AGENT
Maloney Construction, Inc. $55.53 $5,830.65 K.W. Emerson, Inc. $2.42 $254.10 Kovillic Construction Co., Inc. $100.00 $10,500.00 Engineer's Estimate 105 LB $10.00 $1,050.00
5 out of 11Source Selection Information - See FAR 2.101 & 3.104
Project No: CA FTNP YOSE PRES 1(14)
Project Name: Yosemite NP Tunnel Preservation
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A1090 56506-0000 CORING/PRESSURE GROUTING
Maloney Construction, Inc. $474.16 $47,416.00 K.W. Emerson, Inc. $65.22 $6,522.00 Kovillic Construction Co., Inc. $500.00 $50,000.00 Engineer's Estimate 100 LNFT $350.00 $35,000.00
A1095 60201-0300 8-INCH PIPE CULVERT
Maloney Construction, Inc. $378.61 $4,543.32 K.W. Emerson, Inc. $65.75 $789.00 Kovillic Construction Co., Inc. $200.00 $2,400.00 Engineer's Estimate 12 LNFT $175.00 $2,100.00
A1100 60201-0600 18-INCH PIPE CULVERT
Maloney Construction, Inc. $410.81 $17,254.02 K.W. Emerson, Inc. $87.26 $3,664.92 Kovillic Construction Co., Inc. $300.00 $12,600.00 Engineer's Estimate 42 LNFT $200.00 $8,400.00
A1105 60403-0100 INLET, TYPE 1 (SPECIAL)
Maloney Construction, Inc. $11,240.95 $11,240.95 K.W. Emerson, Inc. $1,697.00 $1,697.00 Kovillic Construction Co., Inc. $4,000.00 $4,000.00 Engineer's Estimate 1 EACH $4,200.00 $4,200.00
A1110 60403-0100 INLET, TYPE 1
Maloney Construction, Inc. $8,618.77 $8,618.77 K.W. Emerson, Inc. $2,772.00 $2,772.00 Kovillic Construction Co., Inc. $4,000.00 $4,000.00 Engineer's Estimate 1 EACH $3,600.00 $3,600.00
A1115 60413-0000 TRENCH DRAIN
Maloney Construction, Inc. $1,647.60 $125,217.60 K.W. Emerson, Inc. $1,028.62 $78,175.12 Kovillic Construction Co., Inc. $500.00 $38,000.00 Engineer's Estimate 76 LNFT $900.00 $68,400.00
6 out of 11Source Selection Information - See FAR 2.101 & 3.104
Project No: CA FTNP YOSE PRES 1(14)
Project Name: Yosemite NP Tunnel Preservation
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A1120 60510-0700 6-INCH COLLECTOR PIPE
Maloney Construction, Inc. $143.83 $109,310.80 K.W. Emerson, Inc. $94.96 $72,169.60 Kovillic Construction Co., Inc. $100.00 $76,000.00 Engineer's Estimate 760 LNFT $80.00 $60,800.00
A1125 60510-0800 6-INCH OUTLET PIPE
Maloney Construction, Inc. $184.30 $5,160.40 K.W. Emerson, Inc. $157.14 $4,399.92 Kovillic Construction Co., Inc. $100.00 $2,800.00 Engineer's Estimate 28 LNFT $140.00 $3,920.00
A1130 60515-0400 UNDERDRAIN CLEANOUT, 6-INCH
Maloney Construction, Inc. $1,290.08 $5,160.32 K.W. Emerson, Inc. $267.25 $1,069.00 Kovillic Construction Co., Inc. $250.00 $1,000.00 Engineer's Estimate 4 EACH $350.00 $1,400.00
A1135 60522-0000 SAND
Maloney Construction, Inc. $74.02 $2,442.66 K.W. Emerson, Inc. $715.55 $23,613.15 Kovillic Construction Co., Inc. $100.00 $3,300.00 Engineer's Estimate 33 CUYD $95.00 $3,135.00
A1140 60704-0000 CLEANING CULVERT IN PLACE
Maloney Construction, Inc. $2,558.10 $5,116.20 K.W. Emerson, Inc. $468.00 $936.00 Kovillic Construction Co., Inc. $2,500.00 $5,000.00 Engineer's Estimate 2 EACH $2,000.00 $4,000.00
A1145 60706-0000 CLEANING DRAINAGE STRUCTURE
Maloney Construction, Inc. $2,366.18 $2,366.18 K.W. Emerson, Inc. $381.00 $381.00 Kovillic Construction Co., Inc. $1,000.00 $1,000.00 Engineer's Estimate 1 EACH $875.00 $875.00
7 out of 11Source Selection Information - See FAR 2.101 & 3.104
Project No: CA FTNP YOSE PRES 1(14)
Project Name: Yosemite NP Tunnel Preservation
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A1150 60711-0000 RECONDITION DRAINAGE STRUCTURE
Maloney Construction, Inc. Lump Sum $59,662.54 K.W. Emerson, Inc. Lump Sum $103,859.00 Kovillic Construction Co., Inc. Lump Sum $10,000.00 Engineer's Estimate ALL LPSM Lump Sum $20,000.00
A1155 60901-1900 CURB, CONCRETE, 20-INCH DEPTH
Maloney Construction, Inc. $872.95 $5,237.70 K.W. Emerson, Inc. $302.50 $1,815.00 Kovillic Construction Co., Inc. $300.00 $1,800.00 Engineer's Estimate 6 LNFT $200.00 $1,200.00
A1160 60901-2500 CURB, ASPHALT, 8-INCH DEPTH
Maloney Construction, Inc. $103.97 $5,718.35 K.W. Emerson, Inc. $122.84 $6,756.20 Kovillic Construction Co., Inc. $50.00 $2,750.00 Engineer's Estimate 55 LNFT $100.00 $5,500.00
A1165 62201-0250 DUMP TRUCK, 10 CUBIC YARD MINIMUM CAPACITY
Maloney Construction, Inc. $182.02 $5,460.60 K.W. Emerson, Inc. $125.00 $3,750.00 Kovillic Construction Co., Inc. $125.00 $3,750.00 Engineer's Estimate 30 HOUR $120.00 $3,600.00
A1170 62201-0450 BACKHOE LOADER, 4 CUBIC FOOT MINIMUM RATED CAPACITY BUCKET, 18-INCH WIDTH
Maloney Construction, Inc. $181.84 $2,727.60 K.W. Emerson, Inc. $140.00 $2,100.00 Kovillic Construction Co., Inc. $200.00 $3,000.00 Engineer's Estimate 15 HOUR $140.00 $2,100.00
A1175 62201-2350 POWER BROOM
Maloney Construction, Inc. $197.64 $2,371.68 K.W. Emerson, Inc. $100.00 $1,200.00 Kovillic Construction Co., Inc. $200.00 $2,400.00 Engineer's Estimate 12 HOUR $160.00 $1,920.00
8 out of 11Source Selection Information - See FAR 2.101 & 3.104
Project No: CA FTNP YOSE PRES 1(14)
Project Name: Yosemite NP Tunnel Preservation
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A1180 62201-2360 VACUUM SWEEPER
Maloney Construction, Inc. $199.95 $2,999.25 K.W. Emerson, Inc. $400.00 $6,000.00 Kovillic Construction Co., Inc. $200.00 $3,000.00 Engineer's Estimate 15 HOUR $160.00 $2,400.00
A1185 62201-3600 MANLIFT
Maloney Construction, Inc. $144.51 $1,734.12 K.W. Emerson, Inc. $125.00 $1,500.00 Kovillic Construction Co., Inc. $150.00 $1,800.00 Engineer's Estimate 12 HOUR $160.00 $1,920.00
A1190 62301-0000 GENERAL LABOR
Maloney Construction, Inc. $122.88 $2,457.60 K.W. Emerson, Inc. $72.00 $1,440.00 Kovillic Construction Co., Inc. $100.00 $2,000.00 Engineer's Estimate 20 HOUR $65.00 $1,300.00
A1195 63308-5000 OBJECT MARKER, TYPE CALTRANS TYPE P
Maloney Construction, Inc. $85.69 $1,028.28 K.W. Emerson, Inc. $265.92 $3,191.04 Kovillic Construction Co., Inc. $250.00 $3,000.00 Engineer's Estimate 12 EACH $125.00 $1,500.00
A1200 63401-0300 PAVEMENT MARKINGS, TYPE B, SOLID
Maloney Construction, Inc. $2.29 $6,412.00 K.W. Emerson, Inc. $2.42 $6,776.00 Kovillic Construction Co., Inc. $2.00 $5,600.00 Engineer's Estimate 2,800 LNFT $0.85 $2,380.00
A1205 63401-0900 PAVEMENT MARKINGS, TYPE E, SOLID
Maloney Construction, Inc. $1.14 $13,110.00 K.W. Emerson, Inc. $1.21 $13,915.00 Kovillic Construction Co., Inc. $2.00 $23,000.00 Engineer's Estimate 11,500 LNFT $1.05 $12,075.00
9 out of 11Source Selection Information - See FAR 2.101 & 3.104
Project No: CA FTNP YOSE PRES 1(14)
Project Name: Yosemite NP Tunnel Preservation
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A1210 63403-0500 PAVEMENT MARKINGS, TYPE E
Maloney Construction, Inc. $34.28 $10,626.80 K.W. Emerson, Inc. $36.30 $11,253.00 Kovillic Construction Co., Inc. $5.00 $1,550.00 Engineer's Estimate 310 SQFT $15.00 $4,650.00
A1215 63406-0000 RAISED PAVEMENT MARKER (CALTRANS TYPE G)
Maloney Construction, Inc. $9.14 $2,559.20 K.W. Emerson, Inc. $9.68 $2,710.40 Kovillic Construction Co., Inc. $75.00 $21,000.00 Engineer's Estimate 280 EACH $10.00 $2,800.00
A1220 63502-0600 TEMPORARY TRAFFIC CONTROL, BARRICADE TYPE 3
Maloney Construction, Inc. $137.11 $548.44 K.W. Emerson, Inc. $229.25 $917.00 Kovillic Construction Co., Inc. $500.00 $2,000.00 Engineer's Estimate 4 EACH $325.00 $1,300.00
A1225 63502-1050 TEMPORARY TRAFFIC CONTROL, TUBULAR MARKER
Maloney Construction, Inc. $18.28 $2,742.00 K.W. Emerson, Inc. $42.31 $6,346.50 Kovillic Construction Co., Inc. $100.00 $15,000.00 Engineer's Estimate 150 EACH $30.00 $4,500.00
A1230 63502-1300 TEMPORARY TRAFFIC CONTROL, DRUM
Maloney Construction, Inc. $50.27 $7,540.50 K.W. Emerson, Inc. $145.27 $21,790.50 Kovillic Construction Co., Inc. $100.00 $15,000.00 Engineer's Estimate 150 EACH $70.00 $10,500.00
A1235 63502-1400 TEMPORARY TRAFFIC CONTROL, VERTICAL PANEL
Maloney Construction, Inc. $61.70 $1,851.00 K.W. Emerson, Inc. $193.93 $5,817.90 Kovillic Construction Co., Inc. $250.00 $7,500.00 Engineer's Estimate 30 EACH $80.00 $2,400.00
10 out of 11Source Selection Information - See FAR 2.101 & 3.104
Project No: CA FTNP YOSE PRES 1(14)
Project Name: Yosemite NP Tunnel Preservation
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A1240 63502-1600 TEMPORARY TRAFFIC CONTROL, WARNING LIGHT TYPE B
Maloney Construction, Inc. $102.83 $1,850.94 K.W. Emerson, Inc. $261.44 $4,705.92 Kovillic Construction Co., Inc. $50.00 $900.00 Engineer's Estimate 18 EACH $500.00 $9,000.00
A1245 63502-2000 TEMPORARY TRAFFIC CONTROL, PORTABLE CHANGEABLE MESSAGE SIGN
Maloney Construction, Inc. $3,656.20 $7,312.40 K.W. Emerson, Inc. $7,465.50 $14,931.00 Kovillic Construction Co., Inc. $10,000.00 $20,000.00 Engineer's Estimate 2 EACH $10,000.00 $20,000.00
A1250 63502-3100 TEMPORARY TRAFFIC CONTROL, TRAFFIC SIGNAL SYSTEM
Maloney Construction, Inc. $22,851.21 $22,851.21 K.W. Emerson, Inc. $44,987.00 $44,987.00 Kovillic Construction Co., Inc. $50,000.00 $50,000.00 Engineer's Estimate 1 EACH $7,000.00 $7,000.00
A1255 63503-0400 TEMPORARY TRAFFIC CONTROL, CONCRETE BARRIER
Maloney Construction, Inc. $74.27 $11,140.50 K.W. Emerson, Inc. $639.40 $95,910.00 Kovillic Construction Co., Inc. $100.00 $15,000.00 Engineer's Estimate 150 LNFT $115.00 $17,250.00
A1260 63504-1000 TEMPORARY TRAFFIC CONTROL, CONSTRUCTION SIGN
Maloney Construction, Inc. $20.57 $11,066.66 K.W. Emerson, Inc. $45.27 $24,355.26 Kovillic Construction Co., Inc. $50.00 $26,900.00 Engineer's Estimate 538.00 SQFT $40.00 $21,520.00
A1265 63505-1000 TEMPORARY TRAFFIC CONTROL, PAVEMENT MARKINGS
Maloney Construction, Inc. $60,327.19 $60,327.19 K.W. Emerson, Inc. $7,986.00 $7,986.00 Kovillic Construction Co., Inc. $10,000.00 $10,000.00 Engineer's Estimate 1.0 MILE $5,150.00 $5,150.00
11 out of 11Source Selection Information - See FAR 2.101 & 3.104
Project No: CA FTNP YOSE PRES 1(14)
Project Name: Yosemite NP Tunnel Preservation
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A1270 63506-0500 TEMPORARY TRAFFIC CONTROL, FLAGGER
Maloney Construction, Inc. $70.84 $297,528.00 K.W. Emerson, Inc. $77.75 $326,550.00 Kovillic Construction Co., Inc. $100.00 $420,000.00 Engineer's Estimate 4,200 HOUR $65.00 $273,000.00
A1275 63506-0600 TEMPORARY TRAFFIC CONTROL, PILOT CAR
Maloney Construction, Inc. $82.26 $172,746.00 K.W. Emerson, Inc. $89.85 $188,685.00 Kovillic Construction Co., Inc. $125.00 $262,500.00 Engineer's Estimate 2,100 HOUR $75.00 $157,500.00
A1280 63510-0100 TEMPORARY TRAFFIC CONTROL, TRAFFIC AND SAFETY SUPERVISOR
Maloney Construction, Inc. $4,398.86 $70,381.76 K.W. Emerson, Inc. $4,836.56 $77,384.96 Kovillic Construction Co., Inc. $5,000.00 $80,000.00 Engineer's Estimate 16 WEEK $4,000.00 $64,000.00
Total Schedule - All Items
Maloney Construction, Inc. $2,180,214.60 K.W. Emerson, Inc. $2,255,586.20 Kovillic Construction Co., Inc. $2,957,550.00 Engineer's Estimate $1,845,865.00